1.1
This is the sixth Quarterly Environmental Monitoring and
Audit (EM&A) Summary Report for the Temporary Construction Waste Sorting
Facility at Tseung Kwan O Area 137 (the Project).
This report presents a summary of the environmental monitoring and auditing
works carried out by the ET for the Project for the period from February 2007 to
April 2007.
Project Organization and Contacts of Key
Management
1.2
The project organization is shown in Appendix A. The key
personnel contact names and numbers are summarised in Table 1.1
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
CEDD |
Engineer |
Mr. Lawrence Ng |
2762 5582 |
2714 0113 |
IC(E) (MateriaLab) |
IC(E) |
Mr. Joseph Poon |
2450 8238 |
2450 6138 |
Contractor (Paul Y -CREC(HK) JV) |
Project
Manager |
Mr.
Gene Cheung |
2831 8282 |
2623 9426 |
Project Engineer
(TKO137) |
Mr. H G Gao |
6501 4586 |
-- |
|
ET (MEMCL) |
ET Leader |
Mr. Y T Tang |
3105 8537 |
2891 0305 |
1.3
The construction phase under Contract CV/2004/13 – Temporary
Construction Waste Sorting Facility at Tseung Kwan O
Area 137 commenced on
l
Operation
of Construction Waste Sorting Facilities (CWSF) by mechanical sorting plant;
l
Surface
paving for inland haul road at Portion A;
l
Water pipe line linking Portion B1 and Portion A.
l
Drainage
works at Portion A;
l
Enhanced
dust suppression system at Portion A;
l
Placing
hard core paving for haul road at Portion A; and
l
Levelling of haul road paving at Portion B1.
1.4
The general layout plan of the Project sites showing the
contract areas are shown in Figure 1.1.
1.5
The construction programme is provided in Appendix B.