Pursuant to Section 10 of the
Environmental Impact Assessment Ordinance (the Ordinance), the Director of
Environmental Protection (the Director) granted the Environmental Permit EP-262/2007
to the AIRPORT AUTHORITY HONG KONG (hereinafter referred to as the
“Permit Holder”) on 30 May 2007. Pursuant to Section 13 of the Ordinance, the
Director amends the Environmental Permit (No. EP-262/2007) based on the
Application No. VEP-243/2007. The amendments, described below, are incorporated
into this Environmental Permit (No. EP-262/2007/A). This Environmental Permit
as amended is for the construction and operation of the designated project
described in Part B subject to the conditions specified and attached to Part C
of this Permit.
根據環境影響評估條例(「條例」)第
10 條的規定,環境保護署署長(「署長」)於2007年5月30日將環境許可證編號 EP-262/2007 批予香港機場管理局 (下稱「許可證持有人」)。 根據條例第 13 條的規定,署長因應申請書編號
VEP-243/2007 修訂環境許可證編號 EP-262/2007。下文說明的修訂,已包含在本環境許可證內 (EP-262/2007/A)。本經修訂的環境許可證,適用於建造及營辦本許可證 B 部所說明的指定工程項目,
但須遵守本許可證 C 部所列明及附載的條件。
The issue of this Environmental Permit is based on the documents, approvals and permissions described below :
本環境許可證乃依據下列的文件、批准及許可條件而簽發 :
|
Application No. 申請書編號 |
VEP-243/2007
|
|||
|
Document in the Register : 登記冊上的文件: |
1.
Environmental Assessment Services
for Permanent Aviation Fuel Facility -
Final Environmental Impact Assessment
Report -
Final Environmental Impact
Assessment Report Appendices Volume 1, 2 & 3 -
Executive Summary for Final
Environmental Impact Assessment Report -
Final Environmental Monitoring and
Audit Manual Hereinafter referred to as the “EIA
Report” (Register No.: AEIAR-107/2007) 永久航空煤油設備環境評估服務 -
最終環境影響評估報告 -
最終環境影響評估報告附件第一、第二及第三冊 -
最終環境影響評估報告行政摘要 -
最終環境監察及審核手冊 下稱“環評報告”(登記冊編號:AEIAR–107/2007) |
|||
|
Document in the Register : 登記冊上的文件: |
2.
The Director’s letter of approval
of the EIA Report dated 30 May 2007 referenced Annex (34) to EP2/N9/B/19 環境保護署署長於二○○七年五月三十日發出批准環評報告的信件檔案編號Annex (34) to EP2/N9/B/19 3.
Application for Environmental
Permit dated 22 December 2006 (Application No.: AEP-262/2006) 許可證持有人於二○○六年十二月二十二日提交的許可証申請文件(申請書編號:AEP-262/2006) 4.
Environmental
Permit issued on 30 May 2007 (Permit No.: EP-262/2007) 於二○○七年五月三十日發出的環境許可證 (許可證編號:EP-262/2007) 5.
Application
Document for Variation of an Environmental Permit submitted by the Permit
Holder on 8 November 2007 (Application No.: VEP-243/2007) 許可證持有人於二○○七年十一月八日提交的更改環境許可證申請文件(申請書編號:VEP-243/2007) |
|||
|
|
|
|
||
|
Application No. 申請編號 |
Date of Application 申請日期 |
List of Amendments Incorporated into
Environmental Permit 已包含在環境許可證內的修訂項目 |
Date of Amendments 修訂日期 |
|
VEP- 243/2007 |
8 November 2007 2007年11月8日 |
1)
Vary
Conditions 1.7, 2.5 and 3.6 in Part C 2)
Vary
Figure 6 in Part C |
2007年11月 30 日 |
|
30 November 2007 |
|
|
|
Date 日期 |
|
(Simon
Y. M. HUI) Principal
Environmental Protection Officer for
Director of Environmental Protection 環境保護署署長 (首席環境保護主任 許一鳴代行) |
PART B (DESCRIPTION OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of
the designated project mentioned in Part A of this environmental permit
(hereinafter referred to as “the Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
|
Title of Designated Project 指定工程項目的名稱 |
Permanent Aviation Fuel Facility [This designated project is
hereinafter referred to as “the Project”]. 永久航空煤油設備 [本指定工程項目下稱“工程項目”] 。 |
|
Nature of Designated Project 指定工程項目的性質 |
A permanent aviation fuel facility which includes : -
a storage and transfer of oil facility with a storage
capacity of not less than 1,000 tonnes; and -
a submarine oil pipeline. 一所永久航空煤油設備,包括 : -
貯存量不少於1,000公噸的油類貯存和輸送設施﹔和
|
|
Location of Designated Project 指定工程項目的地點 |
1.
Tuen Mun Area 38 for locating of aviation fuel
storage tank farm; and 2.
Marine area between Tuen Mun Area 38 and Sha
Chau for laying of sub-sea fuel pipelines. The location of the
Project is shown in Figure 1 and Figure 2 of this Permit. 1.
航空煤油儲存油庫處於屯門第38區;和 2.
海底輸油管敷設於屯門第38區與沙洲之間的海域。 |
|
Scale and
Scope of Designated Project |
The Project is to construct and operate a
permanent aviation fuel facility with the following major elements : 1.
a
jetty of two berths to accommodate vessels with capacity up to 80,000 dwt; 2.
a
tank farm, covering an site area of about 6.75ha, with gross fuel tankage
capacity not more than 264,000 m3 on commissioning stage and not
more than 388,000 m3 on final stage; and 3.
a
twin sub-sea pipelines with length of about 4.8km and diameter of about 500mm
to transfer aviation fuel. 工程項目為建造及營辦一所永久航空煤油設備,其主要設施包括: 1.
能容納達80,000載重噸航空煤油運油船的雙泊位碼頭; 2.
總儲油容量於開始階段不多於264,000立方米和最終階段不多於388,000立方米,及工地約6.75公頃的航空煤油儲存油庫;和 3.
長約4.8公里及直徑約500毫米的雙管道每底油管,以輸送航空煤油。 |
1. 一般條件
1.1 許可證持有人及任何從事工程項目的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反環境影響評估條例 (第499章) 的規定,而當局可根據條例採取適當行動。
1.2 許可證持有人須經常確保完全符合現行法例的規定,包括但不限於噪音管制條例 (第400章);空氣污染管制條例 (第311章);水污染管制條例 (第358章);海上傾倒物料條例 (第466章);以及廢物處置條例 (第354章)。本許可證本身不會就根據任何法例提起的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3 許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件或本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地 / 辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4 許可證持有人須把本許可證的一份複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5 許可證持有人須在有關工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證 (包括任何經修訂的許可證) 的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的各處相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。
1.6 許可證持有人須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7 許可證持有人須確保工程項目的設計、建造及營辦,按照下述資料及措施辦理:核准環評報告 (登記冊編號:AEIAR-107/2007)、環境許可證申請書 (申請書編號:AEP-262/2006) 及更改環境許可證申請文件(申請書編號:VEP-243/2007) 所說明的資料及各項建議;登記冊內的其他相關文件;本許可證所說明的資料及緩解措施;根據本許可證內載的條件須向署長存放或獲署長批准的提交文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或默示修訂。
1.8 所有按本許可證規定存放的文件,須在接獲署長的意見 (如有者) 後