Interim Notifications of
Environmental Quality Limits Exceedances
Project |
Contract No. CV/2004/13 Construction
Waste Sorting Facilities at Tseung Kwan O Area 137
and Tuen Mun Area 38 |
Sampling Date |
13 March 2006 |
Time |
09:00 – 09:00 |
Monitoring Location |
TKO1 |
Parameter |
24-hr TSP |
Action / Limit Level |
260 / 260 µg/m3 |
Measured Level |
311.5 µg/m3 |
Major Construction Dust Source(s) During
Measurement |
·
Major dust source was fugitive dust
from dumping and sorting of waste inside the site; ·
Other dust source was from vehicles
movement on the haul road leading to Area A. |
Observed Construction Activities from Other
Construction Site |
·
Vehicles movement and dumping
activities inside the adjacent CWSF. |
Possible reason for Action / Limit Level
Non-compliance |
·
Fugitive dust generated from the
sorting activities inside the CWSF and from vehicle movement on the haul road
leading to Area A. |
Actions taken / to be taken |
·
Fugitive dust was observed during
the site inspections on 6 and 16 March 2006 at dumping and sorting area, the
Contractor was reminded to review the frequency of the water dampening
programme. ·
Water truck had been deployed 4 times for dampening the haul road, yet
frequency had to be increased; ·
ET continue to monitor the
24-hour TSP; ·
Additional monitoring was
required to be conducted if the subsequent monitoring result exceeds the A/L
Level. |
ET Advice |
·
Ensure all sorting activities
and dumping areas are sufficiently dampened; ·
Provide water sprinklers to haul
road, dumping areas and sorting area for water spraying; ·
Implement proper mitigation
measures inside the sorting facilities; ·
Ensure the area near the site
exit and all the haul roads to be sufficiently wet; ·
Advise the dump truck drivers to
travel on the dampened haul roads. |
Remarks |
·
Nil |
Interim Notifications of
Environmental Quality Limits Exceedances
Project |
Contract No. CV/2004/13 Construction
Waste Sorting Facilities at Tseung Kwan O Area 137
and Tuen Mun Area 38 |
Sampling Date |
24 March 2006 |
Time |
09:00 – 09:00 |
Monitoring Location |
TKO1 |
Parameter |
24-hr TSP |
Action / Limit Level |
260 / 260 µg/m3 |
Measured Level |
1358.4 µg/m3 |
Major Construction Dust Source(s) During
Measurement |
·
Major dust source was fugitive
dust from vehicles movement along the haul road between Area A and Area B2; ·
Other dust source was from
dumping and sorting of waste inside the site. |
Observed Construction Activities from Other Construction
Site |
·
Vehicles movement and excavation
activities on the stockpile inside the adjacent CWSF. |
Possible reason for Action / Limit Level
Non-compliance |
·
Exceedance was considered mainly due to the dust emission from
vehicles movement along haul road and from dumping and sorting activities in
Area A; ·
Excavation of stockpile in the
adjacent CWSF had minor contribution to the exceedance. |
Actions taken / to be taken |
·
Fugitive dust was observed
during the site inspections on 23 and 30 March 2006 at dumping and sorting
area, the Contractor was reminded to review the frequency of the water
dampening programme. ·
Water truck had been deployed 4 times for dampening the haul road, yet
frequency had to be increased; ·
ET continue to monitor the
24-hour TSP; ·
Additional monitoring was
required to be conducted if the subsequent monitoring result exceeds the A/L
Level. |
ET Advice |
·
Ensure all sorting activities
and dumping areas are sufficiently dampened; ·
Provide water sprinklers to haul
road, dumping areas and sorting area for water spraying; ·
Implement proper mitigation
measures inside the sorting facilities; ·
Ensure all the haul roads to be
sufficiently wet; ·
Advise the dump truck drivers to
travel on the dampened haul roads. |
Remarks |
·
The
monitoring station TKO1 had been relocated on 23 March 2006 and the first
monitoring event at the new location was conducted on 24 March 2006. |
Interim Notifications of
Environmental Quality Limits Exceedances
Project |
Contract No. CV/2004/13 Construction
Waste Sorting Facilities at Tseung Kwan O Area 137
and Tuen Mun Area 38 |
Sampling Date |
30 March 2006 |
Time |
09:00 – 09:00 |
Monitoring Location |
TKO1 |
Parameter |
24-hr TSP |
Action / Limit Level |
260 / 260 µg/m3 |
Measured Level |
806.6 µg/m3 |
Major Construction Dust Source(s) During
Measurement |
·
Major dust source was fugitive
dust from vehicles movement along the haul road between Area A and Area B2; ·
Other dust source was from
dumping and sorting of waste inside the site. |
Observed Construction Activities from Other
Construction Site |
·
Vehicles movement and excavation
activities on the stockpile inside the adjacent CWSF. |
Possible reason for Action / Limit Level
Non-compliance |
·
Exceedance was considered mainly due to the dust emission from
vehicles movement along haul road and from dumping and sorting activities in
Area A. |
Actions taken / to be taken |
·
Fugitive dust was observed
during the site inspection on 30 March 2006 along haul road and at dumping
and sorting area, the Contractor was reminded to review the frequency of the
water dampening programme; ·
Water truck had been deployed 4 times for dampening the haul road, yet
frequency had to be increased; ·
ET continue to monitor the
24-hour TSP; ·
Additional monitoring for 24-hour
TSP had been scheduled to 6 April 2006. |
ET Advice |
·
Ensure all sorting activities
and dumping areas are sufficiently dampened; ·
Provide water sprinklers to haul
road, dumping areas and sorting area for water spraying; ·
Implement proper mitigation
measures inside the sorting facilities; ·
Ensure all the haul roads to be
sufficiently wet; ·
Advise the dump truck drivers to
travel on the dampened haul roads. |
Remarks |
·
Nil |