12.1.1 This Section
reviews the potential environmental issues associated with land contamination,
and was developed as a result of the desktop research and limited site
assessments performed for this Study. The Section also previews areas for
further assessment in subsequent stages of the study where appropriate. Annex
I comprises a Contamination Assessment Plan (CAP) for the NLDFS EIA Study.
12.1.2 The main
objectives of the NLDFS EIA Study were detailed in Section 1.4.3 above, and land contamination assessment is one of
the sub-tasks outlined in the Study Brief.
The main goal of the land contamination investigation is, therefore, to
address the following:
·
provision of a clear account on the past land use
history including accident records, as far as possible, and the present uses of
the land in question;
·
contamination characterisation to identify the
quality, quantity and extent of the contaminated site (surface area, soil
depth, ground/sea water movements);
·
evaluation of potential impacts of contamination and
selection of appropriate cleanup technologies, and
·
submission of a site cleanup management plan, as
appropriate, to seek approval from the Director of Environmental Protection, in
order to restore the site.
12.1.3
In
terms of land uses identified within the NLDFS EIA Study Area, a number of properties have been identified
with current or historical land uses that may be considered land contaminating
uses, and an evaluation of potential impacts is presented below. An existing shipyard, Cheoy Lee Shipyards,
Ltd. (CLS), to be decommissioned, is located within the Study Area for the
NLDFS. Consequently, the NLDFS EIA will comprise Schedule 3 level coverage of
the environmental impacts arising from shipyard decommissioning, although access
to undertake site investigation works at the shipyard site was not available as
part of the Schedule 3 NLDFS EIA, due to its present operation and private
ownership. Additionally, the
decommissioning of a shipyard comprises a Designated Project under Schedule 2
of the EIAO. Thus a separate and
subsequent EIA Study will be commissioned by CED before the decommissioning of
the shipyard occurs. This subsequent
decommissioning EIA, which, due to access requirements can only commence after
the shipyard site has become available, will include detailed site
investigation and formulation of appropriate methods and procedures, if
required, to decontaminate the shipyard site.
CED presently expect this decommissioning EIA to be completed and
submitted under the EIAO to DEP for approval in 2002. More importantly, this decommissioning EIA will need to be
approved under the EIAO, and an Environmental Permit issued by the DEP before
any decomissioning or construction work can commence in the shipyard area. In
order to provide quantitative information to the limited extent possible, a
preliminary sampling programme was conducted along a stream bed discharging
from the southeastern boundary of the shipyard site. The results are discussed in Section
12.6 below.
12.1.4 At this stage,
property access for site specific investigations for the CLS site in Penny’s
Bay has not been obtained, therefore, information on the potential land
contamination within the shipyard site was based upon on-site observations,
interviews with various site operators and regulatory personnel, and review of
available documentation, including previous study reports. As only limited soil sampling
and analysis has been conducted adjacent to the property boundary (see
discussion below), very little quantitative information regarding the
level of potential contamination of the shipyard site is available at this
stage. However, the evaluation of
impacts and selection of appropriate cleanup technologies of the Schedule 3
NLDFS EIA has been performed using standard and appropriate industry guidelines
and EPD-approved methodologies for the particular contaminating land uses
identified in this Study. CED have
committed more specific soil and groundwater sampling and analysis will be
performed at a later stage, when site access is available, and remediation
after the Schedule 2 decommissioning EIA will overcome any potential problems
and mitigate any contamination.
12.2.1 Assessments of
land contamination and the potential impacts are guided by the EPD's document
note Professional Persons Environmental Consultative Committee Practice Note
3/94 - Contaminated Land Assessment and
Remediation (ProPECC PN 3/94), the Technical Memorandum on Environmental Impact
Assessment Process (EIAO), and the 1999 Guidance Notes for Investigation and
Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards, and
Car Repair/Dismantling Workshops (Guidance Notes). In accordance with these documents, the assessment evaluation
should:
·
provide a clear and detailed account of the present
use of the land in question and the relevant past land use history, in relation
to possible land contamination;
·
identify those areas of potential contamination and
associated impacts, risks or hazards; and
·
as required, submit a plan to evaluate the actual
contamination conditions for soil and/or groundwater.
12.2.2 Under the ProPECC
PN 3/94 note and the Guidance Notes, and in the absence of any formal
legislation requiring cleanup of soil and groundwater contamination in Hong
Kong, the "Dutch Ministry of Housing, Planning and Environmental Soil and
Groundwater Standards” (the Dutch Guidelines) (1994) are used as reference
criteria by the EPD for the classification of contaminated materials. It should be noted that the Dutch
Guidelines, whilst widely recognised and generally applicable on a global
scale, are not enforceable standards in Hong Kong. In the Netherlands, the Dutch Guidelines were developed in the
specific case where the drinking water supply is sourced entirely from
groundwater. Hence, the Dutch
Guidelines are very strict in regard to some specific contaminants, but must be
viewed in the relative context of the Hong Kong situation.
12.2.3 Under the EIA
Ordinance, Annex 19: Guidelines for
Assessment of Other Impacts, consideration shall be given to a number of
potentially contaminating historical land uses, including oil installations,
shipyards/boatyards, car repairing and dismantling, power plants and gas
works. If these land uses are
identified, then the applicant is required to generate a Contamination
Assessment Plan (CAP). Annex I comprises a CAP for the NLDFS
EIA Study.
12.2.4 In this Section,
a review of the proposed development is provided with indications, as
appropriate to the level of assessment conducted, for any further
investigations that may be required.
12.3.1 Based upon the
generally remote and undeveloped locations that comprise the Study Area,
sensitive receivers to potential land contamination are identified as the
current land users (who are engaged in potentially land contaminating
activities), construction workers and future users of the site, including the
proposed Water Recreation Centre.
12.3.2
As detailed in Section 2
above, the developments include reclamation and development of a number of
areas including the Penny's
Bay reclamation which includes the broader Penny's Bay area.
12.3.3 The developments
in Penny’s Bay area will involve the construction and operation of PBRL, Road
P2, and the western section of the Chok Ko Won Link Road, and a Theme Park (Phase
III) Extension, with associated ancillary facilities and developments, existing and
reclaimed land. Some land-based
excavation and grading works will be required for the construction of the
railway and roadways. These projects
are of concern as there may be interphasing with any potentially contaminated
soil underlying the shipyard site, and hence the potential to impact sensitive
receivers.
12.4.1 The objective of
the current land contamination study is to identify and screen any concerns
with respect to potential soil and groundwater contamination for the proposed
NLDFS developments.
12.4.2 The following
methodology has been adopted in this land contamination study:
·
preliminary review of the current and historical land
uses to evaluate the likely level of potential for any soil and ground
contamination;
·
description of the likely nature of any potential
contamination, supplemented, where available, with specific quantitative data
from a limited sampling programme;
·
a preliminary review of potential environmental
impacts or health concerns arising as a result of the development or during
future use of the land, as a result of exposure to potentially contaminated
materials; and
·
overview of typical mitigation measures.
Reference Sources
12.4.3 During this study
reference to the following sources of information was made:
·
Outline
Development Plan (P1884/D2/D (21 January 2000);
·
Hong Kong
Ordinance Survey maps and North East Lantau Port Outline Zoning Plans (S/I-NELP/4,
February 1998) for the Study Area;
·
Draft
North-East Lantau Outline Zoning Plan (Ref:
S/I-NEL/5, dated 13 August 1999);
·
Hong Kong
Geological Survey Solid and Superficial
Geology Series, Map 10, Silver Mine Bay (1986);
·
selected
aerial photographs held at the Government Lands Department;
·
correspondence
with various Government Departments, including the EPD, EPD Local Control
Office (LCO, Urban West & Islands), Planning Department, and Civil
Engineering Department (CED);
·
Lantau Port & Western Harbour
Development Studies, Addendum C, Cheoy Lee Shipyard Reprovisioning, Final Report, April 1993;
·
reviewing
existing data from ERM audit reports performed previously for CLP Power, and
performing site visits and interviewing site management at the Penny’s Bay Gas Turbine Plant (GTP);
·
performing
several site visits and interviewing site management at the CLS site; and
·
subsequently
performing a limited soil sampling and analysis exercise at the CLS site
boundary.
12.4.4 It should be
noted that a separate CAP was generated as an earlier part of the NLDFS EIA (Annex I). However, no site investigation works could be conducted due to
the CLS site access limitations. This
CAP (Annex I) may be reviewed in
conjunction with the future CLS site Schedule 2 EIA.
12.4.5 Selected
stereoscopic pairs of aerial photographs were reviewed for specific information
on the site developments and land use. Table 12.4a outlines selected general
aerial photographs viewed for the northern and eastern portions of Lantau and
the Study Area. Land uses are presented in Figure
12.4a
.
Table
12.4a - Aerial Photograph Review - General NLDFS Area
Location
|
Photos
|
Date
|
North Lantau Area
|
CN18991, CN18992
|
1 November 1997 (10,000 ft)
|
North Lantau Area
|
2614, 2615
|
13 December 1964 (12,500 ft)
|
Siu Ho Wan Sewage and Water Treatment Works
|
CN20495, CN20496, CN20497
|
20 July 1998 (3,000 ft)
|
Siu Ho Wan Pier to Ta Pang Po Jetty
|
CN20474, CN20475
|
July 1993 (3,000 ft)
|
Yiu Lan Facilities at To Kau Wan (established in
1993); Yam O
|
CN20467, CN20468, CN20469
CN20474, CN20475
|
20 July 1998 (3,000 ft)
July 1993 (3,000 ft)
|
Tso Wan and Fa Peng Piers
|
A48858, A48859
|
November 1998
|
12.4.6 However, the
primary concern for potential land contamination was noted to be land use
changes in the Penny’s Bay area, where the CLS site is located. Additional aerial photographs reviewed, with
specific details for this location, are presented in Table 12.4b.
Table 12.4b - Aerial Photograph Review - Penny’s Bay Area
Date
|
Photographs
|
Height
|
Key Issues
|
7
Nov 1998
|
A48861
/ A48862
A48932
/ A 48933 A48934
|
5,000
ft
|
No
changes from 1997; current CLS and neighbouring CLP Penny's Bay Gas
Turbine Plant (GTP) operations noted.
|
15
Aug 1997
10 Sept 1997
|
A45575
/ A45576 A45577
A46039
/ A46040
|
2,000
ft
4,000
ft
|
"Current"
refuse pit noticeable in SE corner of property, with evidence of burning of
waste.
|
24
Apr 1996
12
Oct 1996
|
A42362
/ A42361
CN
14753 / CN14752
|
2,000
ft
5,000
ft
|
Former,
smaller refuse pit #3 noted at SE corner of site in April 1996, near edge of
seawall; Pit #3 no longer visible in October 1996, when "current"
refuse pit excavated.
|
23
Jun 1993
|
A34904
/ A34903
|
2,500
ft
|
CLP
GTP is built. Small ditch or pit (#2) noted along SE seawall, apparently for
refuse disposal.
|
12
May 1992
|
A31057
/ A31058 (oblique photos)
|
6,000
ft
|
Above
ground storage tanks (ASTs) installed at neighbouring CLP GTP as construction
continues; some storage of construction materials in vacant SE portions of
the CLS site.
|
24
Oct 1991
|
A28671
/ A28672 A28673 / A28674
|
2,000
ft
|
Concrete
batching activities at the lot on southeast corner of site. CLP Penny's
Bay GTP site under construction; Evidence of possible refuse disposal or surface pile of burned
refuse in SE portion of site.
|
6
Dec 1990
|
A24941
/ A24942
|
4,000
ft
|
Construction
in Progress at CLP Penny’s Bay GTP. Adjacent portions of SE corner of CLS
site used for quarry and sand/gravel batching plant. Additional expansion of
hull and mould storage area in SE portion of site.
|
6
Dec 1985
|
A03956
/ A03957
|
4,000
ft
|
First
evidence of storage of ship hulls and moulds along SE portion of site.
Neighbouring CLP site still vacant.
|
22
Nov 1984
|
57254
/ 57255
|
6,000
ft
|
Most
of SE portion of site area still vacant. Slipways built into seawall at CLS
site.
|
7
Dec 1978
|
23958
/ 23959
|
4,000
ft
|
All
reclamation work appears completed, with increased number of CLS buildings
and development of seawall. Quarry activity and piles of sand/gravel along SE
portion; neighbouring CLP GTP site vacant and undeveloped. Evidence of refuse
dumping at edge of reclamation on SE portion of site (in former stream
drainage area).
|
13
Dec 1964
|
2614
/ 2615
|
12,500
ft
|
Most
of seawall and small reclamation at head of Penny’s Bay completed; Increased
number of warehouse buildings indicates CLS business operations underway.
|
25
Jan 1963
|
4663
/ 4664
|
3,900
ft
|
Most
of Penny's Bay area is not reclaimed; original shoreline exists, however, at
least six CLS warehouse buildings noted at head of Bay on small reclaimed
portion.
|
22
Jan 1962
|
F42/642-97
F42/642-96
|
N/A
|
Construction
of seawall jetty at very head of Penny’s Bay, with marine reclamation/filling
underway. New warehouse building in
place.
|
1954
|
V81A/RAF/553-72
V81A/RAF/553-73
|
N/A
|
No
reclamation noted. Original Penny’s Bay shoreline is present and appears
untouched.
|
Note:
No aerial photos available for 1995-94, 1989-85, 1983-80, 1975, 1970, 1969,
1968, 1967, 1964
|
Potential Sources of Impact
12.5.1 The sources of
impacts are the potentially contaminating land uses within the Study Area.
12.5.2
The
CLP Power Penny’s Bay gas turbine plant (GTP) is located at the eastern side of
Penny's Bay. This GTP was commissioned
in 1992 with a generating capacity of 300 MW and serves as a peak load and
emergency back-up facility for the HKIA, Tung Chung and the future developments
along NLH and the Study Area. A smaller
electricity substation, near Sham Shui Kok, is part of CLP Power's electricity
distribution system and is directly connected to the Penny's Bay GTP. A series of power lines run from the
substation to Discovery Bay and Tung Chung.
However, the CLP operations are not judged to be a serious concern (see
further discussion in Section 12.5.2
below).
12.5.3
The
Yiu Lian Shipyard, with a site area of approximately 0.8 ha, plus two large
floating docks (Floating Dock No. 3 of 252 m and No.5 of 82 m length,
respectively), is located at To Kau Wan on the northern Lantau coastline. The
main operation of this facility is ship repairing and maintenance, which covers
container vessels, general cargo vessels, bulk carriers, tankers and passenger
vessels. The Government Lease under
which the shipyard is held expires in 2008.
However, this facility is not judged as a major concern as almost all of
the operational activity is performed on the floating docks offshore, and no
aerial photo review or inspection has indicated significant shipyard activities
on the land based portion of the site.
12.5.4
The
Hong Kong Salvage and Towage Company (HKST) currently moors their crane barge
"Proteus 1" north of Yam O.
The 350 tonne crane barge is used for servicing HKST's fleet of tugs as
well as being available for lease to undertake heavy lifting works around Hong
Kong waters. However, due to the
activity taking place offshore, this is again not judged to be a major concern
for potential land contamination.
12.5.5
The
log pond/bay area located along the northern shore of Yam O Bay is operated
under short term tenancy, and the Government can give three months notice for
the operators to vacate. This facility
makes use of shallow sea water in sheltered Yam O Bay to store large logs until
required for use in other areas. The facility consists of piles driven into the
sea bed in a series of storage bays. It
is our understanding that no chemical pretreatment is performed on the logs,
and there is no major land contamination concern.
12.5.6 Therefore,
primary land use of concern with regard to potential land contamination
identified for the Study Area is the shipyard and associated maintenance
activities at the CLS site, located on the north and eastern shores of Penny’s
Bay. The main operations of the CLS
site are constructing and repairing glass-reinforced plastic (GRP) and
fibreglass yachts and boats, and steel hulled ships up to approximately 80 m in
length. Such related activities include
metal and foundry works, some vehicle maintenance work, and waste disposal
activities, and each of these activities has the potential of causing land
contamination (Figure 12.5a). Shipyards and related activities have been
identified by the EPD’s ProPECC PN 3/94 note and Guidance Notes (1999), as land
uses with the potential for contamination, and specific guidelines have been
developed for the assessment and remediaton of such industries.
12.5.7 The typical
contaminants associated with historic shipyard activities, which are known to
occur at CLS, are summarised in Table
12.5a.
Table 12.5a - Potential Contaminants Associated with Historical Shipyard
Land Use
Historical Use
|
Potential Site Contaminants
|
Comments
|
Ship
hull and structural woodworking operations
|
resins,
thinners, wood preservatives and treatment chemicals (possibly including such
as creosote, arsenic trioxide, and chlorophenols), paints
|
·
possible localised spillages
|
Open
scrap and equipment yard, metal foundries, metal workshops
|
heavy
metals and grinding swarf (lead, cadmium, copper, nickel, zinc, TBT) and
cutting oils, possible acids and paints, solvents, and electroplating
effluents
|
·
possible localised spillages
·
fuel storage tanks
|
Ship
and hull construction, maintenance, repair and machining works
|
petroleum
fuel storage, including benzene, toluene, ethyl benzene and xylene (BTEX),
polycyclic aromatic hydrocarbons (PAHs), acids, solvents and degreasants,
antifouling paints (TBT), scrap metals and grinding swarf, asbestos,
anticorrosive compounds
|
·
spillages from
maintenance and dismantling equipment
·
grinding swarf and sandblasting discharges
·
grease and oils on slipways
·
localised areas of contamination
·
possible presence of storage tanks
|
Miscellaneous
chemical storage yards and areas
|
fuel
and chemical storage, solvents, thinner, resins, paints and pigments, PAHs
|
·
localised or general spillage
·
open storage areas
|
Waste
disposal / burn pits
|
residual
amounts of resins, paints, thinners or solvents, fuels, wood preservatives
and other treatment chemicals, heavy metals
|
·
uncontrolled burning activities
·
localised areas of contamination
|
12.5.8 A description of
general hazardous properties of compounds which are or may have been used or
stored in the various areas described is presented in Table 12.5b below.
Localised spillages of any of these potential contaminants may impact
the surrounding soil or groundwater, and may cause negative impacts to
sensitive receivers, including humans involved in future construction
activities.
Table 12.5b - General Properties of Hazardous
Substances Potentially Found in Shipyards
Typical Material
|
General Hazardous Properties
|
Petroleum
hydrocarbons and BTEX
|
·
can be toxic by inhalation, ingestion and contact
·
concentrations may be flammable
|
Oils,
oily wastes
|
·
can be toxic by contact or ingestion
·
concentrations may be flammable
|
Thinners,
organic solvents, degreasants, and wood preservatives
|
·
toxic by contact, inhalation and ingestion
·
concentrations may be flammable
|
Heavy
metals (including arsenic, mercury, copper, chromium, lead, zinc, and TBT)
|
·
can be toxic by ingestion and contact
·
most are toxic to fish, plants, and marine plants
(copper)
·
specific precautions may be required in relation to
monitoring and dust control in site formation works
|
Acids
and alkalis
|
·
toxic and harmful by contact
·
corrosive to metal, concrete
|
Polycyclic
aromatic hydrocarbons (PAHs)
|
·
toxic by contact and ingestion
|
Potential
Impacts
12.5.9 The potential
impacts from contaminated soil and groundwater are identified as follows:
·
health risks to site workers;
·
disposal of contaminated soil, where required;
·
contaminated groundwater disposal, where required; and
·
potential health risks to future users of the site,
including the Water Recreation Centre.
Health Risk to Site Workers
12.5.10Site construction
workers may become exposed to contaminated soils and groundwater during earth
moving operations and the construction of the roadway foundations or any
underground services. The main exposure
routes for site construction workers is direct ingestion of contaminated
materials, either through poor hygiene and eating or smoking on site, or
through direct contact with potentially toxic or harmful contaminants in soils
or sediments.
Disposal of Contaminated Soils
12.5.11In the event that
any contaminated soils are identified during ground development works or
further environmental investigations, they may require disposal as part of the
construction programme. Otherwise,
prior agreement will need to be reached with EPD to ensure that these materials
are properly mitigated or dealt with appropriately, i.e. as part of the
remediation recommended under the Schedule 2 EIA of the CLS site. It should be noted that landfill space is
seriously limited in Hong Kong, therefore landfill disposal of contaminated
soil should only be considered as a last resort. Any contaminated soils which are excavated may be reused as fill
after treatment/remediation or be disposed of at an appropriate facility which
is licensed to accept 'contaminated' soils as a last resort if other options
fail. The actual type(s) and
concentration of contaminants will determine the actual disposal requirement,
following agreement of the proper disposal option with the Waste Facilities
Management Group of the EPD.
Contaminated Groundwater Disposal
12.5.12Where excavations
take place below the water table in areas identified as being contaminated,
there will be a need to dewater the operations for safety and construction
purposes. Where dewatering takes place
through layers of contaminated material or where any contaminated soil is being
excavated and/or dewatered, the water may become contaminated, requiring
appropriate handling and disposal.
Depending on the level of contamination encountered, and subject to the
agreement of the EPD, groundwater will need to be remediated, or more likely
disposed of in an appropriate manner and to ensure compliance with the Water
Pollution Control Ordinance (WPCO).
Potential Health Risks to Future Users of the
Site
12.5.13No contaminated
soil is likely to remain in situ
after remediation to the agreed upon clean up standard, therefore, during the
operational phase of the works, there is considered no potential for impact
associated with any contaminated soil at the site following development of the
PBRL, P2 Road or the Chok Ko Wan Link Road.
In addition, maintenance workers or workers who may be commissioned to
perform maintenance or alterations to the above road or railways at a later
stage will, therefore, not come into contact with any such materials. However, as mentioned above, the CLS
shipyard site will be subject to a separate Schedule 2 EIA for decommissioning,
and all contamination will be remediated or effectively mitigated so as to
prevent any potential negative impact.
Where there is any question of the potential for any residual contamination
to migrate or impact to the proposed artificial lake at the Water Recreation
Centre, it should be noted that the artificial lake will be constructed
offshore and away from the shipyard site, by first dredging the sediment from
the relevant part of Penny’s Bay, followed by placement of an HDPE liner. This liner, whilst designed to hold the
freshwater in, will also mitigate against subsurface contaminant infiltration
assuming the liner integrity is maintained.
The site will be remediated, under the direction of the subsequent
Schedule CLS EIA, to the extent that any former CLS site land contamination
will not adversely affect the lake.
Review of Historic and Current Land Uses
12.6.1 A review of
historical maps and selected historical aerial photos in the NLDFS Area
indicates that the majority of the proposed development of concern will be on
land which has primarily been previously undeveloped, or recently reclaimed
land developed for the CLS shipyard use or the CLP Penny’s Bay GTP. There is little available information to
indicate that there has been any other major industrial usage of concern within
the Study Area. As described above,
based upon past use history and aerial photo review, the log ponds at Yam O and
the floating docks at the Yiu
Lian Shipyard are not judged to be a concern for any potential land
contamination.
Historical Land Uses
12.6.2 The Penny's Bay
area was developed by reclamation in the late 1960s to early 1970s. The main operations at the CLS facility are
and have always been constructing and repairing ships, including steel hulled,
fibreglass, and glass-reinforced plastic (GRP) vessels. Based on discussions with site management,
the main operations appear to have changed little since the initial development
of the property in 1960 and growth through the 1960s. The operations and number of workers employed have always been
based on market demand.
12.6.3 According to CLS
site management, there have been no other uses of the property throughout its
history except for ship building and repair operations. The plating operations are no longer used
(parts are now reportedly purchased from outside suppliers) and the practice of
using tributyl tin in antifouling paints and compounds was terminated in 1995
and is no longer carried out at the site.
Evaluation of Impacts
12.6.4 As a result of
the fact that there has been very little industrial usage of land within the
Study Area other than the CLP GTP and the CLS site, overall historical
contamination concerns are considered to be limited.
12.6.5 There is no
expected environmental impact from the CLP facility. Based upon interviews with CLP Power Hong Kong Limited
management, and the EIA Study Team’s understanding of the results of two
previous environmental due diligence audits performed at the Penny’s Bay GTP in
1996 and 1998 as part of the CLP Power Generation Business Group’s
environmental policy, the GTP facility complies with all appropriate
legislation and does not have any negative environmental issues in relation to
land contamination. There have been no
spill incidents or accidents reported at the site.
12.6.6 The main focus of
potential concern, therefore, relates to the CLS site, which will be
decommissioned. The contamination
concerns would only arise if any historical leakages or spillages have migrated
through to areas where works or workers might interphase with the soil. However, correspondence with various
government authorities revealed that there is generally little information
available on the site relating to land contamination.
12.6.7 The EPD Local
Control Office (Urban West and Islands) indicated in correspondence (EP 742/974/0024 I) that, in relation to
the CLS site, their office had:
·
no record of contamination incident;
·
no record of known spillage accident, uncontrolled or
illegal dumping;
·
no record of illegal dumping site (flytipping
blackspot); and
·
no record of Water Pollution Control Ordinance (WPCO)
and Waste Disposal Ordinance (WDO) prosecution.
12.6.8 The LCO also
indicated that spent lubricating oil, spent solvent, and waste fuel oil were
stored at the CLS site. This was
confirmed by the EIA Study Team’s observation.
12.6.9 Review of the
Chemical Waste Producer Registration (WPN
3881-973-C2269-03, dated 15 September 1994) indicated that the CLS facility
may generate waste spent solvents and lubricating oils.
12.6.10January 1999
correspondence ((17) in FSD/PG43/790/77
(XIV)) from the Fire Services Department (FSD) indicated that there was no
Dangerous Goods (DG) License for the CLS site, and that there was no occurrence
of fire or chemical spillage incident in the last three years.
12.6.11The CLS site was
noted to maintain a Discharge License (EP742/973/0001
I, dated 25 September 1997) under the WPCO, for discharge of effluent from
the canteen and toilets, electroplating workshop, and maintenance of
vessels. Treatment facilities listed
under the Discharge License include the following: a septic tank and soakaway
system; pH adjustment, heavy metal removal and cyanide destruction; and
suspended solid and oil and grease removal.
Current Land Uses
12.6.12The CLS facility
is located on Lot 22 in D.D. 356, and occupies an area of 18.7 ha. Other than
the neighbouring Penny's Bay Gas Turbine Plant operated by CLP Power, there is
no other development in the area.
District Lands Office (Islands) confirmed that the adjacent Chok Ko Wan
Village has been vacated after the clearance exercise conducted by DLO/ Tsuen
Wan in January 1998, under the project of Lantau Port Development Phase I (DLO=s Ref. (14) in DLO/IS 26/41 Pt.9 IS
dated 28 November 1998). Access to
the CLS site is currently by boat only.
12.6.13The main
operations at the CLS facility are constructing and repairing ships, including
steel hulled, fibreglass, and glass-reinforced plastic (GRP) vessels. The site layout (Figure 12.5a) presently includes a number of wet and dry dock
berths, workshops and storage areas.
There are approximately two dozen buildings at the site, including:
·
a canteen and small dormitory;
·
dangerous goods storage building;
·
resins storage room (refrigerated);
·
metal foundry building;
·
two metal workshops;
·
two steel fabrication shops;
·
one mould design workshop;
·
three moulding workshops;
·
three storage warehouses;
·
an office and storage building;
·
vehicle maintenance workshop and area;
·
saw mill;
·
woodworking shop;
·
two boat building shops; and
·
sand blasting building.
12.6.14In addition,
mould and hull storage occupies a large area of vacant land on the southeast
portion of the CLS property.
12.6.15During the EIA
Study Team’s December 1998 CLS site walkthrough, many of the workshop areas
were noted to have unpaved, dirt floors, most notably the foundry building and
metal work shops. Waste disposal was
observed to be into large, unlined pits excavated in the ground near the
southeastern edge of the site, in an area of open land (Figure 12.5a). The waste
disposal pits were also noted to contain an extensive range of solid wastes,
including tyres and drums, and the materials appeared to be burned. In addition, at least 100 old, empty drums
were stored in at least two outside locations (Figure 12.5a), reportedly awaiting pickup for recycling. Many of the drums were on their sides, and
none of the drums were stored within any containment area. A number of the drums were noted to be old
and rusty, indicating a possible lengthy time of storage.
Evaluation of Impacts
12.6.16Detailed
quantitative studies of the CLS property not been undertaken due to access
limitations. However, a limited,
preliminary analysis assessment was made of five soil samples from the land
adjacent to the southeastern property boundary (see discussion below). The
typical contaminants associated with shipyard land use activities generally
include hydrocarbons and fuels, solvents, and heavy metals from plating
activities, metal work or grinding and anti-fouling paints (such as copper,
lead and tributyl tin). The potential
impacts may arise from localised spillages and these contaminants may cause
negative impact to sensitive receivers, including humans, during construction
works or during the operational phase (i.e. users of the Water Recreation
Centre). A description of general
hazardous properties of typical compounds which may have been used or stored at
shipyard sites is presented in Table
12.6a below.
12.6.17It should be
noted that almost all of the CLS facility, including the portions of the site
where the waste disposal pits are located, is on reclaimed land adjacent to
Penny’s Bay. As such, the depth to
groundwater at portions of the site are expected to be no greater than
approximately 2 m. Where contamination
is present (i.e. oils or fuel from past spills), this immiscible material is
not expected to migrate through the groundwater interface or vertically to any
great extent. Likewise, given the area
of reclamation and the somewhat narrow area of land at the base of the steep
hills, and the higher permeability of reclamation fill the horizontal migration
of any contamination is not expected to be extensive. Lastly, as portions of the CLS property have been used for
different, distinct shipyard activities, the contamination, where encountered,
may be localised rather than regional.
Table 12.6a - General Properties of
Hazardous Substances Potentially Found at Shipyards
Typical Material
|
General Hazardous Properties
|
Petroleum hydrocarbons
(including benzene, toluene, xylenes, and ethyl benzene - BTEX)
|
Can be toxic by inhalation, ingestion and contact
Concentrations may be flammable
|
Oils, oily wastes
|
Can be toxic by contact
Concentrations may be flammable
|
Thinners, solvents,
degreasers
|
Toxic by contact,
inhalation and ingestion
|
Heavy Metals (including
copper, zinc, chromium, and lead); mercury; tributyl tin
|
Can be toxic by ingestion and contact
Most are toxic to fish, plants, and marine plants
(especially copper)
Specific precautions may be required in relation to
monitoring and dust control in site formation works
|
Acids (batteries)
|
Toxic and harmful by contact
Corrosive to metal, concrete
|
Polycyclic Aromatic
Hydrocarbons (PAHs)
|
Toxic by contact and
ingestion
|
12.6.18In the absence of
full access to
the shipyard site, a limited sampling and analysis programme was performed on 2
February 2000, with collection of five selected soil samples from a stream bed
discharging along the southeastern property line of the CLS site.
12.6.19A total of five
samples were collected by the EIA Study Team and submitted to the LAM
Geotechnics Limited Environmental Laboratory under chain of custody and
analysed for the following parameters:
·
total petroleum hydrocarbons (TPH) as gasoline and diesel;
·
volatile organic compounds (VOCs);
·
semivolatile organic compounds (SVOCs);
·
priority pollutant heavy metals (13 metals);
·
total cyanide;
·
polychlorinated biphenyls (PCBs); and
·
tributyl tin (TBT).
12.6.20The chemical
analysis results indicated that low levels of TPH as gasoline were detected in
two samples, S-2 (0.12 mg/kg) and S-3
(0.13 mg/kg). The
other three samples were not detected at a laboratory detection limit (DL) of
0.10 mg/kg. No
concentrations of any TPH as diesel were detected in the five samples at the
laboratory’s detection limit (1.0 mg/kg).
12.6.21No concentrations
of any of 36 specific volatile organic compounds (VOCs) were detected in any of
the five samples at the laboratory’s specific DL for that particular compound.
12.6.22No concentrations
of any of 15 specific semivolatile organic compounds (SVOCs), analysed as
polycyclic aromatic hydrocarbons (PAHs), were detected in any of the five
samples at the laboratory’s specific DL for that particular compound.
12.6.23Analysis for
heavy metal compounds indicated low concentrations of 12 specific metal compounds.
There were no concentrations of cadmium or silver detected. Table 12.6b
presents the results of the metals analysis.
Table 12.6b - Results of Heavy Metals
Analysis (all results in mg/kg)
Parameter
|
S-1
|
S-2
|
S-3
|
S-4
|
S-5
|
Dutch
Guideline Values
|
cadmium (Cd)
|
<0.2
|
<0.2
|
<0.2
|
<0.2
|
<0.2
|
1 / 5 / 20
|
chromium (Cr)
|
2.1
|
6.2
|
2.7
|
3.0
|
3.5
|
100 / 250 / 800
|
Nickel (Ni)
|
1.4
|
3.4
|
<1
|
1.4
|
<1
|
50 / 100 / 500
|
Copper (Cu)
|
15
|
11
|
5.9
|
6.4
|
2.7
|
50 / 100 / 500
|
Lead (Pb)
|
40
|
180
|
66
|
49
|
29
|
50 / 150 / 600
|
Zinc (Zn)
|
39
|
67
|
29
|
44
|
70
|
200 / 500 / 3,000
|
Mercury (Hg)
|
<0.1
|
<0.1
|
0.2
|
<0.1
|
<0.1
|
0.5 / 2 / 10
|
Arsenic (As)
|
2.2
|
2.5
|
1.3
|
1.3
|
1.2
|
20 / 30 / 50
|
Silver (Ag)
|
<1
|
<1
|
<1
|
<1
|
<1
|
N/A
|
Barium (Ba)
|
8.4
|
16
|
11
|
38
|
3.8
|
200 / 400 / 2,000
|
Tin (Sn)
|
<1
|
1.4
|
1.0
|
1.1
|
<1
|
20 / 50 / 300
|
Molybdenum (Mo)
|
<1
|
1.0
|
<1
|
1.2
|
<1
|
10 / 40 / 200
|
Cobalt (Co)
|
2.1
|
22
|
1.6
|
1.9
|
1.3
|
20 / 50 / 300
|
Note: mg/kg = milligrams per kilogram.
N/A = There are no specific Dutch Guideline Values for this metal.
|
12.6.24As detailed above
in the ProPECC PN 3/94 Note, the Dutch Guidelines (1994) are used as reference
criteria by the EPD for the classification of contaminated soils. It should be noted that the Dutch Guidelines,
whilst widely recognised and generally accepted on a global scale, are not
enforceable standards in Hong Kong. In
the Netherlands, the Dutch Guidelines (which were revised again in 1995) are
enforceable standards whereby contaminants are subdivided into categories,
dependent upon the various concentrations.
For the purposes of this investigation, soil samples are classified
according to the older version of the Dutch Guidelines as follows:
·
"A" Values are characteristic of clean, uncontaminated soils;
·
"B" Values imply that some form of pollution is present and
further investigation may be required; and
·
“C" Values imply significant pollution and some intervention or
cleanup would be required.
12.6.25Almost all of the
detected metal compounds were noted to be below the respective Dutch “A” Value
concentrations, which would imply clean, uncontaminated soil. Only the
concentration of lead detected in sample S-2 (180 mg/kg) exceeded the
respective Dutch “B” Value of 150 mg/kg. None of the samples exceeded a specific
“C” Value, which would indicate significant pollution.
12.6.26The chemical
analyses did not detect any concentrations in excess of the laboratory’s
respective DLs for total cyanide (at 2 mg/kg), polychlorinated biphenyls (at 10
mg/kg for each of seven specific PCB compounds), or
tributyl tin (at 40 mg/kg), in any of
the five samples.
12.6.27With the
exception of Section 6 above, which
details sediment quality analysis results and potential contaminated sediment
issues in Penny’s Bay, no other assessment of soil or groundwater conditions
has been performed at the CLS site at this time, due to access
limitations. Therefore, there is no in situ data to assess the exact type,
extent or severity of possible contamination on-site. Thus, the scale of any potential impacts can only be estimated
at this stage. However, contamination,
where encountered, is expected to be limited in extent as described above.
12.7.1 The mitigation of
adverse impacts, where required, is expected to be relatively straightforward,
and will follow existing procedures and established protocols. The selection
and implementation of remediation, if required, will be made in accordance with
the EPD’s Guidance Notes document,
which outlines the general process as follows.
Selection
of a Remediation Method
12.7.2
There
are many options available for the remediation of contaminated sites. However,
taking into consideration the characteristics of contaminated sites, including
shipyards in Hong Kong, the following methods may be the more practical options
suitable for use in smaller target sites such as the CLS facility:
·
recovery
trenches or wells;
·
soil
venting/air sparging; and
·
controlled
excavation and disposal
12.7.3
Detailed
descriptions of these three methods are given in the EPD’s 1999 Guidance Notes document. Table
12.7.a below compares the applicability of these methods for the CLS site
and their characteristics.
Table 12.7a - Comparison of Remediation
Methods
Method
|
Principal
Use
|
Level
of Expertise Required
|
Recovery Trenches or Wells
|
Removal of leaked oil that floats on top of
groundwater; a prerequisite if leaked oil is found; used in conjunction with
other remediation methods
|
Moderate
|
Soil Venting/Air Sparging
|
Soil venting for unsaturated zone soil; air
sparging for groundwater; removes volatile chemicals, also promotes
bioremediation
|
High
|
Excavation/Disposal
|
Shallow contamination, one-off excavation
and contaminant removal, addresses all contaminants. Pretreatment of excavated soil prior to
disposal may be required.
|
Little
|
Source: EPD’s Guidance Notes for Investigation and Remediation of Contaminated
Sites of: Petrol Filling Stations, Boatyards, Car Repair/Dismantling
Workshops (1999).
|
12.7.4
The
presented remedial measures are not the only available technologies for
shipyard sites. Additional methods include in-situ
immobilization of contaminants and containment of contaminants. The selection of an appropriate methodology
will depend upon a number of factors, as these particular technologies may only
be applicable in certain special cases.
In addition, the measures will be developed in
conjunction with EPD during the Schedule 2 decommissioning EIA. This decommissioning EIA will need to be
approved under the EIAO, and an environmental permit issued by the
decommissioning or construction work can commence in the CLS site.
12.7.5
In
Hong Kong, there is a serious limitation of available landfill space for
disposal of contaminated materials.
Therefore, the EPD suggest that in-situ
remediation methods should be adopted wherever possible, and excavation and
disposal to landfill should always be the last resort which should be used only
when in-situ remediation is proved to
be not feasible and there is very localized contamination and the quantity of
contaminated soil for landfilling is small.
12.7.6
Acceptance
of disposal of contaminated soil and landfill also depends on the degree of
contamination of soil and the nature of the contamination. Special approval has to be obtained from EPD
for disposal to landfill. In some
cases, contaminated soil must be pretreated or stabilized before landfill
disposal, so as to avoid impacting the biological treatment systems. According to the EPD’s Guidance Notes document, the following factors should be considered
when evaluating the different remediation methods and selecting the most
suitable one for a site:
·
degree and extent of the contamination;
·
anticipated future uses of the site;
·
nature of the contaminants;
·
soil characteristics; and
·
time available for remediation.
12.7.7
Information
on the above factors is usually documented in the Contamination Assessment
Report (CAR) prepared during the site investigation stage and forwarded to EPD
for approval. As detailed above, access has not been granted for the CLS site,
so no detailed on-site assessment has been completed. However, limited data collected in February from immediately
off-site indicates that five selected samples from that specific location are
not contaminated.
Remediation
Action Plan
12.7.8
Upon
review of the appropriate remediation technology, a Remediation Action Plan
(RAP) should be developed in conjunction with the Contamination Assessment
Report (CAR). The RAP provides a
summary of the site conditions, the contamination, and a proposal and
commitment by the project proponent to provide remediation of the site. The EPD’s suggested outline of a RAP is
shown in Table 12.7b. The RAP should be submitted to and approved
by the EPD prior to implementation of any remedial technology. The RAP would also serve as a record for the
project proponent’s use in future monitoring of the remediation progress.
Table 12.7b Outline of a Typical Remediation Action Plan (RAP)
Section
and Title
|
Description
|
Introduction
|
Outline the location of the site. The owner of operator or person
responsible should also be mentioned.
|
Nature of Operation
|
Describe generally the present and past
operations on site and the main contaminated area(s).
|
Description of Extent of Contamination
|
Describe the extent of contamination at the
site. A figure showing the
distribution of the contamination and areas requiring remediation action
should be included.
|
Objectives of Remediation Action Plan
|
State the objectives of the Remediation
Action Plan.
|
Design and Operation of Remediation
|
Outline the type of system to be used for
remediation including a list of requirement and sketches of the proposed
remediation system. If any special
approval has to be obtained from EPD, it should be identified here.
|
Implementation Programme
|
Set out an implementation schedule with the
appropriate actions and milestones for the completion of various
activities. The criteria to be used
to assess the effectiveness of the remediation activities should be included
in this section.
|
Implementation
of Remedial Measures
12.7.9
Implementation
of the Remediation Action Plan can start once the CAR and RAP submissions are
approved by the EPD. The essential
steps involved in remedial programme are detailed in the EPD’s Guidance Notes document. The Guidance
Notes document is developed to provide general guidance for the project
programme on the major steps involved.
In all cases contaminated soil remediation, treatment or disposal of
must be managed in an environmentally sound manner, including compliance with
all relevant legislation and Government requirements. The health and safety measures to be adopted during remediation
work are also described in the EPD’s Guidance
Notes document. In the case of the
shipyard site, the remedial measures will be
developed in conjunction with EPD during the Schedule 2 decommissioning
EIA. This decommissioning EIA will need
to be approved under the EIAO, and an Environmental Permit issued by the DEP
before any remediation or construction work can commence in the CLS site.
Other General Measures During Construction Phase
12.7.10As stated above, it is considered
unlikely that contaminated land issues will be a concern during either the
construction or operation of the NLDFS development, as remediation will be
performed as part of the Schedule 2 EIA for decommissioning of the CLS site
before any remediation or construction at the CLS site. However, as a precaution, it is recommended
that standard good practice measures are implemented during any works during
the construction phase to minimise any potential exposure to contaminated soils
or groundwater. These measures include:
·
The use of bulk earth-moving excavator equipment will minimise
construction workers’ potential contact with contaminated materials;
·
Exposure to any contaminated materials may be minimised by the wearing
of appropriate clothing and personal protective equipment such as gloves (when
interacting directly with contaminated material), providing adequate hygiene
and washing facilities and preventing smoking and eating during such
activities;
·
Vehicles containing any contaminated materials should be suitably
covered to limit potential dust emissions or contaminated wastewater run-off,
and truck bodies and tailgates should be sealed to prevent any discharge during
transport or during wet conditions;
·
Only licensed waste haulers should be used to collect and transport any
contaminated material to an appropriate disposal site and procedures should be
developed to ensure that illegal disposal of wastes does not occur;
·
The necessary waste disposal permits should be obtained, as required,
from the appropriate authorities, in accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation (Cap 354), as
required;
·
Records of the quantities of wastes generated and disposed of should be
maintained; and
·
In accordance with good construction practice, silt traps should be
used to reduce the impact to drainage caused by suspended solids (SS) arising
from disturbed ground, or any construction materials such as cement and
gravel. Groundwater should be disposed
of in accordance with the WPCO.
12.7.11Based upon the
lack of any documented previous spill incidents, and the fact that the
construction in this area of the Study will be performed after a separate
decommissioning Schedule 2 EIA study and remediation (if required) is
completed, the potential for future negative land contamination impacts are not
expected.
Residual Environmental Impacts
12.7.12Due to access
restrictions, residual environmental impacts cannot be fully assessed at this
time. However, given that the CLS
facility will undergo a separate Schedule 2 EIA decommissioning study, and that
remediation will be employed to EPD satisfaction prior to any construction
works being conducted, the potential for residual impacts or future land
contamination concerns will be minimal.
12.8.1
Contaminated
land issues have not been identified as a major concern for the Study Area,
with the exception of the Cheoy Lee Shipyard (CLS) site. However, the NLDFS EIA comprises Schedule 3 level coverage of the
environmental impacts arising from shipyard decommissioning, although access to
the shipyard site was not available as part of the Schedule 3 NLDFS EIA, due to
its present operation and private ownership. A separate and subsequent EIA
Study will be commissioned by CED before the decommissioning of the CLS. This subsequent decommissioning EIA, which,
due to access requirements can only commence after the shipyard property has
become available, will include detailed site investigation and formulation of
appropriate remedial methods and procedures, if required, to decontaminate the
shipyard site. CED presently expect
this decommissioning EIA to be completed and submitted under the EIAO to DEP
for approval in 2002. More importantly,
this decommissioning EIA will need to be approved under the EIAO, and an
Environmental Permit issued by the DEP before any construction work can
commence in the shipyard area.
12.8.2
As
a result of the CLS site Schedule 2 EIA described above, appropriate
remediation will be performed in accordance with EPD guidelines for the
decommissioning of the shipyard site, future potential negative impacts are not
expected. The concerns for potential
impacts of land contamination are reduced further as there have been no
documented spillages or confirmed leakages from this shipyard site, or any
other facilities within the Study Area according to Government sources. Where shipyard facility operations are noted
to be a concern for causing potential contamination, it is noted that standard
mitigation measures will be employed, thereby reducing the need for contact
with any potentially contaminated soils during construction works. In order to
provide quantitative information to the limited extent possible, a preliminary
sampling programme was conducted along a stream bed discharging from the
southeastern boundary of the CLS site.
The results of five soil samples indicated that, whilst low
concentrations of total petroleum hydrocarbons (as gasoline) and 11 heavy metal
compounds were detected in some samples, the concentrations were not a major
concern. Almost all of the detected metal compounds were noted to be below the
respective Dutch “A” Value concentrations, which would imply clean,
uncontaminated soil. Likewise, there was also no sign of elevated levels of
contamination in the marine sediment samples taken from outside the seaward
boundary of the shipyard. Therefore,
assuming that remedial measures prescribed by the CLS site Schedule 2 EIA are
conducted in accordance with appropriate protocols and the Guidance Notes (this will be verified in the CLS site Schedule 2
EIA), there will be no potential residual negative impacts, and no
insurmountable conditions for the future use of the former CLS site for road
and railway access to the Theme Park (Phases I and II) and associated
developments.