7
land
contamination
7.1
Introduction
7.1.1
This
section reviews the potential environmental issues associated with land
contamination and assesses the implications of land contamination for the
proposed land uses at the site in accordance with the EIA Study Brief Clause
6.5.11.
7.2
Environmental
Legislation, Policies, Plans, Standards and Criteria
7.2.1
The
Practice Note for Professional Persons ProPECC PN3/94 “Contaminated Land
Assessment and Remediation” and “Guidance Notes for Investigation and
Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards, and
Car Repair / Dismantling Workshops” issued
by the Environmental Protection Department (EPD) provide guidance on land
contamination assessment. This note
makes reference to criteria developed in the Netherlands, which are most
comprehensive and widely used for contaminated site assessment. There are currently no standards for the
clean-up of contaminated soil and groundwater in Hong Kong. However, the Dutch guidelines are generally
referenced as the criteria for assessing soil and groundwater contamination.
7.2.2
Provisions
for consideration of contamination issues are given in the Section 3 “Potential
Contaminated Land Issues” of Annex 19 “Guidelines for Assessment of Impact on
Sites of Cultural Heritage and Other Impacts” of the Technical Memorandum on
Environmental Impact Assessment Process (EIAO-TM).
7.3
Existing
Land Contamination Condition
7.3.1
Preliminary
information reveals that there are several potential contaminating land uses
within the Study Area:
·
A King Marine, an existing
shipyard, is located at the eastern part of the development area;
·
Royal Hong Kong Yacht Club
(RHKYC) is located at the central part of the development area;
·
Wan Chai West Preliminary
Treatment Works (PTW), a preliminary sewage treatment works, is located at Lung
King Street;
·
Wan Chai East PTW, a
preliminary sewage treatment works, is located between Hung Hing Road and Wan
Shing Street; and
·
some car repairing workshops
are located along the segment between Luard Road and Fleming Road of Jaffe
Road.
7.3.2
It
is anticipated that only limited chemicals are used at these preliminary sewage
treatment works and any chemical waste generated would be handled and disposed
of properly by Government officials. In
addition, the car workshops are located more than 100 m away from the site
boundary of WDII. However, the proposed
construction works for the elevated section of the trunk road would be carried
out to the southern part of the RHKYC.
As such, the concern of the land contamination assessment would be on A
King Marine and the RHKYC.
7.4
Identification
of Sensitive Receivers
7.4.1
Compared
to the future users of the land within the Study Area, construction workers are
more likely to be exposed to any potential contaminated material during
excavation and preparation of foundation works.
Depending on the nature of the contaminants, hazard during preparation
of foundations and subsurface services may be significant. The principal exposure routes for workers
include:
·
direct ingestion of
contaminated soils through eating, drinking or smoking on site; and
·
dermal contact with
contaminated spoil.
7.4.2
Groundwater
contamination, if severe, can be regarded as a source of marine water pollution
in coastal areas as a result of percolation and infiltration.
7.5
Description
of the Environment
A King Marine
7.5.1
The
following background information has been reviewed for the environmental
setting and historical uses of the subject shipyard:
·
Aerial
photographs from Causeway Bay (1968, 32259 of 5.11.80, A20665 of 19.3.90,
A36934 of 5.12.93, CN12608 of 7.12.95, and A50906 of 3.2.00); and
·
Sheet
11 of the Geotechnical Control Office Series HGM 20, Solid and Superficial
Geology Map (Edition 1, 1986).
7.5.2
The
review of relevant historical aerial photographs indicated that full-scale
shipyard operation has been commenced before 1968. However, the scale of operation has been
gradually diminished and eventually business operation at the east portion of
the site ceased in 1994 for the provision of fire station.
7.5.3
The
review of the Solid and Superficial Geology Map indicates that the land within
the subject shipyard is comprised of marine sand overlain by fill and sanitary
fill.
The Royal Hong Kong Yacht Club
7.5.4
The
following background information has been reviewed for the environmental
setting and historical uses of the subject yacht club:
·
Aerial
photographs from Causeway Bay (7222 of 1963, 2381 of 1969, 29775 of 1980,
A20669 of 1990 and CN26290 of 2000); and
·
Sheet
11 of the Geotechnical Control Office Series HGM 20, Solid and Superficial
Geology Map (Edition 1, 1986).
7.5.5
The
review of relevant historical aerial photographs indicated that full-scale
yacht club has been commenced before 1963.
With the construction of Cross Harbour Tunnel at the 1969, the
waterfront was shaped to the recent landscape.
After the construction of the breakwater at the northern side of Kellett
Island and the swimming pool of the yacht club (completed at 1990), no further
change is found afterwards.
7.5.6
The
review of the Solid and Superficial Geology Map indicates that the land within
the subject yacht club is comprised of marine sand overlain by fill and
sanitary fill.
7.6
Assessment
Methodology
7.6.1
The
assessment methodology was developed in accordance with the Practice Note
ProPECC PN3/94 “Contaminated Land
Assessment and Remediation” and “Guidance Notes for Investigation and
Remediation of Contamination Sites of: Petrol Filling Stations, Boatyards, and
Car Repair / Dismantling Workshops” issued by EPD.
Environmental Information Review
7.6.2
Specific
information, that is, historical records of chemical spillage and any
violations of environmental regulations, have been requested from the Fire
Services Department (FSD) and the Local Control Office (LCO) of Environmental
Protection Department (EPD).
7.6.3
Response
from the LCO (Territory South) has been received. There is no record of chemical spillage and
conviction in the study area in connection with land contamination.
Land Contamination Assessment
7.6.4
A
Contamination Assessment Plan (CAP) has been prepared, as a separate document,
for this Project. The CAP is contained
in Appendix 7.1 of this report. This
plan outlines the sampling locations, sampling and testing schedule for
investigation works at A King Marine and the RHKYC. The approximate area of the subject shipyard
and the yacht club are 2,504 m2 and 19,068 m2
respectively. According to EPD’s
“Guidance Notes for Investigation and Remediation of Contamination Sites of:
Petrol Filling Stations, Boatyards, and Car Repair / Dismantling Workshops”,
eight and twenty eight sampling points would be sufficient for the A King
Marine and the RHKYC, respectively.
Sampling plans for the A King Marine and RHKYC sites are presented in
Figures 7.1 and 7.2 respectively.
7.6.5
Since
the study team could not gain access to the subject shipyard and the yacht club,
the proposed sampling locations and number of sampling holes contained in the
CAP are subject to review prior to site investigation works when access to the
site becomes available.
7.6.6
A
Contamination Assessment Report (CAR) shall be compiled after completing the
site investigation works and obtaining results from laboratory. This report shall include comparison of
findings with standards and interpretation.
The laboratory testing results should be interpreted in accordance with
the ProPECC Note No. 3/94. The
contamination levels should be compared with Dutch guidelines or other
international practices as appropriate.
7.6.7
Remediation
Action Plan (RAP) should be prepared in accordance with EPD’s requirements if
necessary and submitted to EPD for approval.
7.7
Identification
of Potential Environmental Impacts
Potential Sources of Impact
A
King Marine
7.7.1
As
site inspection at A King Marine was not possible due to refusal from shipyard
operators. Therefore, only a visual
inspection was conducted outside the shipyard in May 2000.
7.7.2
Based
on the preliminary site observations and our experience with shipyard
operations, the following “hotspot” areas in light of land contamination were
identified:
·
Winch;
·
Slipway;
·
Storage Tank;
·
Workshop;
·
Chemical / Dangerous Goods
Storage Area; and
·
Waste Disposal Area.
7.7.3
Table
7.1 presents the potential contaminants that are likely to be found in the
above-mentioned “hotspots”.
Table
7.1 Potential
Contaminants Associated with Historical Shipyard Operations
Areas
|
Potential Contaminants
|
Winch
|
Lube
oil
|
Slipway
|
Lube
oil residue, anti-fouling agent, paint stripping
|
Storage
tank
|
Petroleum
product
|
Chemical
storage area
|
Paint,
chlorinated solvent, petroleum product
|
Waste
disposal pit
|
Paint,
chlorinated solvent, petroleum product, acid, Lube Oil, anti-fouling agent
|
Workshop
|
Paint,
chlorinated solvent, lube oil, hydraulic oil
|
The Royal Hong Kong Yacht Club
7.7.4
Site
inspection at the RHKYC was also not possible and only a visual inspection was
conducted outside the club in May 2000.
7.7.5
Based
on the preliminary site observations, the following “hotspot” areas in light of
land contamination were identified:
·
Workshop;
·
Hoist;
·
Boat
Storage Area; and
·
Car
park.
7.7.6
Table
7.2 presents the potential contaminants that are likely to be found in the
above-mentioned “hotspots”.
Table 7.2 Potential
Contaminants to be found on The Royal Hong Kong Yacht Club
Areas
|
Potential Contaminants
|
Workshop
|
Lube
oil, hydraulic oil
|
Hoist
|
Lube
oil residue, anti-fouling agent, paint stripping
|
Boat
Storage
|
Petroleum
product
|
Car
park
|
Petroleum
product
|
Potential Impacts
7.7.7
The
implications of potential land contamination for development at A King Marine
and the RHKYC relate to the following:
·
There
may be potentially adverse effects on the health and safety of workers during
site clearance / construction on site due to their potential exposure to
hazardous or flammable materials in soil.
·
Disposal
of potentially contaminated spoil that will arise during site clearance /
construction works.
·
Based
on the consultants’ experience in land contamination assessment for the same
shipyard for Architectural Services Department (ASD) in 1994, contaminants were
primarily due to the heavier fractions of petroleum hydrocarbons and heavy
metals. These contaminants were
relatively immobile and contamination was found to be localised and limited to
the groundwater table. No off-site
migration was detected.
7.7.8
It
is currently proposed to reserve the site at A King Marine for an entertainment
centre, with uses such as an indoor interactive theme park, game stalls,
restaurants, shops and car parking. The
estimated site area of the proposed complex is 7,736 m2.
7.8
Prediction
and Evaluation of Environmental Impacts
7.8.1
The
study team could not gain access to A King Marine and the RHKYC to conduct any
site investigation works. Therefore, we
propose that the land contamination assessment or other relevant site
investigation works should be conducted prior to the commencement of site
clearance / construction works. A CAR
should then be compiled to delineate the extent of land contamination and
assess the associated environmental impacts.
If land contamination is confirmed, a RAP should be devised and
submitted to the EPD for approval. The
CAR/CAP should be submitted to EPD for approval prior to the commencement of
the site clearance / construction works.
7.8.2
Due
to the above reasons, it is suggested that investigation works specified in the
CAP or any subsequent additional investigation in relation to land
contamination assessment should be conducted as part of the Implementation
Schedule of the proposed mitigation measures in the decommissioning stage of
the sites.
7.8.3
A
land contamination survey was undertaken in 1994 at the area of A King Shipyard
before that area was resumed for Causeway Bay Fire Station(). The site investigation results (involved 6
trial pits) did not indicate any soil and groundwater contamination that
warranted remediation. Based on the
findings and recommendations of that Study, there is likely no insurmountable
land contamination impact at the existing A King Shipyard.
7.8.4
According
to the land use plan of the WDII Development, about half of the existing RHKYC
area will be resumed for the development. However, most of the area to be resumed is
carpark area and only a relatively small area, approximately 1,175 m2,
is used for the existing maintenance works area. As this area is protected by concrete paving
and the scale of maintenance works at the RHKYC is smaller than that of the A
King Shipyard, it is anticipated that potential land contamination at the
maintenance area of the RHKYC will not be insurmountable.
7.9
Mitigation
Measures for Land Contamination
7.9.1
Four
possible options are proposed as follows depending on the extent of land
contamination:
·
if the contamination level is low, and risk
assessment indicates that there are no significant risks, then leaving the
contaminant in place in conjunction with capping / stabilisation may be
appropriate;
·
if the contamination level is high but the volume of
contaminated soil is limited, the contaminated soil can be excavated and
disposed of to landfill, subject to EPD’s agreement;
·
if
the contamination level is high and the volume of contaminated soil is
significant, stabilisation may be necessary to treat the contaminated soil to
levels suitable for leaving in-situ as far as possible;
·
if
floating oil exists on the water table, then free product recovery by pumps and
bailing may be required.
7.9.2
Subject
to sampling results, any contaminated land treatments are subjected to EPD’s
requirements on handling, treatment and disposal. Where effluent stream is to be discharged
from site, the discharge should comply with the WPCO and any EPD’s special
requirements.
7.10
Mitigation
Measures for Workers’ Health and Safety
7.10.1
The
following precautionary measures should be implemented to minimise exposure
hazards to workers during site clearance / construction works:
·
site
workers should wear appropriate personal protective equipment (that is, gloves,
masks) when exposed to potential contaminated soil and groundwater;
·
avoid
stockpiling of spoils as far as possible;
·
avoid
using contaminated soil for landscaping;
·
adequate
washing facilities should be provided on site; and
·
engage
licensed collectors to collect any contaminated materials in accordance with
the Waste Disposal Ordinance, Waste Disposal (Chemical Waste) (General)
Regulation.
7.11
Environmental
Monitoring and Audit Requirements
7.11.1
The
requirements for environmental monitoring and audit (EM&A) with respect to
land contamination, if necessary, should be determined upon completion of all
relevant site investigation works.
7.12
Conclusion
7.12.1
This
land contamination assessment includes a review of site history and
environmental information, and a preliminary site inspection (outside the
shipyard and the yacht club). Based on
the available information, the potential for land contamination at the study
area is considered not insurmountable.
Potential contaminants arising from shipyard operations and the yacht
club have been identified in Section 7.7.
7.12.2
The
study team could not gain access to the subject shipyard and the yacht club for
intrusive site investigation works at this stage. It is proposed that site investigation works
should be conducted prior to the commencement of site clearance / construction
works. Furthermore, the proposed
sampling locations, sampling and testing schedule specified in the
contamination assessment plan should be subject to review prior to the site
investigation works. The CAP will be
revised and submitted to EPD for approval prior to the commencement of the land
contamination assessment work on site.