2                    PROJECT DESCRIPTION

 

Location and Scale of the Project

 

2.1              The proposed site is located on the eastern coast of Lung Kwu Chau as shown in Figure 2.1.  The location of the existing jetty is also shown on Figure 2.1.

 

Construction and Operational Activities

 

2.2              The major activities involved during the construction stage of the Project are dredging for foundation of the jetty and catwalk, laying of rock bedding, construction of concrete catwalk, extension of an existing footpath, dredging for approach channel and demolition of the existing jetty.  A maximum production rate for the dredging works is 500 m3 per day, with one dredger working on-site at any time. 

 

2.3              During the operation stage, the only activities at the proposed jetty will be the berthing and mooring of vessels for the purpose of servicing and maintaining the DVOR/DME station and for emergency repair work, and infrequent maintenance dredging of the approach channel.

 

Project Programme

 

2.4              The planning, design and supervision of construction of the proposed jetty will be conducted by CED.  The construction works is scheduled to commence in March 2003 for completion by December 2003.   

 

2.5              It is expected that this Project has no major interaction with other projects.

 

Preferred Jetty Location and Design Option

 

2.6              Under the preliminary design given in the EIA Study Brief, the Project comprises construction of a precast concrete blockwork jetty and a concrete catwalk and dredging of an approach channel.  Alternative jetty location and design options have been investigated and the preliminary design has been refined from an environmental perspective.  Alternative transportation modes for servicing and maintaining the DVOR/DME station have also been assessed with regard to their environmental benefits and disbenefits.  Construction of the proposed jetty is considered necessary as there are no other modes of transportation available other than by sea to transport the required equipment and personnel to the island and to provide access to facilitate emergency repair work of the DVOR/DME Station.  

 

2.7              In the vicinity of the existing small jetty, two alternative locations (Options 2 and 3) have been identified in addition to the initially proposed jetty location (Option 1 as shown in Figure 2.1).  An evaluation of the environmental aspects of these alternative locations was undertaken with respect to the issues of water quality/dredged sediment, ecology, archaeology and visual/landscape. 

 

2.8              Option 3 was preferred after the evaluation of the environmental benefits and disbenefits of the three options.  Comparing with Option 1, the length of the catwalk in Option 3 was substantially reduced and the dredging area was smaller.  This would minimise the area of seabed affected by the construction activities and the associated water quality, ecology, archaeology and visual/landscape impacts.  Option 2 is a less preferred location for the jetty compared to Option 3.  This location has a natural shoreline, with the highest density of intertidal organisms.  Extension of a path to this location would cause major disturbance to the coastal terrestrial habitats owing to the need for major construction works.  In addition, Option 2 is sited near the shipwreck area to the north of the bay where soft corals are attached to the wreck.  Option 3 was preferred to Option 2 as the majority of the shore and backshore areas of Option 3 are already exposed to significant human disturbance.

 

2.9              The preferred option selected for the location of the jetty (refer to Figure 2.2) incorporates the recommendations raised at the Marine Parks Committee meeting held on 9 November 2001.  The main environmental benefits of the proposed jetty location are that it would require a smaller dredging area and cause less intrusion into the bay of the adjacent beach, and therefore would have less impact on the dolphins.  Support from the Lung Kwu Tan villagers for the preferred option has been obtained.

 

2.10          Based on the preferred jetty location, the scope of the Project comprises the following:

·        construction of a precast concrete blockwork jetty (10 m by 20 m) with a single berth;

·        construction of a concrete catwalk (approximately 22 m long);

·        dredging of an approach channel to a level of –2.5 mCD in front of the berth;

·        installation of miscellaneous facilities on the jetty, including lighting, navigation light, fendering, handrails, bollards, tide gauge, etc;

·        demolition of the existing jetty upon completion of the proposed jetty; and

·        extension of an existing footpath.

 

2.11          The environmental benefits and disbenefits of alternative design options for the jetty have been considered.  The following design option is preferred:

·        Adopt a blockwork structure to eliminate the need for any piling works which would be the most significant potential source of impact on the dolphins.

·        Use pre-cast structures to minimise the time of construction and reduce water quality impacts.

·        Provide openings along the bottom of the catwalk to allow seawater circulation.  It is recommended that the number/size of openings beneath the catwalk be maximized as far as practicable to allow seawater circulation.

·        Minimise overall jetty structure to minimise dredging works and associated impacts.