Environmental Permit No.   EP-192/2004

環境許可證編號 EP-192/2004

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Section 10

 

環境影響評估條例

(499)

10

 

ENVIRONMENTAL PERMIT TO OPERATE A DESIGNATED PROJECT

 

營辦指定工程項目的環境許可證

 

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection (the Director) grants this environmental permit to the MTR CORPORATION LIMITED (hereinafter referred to as the "Permit Holder") to operate the designated project described in Part B subject to the conditions specified in Part CThe issue of this environmental permit is based on the documents, approvals or permissions described below:

 

根據《環境影響評估條例》(環評條例)10條的規定,環境保護署署長(署長)將本環境許可證批予地鐵有限公司(下稱許可證持有人),以營辦B所說明的指定工程項目,但須遵守C所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發:

 

 

 

Application No.

申請書編號

 

AEP-192/2004

Document in the Register :

登記冊上的文件:

 

1.        Project Profile –

“Tung Chung Cable Car Project – Ngong Ping Stream Diversion”

(Register No.: PP-193/2003)

 

工程項目簡介

      東涌吊車項目 - 昂坪溪流改道

      (登記冊編號:PP-193/2003

 

2.        The Director’s letter of permission to apply directly for environmental permit dated 4 September 2003 referenced EP2/N9/Q/83

 

環境保護署署長於二○○三年九月四日發出許直接申請環境許可證的件檔案編號EP2/N9/Q/83

 

3.        Tung Chung Cable Car Project

-          Environmental Impact Assessment Report (Final)

-          Environmental Impact Assessment - Executive Summary

-          Environmental Monitoring and Audit Manual

Hereinafter referred to as the “EIA Report” (Register No. : AEIAR-074/2003)

 

Document in the Register :

登記冊上的文件:

 

 

東涌吊車項目

-          環境影評估報告(最終)

-          環境影評估報告 - 行政摘要

-          環境監察及審核手冊

     下稱“環評報告”(登記冊編號AEIAR-074/2003

 

4.        The Director’s letter of approval of the EIA Report dated 9 June 2003 referenced EP2/N9/Q/83

 

         環境保護署署長於二○○三年六月九日發出批環評報告的信件檔案編號EP2/N9/Q/83

 

5.        Application for Environmental Permit dated 10 October 2003 (Application No.: AEP-178/2003) for construction of the designated project

 

許可證持有人於二○○年十月十日提交的許可証申請文件(申請書編號:AEP-178/2003以建造指定工程項目

 

6.        Environmental Permit issued on 7 November 2003 (Permit No. EP-178/2003) for construction of the designated project

 

於二○○年十一月七日發出的環境許可證 (許可證編號 EP-178/2003)以建造指定工程項目

 

7.        Application for Environmental Permit dated 20 July 2004 (Application No.: AEP-192/2004) for operation of the designated project

 

許可證持有人於二○○年七月二十日提交的許可証申請文件(申請書編號:AEP-192/2004以營辦指定工程項目

 

 

 

 

 

 

 

 

   August 2004

 

 

Date

日期

 

(Elvis W. K. AU)

Assistant Director

(Environmental Assessment and Noise)

for Director of Environmental Protection

環境保護署署長

(助理署長(環境評估及噪音) 區偉光代行)

 

 

 


PART B (DESCRIPTION OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as “the Permit”):

下列為本環境許可證(下稱許可證”)A部所提述的指定工程項目的說明:

 

Title of Designated Project

指定工程項目的名稱

 

Tung Chung Cable Car Project – Ngong Ping Stream Diversion

(This designated project is hereafter referred to as “the Project”)

東涌吊車項目 - 昂坪溪流改道 (本指定工程項目下稱“工程項目”)

 

Nature of Designated Project

指定工程項目的性質

 

Operation of a diverted stream and a ditch which discharge into an area of less than 300m from a conservation area at Ngong Ping. The diverted stream falls partly in the Lantau North Country Park.

營辦一段改道溪流和一段支流渠道而其排水入一個距離昂坪自然保育區少於三百米的地區。該段改道溪流部分位於北大嶼郊野公園內

 

Location of Designated Project

指定工程項目的地點

 

 

Ngong Ping.

昂坪

 

The location of the Project is shown in Figure 1 of this Permit.

工程項目的地點展示於本許可證圖1

 

Scale and Scope of Designated Project

指定工程項目的規模和範圍

The Project mainly consists of a diverted stream of approximately 303m long and a ditch of approximately 86m long at Ngong Ping.

工程項目主要包括位於昂坪的一段長約 303 米的改道溪流和一段長約 86 米的支流渠道

 

 


C (許可證條件)

 

1.       一般條件

 

1.1     許可證持有人及任何從事工程項目的人士必須符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反環境影響評估條例 (「環評條例」) (499) 的規定,而當局可根據條例採取適當行動。

 

1.2     許可證持有人須經常確保完全符合現行法例的規定,包括但不限於噪音管制條例(400);空氣污染管制條例(311);水污染管制條例(358);廢物處置條例(354);郊野公園條例 (208)以及水務設施條例(102)。本許可證本身不會就根據任何法例提起的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。

 

1.3     許可證持有人須把本許可證的複本交予營辦工程項目的負責人,並確保這些人士完全明白本許可證的所有條件與規定。

 

1.4     許可證持有人須依據本許可證B的工程項目說明,營辦工程項目。

 

1.5     許可證持有人須確保工程項目的營辦,按照下述資料及措施辦理:工程項目簡介 (登記冊編號:PP-193/2003)及登記冊內的其他相關文件所說明的資料及建議,以及本許可證所說明的資料及緩解措施。

 

 

2.       特定條件

 

2.1     為免對附近環境易受破壞地區造成不良的環境影響,除非另獲署長書面批准,疏浚或維修工程均不得在四月至九月 (首尾兩月包括在內) 期間的任何時間內進行。

 

2.2     不得為進行疏浚或任何其他維修工程而闢建臨時通道或運料路。

 

2.3     任何種類的物料,均不得傾倒於環境易受破壞地區內,這些地區包括北大嶼郊野公園、南大嶼郊野公園、昂坪具有特別科學價值的地點、鳳凰山特別地區與具有特別科學價值的地點,以及自然保育區。因疏浚或任何其他維修工程而引致的淤泥或物料,只可於署長批准的指定位置處置。因疏浚或維修工程而引致淤泥或物料的處理處置安排,須保存記錄,以供署長或獲授權人員任何時間內查閱。

 

註:

 

1.       本許可證共有3部,即A (許可證主要部分)B (指定工程項目的說明) C (許可證條件)。任何援引本許可證的人士須就條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。

 

2.       如違反本許可證的任何條件,署長或獲授權人員可在環境運輸及工務局局長的同意下勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。

 

3.       許可證持有人可根據環境影響評估條例 (「條例」) 13條的規定向署長申請更改本許可證的條件。許可證持有人須以經修訂的許可證替換在工程項目的工地內展示的原有許可證。

 

4.       承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據條例第12條的規定向署長申請新的環境許可證。

 

5.       根據條例第14條的規定,署長可在環境運輸及工務局局長的同意下暫時吊銷、更改或取消本許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。

 

6.       如本許可證在工程項目營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據條例規定取得另一份環境許可證。根據條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下營辦條例附表2所列明的指定工程項目,即屬犯罪。

 

7.       如任何人在違反本許可證的條件下營辦工程項目,根據環評條例,即屬犯罪:

 

(i)      一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;

(ii)      一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;

(iii)     一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;

(iv)     一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;以及

(v)      在任何情況下如該罪行屬連續性質,法院或裁判官可就其信納該罪行連續的每一天另處罰款10,000元。

 

8.       許可證持有人可在接獲本許可證後30天內,根據條例第17條就本許可證的任何條件提出上訴。

 

9.       上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。

 

 

環境許可證編號 EP-192/2004


圖 1


[ ] / [ ]