Appendix 4.1     
Assumed Powered Mechanical Equipment for Pumping Stations (P1a, P1b, & P2) Construction (Unmitigated)
Foundation
Excavation
Powered Mechanical Equipment Reference No. Items SWL/Item On-Time Sub-total Total SWL Total SWL
(PME)     dB(A) % SWL dB(A) dB(A) dB(A)
Excavator (mini) BS C.3, item 108 2 97 100% 100    
Hydraulic breaker CNP 027 1 122 100% 122    
Lorry (mini) BS C.8, item 25 2 96 100% 99 122.0 122.05
Formwork, reinforcement & fixing
Powered Mechanical Equipment Reference No. Items SWL/Item On-Time Sub-total Total SWL Total SWL
(PME)     dB(A) % SWL dB(A) dB(A) dB(A)
Mobile crane (mini) BS C.7, item 118 2 99 100% 102 102.5  
Bar bender and cutter (electric) CNP 021 2 90 100% 93
Concreting
Powered Mechanical Equipment Reference No. Items SWL/Item On-Time Sub-total Total SWL Total SWL
(PME)     dB(A) % SWL dB(A) dB(A) dB(A)
Lorry (mini) BS C.8, item 25 2 96 100% 99    
Concrete mixer (electric) CNP 045 2 96 100% 99    
Air Compressor CNP 002 2 102 100% 105    
Vibratory poker, hand-held CNP 170 2 113 100% 116 116.5 116.50
Backfilling
Powered Mechanical Equipment Reference No. Items SWL/Item On-Time Sub-total Total SWL Total SWL
(PME)     dB(A) % SWL dB(A) dB(A) dB(A)
Compactor CNP 050 2 105 100.0% 108 108.0 108.01
Superstructural Works
Formwork, reinforcement & fixing
Powered Mechanical Equipment Reference No. Items SWL/Item On-time Sub-total Total SWL Total SWL
(PME)     dB(A) % SWL dB(A) dB(A) dB(A)
Mobile crane (mini) BS C.7, item 118 2 99 100% 102 102.5  
Bar bender and cutter (electric) CNP 021 2 90 100% 93
Concreting
Powered Mechanical Equipment Reference No. Items SWL/Item On-Time Sub-total Total SWL Total SWL
(PME)     dB(A) % SWL dB(A) dB(A) dB(A)
Lorry (mini) BS C.8, item 25 2 96 100% 99    
Concrete mixer (electric) CNP 045 2 96 100% 99    
Air Compressor CNP 002 2 102 100% 105    
Vibratory poker, hand-held CNP 170 2 113 100% 116 116.5 116.50
Note:
BS  BS5228 (1997) Part 1 Noise and Vibration Control on Construction and open sites