Environmental Permit No. FEP-02/075/2000

環境許可證編號FEP-02/075/2000

 

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Sections 10 & 12

環境影響評估條例

(499)

1012

 

ENVIRONMENTAL PERMIT TO OPERATE A DESIGNATED PROJECT

營辦指定工程項目的環境許可證

 

 

 

PART A    ( MAIN PERMIT )

A           ( 許可證主要部分)

 

Pursuant to Sections 10 and 12 of the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection (the Director) grants this environmental permit to the DRAINAGE SERVICES DEPARTMENT (hereinafter referred to as the “Permit Holder”) to operate the designated project described in Part B  subject to the conditions specified in Part C.  The issue of this environmental permit is based on the documents, approvals or permissions described below :

 

根據《環境影響評估條例》(環評條例)1012條的規定,環境保護署署長(署長)將本環境許可證批予渠務署(下稱許可證持有人”)以營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發:

 

 

Application No.

申請書編號

FEP-077/2007

 

 

Document in the Register

登記冊上的文件

1.     Yuen Long Bypass Floodway Feasibility Study

Final EIA Study Report, Executive Summary and Final Environmental Monitoring & Audit Manual (Register No. AEIAR-003/1998)

[ Hereinafter referred to as “the EIA Report” ]

元朗排水繞道可行性研究 - 最後環評研究報告、行政摘要及最後環境監察及審核手冊(登記冊編號:AEIAR-003/1998)

[下稱"環評報告"]

 

2.     Yuen Long Bypass Floodway Feasibility Study

Reassessment of Ecological Mitigation Measures

Final Report

[ Hereinafter referred to as “the Ecological Reassessment Report” ]

元朗排水繞道可行性研究 - 重新評估生態緩解措施最後報告

[下稱"生態重估報告"]

 

3.          Application for Environmental Permit dated 18 July 2000 (Application No. : AEP-075/2000) for construction and operation of the designated project

於二OOO年七月十八日提交的環境許可證申請文件(申請書編號:AEP-075/2000)建造及營辦指定工程項目

 

 

 

 

 

4.     Environmental Permit ( No. EP-075/2000 ) issued on 16 August 2000

於二OOO年八月十六日簽發環境許可證(編號EP-075/2000)

 

5.      Application for Further Environmental Permit dated 10 January 2003 (Application No. : FEP-060/2003) for construction of the designated project

於二OO三年一月十日提交的新的環境許可證申請文件(申請書編號 : FEP-060/2003)建造指定工程項目

 

6.    Environmental Permit (No. FEP-01/075/2003) issued on 6 February 2003

        於二OO三年二月六日簽發的環境許可證(編號FEP-01/075/2003)

 

7.      Application for Variation of an Environmental Permit dated 22 April 2003 (Application No. : VEP-093/2003) for construction of the designated project

OO年四月二十二日提交更改環境許可證申請文件(申請書編號 : VEP-093/2003)建造指定工程項目

 

8.       Environmental Permit (No. EP-01/075/2003/A) issued on 19 May 2003

於二OO三年五月十九日簽發環境許可證(編號EP-01/075/2003/A)

 

9.     Application for Further Environmental Permit dated 26 March 2007 (Application No. : FEP-077/2007) for operation of the designated project

於二OO七年三月二十六日提交的新的環境許可證申請文件(申請書編號 : FEP-077/2007)營辦指定工程項目

 

 

 

     April 2007

 

 

 

 

 

 

 

Date

日期

 

(WONG Hon-meng)

Principal Environmental Protection Officer (Strategic Assessment)

for Director of Environmental Protection

環境保護署署長

( 首席環境保護主任(策略評估)黄漢明代行 )

 


 

PART B  ( DESCRIPTIONS OF DESIGNATED PROJECT )

B          ( 指定工程項目的說明 )

 

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit ( hereinafter referred to as “the Permit” ) :

 

下列為本新的環境許可證( 下稱許可證”)A部所提述的指定工程項目的說明:

 

 

Title of Designated Project

指定工程項目的名稱

 

 

Yuen Long Bypass Floodway

[ Hereinafter referred to as “the Project” ]

 

元朗排水繞道

[下稱工程項目”]

 

 

 

Nature of Designated Project

指定工程項目的性質

 

Waterways and drainage works

 

水道及排水工程

 

 

 

Location of Designated Project

指定工程項目的地點