Table A2-1 Construction Plant Inventory (No Mitigation Measures)
Activity ID Activity Noise Source TM ref UNIT SWL/unit Barrier Atten sub-SWL
101 General Site Clearance / Demolition Works
Group 1: demolition Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Backhoe CNP 081 1 112 0 112 1.58E+11
Excavator CNP 081 1 112 0 112 1.58E+11
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Breaker, excavator mounted  CNP 028 1 122 0 122 1.58E+12
Total = 123 1.96E+12
Group 2: clearance  Bulldozer CNP 030 1 115 0 115 3.16E+11
Crawler Crane  CNP 048 1 112 0 112 1.58E+11
Dump Truck CNP 067 2 117 0 120 1E+12
Excavator CNP 081 1 112 0 112 1.58E+11
Total = 122 1.64E+12
102-P1 Construction of Kam Tin SPS
Group 1: foundation work Piling, large diameter bored, reverse circulation drill CNP 166 2 100 0 103 2E+10
Wheeled Excavator/Loader CNP 081 1 112 0 112 1.58E+11
Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Dump Truck CNP 067 2 117 0 120 1E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Mobile crane CNP 048 1 112 0 112 1.58E+11
Total = 122 1.43E+12
Group 2: superstructure Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Handheld Breaker (mass > 35kg) CNP 026 1 114 0 114 2.51E+11
Concrete lorry mixer CNP 044 1 109 0 109 7.94E+10
Poker vibrator CNP 170 1 113 0 113 2E+11
Bar bender and cutter CNP 021 1 90 0 90 1E+09
Lorry CNP 141 1 112 0 112 1.58E+11
Mobile crane CNP 048 1 112 0 112 1.58E+11
Saw, circular, wood CNP 201 1 108 0 108 6.31E+10
Total = 120 9.36E+11
102-P2 Construction of Sha Po SPS
Group 1: foundation work Piling, large diameter bored, reverse circulation drill CNP 166 2 100 0 103 2E+10
Wheeled Excavator/Loader CNP 081 1 112 0 112 1.58E+11
Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Dump Truck CNP 067 2 117 0 120 1E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Mobile crane CNP 048 1 112 0 112 1.58E+11
Total = 122 1.43E+12
Group 2: superstructure Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Handheld Breaker (mass > 35kg) CNP 026 1 114 0 114 2.51E+11
Concrete lorry mixer CNP 044 1 109 0 109 7.94E+10
Poker vibrator CNP 170 1 113 0 113 2E+11
Bar bender and cutter CNP 021 1 90 0 90 1E+09
Lorry CNP 141 1 112 0 112 1.58E+11
Mobile crane CNP 048 1 112 0 112 1.58E+11
Saw, circular, wood CNP 201 1 108 0 108 6.31E+10
Total = 120 9.36E+11
102-P3 Construction of Nam San Wai SPS
Group 1: foundation work Piling, large diameter bored, reverse circulation drill CNP 166 2 100 0 103 2E+10
Wheeled Excavator/Loader CNP 081 1 112 0 112 1.58E+11
Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Dump Truck CNP 067 2 117 0 120 1E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Mobile crane CNP 048 1 112 0 112 1.58E+11
Total = 122 1.43E+12
Group 2: superstructure Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Handheld Breaker (mass > 35kg) CNP 026 1 114 0 114 2.51E+11
Concrete lorry mixer CNP 044 1 109 0 109 7.94E+10
Poker vibrator CNP 170 1 113 0 113 2E+11
Bar bender and cutter CNP 021 1 90 0 90 1E+09
Lorry CNP 141 1 112 0 112 1.58E+11
Mobile crane CNP 048 1 112 0 112 1.58E+11
Saw, circular, wood CNP 201 1 108 0 108 6.31E+10
Total = 120 9.36E+11
102-P4 Construction of Shui Tsan Tin SPS
Group 1: foundation work Piling, large diameter bored, reverse circulation drill CNP 166 2 100 0 103 2E+10
Wheeled Excavator/Loader CNP 081 1 112 0 112 1.58E+11
Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Dump Truck CNP 067 2 117 0 120 1E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Mobile crane CNP 048 1 112 0 112 1.58E+11
Total = 122 1.43E+12
Group 2: superstructure Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Handheld Breaker (mass > 35kg) CNP 026 1 114 0 114 2.51E+11
Concrete lorry mixer CNP 044 1 109 0 109 7.94E+10
Poker vibrator CNP 170 1 113 0 113 2E+11
Bar bender and cutter CNP 021 1 90 0 90 1E+09
Lorry CNP 141 1 112 0 112 1.58E+11
Mobile crane CNP 048 1 112 0 112 1.58E+11
Saw, circular, wood CNP 201 1 108 0 108 6.31E+10
Total = 120 9.36E+11
102-P5 Construction of Ng Ka Tsuen SPS
Group 1: foundation work Piling, large diameter bored, reverse circulation drill CNP 166 2 100 0 103 2E+10
Wheeled Excavator/Loader CNP 081 1 112 0 112 1.58E+11
Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Dump Truck CNP 067 2 117 0 120 1E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Mobile crane CNP 048 1 112 0 112 1.58E+11
Total = 122 1.43E+12
Group 2: superstructure Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Handheld Breaker (mass > 35kg) CNP 026 1 114 0 114 2.51E+11
Concrete lorry mixer CNP 044 1 109 0 109 7.94E+10
Poker vibrator CNP 170 1 113 0 113 2E+11
Bar bender and cutter CNP 021 1 90 0 90 1E+09
Lorry CNP 141 1 112 0 112 1.58E+11
Mobile crane CNP 048 1 112 0 112 1.58E+11
Saw, circular, wood CNP 201 1 108 0 108 6.31E+10
Total = 120 9.36E+11
102-P6 Construction of Pang Ka Tsuen SPS
Group 1: foundation work Piling, large diameter bored, reverse circulation drill CNP 166 2 100 0 103 2E+10
Wheeled Excavator/Loader CNP 081 1 112 0 112 1.58E+11
Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Dump Truck CNP 067 2 117 0 120 1E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Mobile crane CNP 048 1 112 0 112 1.58E+11
Total = 122 1.43E+12
Group 2: superstructure Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Handheld Breaker (mass > 35kg) CNP 026 1 114 0 114 2.51E+11
Concrete lorry mixer CNP 044 1 109 0 109 7.94E+10
Poker vibrator CNP 170 1 113 0 113 2E+11
Bar bender and cutter CNP 021 1 90 0 90 1E+09
Lorry CNP 141 1 112 0 112 1.58E+11
Mobile crane CNP 048 1 112 0 112 1.58E+11
Saw, circular, wood CNP 201 1 108 0 108 6.31E+10
Total = 120 9.36E+11
102-P7 Construction of Leung Uk Tsuen Sewage SPS
Group 1: foundation work Piling, large diameter bored, reverse circulation drill CNP 166 2 100 0 103 2E+10
Wheeled Excavator/Loader CNP 081 1 112 0 112 1.58E+11
Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Dump Truck CNP 067 2 117 0 120 1E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Mobile crane CNP 048 1 112 0 112 1.58E+11
Total = 122 1.43E+12
Group 2: superstructure Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Handheld Breaker (mass > 35kg) CNP 026 1 114 0 114 2.51E+11
Concrete lorry mixer CNP 044 1 109 0 109 7.94E+10
Poker vibrator CNP 170 1 113 0 113 2E+11
Bar bender and cutter CNP 021 1 90 0 90 1E+09
Lorry CNP 141 1 112 0 112 1.58E+11
Mobile crane CNP 048 1 112 0 112 1.58E+11
Saw, circular, wood CNP 201 1 108 0 108 6.31E+10
Total = 120 9.36E+11
103 Sewers and Rising Mains using Open Trench Method (including earthworks activities)
Group 1: site preparation Piling, oscillator CNP 165 1 115 0 115 3.16E+11
Excavator with Multi Attachments CNP 081 1 112 0 112 1.58E+11
Breaker, excavator mounted  CNP 028 1 122 0 122 1.58E+12
Total = 123 2.06E+12
Group 2: trench excavation and earthworks Excavator CNP 081 1 112 0 112 1.58E+11
Dump Truck CNP 067 2 117 0 120 1E+12
Roller / Vibrating Roller CNP 186 1 108 0 108 6.31E+10
Total = 121 1.22E+12
Group 3: finishes Concrete Mixer Truck CNP 044 1 109 0 109 7.94E+10
Concrete Poker Vibrator CNP 170 1 113 0 113 2E+11
Crawler Crane with Concrete Skip CNP 048 1 112 0 112 1.58E+11
Flat Bed Lorry CNP 141 1 112 0 112 1.58E+11
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Total = 118 6.59E+11
104 Sewers and Rising Mains using Pipe Jacking Method
Group 1: site preparation Air Compressor (Air Flow > 30 cub. m/min) CNP 003 1 104 0 104 2.51E+10
Excavator with Multi Attachments CNP 081 1 112 0 112 1.58E+11
Breaker, excavator mounted  CNP 028 1 122 0 122 1.58E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Total = 123 1.83E+12
Group 2: pipe jacking Concrete Mixer Truck CNP 044 1 109 0 109 7.94E+10
Crawler Crane with Concrete Skip CNP 048 1 112 0 112 1.58E+11
Dump Truck CNP 067 2 117 0 120 1E+12
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Water Pump CNP 281 2 88 0 91 1.26E+09
Total = 121 1.3E+12
105 Road Pavement and Finishes Ballast Tamper CNP 029 2 105 0 108 6.32E+10
Compactor CNP 050 1 105 0 105 3.16E+10
Road Roller CNP 185 1 108 0 108 6.31E+10
Lorry CNP 141 1 112 0 112 1.58E+11
Asphalt Paver CNP 004 1 109 0 109 7.94E+10
Loader CNP 081 1 112 0 112 1.58E+11
Generator, silenced CNP 101 1 108 0 108 6.31E+10
Total = 118 6.17E+11
107a Piling - Construction of SPS / Sewer and Rising Mains Generator, silenced CNP 101 1 108 0 108 6.31E+10
Total = 108 6.31E+10
107b Piling - Construction of SPS / Sewer and Rising Mains Hydraulic Hammer (double acting ) driving steel pile PP-TM 1 129 0 129 7.94E+12
Total = 129 7.94E+12
Correction for No. of PME = 10 log (no. of PME)
Sub_SWL1 = SWL (CNP/BS5228) + Correction for No. of PME -  Barrier Corection
Total  Sub_SWL = 10 log( 10^(Sub_SWL1/10) +10^(Sub_SWL2/10) +10^(Sub_SWL3/10) +10^(Sub_SWLn/10))