Annex 2-B Comparison South Soko Alternatives                   

 


1                                            Environmental Assessment

An evaluation of the potential impacts identified in Part 2 – Section 2.1 as a result of the construction and operation of each of the South Soko terminal options has been undertaken to determine the key issues.  The importance (ie significance) of potential impacts has been evaluated using the concepts described within the aforementioned section.  The result of this evaluation is presented below.  From these results, a comparison of each preliminary layout (the Layout) and design option is presented based on the number of important or significant issues.


1.1                                      Accidental Spills/Leaks/Dropped Objects

LNG receiving terminals have an excellent safety record, accidental events such as spills and leaks, vessel grounding/ collisions, dropped objects and loss of materials either on land or into the sea during construction or operation of the LNG terminal are potential scenarios which may result in adverse impacts on the environment and personnel injury.

The severity of impacts as a result of accidental events will depend on a number of factors including the nature of the event (ie type of hazard – hazardous material release, physical impact etc.), the magnitude of the event (eg quantities of material actually released) as well as the sensitivity of the environment at the accident location/ impact site.

Whilst the consequences (ie scale of damage) resulting from accidental events may be severe, the likelihood of their occurrence is typically unlikely to very unlikely.  However, this resultant low level of risk associated with such events is traditionally only achieved by the application of the highest standards of HSE management including hazard identification, risk assessment and the implementation of extensive control and recovery measures.  Nevertheless, regardless of the layout and design each option is considered to have a negligible impact due to the unlikely event of such an event occurring.

The evaluation of impacts as a result of accidental spills/leaks/dropped objects for each of the South Soko terminal layout options are presented in Table 1.1.

Table 1.1        Evaluation of Impacts for Accidental Spills/Leaks/Dropped Objects

  

1.2                                      Air Emissions

Air quality impacts may potentially arise through the following:

·   Construction vehicle/equipment/ vessels engine exhaust emissions (eg. primarily NOx, CO, NMHC (non methane hydrocarbon) and small quantities of SO2, particulates and smoke);

·   Construction emissions from concrete batching plant; and,

·   Operational emissions from SCVs, LNG carrier generators during unloading of LNG, gas-turbine generators, onsite vehicles, emergency generators, diesel-driven firewater pumps and the hydrocarbon emissions from emergency venting (e.g., NOx, CO, SO2 and HC). 

Due to the relatively remote location of the South Soko terminal and the implementation of good site practice and the control measures stipulated in the Air Pollution Control (Construction Dust) Regulation, the adverse air quality impact arising from the above potential sources during construction phase is not expected.

Associated impacts are therefore considered to be negligible for all options.  Emissions associated with the concrete batching plant to be located during construction works may, however, result in low impacts to air quality, regardless of layout design.  Similarly, as each layout would require the installation of provisions for emergency venting of gas, potentially low impacts to air quality may result during operations.  Impacts to air quality may also affect visibility, hence aesthetics, albeit likely to be of negligible impact for all layout options.

The evaluation of impacts to air emissions for each of the South Soko terminal layout options are presented in Table 1.2.

Table 1.2        Evaluation of Impacts for Air Emissions

  


1.3                                      Run-off

Potential sources of impact through run-off during the construction and operation of the LNG terminal may include:

·    Rainfall run-off from disturbed site areas/ construction material stockpiles; and,

·    Entrainment of debris and refuse in stormwater run-off resulting in the fouling of receiving water resources.

Runoff and drainage from the earthworks and construction areas may contain elevated sediment loads resulting in increased turbidity in the surrounding waters.  Such increases may subsequently affect marine organisms that inhabit these waters.  Run-off may also contain debris (litter) as well as other contaminants (eg oil, grease, fuels etc) unless effectively controlled on-site. 

It is considered that although control measures will likely be enforced to reduce surface run-off in each of the layout options, environmental impacts to resources/receptors would range from negligible (ie aesthetics) to those which may be considered to be of low impact (ie water quality, intertidal/ subtidal habitats, etc) due to the ecological value of these sensitive receivers.  Such impacts would be unlikely to differentiate between layout design during either construction or operation of the LNG terminal.

The evaluation of impacts from run-off for each of the South Soko terminal layout options are presented in Table 1.3.

Table 1.3         Evaluation of Impacts for Run-off

  


1.4                                      Blasting

Potential sources of impact through blasting works during the construction of the LNG terminal may include:

·    Acute increases in environmental noise and subsequent impacts to biological and human sensitive receivers within proximity to works; and

·    Exposure to hazardous substances with subsequent concerns to health and safety.

Each of the three layout options will involve the use of explosive materials to conduct blasting operations during the excavation of rock from the existing hillsides.  Regardless of the volume of blasting to be required, magazine storage and explosive manufacturing plant will be temporarily located on site.  The storage and use of such materials have the potential to result in adverse impacts through direct exposure to blast materials, ie habitat and terrestrial flora and fauna, and indirect impacts through increased noise, vibration and noise.  Although underwater blasting is not necessary for the construction of any of the potential layouts, it can be expected that terrestrial works may have adverse consequences on marine habitats and organisms, albeit likely to be of negligible consequence.  Due to the requirement for such works at all sites, impacts are considered to be of a similar severity between layout options.

The evaluation of impacts associated with blasting during construction for each of the South Soko terminal layout options are presented in Table 1.4.

Table 1.4         Evaluation of Impacts for Blasting

  


1.5                                      Discharges to Soil/ Groundwater

Potential sources of soil and groundwater contamination associated with the construction and operation of the LNG terminal may include:

·    Inappropriate storage/ handling and disposal of waste materials;

·    Accidental spills and leaks of environmentally hazardous materials (oils, cleaning residues, hazardous materials etc); and

·    Inappropriate management and control of on-site operations (including effluents, fuel and hazardous material storage and use etc).

Minor spills during re-fuelling, lube/ hydraulic oil, oil filter etc. change-outs from construction equipment (eg generator sets) and vehicles have the potential to result in localised contamination.  A leak from a temporary fuel storage tank has the potential to cause significant soil and groundwater contamination.  Risks of soil and groundwater contamination can be controlled via effective operational and hardware control measures.  Providing such measures are identified and are implemented in an effective manner, risks of contamination can be maintained to within acceptable levels.  For the purposes of this consideration of alternatives, it has been determined that each layout would have the potential to result in similar environmental impacts to resources/receptors, regardless of configuration or design.

The evaluation of impacts associated with discharges to soil/groundwater for each of the South Soko terminal layout options are presented in Table 1.5.

Table 1.5         Evaluation of Impacts for Discharges to Soil/Groundwater

  

1.6                                      Effluents (Cleaning/Recycling/Disposal)

Potential impacts to resources/receptors through effluent (cleaning/recycling/disposal) associated with the construction and operation of the LNG terminal may include:

·   Wastewater from typical construction activities (eg. concreting, dredged spoil storage/ removal, painting etc);

·   Sanitary effluents from temporary chemical toilets for construction workers’ day use; and

·   Routine disposal of operational effluents (ie ‘black water’ composed of human body wastes from toilets and urinals and ‘grey water’ from showers, sinks, laundries, kitchens etc) from operational staff.

In order to clean/recycle/dispose of effluents generated through the construction and operation of the LNG terminal it is expected that a small-scale package, such as a Blivet Sewage Treatment Works or RBC plant, will be installed during both phases of works.  Treated construction phase effluent will be discharge through a temporary outfall. 

During the operational phases, effluent is expected to be treated and disposed offshore via a combined sewage and cooled water discharge outfall.  Although all effluent will be treated to meet the required discharge standards prior to mixing within the outfall, the potential for impacts to the surrounding water body and consequently the marine flora and fauna located within it, would be expected to have the potential to undergo an increase in impact likelihood.  Such impacts would, however, be expected to be of limited time duration and low severity.

For the purposes of this consideration of alternatives, it has been determined that each layout would have the potential to result in similar environmental impacts to resources/receptors as a result of effluent generation and discharge, regardless of configuration or design.

The evaluation of impacts from effluents (cleaning/recycling/disposal) for each of the South Soko terminal layout options are presented in Table 1.6.

Table 1.6        Evaluation of Impacts for Effluents (Cleaning/Recycling/Disposal)

   

1.7                                      Excavation

Excavation will be required for each layout option as part of the construction of the South Soko terminal for the following reasons:

·    To enable the tanks to be founded directly onto rock which will permit the use of pad/raft foundations, thus negating the need for deep foundations; and

·    To screen the tanks from the visually sensitive receivers on the south side of Lantau island.

Impacts associated with the excavation of material associated with the construction will primarily occur through dust generated from excavation activities, increase in terrestrial noise and visual and aesthetic impacts through alteration of the existing landscape.  In addition, due to the identification of sites of archaeological interest and cultural resources within the areas required to be excavated, impacts to such will occur.

On the basis of the designs of each layout, Options 1 and 3 will require the excavation of  approximately 2.1 Mm3 and 2.3 Mm3, respectively, of soil and rock.  In contrast, Option 2 will only require the excavation of approximately 1.3 Mm3 of soil and rock.  As the location of the removal of material is relatively similar, ie either the northern or southern hill slopes, or both, it would be fair to assume that the differences in excavated material requirements would have similar differences in the potential for impacts to occur.  As such, Option 2 is considered to have less severity of impact than Options 1 and 3.

The evaluation of impacts from excavation for each of the South Soko terminal layout options are presented in Table 1.7. 

Table 1.7         Evaluation of Impacts for Excavation

 

1.8                                      Marine Anchoring

Vessel anchoring (anchor deployment and recovery) within the vicinity of the construction site will result in localised seabed sediment/ substrate disturbance and alterations to the seabed profile.  Anchor operations may also result in secondary impacts on water quality (local increases in turbidity) and harm to the subtidal marine fauna living in the seabed.  It is likely that any impacts that may occur would be more severe during construction operations when there will be increased marine traffic to the site and the higher likelihood of anchoring occurring.  Impacts, however, would be expected to be similar between options regardless of layout design.

The evaluation of impacts from marine anchoring for each of the South Soko terminal layout options are presented in Table 1.8.

Table 1.8         Evaluation of Impacts for Marine Anchoring

  


1.9                                      Marine Dredging and Disposal

Marine dredging operations during construction may release sediment into suspension within the surrounding waters by the following mechanisms:

·    Impact of the dredging equipment (eg grab, trailer arm) on the seabed as it is lowered;

·    Washing of sediment off the outside of the grab as it is raised through the water column and when it is lowered again after being emptied;

·    Leakage of water from the grab as it is hauled above the water surface;

·    Spillage of sediment from over-full grabs;

·    Loss from grabs which cannot be fully closed due to the presence of debris;

·    Release by splashing when loading barges by careless, inaccurate methods;

·    Disturbance of the seabed as the closed grab is removed, which may be exacerbated by the release of gas (if present) from the disturbed sediments;

·    During the transport of dredging materials, sediment may be lost through leakage from barges;

·    Changes in hydrodynamics due to changes in bathymetry; and,

·    Aesthetic impacts through generation of sediment plumes.

The disposal of this dredged spoil material has the potential to result in a range of direct and indirect adverse impacts including:

·    Water column impact (elevated suspended solids levels during spoil discharge);

·    Indirect effects on marine ecology due to degraded water quality;

·    Alteration of seabed sediments (accumulation of dredged material);

·    Smothering effects on benthic (seabed) ecology;

·    Indirect effects on fisheries due to both degraded water quality as well as seabed deposition of spoil; and,

·    Aesthetic impacts through generation of sediment plumes.

 

According to the engineering design of the three layouts for the South Soko terminal one of the major differences appears to be in the dredging and subsequent disposal requirements of marine sediments.  Both Option 1 – Base Case and Option 2 – Full Reclamation have been estimated to require approximately 3.36 Mm3 of marine sediments to be removed in order to dredge the approach channel and turning basin to the required depth for safe LNG carrier passage (-15mPD).  In contrast, Layout 3 – SE Jetty will only require 1.07Mm3 of marine sediments to be removed. 

The primary difference is the approach channel and turning circle for this layout has been designed to only come into the southeastern side of South Soko Island, which is in contrast to Options 1 and 2 where the channel circumnavigates the southern, eastern and northern sides of the island before ending at the northwest near Sai Wan Bay.

The increased dredging requirements of Options 1 and 2 will have subsequent increases in potentially adverse consequences to resources and receptors, such as those to water quality, marine habitats (both intertidal and subtidal), marine mammals, as well as fisheries resources and operations.  These differences have been reflected in the impact severity and likelihood assessments.

The evaluation of impacts from marine dredging and disposal for each of the South Soko terminal layout options are presented in Table 1.9.

Table 1.9         Evaluation of Impacts for Marine Dredging and Disposal

  

1.10                                  Marine Traffic

Construction will generate additional marine traffic within and into the study area.  Marine vessel traffic generated by the project will include vessels for dredging, construction barges, delivery of equipment, materials and supplies and removal of marine dredged material.  These additional construction vessel movements have the potential to cause:

·   Increased marine accidents;

·   Interference with vessels approaching, departing and moored in the immediate surroundings;

·   Interference with other marine vessels, eg recreational, fishing vessels etc.;

·   Increase in terrestrial and underwater noise; and

·   Increase in likelihood for collision with marine mammals.

For the purposes of this consideration of alternatives, it has been determined that each layout would have the potential to result in similar environmental impacts to resources/receptors as a result of marine traffic, regardless of configuration or design.

The evaluation of impacts from marine traffic for each of the South Soko terminal layout options are presented in Table 1.10.

Table 1.10       Evaluation of Impacts for Marine Traffic

  


1.11                                  Noise

The principal sources of noise during construction activities will include:

·    Piling (hydraulic hammer type piling rig);

·    Blasting (explosives);

·    General construction equipment (eg. compressors, cranes, generators sets etc.) and activities (hammering, cutting, grinding, welding etc.); and

·    Transport vehicles (cars and trucks)/construction vessels.

It is assumed that the equipment to be employed during the construction of the site would be similar regardless of which layout design would be constructed.  Operational noise associated with the terminal is not expected to be severe. 

For the purposes of this consideration of alternatives, it has been determined that each layout would have the potential to result in similar environmental impacts to resources/receptors as a result of noise, regardless of configuration or design.

Note that potential ecological impacts and impacts on fisheries associated with underwater noise generated during piling works are included in Section 1.12 below.

The evaluation of impacts from noise for each of the South Soko terminal layout options are presented in Table 1.11.

Table 1.11       Evaluation of Impacts for Noise

  

1.12                                  Piling

Piling will cause vibration in the surrounding seabed/ ground.  Driving of piles in water will generate a certain amount of underwater sound.  Other underwater sound generation will occur from additional marine construction activity, such as dredging as well as support vessel operations.

Excessive underwater sound generation has the potential to disturb marine life (eg. fish, turtles, mammals etc.).  Marine mammals rely on acoustic information to communicate and to explore their environment.  Therefore, it is desirable to attenuate any sound generated that has the potential to significantly disrupt communication or echolocation activities of marine mammals near construction activities.

Piling operations will be required for all layouts in order to construct the jetty and trestle for the LNG carrier.  Layout Options 1 and 2 of the South Soko terminal would require the jetty to be constructed in the northeastern Sai Wan Bay of South Soko Island, whereas, Option 3 will have the jetty located on the southeastern side of the island. 

Long-term monitoring of marine mammal abundance and distribution in these waters (Part 2 – Section 10) indicates that marine mammal sightings in the general area of South Soko were infrequent, with more sightings in the waters in the vicinity of Options 1 and 2, compared with waters surrounding the jetty in Option 3.  Given the low density of marine mammals near to proposed piling activity, the potential for adverse impacts to occur to marine mammals as a result of marine piling operations is lowest for Option 3. 

The evaluation of impacts from piling activities for each of the South Soko terminal layout options are presented in Table 1.12.

Table 1.12       Evaluation of Impacts for Piling

  

1.13                                  Reclamation

The engineering design of Option 2 – Full Reclamation will require the reclamation of approximately 13 hectares (ha) of existing marine habitats.  The majority of reclamation will occur to the west of the existing platform to house the proposed turbine substation, utility area and laydown area.  The area to the east of the platform will be used for the service berth. 

In comparison, both Options 1 and 2, Base Case and SE Jetty respectively, will require only approximately 1.7 ha of marine habitats to be reclaimed.  This will primarily be needed for the utility pier on the west of the platform (or for Tank 3 for the SE Jetty layout) and to the east for the service berth.

The differences in reclamation area will result in subsequent increases in potential impacts to resources and receptors, such as those to water quality, marine habitats (both intertidal and subtidal), marine mammals, fisheries resources and operations as well as visual and aesthetics.  These differences have been reflected in the impact severity and likelihood assessments.

The evaluation of impacts from reclamation for each of the South Soko terminal layout options are presented in Table 1.13.

Table 1.13       Evaluation of Impacts for Reclamation

  

1.14                                  Site Formation

Site formation works at each option will involve the consideration of the volume of excavated materials, the potential for afteruse, slope stabilisation and maintenance.  It is noted that volumes of excavated material and afteruse are considered under excavation and waste generation and disposal, therefore for the purposes of assessing the environmental consequences of site formation the focus has been to identify any key differences between overall site formation, stabilisation and maintenance.

Each of the three layout options will be prepared, excavated and stabilised in similar formats (see Section 1.7 above).  As such, it is expected that the differences between the three layouts will not be significant enough to differentiate between in terms of environmental impacts.  Similar impacts to waste generation and disposal as well as landscape, aesthetics and archaeological resources may then be expected to occur for each layout.  Thus, for the purposes of this consideration of alternatives, it has been determined that each layout would have the potential to result in similar environmental impacts to resources/receptors as a result of site formation , regardless of configuration or design.

The evaluation of impacts from site formation for each of the South Soko terminal layout options are presented in Table 1.14.

Table 1.14       Evaluation of Impacts for Site Formation

  

1.15                                  Waste Generation and Disposal

All options will require the excavation of rock from the existing hillsides in order to provide sufficient flat land to meet the functional requirements of the LNG terminal.  However, as the Option 2 layout design will involve the construction of a comparatively large area of reclamation, it has been estimated that all excavated material under this design will be able to be reused in the reclamation.  In addition, it is expected that up to 1,261,000 m3 of fill will need to be imported, possibly from existing construction and demolition (C&D) waste storage facilities.  Hong Kong is currently storing surplus C&D material, thus the necessity to import such material would be considered to be a positive impact for the Option 2 layout.

In contrast to Option 2, the design of Options 1 and 3, the Base Case and SE Jetty, respectively, will result in a surplus of approximately 0.04 and 0.12 Mm3 of soil following excavation and construction works.  This material will be exported to allocated waste disposal facilities and would be considered as a potentially high impact to such facilities. 

The evaluation of impacts waste generation and disposal for each of the South Soko terminal layout options are presented in Table 1.15.

Table 1.15       Evaluation of Impacts for Waste Generation and Disposal

  

1.16                                  Antifoulants

During the operation of the LNG terminal discharges will include cooled water, as seawater will be used for warming the LNG in the Open Rack Vaporizers.  For operational reasons, the discharges will likely contain antifoulants.  Although all discharges will be designed to comply with the Water Pollution Control Ordinance Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters, impact(s) to marine ecological and fisheries habitats within the surrounding waters needs to be assessed and managed.

For the purposes of this consideration of alternatives, it has been determined that each layout would have the potential to result in similar environmental impacts to resources/receptors as a result of antifoulant discharge, regardless of configuration or design.

The evaluation of impacts from antifoulants for each of the South Soko terminal layout options are presented in Table 1.16.

Table 1.16       Evaluation of Impacts for Antifoulants

  

 


1.17                                  Cooled Water Discharge

As mentioned above, the operation of the terminal is expected to involve the intake of seawater into open rack vaporisers and the discharge of cooled seawater.  The volume of seawater intake and the cooled seawater in the effluent has the potential to impact marine ecological and fisheries habitats in the surrounding waters through a localised reduction in water temperature.

As with antifoulants, for the purposes of this consideration of alternatives, it has been determined that each layout would have the potential to result in similar environmental impacts to resources/receptors as a result cooled water discharge, regardless of configuration or design.

The evaluation of impacts from cooled water discharge for each of the South Soko terminal layout options are presented in Table 1.17. 

Table 1.17       Evaluation of Impacts for Cooled Water Discharge

  

1.18                                  Layout Characteristics

The construction of the reclamation, jetty and dredged areas will result in localised alterations in the water flows (both in terms of velocity and direction).  Altered water flows have the potential to result in secondary effects on the sedimentary regime in the vicinity of the site; increased or changed water flow patterns have the potential to result in localised scour (ie. resuspension) of seabed sediments.  Conversely the creation of areas of calmer or lower velocity water flows have the potential to result in increased sedimentation effects.

The reclamation requirements for layout Option 2, Full Reclamation, may be expected to potentially change the hydrodynamics in the surrounding waters.  Impacts as a result of these changes may occur to water quality, marine ecological and fisheries sensitive receivers.  In addition, the extended footprint of the site would likely increase the exposure to visual sensitive receivers, such as those on Lantau Island.  Such operational impacts are considered to be a disadvantage of this layout in comparison to the others under investigation.

The evaluation of impacts from the layout characteristics for each of the South Soko terminal layout options are presented in Table 1.18.

Table 1.18       Evaluation of Impacts for Layout Characteristics