Site Inspection Summary

 

Inspection Information

Date:

2 March 2006

Time:

14:30

Site:

Tseung Kwan O Area 137

Inspection No.:

23

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow up Observations

 

 

1.

Fugitive dust was observed during transferring and dumping of waste/materials. Haul road appeared dry and fugitive dust was observed. The Contractor was reminded to provide sufficient water spraying.

 

 

2.

Maintenance of equipment was not observed and contaminated soil had been removed.

 

 

3.

Rubbish inside catchpits along haul road in Area B2 had been cleared.

 

 

4.

As advised by the Contractor the Water Discharge License had yet applied and the Contractor was reminded to provide a drainage plan for the site as soon as possible.

 

 

 

 

 

 

 

New Observation

 

 

5.

The Construction of chemical waste store was in progress. The Contractor was also reminded to provide drip tray to all chemical drums and buckets.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

-          Nullah inside the site was filled with dumped construction waste. The nullah was not in use and had already been blocked up by the adjacent CWSF. The Contractor agreed to clear the construction waste as soon as possible and provide bunding along the site boundary to prevent runoff during wet season.

 

 

 

 


Site Inspection Summary

 

Inspection Information

Date:

6 March 2006

Time:

15:00

Site:

Tseung Kwan O Area 137

Inspection No.:

25

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow up Observations

 

 

1.

Haul road appeared sufficiently wet. However, fugitive dust was observed during sorting of materials. The Contractor agreed to provide manual spraying during sorting activities and increase the water spraying frequency along haul road.

 

 

2.

The chemical waste store was still under construction.

 

 

3.

Nullah was filled with waste. The Contractor agreed to remove all rubbish from the nullah by April 2006.

 

 

4.

As advised by the Contractor the Water Discharge License had yet applied and the Contractor was reminded to provide a drainage plan for the site as soon as possible.

 

 

 

 

 

 

 

New Observation

 

 

5.

Small pieces of rubbish were observed inside the catchpit at Area B2. The Contractor was reminded to clear the rubbish.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

-          Nullah inside the site was filled with dumped construction waste. The Contractor agreed to clear the construction waste by April 2006.

 

 


Site Inspection Summary

 

Inspection Information

Date:

16 March 2006

Time:

14:15

Site:

Tseung Kwan O Area 137

Inspection No.:

27

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow up Observations

 

 

1.

Fugitive dust was observed along haul road at area B2 and during sorting and dumping activities. The Contractor agreed to provide water spraying and sprinklers at tipping hall and increase the water spraying frequency along haul road.

 

 

2.

The chemical waste store was yet provided. The Contractor agreed to provide by 24 March 2006.

 

 

3.

Nullah was filled with waste. The Contractor agreed to remove all rubbish from the nullah or provide temporary drainage diversion by April 2006.

 

 

4.

As advised by the Contractor the Water Discharge License had yet applied and the drainage plan had yet submitted. The Contractor agreed to provide the drainage plan by 20 March 2006.

 

 

5.

Clearing of rubbish and mud for the catchpit at Area B2 was observed.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Date:

23 March 2006

Time:

14:30

Site:

Tseung Kwan O Area 137

Inspection No.:

30

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow up Observations

 

 

1.

Haul road was sufficiently wet, but fugitive dust was observed during sorting and dumping of waste. The Contractor was reminded to provide water spraying for sorting and dumping activities as soon as possible.

 

 

2.

The chemical waste store was yet provided. The Contractor was reminded to provide a chemical waste store as soon as possible.

 

 

3.

Clearing of waste from the nullah was in progress. The Contractor agreed to remove all rubbish from the nullah or provide temporary drainage diversion by April 2006.

 

 

4.

As advised by the Contractor the Water Discharge License had yet applied and the drainage plan had yet submitted. The Contractor was reminded to provide the drainage plan for review as soon as possible.

 

 

 

 

 

 

 

New Observation

 

 

5.

Water ponding was found outside the site office at Area B1. The Contractor was reminded to fill the area or remove the water regularly.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Date:

30 March 2006

Time:

15:00

Site:

Tseung Kwan O Area 137

Inspection No.:

32

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow up Observations

 

 

1.

Fugitive dust was observed during transferring and dumping of waste. The Contractor was reminded to provide water spraying for sorting and dumping activities as soon as possible.

 

 

2.

The construction of chemical waste store was in progress. The Contractor was reminded to provide labels to the chemical waste store and all chemical waste drums.

 

 

3.

Clearing of waste from the nullah was in progress. The Contractor agreed to remove all rubbish from the nullah by 7 April 2006.

 

 

4.

The drainage plan had been submitted and is under review by the ET. The Contractor was advised to apply for the Water Discharge License as soon as possible.

 

 

5.

Water ponding outside the site office at Area B1 had been removed.

 

 

 

 

 

 

 

New Observations

 

 

6.

Oily water was found accumulated inside the drip tray next to the tipping hall at Area A and waste oil was found in an open bucket. The Contractor was reminded to remove oily water in drip tray and store all chemical waste in the chemical waste store.

 

 

7.

Rubbish was found scattered around the container office in Area A. The Contractor was reminded to improve housekeeping on site.

 

 

8.

Stagnant water was found inside the nullah at Area A.  The Contractor was reminded to clear the stagnant water regularly to prevent mosquitoes breeding.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil