13                CONCLUSION

13.1          Introduction

13.1.1      This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the WDII development, with the consideration of the potential cumulative impact from the CRIII and the CWB & IECL projects.  The key environmental outcomes arising from this EIA are:

·         the existing air sensitive receivers from Central to Causeway Bay will be protected from adverse construction air quality impact by the recommended dust control measures (Section 3.8.1) during construction phase;

·         as no adverse operational air quality impacts at the existing and planned air sensitive receivers from Central to Causeway Bay are predicted, mitigation measures are not considered necessary;

·         the existing residential noise sensitive receivers from Central to Causeway Bay, including Causeway  Centre, Gloucester Road 169 - 170, Elizabeth House, Riviera Mansion, Mayson Garden, Belle House and Victoria Centre will be protected from adverse construction noise impact by the adoption of quiet powered mechanical equipment (PME) (Section 4.8) during construction phase;

·         as no adverse road traffic noise impacts at the existing noise sensitive receivers from Central to Causeway Bay are attributed to the ‘New’ roads, direct mitigation measures are not necessary;

·         adverse water quality impact at the seawater intakes along the Central, Wan Chai and Causeway Bay waterfront is predicted during marine works.  Mitigation measures, including reduction in dredging rates and implementation of silt curtains and installation of silt screens are considered necessary to alleviate the impact; and

·         the WDII reclamation will only result in minimal change in flow regime.

13.1.2      The Implementation Schedules of the recommendations are presented in Section 14.  The principal findings of this Report are summarised below.

13.2          Air Quality Impact

Construction Phase

13.2.1      During reclamation, filling and surcharging were identified as the major dust sources.  Entrusted work of the CWB tunnel section would also cause potential dust nuisance during excavation and backfilling.  Due to the complexity of the activities, ten worst case scenarios of the construction schedules were identified and modelled using the FDM model.

13.2.2      Exceedances occur at the ASRs in the vicinity during construction.  In order to achieve the Air Quality Objectives, the following mitigation measures for all WDII works including entrustment works from HyD are recommended:

·         strictly limit the truck speed on site to below 10 km per hour and water spraying to keep the haul roads in wet condition;

·         twice daily watering of the work site with active operations when the weather and the work site are dry;

·         watering during excavation and material handling;

·         provision of vehicle wheel and body washing facilities at the exit points of the site, combined with cleaning of public roads where necessary; and

·         tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.

13.2.3      With the above mitigation measures on WDII, the air quality at all ASRs will comply with the 1-hour and 24-hour TSP criteria.  There will be no adverse residual air quality impact due to the WDII construction activities.

Operational Phase

13.2.4      The dispersions of NO2, RSP and CO, arising from the background pollutant levels within and adjacent to the WDII, vehicle emissions from open road networks, tunnel portal and ventilation building emissions from the CWB & IECL, tunnel portal emissions from the CHT, and portal emissions from existing underpasses and planned deckovers, were modelled using the CALINE4 and ISCST3 models. 

13.2.5      Results show that the predicted air quality at the ASRs will comply with the AQOs. No mitigation measures are proposed.

13.3          Noise Impact

Construction Phase

13.3.1      This assessment has predicted the WDII construction noise impacts during normal daytime, taking into account other concurrent projects including the CRIII and CWB & IECL projects and the Causeway Bay Flyover project.  With the use of silenced equipment and movable barriers for WDII construction tasks and implementation of the noise mitigation measures proposed in the CRIII and CWB & IECL EIA Reports, the noise levels at most of the representative NSRs would comply with the construction noise criteria.  Noise exceedences are still predicted at performing art centres.  However, these NSRs are equipped with central air-conditioning systems and good noise insulation facilities.  In addition, they do not rely on openable windows for ventilation.  No adverse noise impacts are therefore expected at the indoor environment of these NSRs.

13.3.2      The proposed cross harbour water mains will extend from Wan Chai near the HKCEC Extension to connect to the existing system near the Museum of Arts at the Tsim Sha Tsui promenade.  Insignificant construction noise impacts are expected on the indoor environment of the NSRs such as the Hong Kong Space Museum and the Museum of Arts, which are close to the construction site at Tsim Sha Tsui, as they have blank facades / fixed windows and are provided with central air conditioning, and therefore do not rely on openable windows for ventilation.

13.3.3      An indicative assessment has been undertaken for possible construction activities during restricted hours (1900 to 2300) associated with the reclamation works of the Project.  With the reduction of plant numbers, adoption of quiet plant and reduction of on-time percentage for some equipment, the predicted noise levels at all representative residential NSRs would comply with construction noise criterion of 65 dB(A).  Noise exceedences of the 65 dB(A) criterion at HKCEC are still predicted at certain period, for plant working close to the HKCEC Extension.  It should be noted that the results of the construction noise impact assessment for restricted hours (1900 to 2300) are for indicative purposes; the Noise Control Authority will process any CNP application, based on the NCO and the relevant technical memoranda in addition to considering the contemporary situations / conditions.

13.3.4      A construction noise EM&A is recommended to check the compliance of the noise criteria during normal daytime working hours. 

Operational Phase

13.3.5      The potential road traffic noise impacts have been assessed based on the worst case traffic flows in 2027, taking into consideration of the recommended mitigation measures on the IECL according to the CWB & IECL EIA Report.  The noise levels at most of the NSRs are predicted to exceed the EIAO-TM traffic noise criteria.  However, these noise exceedences are mainly attributed to the existing roads and the IECL.  The ‘New’ road noise contributions to the overall noise level are negligible (that is, less than 1.0 dB(A)).

13.3.6      In addition, some NSRs such as the Art Centre and HKCEC Extension are equipped with central air-conditioning systems and noise insulation facilities, and they do not rely on openable windows for ventilation.  Therefore, adverse traffic noise impacts are not expected at the indoor environment of these NSRs.

13.3.7      No adverse impacts from helicopter noise and fixed noise sources including ventilation shaft noise from the CWB ventilation buildings are anticipated at the existing and planned NSRs.

13.4          Hydrodynamics, Water and Sediment Quality Impacts

Construction Phase

13.4.1      The water quality impact during the reclamation of WDII has been quantitatively assessed using the Delft3D Model.  Suspended sediment is identified as the most significant water quality parameter during the reclamation.  The worst-case scenarios during reclamation have been assessed and it is predicted that potential water quality impacts would occur along waters at Central, Wan Chai and Causeway Bay Typhoon Shelter.  The water quality impacts upon the seawater intakes could be effectively minimised with the implementation of the proposed mitigation measures.  There will be no residual water quality impact due to the WDII reclamation works alone.  An environmental monitoring and audit programme is required to ensure the effectiveness of the proposed water quality mitigation measures.

13.4.2      Water quality impacts from land-based construction, including road works, waterfront facilities and public utilities, are associated with the surface runoff, effluent discharge from the site, and sewage from on-site construction workers.  Impacts can be controlled to comply with the WPCO standards by implementing the recommended mitigation measures.  No unacceptable residual impacts on water quality are anticipated.

Operational Phase

13.4.3      An assessment of the hydrodynamic impact due to the WDII has been made using the Delft3D model.  With this quantitative modelling tool, impacts have been assessed for the dry and wet seasons over a spring-neap tidal cycle.  For both seasons, the baseline and operation simulations have been compared.  It is concluded that:

·         The wet season ebb tide flow speeds in Victoria Harbour are higher than that in the dry season.  For the flood tide simulations, the flow speeds are more comparable between the two seasons.

·         The flow speed distributions within Victoria Harbour before and after the implementation of the WDII Project are very similar.  The reclamation will only cause slight change in the prevailing currents in the study area.

·         The predicted mean discharges across the Victoria Harbour East (Lei Yue Mun) and Victoria Harbour West (Yau Ma Tei – Western District) will be decreased by less than 5% and 2%, respectively, during the wet season after the completion of WDII reclamation, as well as other reclamations within the Victoria Harbour, including the CRIII, Kowloon Point Development, the South East Kowloon Development, the Yau Tong Bay Development and the Western Coast Road reclamation.

·         The predicted mean discharges across the Victoria Harbour East (Lei Yue Mun) and Victoria Harbour West (Yau Ma Tei – Western District) will be decreased by about 4% and less than 1.5%, respectively, during the dry season after the completion of WDII reclamation, as well as other reclamations within the Victoria Harbour, including the CRIII, Kowloon Point Development, the South East Kowloon Development, the Yau Tong Bay Development and the Western Coast Road reclamation.

·         It is predicted that the change of mean discharges through the Victoria Harbour East and Victoria West due to the WDII reclamation alone will be less than 1%.

13.4.4      Therefore, it is concluded that the WDII reclamation will have minimal impact on the hydrodynamic regime of the study area.

13.4.5      An assessment of the water quality impact during the operation of WDII has been carried out using the Delft3D model.  Comparison between the baseline and operational water quality modelling results suggests that the levels of pollutant near Wan Chai and the neighbouring areas are similar under both baseline and operational scenarios.  No unacceptable impacts associated with the operation of the WDII upon the water quality in Victoria Harbour are envisaged.  Based on the modelling results, operational phase mitigation measures are not considered necessary.  Operational water quality monitoring and audit is therefore not considered necessary.

13.5          Waste Management

13.5.1      A review of the sediment quality data from the marine ground investigation works indicates that the majority of the marine sediments to be dredged in the proposed WDII area are classified as Category H (biological test not required).  The dredged sediment will therefore not be suitable for open sea disposal.  With the implementation of the mitigation measures detailed in Section 6.7 in accordance with the requirements of WBTC No. 3/2000, no residual impact is predicted.

13.5.1      To determine the disposal requirements of the Category H sediment (with Total PCBs exceeding 10 times the LCEL) identified within the Causeway Bay typhoon shelter, Tier III biological screening (dilution test) would be required for the sediment sampling and testing to be carried out in the further ground investigation works at the design phase of the Project.  Biological screening will also be required for any identified Category M sediment in the further ground investigation works for the Project.  The need for any special treatment / disposal procedures for dredged sediments from the Causeway Bay typhoon shelter will be examined in detail at the design stage of the Project, as necessary, based on the results of biological screening.  It has been agreed with EPD that special disposal arrangements, rather than pre-treatment, would be acceptable provided there would be negligible loss of sediment to the marine environment during the dumping operations.  A review of possible disposal arrangements has recommended containment of the contaminated sediments during dumping to prevent any release of material to the marine environment.  Field trials are recommended to be undertaken during the detailed design stage (using uncontaminated mud) to establish the optimum handling method.

13.5.2      Wastes generated by the construction activities are likely to include C&D materials (including excavated material and demolition material), general refuse and chemical waste.  Provided that these identified waste arisings are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts are not anticipated.

 

 

 

13.6          Land Contamination

13.6.1      This land contamination assessment includes a review of site history and environmental information, and a preliminary site inspection (outside the shipyard and the yacht club).  Based on the available information, the potential for land contamination at the study area is considered not insurmountable.  Potential contaminants arising from shipyard operations and the yacht club have been identified in Section 7.7.

13.6.2      The study team could not gain access to the subject shipyard and the yacht club for intrusive site investigation works at this stage.  It is proposed that site investigation works should be conducted prior to the commencement of site clearance / construction works.  Furthermore, the proposed sampling locations, sampling and testing schedule specified in the contamination assessment plan should be subject to review prior to the site investigation works.  The CAP will be revised and submitted to EPD for approval prior to the commencement of the land contamination assessment work on site.

13.7          Terrestrial Ecology

13.7.1      The terrestrial ecological resources within the study area comprise a variety of habitat types including man-made terrestrial habitat and associated bird community.  No terrestrial sensitive receivers are in the vicinity of the study area and the nearest country park, the Aberdeen Country Park, is approximately 2 km inland to the south.  Apart from isolated trees over the study area, the most significant green area is the Victoria Park.  The current ecological assessment shows that the terrestrial ecological resources present within the study area are considered of low ecological value.

13.7.2      It is anticipated that no specific mitigation measures will be required for the potential terrestrial ecological impacts to preserve ecological resources in the study area.

13.8          Marine Ecology

13.8.1      Literature reviews of existing information supplemented with the results of recently undertaken field surveys on marine ecological resources indicate that the intertidal habitats and soft benthic habitats within the Study Area are of low ecological value.  There are no ecological sensitive receivers, such as SSSIs, Fish Culture Zones and Marine Parks and / or Reserves and other areas of ecological importance or conservation interest, in and within the immediate vicinity of the study area.

13.8.2      The dredging and reclamation works will result in the permanent loss of approximately 28.5 hectares of soft bottom benthic habitat.  Approximately 1,110m of rock armoured sloping seawall and 440m of sloping seawall (with granite facing) will be permanently lost due to reclamation or removal of existing breakwaters.  Approximately 2,800m of existing vertical seawall will also be lost during the reclamation, but some 1.5 km of new caisson seawall and 1.3 km of new blockwork seawall will be constructed.  These seawalls are expected to provide habitat of similar ecological value to that of the existing blockwall seawalls that constitutes the main part of the reclaimed intertidal habitat.  Since the benthic community and intertidal community in the study area are of low ecological value, only minor impacts are anticipated from the reclamation works.  Similar intertidal flora and fauna existing at present are expected to recolonise the new seawall.

13.8.3      Based on the prediction of construction phase water quality modelling, impacts to benthic and intertidal assemblages immediately outside the reclamation site are expected to occur during the construction phase.  However, since the seabed community and intertidal community in the vicinity of the study area are of low ecological value and in view of the impact of suspended solids elevation is temporary, only minor impact is anticipated.

13.9          Landscape and Visual

13.9.1      Landscape and visual impacts are summarised below for each of the three Designated Projects and the Schedule 3 Project.

            DP1 : Reclamation Works

            Predicted Landscape and Visual Impacts in the Construction Phase

13.9.2      Adverse landscape impacts of substantial significance would be felt by:

·         HKCEC Promenade and Approach Roads (LR5), which would be directly affected by the reclamation works on the east and west sides of the HKCEC;

·         Causeway Bay Typhoon Shelter Wharf (LR13), Noon Day Gun (LR17), Floating Tin Hau temple (LR18) and Typhoon Shelter (LR19), which would all be disrupted by the reclamation and IECL; and

·         The landscape character zones LZ1, LZ3, LZ6A, LZ13, LZ18, LZ19, LZ20, LZ21, LZ25, and LZ29, each of which would suffer a large magnitude of change in landscape character due to the reclamation construction works.

13.9.3      Adverse landscape impacts of moderate significance would be felt by:

·         Victoria Harbour (LR1A); and

·         The landscape character zones LZ15, LZ17 and LZ22.

13.9.4      The remaining residual landscape impacts would be insubstantial.

13.9.5      Adverse visual impacts of substantial significance would be felt by:

·         High-rise properties located along the southern and eastern edges of the primary zone of visual influence, which are in close proximity to the development and which face directly towards Victoria Harbour, where the construction activities associated with the reclamation works would be in full view and would constitute a large magnitude of change to the existing harbour views;

·         The Royal Hong Kong Yacht Club (OU1) and Hong Kong Police Officer’s Club (GIC7), which are adjacent to the existing seawall, and which would suffer a large magnitude of change in views during construction; and

·         Fenwick Pier Street Public Open Space (O1) which would be demolished by the construction works, and HKCEC Extension Open Space and Promenade (O3) which would undergo major reconstruction.

13.9.6      Adverse visual impacts of moderate significance would be felt by:

·         High-rise properties located along the south-eastern edge of the primary zone of visual influence, in Causeway Bay, which are further way from the development and / or which do not face directly towards Victoria Harbour.  The construction activities associated with the reclamation, roadworks, and building and open space developments would be partially visible, from a distance, and would constitute a small to medium magnitude of change to their existing harbour views; and

·         High-rise hotels located in Tsim Sha Tsui, along the northern edges of the primary zone of visual influence, where the construction activities associated with the reclamation, roadworks, and building and open space developments would be visible across the harbour, and would constitute a small to medium magnitude of change to the existing harbour views.

13.9.7      The remaining residual visual impacts would be slightly adverse or insubstantial.

Predicted Landscape and Visual Impacts in the Operation Phase

13.9.8      After all mitigation measures are implemented and have matured over 10 years, there would still be some residual adverse landscape impacts of moderate significance, which would be felt by:

·         The landscape character zone LZ19  - Police Officers Club, due to the reclamation and replacement of the typhoon shelter adjacent to the Club with the planned commercial development in site WDII/28; and

·         The landscape character zone LZ22  - Shipyard and Fire Station, due to the reclamation and development of the Leisure Complex.

13.9.9      The remaining landscape impacts would be adverse impacts of slight or insubstantial significance, or beneficial impacts of slight or moderate significance.

13.9.10   After all mitigation measures are implemented and have matured over 10 years, there would still be some residual adverse visual impacts of substantial significance, which would be felt by:

·         The Hong Kong Police Officers’ Club (GIC7) which would be visually dominated by the IECL and the planned commercial development in site WDII/28.

13.9.11   Residual adverse impacts of moderate significance would be felt by:

·         The Royal Hong Kong Yacht Club (OU1), which although presented with attractive views of the planned Marina, would have less open views of the harbour than it currently has.

·         The remaining visual impacts would be adverse impacts of slight or insubstantial significance, or beneficial impacts of slight significance.

Conclusion

13.9.12   It is considered that under Annex 10 of the EIAO, the residual landscape and visual impacts associated with the DP1 : Reclamation Works are acceptable with mitigation measures.

            DP2 : WDII Major Roads

Predicted landscape and Visual Impacts in the Construction Phase

13.9.13   Adverse landscape impacts of substantial significance would be felt by:

·         Fenwick Pier Street Public Open Space (LR3), which would require to be completely demolished;

·         HKCEC Promenade and Approach Roads (LR5), which would be affected by the new road works on the east and west sides of the HKCEC;

·         Trees along Convention Avenue and Hung Hing Road (LR20) due to disruption from the new road works; and

·         The landscape character zones LZ1, LZ3, LZ6, LZ6A, LZ13, LZ18, LZ25, LZ26, LZ27, and LZ28, each of which would suffer a large magnitude of change in landscape character due to the road construction elements.

13.9.14   Adverse landscape impacts of moderate significance would be felt by:

·         The landscape character zones LZ16, LZ17 and LZ24.

13.9.15   Remaining landscape impacts would be slight or insubstantial.

13.9.16   Adverse visual impacts of substantial significance would be felt by:

·         High-rise properties located along the central southern edge of the primary zone of visual influence, between Fleet Arcade (C15) in the west and the Sun Hung Kai Centre (C28) in the east, which are in close proximity to the roadworks and which face directly towards them, where the construction activities would be in full view and would constitute a large magnitude of change to the existing views; and

·         Fenwick Pier Street Public Open Space (O1) which would be demolished by the construction works, and HKCEC Extension Open Space and Promenade (O3) which would undergo major reconstruction.

13.9.17   Adverse visual impacts of moderate significance would be felt by:

·         High-rise properties located along the southern edge of the primary zone of visual influence, between the national Mutual Building (C29) and the Excelsior Hotel, (C32) which are further way from the roadworks and for whom the construction activities would constitute a small to medium magnitude of change to the existing views; and

·         HKCEC Open Space (O2) and Renaissance Harbour View Open Space (O4), which would experience intermediate magnitude of change to their visual context.

13.9.18   Remaining visual impacts would be slight or insubstantial.

Predicted Landscape and Visual Impacts in the Operation Phase

13.9.19   After all mitigation measures are implemented and have matured over 10 years, the remaining landscape impacts would be insubstantial, or beneficial impacts of slight significance.

13.9.20   After all mitigation measures are implemented and have matured over 10 years, there would still be some residual adverse visual impacts, as indicated in Table 10.9 and Figure 10.29, but these would be of only slight significance due primarily to the mitigating effect of the planting in the extensive roadside amenity areas

Conclusion

13.9.21   It is considered that under Annex 10 of the EIAO, the residual landscape and visual impacts associated with the DP2 : WDII Major Roads are acceptable with mitigation measures.

DP3 : Kellett Island Marina

Predicted Landscape and Visual Impacts in the Construction Phase

13.9.22   Adverse landscape impacts of slight significance would be felt by Victoria Harbour (LR1A and LZ29) due to the small reduction in total area of the harbour.

13.9.23   The remaining landscape impacts would be insubstantial.

13.9.24   Adverse visual impacts of substantial significance would be felt by:

·         The Royal Hong Kong Yacht Club (OU1) which would be in close proximity to the works, which would create a large magnitude of change in views during construction.

13.9.25   Adverse visual impacts of moderate significance would be felt by:

·         High-rise properties located along the southern and eastern edges of the primary zone of visual influence, which are in close proximity to the Marina and which face directly towards it, where the construction activities would be in full view and would constitute an intermediate magnitude of change to the existing harbour view.

13.9.26   The remaining visual impacts would be slightly adverse or insubstantial.

            Predicted Landscape and Visual Impacts in the Operation Phase

13.9.27   There is no way to effectively mitigate for the loss in harbour area, and therefore the residual impacts in the operational phase would remain as adverse impacts of slight significance on Victoria Harbour (LR1A and LZ29).

13.9.28   Other landscape impacts would be insubstantial.

13.9.29   After all mitigation measures are implemented and have matured over 10 years, there would still be some residual adverse visual impacts of slight significance felt by the Royal Hong Kong Yacht Club, which, although possessing an attractive view of the Marina itself, would no longer have wide views of the Victoria Harbour and Tsim Sha Tsui East.

13.9.30   The remaining visual impacts would be adverse impacts of insubstantial significance.

            Conclusion

13.9.31   It is considered that under Annex 10 of the EIAO, the residual landscape and visual impacts associated with the DP3 : Kellett Island Marina are acceptable with mitigation measures.

Schedule 3 Project : WDII

Summary of Impacts during the Construction Phase

13.9.32   Adverse landscape impacts of substantial significance would be felt by:

·         Fenwick Pier Street Public Open Space (LR3), which would require to be completely demolished;

·         HKCEC Promenade and Approach Roads (LR5), which would be affected by the new road works on the east and west sides of the HKCEC;

·         Tree Planting adjacent to the Sewage Works, Hung Hing Road (LR10), the Royal Hong Kong Yacht Club (LR11) and Trees along Convention Avenue and Hung Hing Road (LR20) due to disruption from the new road works;

·         Causeway Bay Typhoon Shelter Wharf (LR13), Noon Day Gun (LR17), Floating Tin Hau temple (LR18) and Typhoon Shelter (LR19), which would all be disrupted by the reclamation and IECL; and

·         The landscape character zones LZ1, LZ3, LZ6A, LZ13, LZ18, LZ19, LZ20, LZ25, LZ26, LZ27, LZ28 and LZ29, each of which would suffer a large magnitude of change in landscape character due to the various construction elements.

13.9.33   Adverse landscape impacts of moderate significance would be felt by:

·         Victoria Harbour (LR1A) due to the reclamation;

·         Victoria Park (LR14) due to disruption caused by the construction of the two pedestrian linkages to the waterfront;

·         The landscape character zone LZ11 (PTI), due to the conversion of the open air PTI to a covered PTI under the CDA development; and

·         The landscape character zones LZ15, LZ17, LZ22, LZ23, and LZ24.

13.9.34   The remaining landscape impacts will be slight adverse or insubstantial.

13.9.35   Adverse visual impacts of substantial significance would be felt by:

·         High-rise properties located along the southern and eastern edges of the primary zone of visual influence, which are in close proximity to the development and which face directly towards Victoria Harbour, where the construction activities associated with the reclamation, roadworks, and building and open space developments would be in full view and would constitute a large magnitude of change to the existing harbour views;

·         The Royal Hong Kong Yacht Club (OU1) and Hong Kong Police Officer’s Club (GIC7), which would be surrounded by the various developments, which would create a large magnitude of change in views during construction; and

·         Fenwick Pier Street Public Open Space (O1) which would be demolished by the construction works, and HKCEC Extension Open Space and Promenade (O3) which would undergo major reconstruction.

13.9.36   Adverse visual impacts of moderate significance would be felt by:

·         High-rise properties located along the south-eastern edge of the primary zone of visual influence, in Causeway Bay, which are further way from the development and / or which do not face directly towards Victoria Harbour, where the construction activities associated with the reclamation, roadworks, and building and open space developments would be partially visible from a distance, and would constitute a small to medium magnitude of change to the existing harbour views;

·         High-rise hotels located in Tsim Sha Tsui, along the northern edges of the primary zone of visual influence, where the construction activities associated with the reclamation, roadworks, and building and open space developments would be visible across the harbour, and would constitute a small to medium magnitude of change to the existing harbour views; and

·         HKCEC Open Space (O2), Renaissance Harbour View Plaza (O4), Wan Chai Sports Ground (O6), and Victoria Park (O8), which would suffer due to adjacent reclamation works, roadworks, and building construction works.

13.9.37   The remaining visual impacts would be slight or insubstantial.

            Schedule 3 Project : WDII - Predicted Landscape and Visual Impacts in the Operation Phase

13.9.38   After all mitigation measures are implemented and have matured over 10 years, there would still be some residual adverse landscape impacts of moderate significance, which would be felt by:

·         The landscape character zone LZ18 - RHKYC, due to the loss of trees and the visual influence of the adjacent IECL.

·         The landscape character zone LZ19  - Police Officers Club, due to the visual influence of the IECL; and

·         The landscape character zone LZ22  - Shipyard and Fire Station, due to the reclamation and development of the Leisure Complex.

13.9.39   The remaining landscape impacts would be adverse impacts of slight or insubstantial significance, or beneficial impacts of slight or moderate significance as noted in Table 10.17.

13.9.40   After all mitigation measures are implemented and have matured over 10 years, there would still be some residual adverse visual impacts of substantial significance, which would be felt by:

·         The Great Eagle Centre (C25), Harbour Centre (C26) and Causeway Centre (C/R1), which would have their harbour views blocked substantially by the planned CDA development in site WDII/11;

·         Hoi Kung Court (C/R20), Hoi To Court (C/R21), Hoi Deen Court (C/R22), World Trade Centre (C31) and Excelsior Hotel (C32), which would have their harbour views partially obscured by the planned commercial development in site WDII/28, and which would also have clear views of the IECL;

·         The Hong Kong Police Officer’s Club (GIC7) which would be visually dominated by the IECL and the planned commercial development in site WDII/28; and

·         Planned Waterfront ROS (O13 - East of Harbour Museum) and Planned ROS – Causeway Bay Open Space (O17) which would both suffer a large impact from the IECL.

13.9.41   Adverse visual impacts of moderate significance would be felt by:

·         Renaissance Harbour View Hotel C23) and Sun Hung Kai Centre (C28), which would have their harbour views partially obscured by the planned CDA development in site WDII/11.

·         Sino Plaza (C30) and the high-rise properties along Gloucester Road to the east of the Excelsior Hotel (C/R5, C/R6, C/R7 and C/R8), which would have their harbour views slightly obscured by the planned commercial development in site WDII/28, and which would also have clear views of the IECL;

·         Victoria Mark Mansion (C/R9), Chesterfield Mansion (C/R10) and Greenfield Mansion (C/R11) which will be impacted by views of the IECL and the planned Leisure and Entertainment Complex in site WDII/30.

·         High-rise properties along the eastern edge of the primary ZVI due to their clear views along the length of the IECL;

·         The Royal Hong Kong Yacht Club (OU1), which although presented with attractive views of the planned Marina, would no longer have the open views of the harbour and Tsim Sha Tsui that it currently has, and would have views to the south impacted by the IECL; and

·         Planned Commercial Development in WDII/28 (C51) due to the impact caused by the IECL.

13.9.42   The remaining visual impacts would be adverse impacts of slight or insubstantial significance, or beneficial impacts of slight significance.

            Schedule 3 Project : WDII - Conclusion

13.9.43   Overall, it is considered that, in the terms of Annex 10 of the EIAO TM, the residual landscape and visual impacts are acceptable with mitigation measures.

13.9.44   However, the ability to meet Government's planning objective (Section 10.3) to create a world-class harbour frontage, in respect of visual and landscape impacts, is significantly constrained in the area adjacent to the IECL.  This is due to the dominating visual presence of the IECL and also because a large landscape area would lie under the IECL.  The ability to screen the IECL from users of the waterfront is dependent on the ability to plant substantial large canopy trees over the 26 m wide drainage reserve.  Tree planting over the drainage reserve is therefore a very critical component of the overall mitigation measures.

13.10      Biogas

13.10.1   Organically enriched material is planned to be left in-situ at the WDII reclamation within the western and eastern corners of the Causeway Bay Typhoon Shelter.  As methane gas could be generated under anaerobic conditions, there is a potential for this gas to be released either during construction or after development of the reclaimed area.

13.10.2   The predicted methane emission from the WDII reclamation suggests that the methane gas generation potential is not expected to pose a development constraint.  In view of the exceedance of the recommended maximum “safe” rate of methane emission (derived for WDII from Waste Management Paper No. 26A) under the worst case scenario of 100% biodegradable total organic carbon and the identification of ‘at risk’ rooms at the proposed developments at the western and eastern corners of the typhoon shelter reclamation, it is recommended that monitoring of gas emission rates should be undertaken in the immediate post-reclamation period.  The review of the gas monitoring results would determine the need for gas protection measures to be incorporated in the building design to prevent the ingress and / or accumulation of any methane gas emissions to potentially dangerous concentrations.  With the incorporation of the recommended gas protection measures in the design of the developments, if necessary, together with the implementation of other recommended precautionary measures during construction activities, the risk to people and property due to biogas emissions from the WDII reclamation is considered to be low. 

13.11      Environmental Monitoring and Audit

13.11.1   Environmental monitoring and audit are recommended for construction dust monitoring, construction and operation noise, water quality and release of biogas.  Site inspection / audit is also recommended for waste management during construction and implementation of landscaping measures during operation.  Details of the recommended mitigation measures, monitoring procedures and locations will be presented in a stand-alone Environmental Monitoring and Audit Manual (EM&A).  This will enable the Contractor to have early warning and provide necessary action to reduce impacts at specific areas if the assessment criteria are approached.  The effectiveness of on-site control measures could also be evaluated through the monitoring exercise.  All the recommended mitigation measures should be incorporated into the EM&A programme for implementation.

13.12      Overall Conclusion

13.12.1   The findings of this EIA have provided information on the nature and extent of environmental impacts arising from the construction and operation of the Project.  The EIA has, where appropriate, identified mitigation measures to ensure compliance with environmental legislation and standards.

13.12.2   Overall, the EIA Report for the development of WDII has predicted that the Project will generally comply with all environmental standards and legislation after the proposed construction and operational stage mitigation measures are implemented.  This EIA has also demonstrated the general acceptability of the residual impacts from the Project and the protection of the population and environmentally sensitive resources.  Environmental monitoring and audit mechanisms have been recommended before and during construction and operation, where necessary, to verify the accuracy of the EIA predictions and the effectiveness of recommended mitigation measures.