Calculation of Construction Noise Impact at the NSRs
NSR: N1 - Hei Ling Chau Correctional Institution
    Horizontal  Vertical  Slant Overall Correction  
Construction Distance Distance Distance SWL Distance Barrier Façade CNL
       
Location B:      
B-1 Transportation of plants 640 60 643 117 -64 -10 3 46
B-2 Rock breaking 640 60 643 106 -64 -10 3 35
B-3 Piling, Excavation, Soil nailing 640 60 643 116 -64 -10 3 45
B-4 Concreting 640 60 643 113 -64 -10 3 42
B-5 Transportation of turbine  640 40 641 115 -64 -10 3 44
Wind Turbine Site 740 10 740 123 -65 -10 3 51
                   
NSR: N2 - Hei Ling Chau Addiction Treatment Centre (Annex)
    Horizontal  Vertical  Slant Overall Correction  
Construction Distance Distance Distance SWL Distance Barrier Façade CNL
       
Location B:      
B-1 Transportation of plants 75 5 75 117 -46 0 3 74
B-2 Rock breaking 75 5 75 106 -46 0 3 63
B-3 Piling, Excavation, Soil nailing 75 5 75 116 -46 0 3 74
B-4 Concreting 75 5 75 113 -46 0 3 71
B-5 Transportation of turbine  75 22 78 115 -46 0 3 73
Wind Turbine Site 380 60 385 123 -60 -10 3 57
                   
NSR: N3 - Staff Quarters
    Horizontal  Vertical  Slant Overall Correction  
Construction Distance Distance Distance SWL Distance Barrier Façade CNL residual impact
       
Along route (1)      
R-1a Slope cutting - rock breaking 2 2 3 106 -17 -10 3 82 7
R-1b Slope cutting - site clearence 2 2 3 105 -17 -10 3 81 6
R-2 Erection of temporary platform 2 2 3 103 -17 -10 3 79 4
R-3a Backfilling - compacting 2 2 3 107 -17 -10 3 83 8
R-3b Backfilling - excavation 2 2 3 105 -17 -10 3 81 6
R-3c Backfilling - site clearence 2 2 3 105 -17 -10 3 81 6
                   
(1) Mitigated with quiet construction plant and noise barriers