2.1.1 The main objective of this Project --upgrading and reconstructing the existing Peng Chau Sewage Treatment Works (STW) is to provide sufficient treatment capacity and adequate treatment levels to meet the demand of the projected catchment from Peng Chau as to minimise the water quality impact and the associated odour nuisance due to the untreated discharge.
2.1.2 The Project involves the construction of a secondary treatment works incorporating nitrification, de-nitrification and disinfection facilities. Emergency overflow outfall, storm tanks and a submarine outfall, which will extend with a short distance offshore from the boundary of the STW site are also to be constructed. At present, the Project is in preliminary design stage.
2.2.1 Various consultations were carried out between December 2003 and February 2004 to solicit the public views and support on the proposed STW Upgrade. The consulted parties included the Peng Chau/Discovery Bay Area Committee, Peng Chau Fishermen Association (PCFA), Green Peng Chau Association (GPCA), resident representatives of Sea Crest Villa and Islands District Council (IDC). Summary of the consultations are presented in Table 2-1.
Table 2-1 Summary of Public Consultations
Date of Consultation |
Consulted Parties |
Key Concerns and Suggestions of the Consulted Parties |
Project Proponent’s/ Study Team’s Responses |
Overall Views on the Project |
17 December 2003 |
Peng Chau/Discovery Bay Area Committee |
The environmental impact arising from the project should be acceptable. |
There will be no unacceptable environmental impact from the Project if mitigation measures were implemented. |
Support |
6 January 2004 |
Peng Chau Fishermen Association |
The north-west coast of Tai Lei Island might be a better location for the outfalls. |
A desktop review was conducted on the outfall location suggested by PCFA. It was found in the review that the originally proposed south-west direction was the preferred option. |
Support |
13 January 2004 |
Green Peng Chau Association |
The stakeholders expressed their concern that the effluent from the outfalls might have impact on nearby marine ecology, such as the hippocampus kuda, a species of seahorse, which was found in a dive survey conducted in the vicinity of Tai Lei Island in 2001. |
As suggested by Oceanway Corporation Limited, who conducted the 2001 dive survey, the hippocampus kuda found was not a protected species and it could be found in other marine area in Hong Kong. Unlike sessile marine organisms, seahorse would swim away from affected area and the potential impact on seahorse is thus considered insignificant. In addition, based on the experience of the diving team, the proposed south-west direction was the location with least impact to nearby marine ecology. |
Support |
15 January 2004 |
Resident Representatives of Sea Crest Villa |
The appearance of the STW should be improved. |
The future appearance of the STW will be improved. |
Support |
9 February 2004 |
Islands District Office |
The stakeholders expressed their concern on the potential impact on the marine environment around Peng Chau and Discovery Bay. And the appearance of the proposed STW should be aesthetic. |
There will be no unacceptable impact to the marine environment arising from the Project if mitigation measures were implemented. The appearance of the proposed STW will be aesthetic |
Support |
Please refer to Appendix 2A for the details of the public consultations.
i. Phase 1 Works:
(a) construction of a new STW adjacent to the existing STW comprising secondary treatment with nitrification, de-nitrification and disinfection;
(b) construction of two new submarine outfalls;
(c) provision of de-odourization facilities;
(d) provision of associated sludge treatment facilities;
(e) extension of inlet pumping mains; and
(f) construction of equalisation tank.
ii. Phase 2 Works:
(a) demolition of the existing treatment facilities;
(b) construction of sludge drying bed; and
(c) construction of remaining works.
Flow Considerations
This outfall is located to the southwest area of Peng Chau STW, with the same orientation as the proposed outfall in the PPFS stage. The outfall points towards the channel between Tai Lei Island and Discovery Bay of Lantau. Scattered live coral colonies are found in the outcrop boulder to the southwest of Tai Lei Island (Figure 8-3). Potential impacts from this option to the marine sensitive receiver will be addressed in later section.
This outfall is located to the northwest area of Peng Chau STW, in the vicinity of the pier for transporting refuse. The terrestrial components of alignments would pass through natural habitats of intertidal area. Disturbance of terrestrial and intertidal habitats are likely to occur. The area is composed of mainly non-ecological important dead coral skeleton but some small patches of corals were identified in the marine ecological surveys conducted for this Project.
Option C is located to the eastern side of Tai Lei Island. The outfall is located in the small channel between Tai Lei Island and Peng Chau Island. The terrestrial components would pass through other properties on Tai Lei Island such as LPG storage yard and refuse collection point. The marine component is proposed next to areas where scattered and rich live corals are found in the vicinity. Live corals found in these areas are of low abundance but with relatively high species richness.
Option D is located to the south of Tai Lei Island, parallel to the southern pier. Scattered corals colonies are found around the small outcrop boulder located to the southwest of Tai Lei Island. This site falls within the proposed typhoon shelter for Peng Chau (See Figure 1-1). The implementation schedule of the proposed typhoon shelter, however, is not definite. The presence of typhoon shelter in this area would further decrease the water movement to the south Tai Lei Island.
Option A: This option would have the least air quality impact, noise impact and waste management implication during construction phase due to short terrestrial outfall component. Dredging activities for outfall construction may pose potential impact on the small isolated coral colonies found in the vicinity. No terrestrial ecological impact is anticipated. Due to the shelter of rocky areas of northwest of Tai Lei, the dispersion characteristic in the area is likely worse than Option B but better than Options C and D.
Option B: This option would involve long terrestrial outfall components where higher impacts on air quality, noise, waste management implication and terrestrial and intertidal ecology during construction phase are expected. Despite that better effluent dispersion characteristic can be achieved in this area, the marine ecological survey conducted for this Project revealed that small patches of live coral colonies are found in the vicinity. The marine ecological impact is anticipated to be better than Option C but worse than Options A and D.
Option C: This option would have long terrestrial outfall components on the formed lands. Higher impact on waste management implication than short terrestrial outfall options A and D. This option is closest to the residential areas of Peng Chau Island and higher construction noise and air quality impacts are expected. The marine ecological environment in the area is highly sensitive due to the presence of live coral communities of low abundance and relatively high species richness.
Table 2-2 Impacts Summary for Four Outfall Options
|
Option A –South West Tai Lei |
Option B –North West Tai Lei |
Option C – East of Tai Lei |
Option D – South of Tai Lei |
|
Environmental Issues |
|||||
Air Quality |
Construction Phase |
Potential dust impact from short terrestrial outfall. Same potential impact as Options B and D. |
Construction of terrestrial outfall alignment mostly by tunnelling through the northern rocky shore. Same potential impact as Options A and D. |
Greatest potential fugitive dust impact due to long terrestrial outfall alignment. |
Potential impact from short terrestrial outfall. Same potential impact as Options A and D. |
Operation Phase |
The outfall component would not give rise to operational phase air quality impact such as odour. No difference in operational air quality is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase air quality impact such as odour. No difference in operational air quality is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase air quality impact such as odour. No difference in operational air quality is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase air quality impact such as odour. No difference in operational air quality is anticipated among 4 proposed options. |
|
Noise Impact |
Construction Phase |
Potential impact from short terrestrial outfall. Same potential impact as Option D. |
Construction of terrestrial outfall alignment mostly by tunnelling through the northern rocky shore, longer construction period, more Powered Mechanical Equipment involved. Less impact than Option C but greater than Options A and D. |
Longest terrestrial outfall alignment would likely to have longest construction period. Outfall location is closest to NSR, greatest potential impact. |
Potential impact from short terrestrial outfall. Same potential impact as Option A. |
Operation Phase |
The outfall component would not give rise to operational phase noise impact. No difference in operational noise impact is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase noise impact. No difference in operational noise impact is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase noise impact. No difference in operational noise impact is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase noise impact. No difference in operational noise impact is anticipated among 4 proposed options. |
|
Water Quality |
Construction Phase |
Live coral colonies are found in the northeast (NE) and in the seabed of outcrop boulder to the southwest (SW) of Tai Lei. The former colonies are of low abundance but relatively high species richness and with a higher coral coverage. Coral in the southwest are present in small isolated patches and are anticipated to be less significant than the NE colonies. This option is closest to the SW colonies but farthest away from the NW colonies. The overall dredging impacts may be the smallest among four options. |
Closer to live corals colonies in Tai Lei NE. Higher potential dredging impact than Option A and Option D but less than Option C. |
Alignment closest to a relatively large is of live coral communities. Greatest potential impact due to re-deposition of suspended solids from dredging. Greater potential impact than Options A, B and D. |
This option, located between Option A and Option C, would have larger potential impact on corals than Option A but less than Option C. |
Operation Phase |
Dispersion and dilution characteristics worst than Option B. |
Better dispersion and dilution characteristics than Options A, C and D. |
Effluent discharge would likely have impact upon the live coral communities. Poor dispersion and dilution conditions of surrounding marine water. |
Poor dispersion and dilution characteristics at the proposed location. Worse flushing conditions encountered after implementation of Peng Chau typhoon shelter. Discharge at typhoon shelter is not recommended. |
|
Waste Management Implications |
Construction Phase |
Short terrestrial outfall component. Impact not significant. Same potential impact as Option D. |
Relatively long terrestrial outfall. Impact not significant but more excavated waste than Option A and Option D. |
Relatively long terrestrial outfall. Impact not significant but more excavated waste than Option A and Option D. |
Short terrestrial outfall component. Impact not significant. Same potential impact as Option A. |
Operation Phase |
The outfall component would not give rise to operational phase waste management implications No difference is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase waste management implications No difference is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase waste management implications No difference is anticipated among 4 proposed options. |
The outfall component would not give rise to operational phase waste management implications No difference is anticipated among 4 proposed options. |
|
Ecology (marine and terrestrial) |
Construction Phase |
Live coral colonies are found in the northeast (NE) and in the seabed of outcrop boulder to the southwest (SW) of Tai Lei. The former colonies are of low abundance but relatively high species richness and with a higher coral coverage. Coral in the southwest are present in small isolated patches and are anticipated to be less significant than the NE colonies. This option is closest to the SW colonies but farthest away from the NW colonies. The overall dredging impacts may be the smallest among four options. No natural terrestrial habitat along the alignment, no impact is anticipated. |
Closer to live corals colonies in Tai Lei NE. Higher potential dredging impact than Option A and Option D but less than Option C. Hill slope and natural intertidal zone are located along the terrestrial alignment. Greatest impact on intertidal and terrestrial ecology. |
Alignment closest to a relatively large are of live coral communities. Greatest potential impact due to re-deposition of suspended solids from dredging. Greater potential impact than Options A, B and D. No natural terrestrial habitat along the alignment, no impact is anticipated. |
Farthest from live coral area compared with other options. Least potential impacts are anticipated. No natural terrestrial habitat along the alignment, no impact is anticipated. |
|
Operation Phase |
Coral colonies in small isolated patches are found in the vicinity. Less potential impact than Option C and Option B due to outfall discharge. Higher potential impact than Option D. The outfall component would not give rise to terrestrial ecological impacts during operational phase. No difference in operational terrestrial ecological impact is anticipated among 4 proposed options. |
Best dispersion and dilution characteristics are anticipated among four proposed options. Larger and more abundant isolated coral patches than Option A are found in the vicinity. Higher potential operational impact than Option A and Option D but less than Option C. The outfall component would not give rise to terrestrial ecological impacts during operational phase. No difference in operational terrestrial ecological impact is anticipated among 4 proposed options. |
Effluent discharge would likely have impact upon the live coral communities. The greatest marine ecological impact. The outfall component would not give rise to terrestrial ecological impacts during operational phase. No difference in operational terrestrial ecological impact is anticipated among 4 proposed options. |
Farthest from live coral area compared with other options. Least potential impacts are anticipated. The outfall component would not give rise to terrestrial ecological impacts during operational phase. No difference in operational terrestrial ecological impact is anticipated among 4 proposed options. |
Cultural Heritage |
Construction Phase |
No cultural heritage site of interest is found. No impact. |
No cultural heritage site of interest is found. No impact. |
No cultural heritage site of interest is found. No impact. |
No cultural heritage site of interest is found. No impact. |
Operation Phase |
No cultural heritage site of interest is found. No impact. |
No cultural heritage site of interest is found. No impact. |
No cultural heritage site of interest is found. No impact. |
No cultural heritage site of interest is found. No impact. |
|
Engineering Constraints |
No apparent engineering constraints are identified for Option A. |
This option appeared to be technically unsound with a pipe through rocky hills. Regions beyond the natural intertidal zone where dead coral skeletons were identified. Construction of submarine outfall through these shallow skeleton area is difficult as compared with other options. |
The location of outfall is very close to live coral areas, which would pose difficulties in avoiding them during construction. In addition, this option would have the longest terrestrial pipeline component, passing through other existing properties. |
No apparent engineering constraints are identified for this option. |
|
Land Issue Constraints |
No apparent land issue constraints are identified for Option A. |
No apparent land issue constraints are identified for Option B. |
The terrestrial component of outfall would be laid on other existing properties on the eastern Tai Lei. |
This option is located at the planned typhoon shelter area by CED. The implementation schedule of typhoon shelter is not definite. Should the typhoon shelter be implemented, submarine outfall would need to be relocated. |
Option D: This option would have the least air quality impact, noise impact and waste management implication during construction phase due to short terrestrial outfall component. No terrestrial ecological impact and least marine ecological impact are anticipated. However, the area is poorly flushed. The area has been proposed for Peng Chau typhoon shelter and worse flushing conditions would be encountered after implementation of typhoon shelter. Discharge at typhoon shelter is not recommended.
Table 2-3 Configurations of STW and Emergency Overflow Outfall
Configurations |
STW Outfall |
Emergency Overflow Outfall |
Approximate Pipe Length (m) |
100 |
40 |
Minimum Discharge Depth (m) |
8 |
3 |
No. of Risers |
2 |
1 |
No. of Jet per Riser |
4 |
N.A. |
Riser Separation (m) |
10 |
N.A. |
Jet Diameter (mm) |
100 |
250 |
(a) The proposed outfall and emergency overflow outfall are quite short (100m and 40m respectively). Therefore, it is not a cost-effective option to employ HDD method.
(b) Based on the geological investigation data, the proposed profile of the outfalls will go through Grade V rock. This is not practicable for HDD construction method as it is designed to drill through better Grade of rock. As such, drilling is still required.
(c) There is a minimum curvature requirement of the HDD alignment. Based on the GI results, the HDD alignment has to be reasonably deep and stop inside the rock layer at the end of the 100m outfall. To retrieve the head and construct the risers, open cut is still required at this end.
(d) As major dredging is still required for the HDD option, the environmental advantages of HDD over open trench method is diminished to very marginally.
Secondary/Biological Treatment Technology
o Oxidation Ditch (OD);
o Sequencing Batch Reactor (SBR);
o Rotating Biological Contactor (RBC);
o Biological Aerated Filter (BAF);
o Conventional Activated Sludge System (CAS); and
o Membrane Bioreactor (MBR)
o Operation and Maintenance Cost and Requirement;
o Capital Cost;
o Requirement of Pretreatment and/or Secondary Sedimentation;
o Reliability;
o Ability to handle wide flow and load variations;
o Simplicity and Ease of Operation;
o Ability to Utilise Existing Peng Chau STW Facilities;
o Ease of Expansion;
o Size of Required Footprint;
o Ability of Nitrification/Denitrification; and
o Capability of Producing Effluent Meeting Discharge Criteria
Table 2-4 Evaluation of Secondary Treatment Processes
Criteria |
OD |
SBR |
RBC |
BAF |
CAS |
MBR |
Operation and Maintenance Cost and Requirement |
Low |
Low |
Moderate |
Highly dependent on instrumentation and controls, high O&M cost and requirement. |
High operation and maintenance cost and requirement. |
High. Energy requirement is high. Regular replacement of membrane is needed. |
Capital Cost |
High capital cost due to large footprint |
low |
Low |
High |
High capital cost due to larger footprint |
High |
Requirement of Pretreatment and /or secondary sedimentation |
Screens and Secondary clarifier are needed |
Only screens are required. |
Screens, Primary and secondary clarifiers are required. |
Fine screens and primary clarifier are required. |
Screens, primary and secondary clarifiers are required. |
Fine screens are required. |
Reliability |
Reliable |
Reliable |
Performance varied with flow rate and temperature. |
Average |
Reliable |
Reliable |
Ability to handle wide flow and load variations |
Sludge bulking is likely from low food to mass ratio. |
Yes |
Difficult |
Average |
Average |
Yes |
Simplicity and Ease of Operation |
Simple and easy to operate |
Simple and easy |
Simple and easy |
Lack of local operating experience |
Simple and easy to operate |
Lack of local operating experience |
Ability to Utilise Existing Peng Chau STW Facilities |
No |
No |
Yes. The secondary treatment process of the existing STW is also RBC. |
No |
No |
Yes. MBR can be placed within the existing facility |
Ease of Expansion |
Difficult |
Easy, scalable |
Moderate |
Moderate |
Moderate |
Easy |
Size of Required Footprint |
Large |
Medium |
Large |
Small |
Large |
Small |
Ability of Nitrification/ Denitrification |
Yes |
Yes |
No |
Yes |
Yes |
Yes |
Capable of Producing Effluents Meeting Discharge Criteria |
Yes |
Yes |
No |
Yes |
Yes |
Yes |
Disinfection Technology
Table 2-5 Evaluation of Chlorination and UV Radiation
Criteria |
Chlorination |
UV Radiation |
Total Cost (capital and recurrent) |
Low |
High |
Ability to achieve disinfection standards |
Yes |
Yes |
Footprint Size |
Larger |
Smaller |
Implications due to large flow variations |
More flexible and can better cope with the flow variation |
More difficult on operation and maintenance to meet the flow changes |
Environmental impacts |
Effluent from the plant is relatively small and the potential water quality impact can be mitigated through dechlorination |
Insignificant environmental impacts with proper handling of spent UV lamps |
(a) Potential Port Development East of Peng Chau: As stated in EPD’s Outlying Islands Sewerage Master Plan Stage 2 Review (SMP 2002) (EPD, 2002a), the potential port development remains on the current Draft North-East Lantau Outline Zoning Plan. The proposed port development area extends from the NE coast of Lantau to Siu Kau Yi Chau and Kau Yi Chau. An EIA study has been performed under the Northshore Lantau Development Feasibility Study and potential water quality impacts were evaluated. The SMP 2002 has considered the findings from the Northshore Lantau EIA and recommended a short submarine outfall for the Peng Chau Upgrading Project. The later EIA scope developed for Peng Chau Upgrading Project has excluded the location of potential port development as water quality assessment area (1km from the STW) since the port development has already been taken into account.
(b) Remaining Works for Construction of Footpath along Pak Wan, Peng Chau: This project is being carried out by the Home Affairs Department (HAD). It was commenced in December 2002 and is anticipated to complete in mid 2004, which is prior to the start of construction of Peng Chau STW Upgrade. Thus, the footpath project is unlikely to have cumulative impact on the sensitive receivers.
(c) Reconstruction of Peng Chau Public Pier: The public pier located in central Peng Chau was reconstructed. The reconstruction works were commenced in May 2002 and was completed in January 2004. It is anticipated that this reconstruction work would not have any cumulative environmental impacts with the proposed Peng Chau STW Upgrade.
(d)
The CED is also planning to build a
typhoon shelter to provide some 40-ha anchorage and mooring area at the
southwest side of Peng Chau. It
involves the erection of navigation lights and warning signboards and
construction of a breakwater, navigation channels, landing facilities, boat
landing steps at each light beacon and a water-selling kiosk. The location is
shown in Figure
2-87. It is stated in SMP 2002
that the proposed typhoon shelter might be required by 2016. However, based on
the recent information received from the Marine Department and CED, no definite
implementation schedule for typhoon shelter has been set.
(e) Outlying Islands Sewerage Stage 1 Phase 2- Construction of Village Sewerage at Peng Chau and Cheung Chau Phase 1 (Package H). This is an in-house project of DSD. Package H consists of the construction of about 1.7-km of sewers, 400m of twin 250mm rising mains, a new sewage pumping station and temporary pump pit to replace the existing Kam Peng Estate sewage pumping station (which will also be demolished under Package H) and rehabilitation of some 300m of existing sewers (Figure 2-7). Construction of Package H was started in September 2002 and is scheduled to complete in mid 2005 followed by a one-year maintenance period. The construction period of this project partially overlaps with Peng Chau STW Upgrade construction.
(f) Peng Chau Helipad. This project is to be carried out by the Civil Engineering Department (CED) to construct a helipad in Peng Chau for transporting residents to the urban area for medical treatment in case of emergency. The proposed helipad and associated access road will be constructed by reclamation. The location of the selected site is shown inFigure 2-7. The construction period of Peng Chau Helipad is scheduled to begin in March 2005 and end in February 2006. The construction period falls within the Peng Chau STW’s Upgrade construction schedule.