1.
INTRODUCTION
1.1.
In 1993 the Environmental Protection Department (EPD)
commissioned a Sewerage Master Plan (SMP) study of the Outlying Islands. The
areas studied included: Lantau Island, Lamma Island, Cheung Chau, Peng Chau and
some other smaller islands to the west and south of Hong Kong. The SMP was completed in 1994 and made
recommendations which included some improvements and extensions to the existing
sewerage infrastructure.
1.2.
Further to the SMP Study, Drainage Services Department (DSD)
was commissioned by Environmental Protection Department (EPD) to carry out a
Preliminary Project Feasibility Study (PPFS) for the Outlying Islands Sewerage
Stage 1 Phase II in 1996. The
Project which forms part of the Outlying Island Sewerage Project, includes the
design and construction of sewerage at Cheung Chau, Peng Chau and Lamma Island
(Sok Kwu Wan and Yung Shue Wan).
1.3.
Package J, which is one of the packages under the Outlying
Islands Sewerage Stage 1 Phase II, consists of provision of sewage treatment and
disposal facilities as well as a sewerage system including pumping stations and
rising mains to collect and transfer the sewage and wastewater arising from the
Sok Kwu Wan catchment areas to the proposed sewage treatment and disposal
facilities. On 1st May 1998
Drainage Services Department (DSD) commissioned Maunsell Consultants Asia Ltd
(MCAL) as lead consultants to implement the Outlying Islands Sewerage Scheme
Stage 1 Phase II works, Package J Sok Kwu Wan Sewage Treatment and Disposal
Facilities (hereinafter termed the Project) under Agreement No. CE 20/96.
1.4.
The submarine sewage outfall is classified as designated
project under Schedule 2 Part 1, F.6 of the Environmental Impact Assessment
Ordinance (EIAO). According to the
draft Lamma Island Outline Zoning Plan (OZP) No. S/I-LI/4, a pumping station
(P1a), some of the sewer alignments and the proposed sewage treatment works
(STW) fall within Conservation Area (CA) and hence these works are also
classified as designated projects under Schedule 2 Part 1, Q1 of the EIAO. Maunsell Environmental Management
Consultant Ltd. was commissioned by MCAL to carry out an Environmental Impact
Assessment (EIA) Study in order to assess the potential environmental impacts arising
from the construction and operation phases of the Project.
Objectives of the EIA Study
1.5.
The purpose of this EIA study is to assess the environmental
issues arising from the construction and operation phases of the Project, and
to recommend appropriate mitigation measures for all identified adverse
environmental impacts.
1.6.
The objectives of the EIA Study are described below:
(a)
to describe the Project and associated
works together with the requirements for carrying out the Project;
(b)
to identify and describe the elements
of the community and environment likely to be affected by the Project, and/or
likely to cause adverse impacts upon the Project, including both the natural
and man-made environment;
(c)
to identify and quantify emission
sources and determine the significance of impacts on sensitive receivers and
potential affected uses;
(d)
to identify and quantify the potential
fisheries impacts, especially potential impacts on Sok Kwu Wan fish culture
zone, associated with the Project;
(e)
to identify and quantify any potential
losses or damage to flora, fauna and natural habitats;
(f)
to identify existing landscape and
visual quality in the “study area” for the purpose of evaluating the landscape
and visual impact of the Project;
(g)
to propose the provision of
infrastructure or mitigation measures so as to minimize pollution,
environmental disturbance and nuisance during construction, operation of the
Project;
(h)
to identify, predict and evaluate the
residual (i.e. after practicable mitigation) environmental impacts and
cumulative effects expected to arise during the construction, operation stages
of the Project in relation to the sensitive receivers and potential affected
uses;
(i)
to identify, assess and specify
methods, measures and standards, to be included in the detailed design,
construction, operation of the Project which are necessary to mitigate these
impacts and reduce them to acceptable levels;
(j)
to design and specify the
environmental monitoring and audit requirements necessary to ensure the
implementation and the effectiveness of the environmental protection and
pollution control measures adopted;
(k)
to investigate the extent of
side-effects of proposed mitigation measures that may lead to other forms of
impacts;
(l)
to identify constraints associated
with the mitigation measures recommended in the study; and
(m)
to identify any additional studies
necessary to fulfill the objectives to the requirements of the EIA Study
The Approach
1.7.
The assessment was conducted in accordance with the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM) and based on
information available at the time of this EIA study. Relevant reports and drawings have been reviewed and
findings have been incorporated where appropriate in this EIA Report. Relevant studies to this study are
listed below:
·
Final Report of the Outlying Islands
Sewerage Master Plan Study;
·
South West New Territories Development
Strategy Review;
·
Territorial Development Strategy
Review;
·
North Lantau & Islands Development
Programme;
·
Rural Planning and Improvement
Strategy; and
·
Integrated Sludge Disposal Study.
1.8.
The quantitative modelling and calculations, together with the
input parameters, have been verified and agreed with the relevant government
departments. Where applicable,
realistic worst case scenarios have been adopted. Although the data used in the assessment have gaps, it is
considered that the data is sufficient and suitable for the purpose of impact
prediction. The selection, use and
reliability of data used in the assessment is discussed in each of the
technical assessment sections. The
assumptions used in the assessment are also explained where relevant in each
section.
1.9.
The background to the Project and the objectives of this
report are introduced in Section 1.
Description of the Project is provided in Section 2. Sections 3 through 10 detail the
results of the environmental assessment of each key subject area, covering
relevant legislation, existing environmental conditions, assessment criteria
and methods, and assessment findings.
Sections 3 – 10 include:
Section 3:Air Quality
Section 4: Noise
Section 5: Water Quality
Section 6: Sediment Contamination
Section 7:Solid Waste
Section 8: Ecological Impact
Section 9 Fisheries Impact
Section 10: Visual and Landscape Impact
1.10.
Since the EIA Study Brief does not require a heritage impact
assessment (HIA) for the proposed Project, the EIA Report does not include the
HIA. Nevertheless, the cultural
heritage aspects of the Project have been separately conducted and the results
indicate that the proposed project would not result in any adverse cultural
heritage impacts.
1.11.
An outline of the requirements for Environmental Monitoring
and Audit (EM&A) programmes to be included in the development is discussed
in Section 11. Detailed EM&A
programmes are presented in a separate EM&A Manual. A detailed implementation schedule of
the recommended mitigation measures are provided in Section 12. A conclusion of the whole assessment is
given in Section 13.