4.1.1
During
the construction phase, there will be potential dust impacts on existing
sensitive receivers from the construction activities undertaken at the Project
site. During operation phase, the
air quality impacts arising from the proposed extension would be minimal. This
section presents the assessments of dust impacts during the construction phase
since operational air quality is not an issue on this Project.
4.2.1
The
air quality impact assessment criteria make reference to the Hong Kong Planning Standards and Guidelines
(HKPSG), the Air Pollution Control
Ordinance (Cap. 311) (APCO), and Annex
4 of the Technical Memorandum on
Environmental Impact Assessment Process (EIA-TM).
4.2.2
The
APCO provides powers for controlling air pollutants from a variety of stationary
and mobile sources and encompasses a number of Air Quality Objectives
(AQOs). Currently AQOs stipulate
concentrations for a range of pollutants namely nitrogen dioxide (NO2),
sulphur dioxide (SO2), total suspended particulates (TSP),
respirable suspended particulates (RSP), carbon monoxide (CO), photochemical
oxidants (O3) and lead (Pb).
The AQOs are listed in Table 4.1.
4.2.3
For
construction dust, Annex 4 of EIA-TM
specifies a TSP limit in air averaged over a 1-hour period of 500 µg/m3. The maximum acceptable TSP concentration
averaged over a 24-hour period is 260 µg/m3, as defined in the AQOs.
4.2.4
The
HKPSG specifies buffer distances between sources of pollution and sensitive
land uses to ensure acceptable air quality at the sensitive land uses. Examples of recommended buffer distances
extracted from the HKPSG for relevant source and sensitive land use
combinations are given in Table 4.2.
The actual buffer distances required to avoid adverse air quality impacts
associated with the construction site would be reviewed based on the findings
of this assessment.
Table
4.1
Pollutant (Concentration in micrograms per cubic metre1) |
Averaging Time |
||||
1 hour2 |
8 hours3 |
24 hours3 |
3 months4 |
1 year4 |
|
|
800 |
- |
350 |
- |
80 |
Total Suspended Particulates (TSP) |
5007 |
- |
260 |
- |
80 |
Respirable Suspended Particulates (RSP)5 |
|
- |
180 |
- |
55 |
Nitrogen Dioxide (NO2) |
300 |
- |
150 |
- |
80 |
Carbon Monoxide (CO) |
30000 |
10000 |
- |
- |
- |
Photochemical Oxidants (as Ozone (O3))6 |
240 |
- |
- |
- |
- |
Lead |
- |
- |
- |
1.5 |
- |
Notes:
1 Measured
at 298 K and 101.325 kPa.
2 Not
to be exceeded more than three times per year.
3 Not
to be exceeded more than once per year.
4 Arithmetic
mean.
5 Respirable
suspended particulates means suspended particulates in air with a nominal
aerodynamic diameter of 10 micrometres or smaller.
6 Photochemical
oxidants are determined by measurement of ozone only.
7 Not
an AQO but is a criteria for evaluating air quality impacts as stated in Annex
4 of EIA-TM.
Table 4.2 HKPSG
Recommended Buffer Distances
Pollution Source |
Parameter |
Buffer Distance |
Permitted Uses |
Road and Highways |
Type of Road |
||
Trunk Road and
Primary Distributor |
> |
Active and passive
recreation uses |
|
3 - |
Passive recreational
uses |
||
< |
Amenity areas |
||
District Distributor |
> |
Active and passive
recreational uses |
|
< |
Passive recreational
uses |
||
Local Distributor |
> |
Active and passive
recreational uses |
|
< |
Passive recreational
uses |
||
Under Flyovers |
- |
Passive recreational
uses |
|
Industrial Areas |
Difference in Height between Industrial
Chimney Exit and the Site |
||
< |
> |
Active and passive
recreational uses |
|
5 - |
Passive recreational
uses |
||
20 - |
> |
Active and passive
recreational uses |
|
5 - |
Passive recreational
uses |
||
|
> |
Active and passive
recreational uses |
|
5 - |
Passive recreational
uses |
||
> |
> |
Active and passive
recreational uses |
|
Construction and
earth moving activities |
- |
< |
Passive recreational
uses |
> |
Active and passive recreational
uses |
Extracted from Table 3.1 (Guidelines on
Usage of Open Space Site) of the HKPSG
Remarks: (a) The buffer distance is the
horizontal, shortest distance from the boundary of the industrial lot, the position
of existing chimneys or the edge of road kerb, to the boundary of open space
sites.
(b) Amenity
areas are permitted in any situation.
4.2.5
The Air Pollution Control (Construction Dust)
Regulation specifies processes that require special control. Contractors
and site agents are required to inform
4.3.1
The
study area is classified as a rural area as less than 50% of an area within
4.3.2
Existing
air quality in the area is influenced by emissions from:
·
Diesel
powered traffic on Kau Sai Chau is limited to maintenance vehicles and a small
fleet of transfer buses running between pier and administration building. Other
vehicles and golf carts that are battery powered.; and
·
traffic
emission and to a much lesser extent industrial emission from Sai Kung
4.3.3
As no
monitoring station for particulates is set up by
Table 4.3 Five Year Average
Pollutants Concentrations at
Pollutant |
Annual
Average (µg/m3) |
5
Years Average Concentration (µg/m3) |
||||
1999 |
2000 |
2001 |
2002 |
2003 |
||
TSP |
76 |
58 |
67 |
62 |
78 |
68.2 |
4.4.1
Air
sensitive receivers (ASRs) were identified within the study area (i.e.
Table 4.4 Summary of
Identified Air Sensitive Receivers
ASR ID |
Name |
No. of Storey |
Base Elevation (mPD) |
Distance from the Nearest Work Site
Boundary (Approximate, m) |
YTTV |
|
3 |
+6.8 |
1300 |
LLC |
Louisa
Landale Campsite |
2 |
+17.9 |
980 |
GCAB1 |
|
2 |
+35.0 |
0(a) |
GCAB2 |
|
2 |
+33.7 |
0(a) |
PGC |
Public
Golf Course |
- |
various |
0(b) |
KSCV |
|
3 |
+6.0 |
1060 |
Remarks: (a) ASRs are within the proposed work site
boundary.
(b) The existing
public golf course is right next to the proposed work site boundary.
4.5.1
In order
to assess the potential dust impacts associated with the construction of the
proposed Project, potential sources of air emissions from the construction
sites were identified. Dust mitigation measures stipulated in the Air Pollution Control (Construction Dust)
Regulation which are relevant to the associated construction activities
were then identified and presented in this report.
4.5.2
In
this assessment, the dispersion of
4.5.3
For
the earthworks at the proposed third golf course, the estimated total cut and
fill volumes are
4.5.4
We
have adopted the tentative construction programme that will start from February
2006 to February 2007 and details are shown in Appendix 4.1. Earthwork will be carried out in phases
at different areas as shown in Figure 4.2.
Based on the construction programme, the earthworks will be carried out
separately in three groups: Group A includes Hole 11, 12, 13, 14, 15 and 16
with a cut-and-fill volume of
4.5.5
The
quantity of dust generated from construction is a function of the size of the
construction area and the intensity of activity. For the dust calculations for
cut-and-fill operations and haul road constructions, the emission factor as
suggested by the Section
4.5.6
According
to Section 11.12 of AP-42, the
emission factor for mixer loading was adopted for estimating the emission from
the operations of the anticipated concrete batching plant. The maximum daily
production rate will be
4.5.7
To
determine the emissions from the access roads, the emission factors in Sections
4.5.8
As the
dust arising activities from the Project construction will be mainly excavation
and filling, crushing activities, wind erosion, operation of concrete batching
plant and traffic dust on haul roads, the selected emission factors are
conservative. Appendix 4.2 provides
the detailed calculation of emission factors for different dust emission activities.
4.5.9
The
tentative construction programme is presented in Appendix 4.1. The details
description of works is listed in Table 4.5.
Table 4.5 Description
of Construction Works at the Proposed Third Golf Course
Section |
ID |
Work |
Work description |
Section 1 – Construction work in portion
1 |
S10500200 |
Construction of low level intake &
pumping station |
mainly formworks and steel works and concreting |
S10500400 |
Construction of gravity drain |
minor excavation |
|
Section 2 - Construction work in portion
2 |
S20400200 |
Excavation and construction of
desalination plant |
Sand dredging in the sea and mainly formworks and
steel works and concreting |
S20400300 |
Construct transformer/switch room |
mainly formworks and steel works and concreting |
|
S20400400 |
Construction of storage area |
- |
|
Section 5 |
|
Establishment works |
Planting |
Section 9 – Construction Works in Portion
5 |
S91101010 |
Construction of slope works |
Minor cut
and fill along haul road |
S91101050 |
Construction of halfway house & rain
shelter |
Concreting |
|
S91101100 |
Earth/slope construction works |
Major
cut and fill |
|
(S91101350, 490, 590, 690, 790, 890) |
Construction of golf course no.11-16 |
Minor
grading, landscape, planting |
|
(S91101350, 115, 290, 390, 490, 590, 690) |
Construction of golf course no.3-9 |
Minor
grading, landscape, planting |
|
(S91303125, 250,390, 490, 590) |
Construction of golf course
no.1,2,10,17,18 |
Minor
grading, landscape, planting |
|
Slope restoration |
S92300400 |
Slope restoration works |
Soil
nail, slope reinstatement |
4.5.10
According
to the programme in Appendix 4.1 and Table 4.5, the major dusty activities are
summarized as follows:-
l
Construction
of haul road (ID: P00000180);
l
Excavation
& construction of
l
Earth/slope
construction works (ID: S91101100, S91401010; S91303100).
4.5.11
In the
FDM model inputs, three worst scenarios have been considered according to the programme
of dusty activities. Scenario A includes the dust sources from Group A
activities plus the constructions of haul roads and Lake 1D, wind erosion of
the whole site, operation of the proposed concrete batching plant and traffic
dust from haul roads within work areas for Scenario A. Scenario B includes the
dust sources from Group B activities plus the constructions of Lake 1D, wind
erosion of the whole site, operation of the concrete batching plant and traffic
dust from haul roads within work areas for Scenario B. Scenario C includes the
dust sources from Group C activities plus wind erosion in the whole sites,
operations of concrete batching plant and traffic dust from haul roads within
work areas for Scenario C. The summary of these scenarios are presented in
Table 4.6.
Table
4.6 Description of Worst
Scenario
Scenario |
Dust Source |
Work ID |
Emission Factor |
A |
Construction of haul roads |
P00000180 |
Haul road construction# |
Excavation & construction of |
S20401300 |
Heavy construction |
|
Earth/slope construction works at Hole 11, 12, 13, 14, 15
and 16 |
S91101100 |
Heavy construction |
|
Operation of concrete batching plant |
- |
Concrete batching plant |
|
Traffic at haul roads (within the area of
Hole 11, 12, 13, 14, 15 and 16) |
- |
Unpaved road |
|
Traffic at existing road |
- |
Paved road |
|
Wind erosion at whole site |
- |
Wind erosion |
|
B |
Excavation & construction of |
S20401300 |
Heavy construction |
Earth/slope construction works at Hole 3, 4, 5, 6, 7, 8 and
9 |
S91401010 |
Heavy construction |
|
Operation of concrete batching plant |
- |
Concrete batching plant |
|
Traffic at haul roads (within the area of
Hole 3,
4, 5, 6, 7, 8 and 9) |
- |
Unpaved road |
|
Traffic at existing road |
- |
Paved road |
|
Wind erosion at whole site |
- |
Wind erosion |
|
C |
Earth/slope construction works at Hole 1, 2, 10, 17, 18 and
S10 |
S91303100 |
Heavy construction |
Operation of concrete batching plant |
- |
Concrete batching plant |
|
Traffic at haul roads (within the area of
Hole 1,
2, 10, 17, 18 and S10) |
- |
Unpaved road |
|
Traffic at existing road |
- |
Paved road |
|
Wind erosion at whole site |
- |
Wind erosion |
# Remarks: The emission factor for heavy
construction was adopted in haul road construction. However, as a line source
emission for haul road construction, adjustments were made in order to convert
an area source to a line source by multiplying the road width. Details
calculations are shown in Appendix 4-2.
4.5.12
For
the cut-and-fill operations, maximum two holes will be worked simultaneously.
The average concurrent working area for cut-and-fill operations in Group A will
be
4.5.13
The
five years average TSP concentration as presented in Table 4.3 was estimated to
be 68.2 µg/m3. For the
purpose of this assessment, this value has been used as an indication of the
future TSP background concentration.
4.5.14
No
quantitative assessment for the operational air quality arising from the
Project is required.
4.6.1
The
principal potential source of air quality impact arising from the construction
of the proposed works is fugitive dust. The exposed areas, once formed into
designed level, will be immediately covered with grass turfs to prevent dust
and erosion.
4.6.2
Potentially
dusty construction activities include the site formation of the new golf course
extension and the construction of a temporary jetty (eastern side) and
desalination plant near existing pier. The main dust generation sources will be
earthwork. Other works are not expected to generate any significant level of
dust.
4.6.3
In
addition, the construction activities near the Study area have been
reviewed. Site formation, which is
the main dust generating activity of the realignment of Hiram’s Highway (Ho
Chung –
4.6.4
The
construction dust impacts have been predicted using FDM model. The sample
input/output files for the FDM modeling are given in Appendix 4.3. The modeling
results with background are summarized in Table 4.7.
Table 4.7 Unmitigated Construction Dust
Concentrations at the Representative ASRs (Background Included)
Height |
ASR |
Scenario A |
Scenario B |
Scenario C |
|||
1-hr |
24-hr |
1-hr |
24-hr |
1-hr |
24-hr |
||
|
YTTV |
547.07 |
96.83 |
306.47 |
85.42 |
433.08 |
91.74 |
LLC |
691.53 |
106.63 |
384.83 |
92.67 |
542.65 |
94.41 |
|
GCAB1 |
1503.23 |
248.98 |
1310.56 |
248.32 |
2334.39 |
344.68 |
|
GCAB2 |
3285.71 |
434.37 |
2887.85 |
401.73 |
3184.12 |
530.68 |
|
KSCV |
503.44 |
112.00 |
269.35 |
85.38 |
365.57 |
87.86 |
|
|
YTTV |
567.36 |
98.62 |
310.19 |
85.91 |
442.33 |
93.00 |
LLC |
705.54 |
107.59 |
384.27 |
92.88 |
540.75 |
95.18 |
|
GCAB1 |
1192.66 |
207.64 |
1024.49 |
206.82 |
1796.98 |
288.68 |
|
GCAB2 |
1636.30 |
268.49 |
1500.61 |
255.40 |
1625.29 |
371.24 |
|
KSCV |
506.17 |
113.81 |
278.58 |
86.06 |
376.30 |
88.89 |
|
|
YTTV |
491.87 |
95.31 |
266.31 |
83.76 |
375.77 |
89.88 |
LLC |
594.78 |
101.47 |
318.68 |
90.07 |
439.42 |
91.23 |
|
GCAB1 |
808.03 |
154.69 |
526.74 |
147.29 |
824.01 |
183.87 |
|
GCAB2 |
822.54 |
175.31 |
625.46 |
148.08 |
924.26 |
206.06 |
|
KSCV |
422.47 |
108.63 |
249.37 |
83.73 |
331.17 |
86.14 |
Remarks: Boldfaced value means exceedance of dust
limits.
4.6.5
In the absence of any mitigation measures on the
construction activities, the construction dust levels at some ASRs in Table 4.7
were higher than the guideline and limits as stipulated in the EIA-TM. Dust
suppression measures are therefore recommended to reduce emissions from the
site to ensure the criteria would not be exceeded.
4.6.6
Operational
air quality impact is unlikely a key environmental issue as the golfers are transported
using battery operated golf carts. The additional traffic generated around
4.7.1
In
order that nuisance to air sensitive receivers is minimized, it is important to
minimize dust emissions from construction activities including cut and fill
operations and trucks movements on haul road. In 1997, the Air Pollution Control (Construction Dust) Regulation came into
effect to control dust emission from construction works. Appropriate dust control measures should
be implemented during construction stage in accordance with the requirements in
the Air Pollution Control (Construction
Dust) Regulation. Dust control techniques should be considered to control
dust to a level not exceeding the AQOs as well as the 1-hour TSP guideline
level. These measures include:
·
Adoption
of good site practices;
·
Avoid
practices likely to raise dust level;
·
Frequent
cleaning and damping down of stockpiles, dusty areas of the Site and the haul
roads;
·
Reduce
the speed of the vehicles (say 10 kph) on the haul road;
·
Reducing
drop height during material handling;
·
Provision
of wheel-washing facilities for Site vehicles leaving the Site;
·
Regular
plant maintenance to minimize exhaust emission;
·
Sweep
up dust and debris at the end of each shift; and
·
If
concrete batching plant or rock crushing plant is planned to be used, a license
from EPD may be required depending on the total silo capacity since they are
specified processes under the APCO.
Modern plant should be designed to limit emissions.
4.7.2
With
the implementation of the above dust suppression measures, the construction
dust concentration can be highly reduced. According to the AP-42, a dust
removal efficiency of 50% can be achieved by watering twice a day. It is suggested to provide watering
eight times a day (i.e. hourly watering) in the working areas such that a dust
removal efficiency of 1 – (50% x 50% x 50%) = 87.5% can be achieved.
Furthermore, watering of twice a day is suggested in other inactive exposed
areas (assumed as wind erosion only). The mitigated construction dust
concentrations are summarized in Table 4.8.
Table 4.8 Mitigated Construction Dust
Concentrations at the Representative ASRs (Background Included)
Height |
ASR |
Scenario A |
Scenario B |
Scenario C |
|||
1-hr |
24-hr |
1-hr |
24-hr |
1-hr |
24-hr |
||
|
YTTV |
136.21 |
73.99 |
102.25 |
72.56 |
116.57 |
73.10 |
LLC |
152.91 |
75.92 |
115.88 |
74.22 |
135.87 |
74.48 |
|
GCAB1 |
270.92 |
104.97 |
250.21 |
105.11 |
364.68 |
116.35 |
|
GCAB2 |
486.65 |
132.14 |
444.61 |
129.03 |
480.86 |
144.36 |
|
KSCV |
125.77 |
76.51 |
99.88 |
73.06 |
107.61 |
73.54 |
|
|
YTTV |
139.04 |
74.34 |
102.84 |
72.79 |
117.83 |
73.38 |
LLC |
154.74 |
76.14 |
115.93 |
74.35 |
135.81 |
74.70 |
|
GCAB1 |
217.61 |
95.23 |
198.37 |
95.29 |
293.57 |
105.50 |
|
GCAB2 |
270.31 |
104.37 |
255.17 |
103.20 |
269.40 |
117.76 |
|
KSCV |
126.09 |
76.82 |
101.26 |
73.25 |
109.04 |
73.79 |
|
|
YTTV |
128.30 |
73.66 |
96.74 |
72.25 |
109.03 |
72.76 |
LLC |
139.66 |
74.96 |
106.26 |
73.60 |
121.64 |
73.78 |
|
GCAB1 |
166.89 |
84.82 |
129.46 |
83.92 |
166.22 |
88.30 |
|
GCAB2 |
167.32 |
86.74 |
143.65 |
83.53 |
179.43 |
90.80 |
|
KSCV |
114.96 |
75.82 |
96.62 |
72.60 |
103.06 |
73.03 |
4.7.3
Based on
the results in Table 4.8, no exceedance of the relevant dust limits is
identified. Furthermore, it is observed that the highest
4.8.1
With
the implementation of the recommended dust suppression measures, the predicted
construction dust levels at all the receivers were below the relevant AQOs and
the dust guideline.
4.8.2
No
adverse residual operational air quality impact would be expected.
4.9.1
Impacts
from concurrent projects will be negligible due to the large distance
separation.
4.10.1
An
EM&A programme should be undertaken, which would focus on those ASRs of particular concern, in order to identify and rectify any
problems. A recommended EM&A programme has been
presented separately in the EM&A Manual.
4.11.1
The
construction dust concentration levels at most identified ASRs based on the worse
case scenario were predicted to exceed the AQOs and the 1-hour dust guideline.
With the implementation of the appropriate dust suppression measures such as
regular watering and covering the exposed stockpiles with tarpaulin, the
construction dust impacts could be highly reduced to the acceptable levels.
4.11.2
No
insurmountable residual construction dust impact would be expected.
4.11.3
No
operational air quality impact is expected. Thus, no mitigation measures for air
quality during operation phase would be required. No adverse residual operational air
quality would also be expected.
4.11.4
An
EM&A programme should be undertaken during the construction phase, which
would focus on those ASRs of particular concern, in order to identify and
rectify any problems.