2                                            Consideration of south soko terminal alternatives

The following section presents a consideration of the alternatives for the South Soko terminal.  The section has been divided into a discussion of the following:

·       Consideration of Different Layouts and Design Options;

·       Consideration of Alternative Construction Methods;

·       Consideration of Pipeline Alignment; and,

·       Consideration of Power and Water Supply.

Based on the above considerations, the Environmental Impact Assessment of the preferred South Soko terminal scenario is presented in subsequent sections.

2.1                                      Consideration of Different Layouts and Design Options

In accordance with Clause 3.3.4 of the EIA Study Brief (ESB-126/2005), this section presents considerations of the different layouts and design options that have been assessed as part of the overall assessment of alternatives for the South Soko LNG terminal.  The methodology, criteria and findings are presented. 

The assessment was conducted to investigate the environmental considerations of each preliminary layout and design option and to examine the engineering aspects for each.  The assessment thus considers both the difficulties of the construction and operation of each facility as well as the associated potential environmental impacts.

2.1.1                               Layout Options

The basic requirements of a LNG receiving terminal in Hong Kong have been described in detail in Part 1 - Section 3.  Justifications for South Soko Island being considered as one of two sites for the LNG receiving terminal in Hong Kong have been presented in Part 1 – Section 4. 

Several terminal layout options on South Soko Island have been considered.  As there is relatively limited flat land on South Soko Island to accommodate the necessary infrastructure, the method of providing sufficient land, either by reclamation or excavation of the existing hillsides has been considered.  In addition, due to the outline of the coastline, several options for the location of the LNG carrier berth have been considered.  These provide differences in dredging requirements and marine navigation complexity due to the delineation of the approach channel and turning basin.

Three layouts have been selected for further assessment in order to provide a comprehensive assessment of different design options.  The layouts present a wide range of engineering options and subsequent environmental considerations for the construction and operation of the South Soko Island terminal.  Each of the layouts has been prepared so that distances between the facilities within the LNG terminal show broad compliance with EN 1473.  The three layouts are presented below in terms of the general design and construction methods.

Option 1 – Base Case

The Base Case layout (Option 1) is derived from a combination of reclamation and excavation, for the purpose of maintaining a balance between the cut and fill quantities (Figure 2.1).  The excavation on the northern side of the site will be undertaken to provide sufficient land area, initially for two tanks with provision for a third tank in the future.  The tank excavation area is completely within the northern hillside for two purposes:

1.    To enable the tanks to be founded directly onto rock which will permit the use of pad/raft foundations thus negating the need for deep foundations; and

2.    To screen the tanks from the visually sensitive receivers on the south side of Lantau Island to the extent reasonably practicable.

The excavation on the southern side of the site will be undertaken to provide sufficient land area for the process plant and associated facilities to maintain the regulatory safe distances from the storage tanks in accordance with EN 1473.  The elevation of these facilities will be up to +10mPD in order to reduce the volume of cutting and to provide a raised platform to prevent wave overtopping to the process area.

Land will be reclaimed immediately to the west of the former detention centre for the proposed utility pier, and to the east of the platform for the proposed service jetties.

The LNG carrier jetty will be located at the northwestern side of South Soko Island, which is sheltered from offshore wave conditions.  The approach channel leading to the jetty will be longer and will require more precise manoeuvring for the transit and turning.  The dredging quantities required to create the approach channel and turning basin will be comparatively higher than the other design options as the existing water depth is slightly shallower.

Option 2 – Full Reclamation

The Full Reclamation layout (Option 2) was considered to reduce the amount of land excavation by increasing the area of reclamation within the Sai Wan Bay (Figure 2.2).  For this option, the 3 tanks are located further south towards the existing reclamation platform.  The excavation of the southern side of the site will be undertaken to provide sufficient land area for the process plant and associated facilities.  The elevation of these facilities will be up to +10mPD in order to reduce the volume of cutting and to provide a raised platform to prevent wave overtopping to the process area.

Area will be reclaimed within the Sai Wan Bay to house the proposed gas turbine substation, utility area and laydown area.  The area to the east of the platform will be for the service jetties.

As in Option 1 the LNG carrier jetty will be located at the northwestern side of South Soko Island.

Option 3 – South East Jetty

The basic plan of the South East (SE) Jetty layout (Option 3) is also similar to Option 1 with the three tanks located within the north side of the site (Figure 2.3).  The excavation on the southern side of the site will be undertaken to a platform of up to +10mPD to house the process plant and associated facilities.

The location of the jetty in Option 3 is revised to suit the ‘no reclamation’ layout as the design distance requirement between the berthing head and the process area/storage tanks may be satisfied with a shorter trestle.  The jetty is therefore moved closer to the shore.  The estimated land area required is slightly larger than in Options 1 and 2 and is measured to be 38.6 ha.  A small amount of land will be reclaimed immediately to the west of the existing platform for the proposed utility pier, and to the east of the platform for the proposed service jetties.

The main difference between this option and the above two options is that the LNG carrier jetty will be located at the southeastern side of South Soko Island.  This location has the advantage of having the shortest approach channel and fewer manoeuvres to berth the carrier alongside the jetty.  Less dredging will be also be required as the water depth on the southeast side of the island is generally deeper. 

Engineering Works Criteria

In order to satisfy each of the terminal requirements described in Part 1 - Section 3, it is necessary to undertake site formation, dredging and reclamation works at each of the layout options at South Soko Island.  The key engineering works criteria for each layout option are summarised in Table 2.1.


Table 2.1        Summary of Engineering Works Criteria (based on conceptual indicative site layouts – numbers are approximate)

Engineering Criteria

Option 1

(Base Case)

Option 2

(Full Reclamation)

Option 3

(SE Jetty)

Site Area (ha)

 

29

35

38.6

Volume of Dredging for Reclamation at South Soko Island (106m³)

 

0.18

0.22

0.18

Volume of Dredging for Approach Channel & Turning Basin (106m³)

 

3.36

3.36

1.07

Volume of Dredging for Submarine Gas Pipeline (106m³)

 

1.44

1.44

1.44

Volume of Excavation Disposed (106m³)

 

0.04

0

0.12

Volume of Fill Imported (106m³)

 

0.28

1.26

0.14

Size of Reclamation (hs)

1.7

13

1.7

Length of Natural Coastline Affected (m)

 

450

600

450

Length of Seawall (m)

 

1,100

1,360

1,100

Seawall modification (ha)

1.3

0.5

1.3

Length of Trestle (m)

 

200

200

240

 

The layouts described above have been assessed and compared in terms of the engineering works required and the potential for environmental impacts through construction and operation.  Each of these assessments is presented below and the findings combined to determine preferred overall site layout.

2.1.2                               Engineering Assessment

Overall Engineering Assessment Criteria

A set of key engineering assessment criteria have been established to enable a quantitative comparison of the three layout options to be scored and ranked in accordance with their relative merits and demerits.  As each of the assessment criteria do not have an equivalent impact on the overall construction of the terminal facility, a relative importance factor has been applied to each as shown in Table 2.2.


Table 2.2        Overall Engineering Assessment Criteria & Associated Relative Importance Factors

Engineering Assessment Criterion

Relative Importance Factor

Construction of site formation works

0.30

Construction of site reclamation works

0.30

Construction of approach channel and turning basin

0.20

Marine navigation

0.10

Construction of  facility foundations

0.10

Total

1.00

The rationale for the relative importance factor is given below.

·      It was considered logical for the sum of the relative importance factors to add up to unity.  In this manner each relative importance factor also directly represents the percentage importance to the whole process.

·      The major engineering works for each of the layout options is considered to be the construction of the site formation and reclamation.  These assessment criterions are therefore given an equally high relative importance factor of 30% each.

·      The next major engineering works for the layout options is the construction of the approach channel and turning basin.  This assessment criterion is therefore assigned a reasonable importance factor of 20%.

·      South Soko Island is only accessible from the sea and therefore construction boats and barges will be used for the import and export of materials to the site.  Marine craft will also be employed for the dredging of the approach channels.  Since the approach to the site will be remote to major marine thoroughfares a relatively low importance factor of 10% is assigned to this criterion.

·      The construction of the facility foundations and the receiving terminal facility itself will generally employ conventional construction techniques which will be similar to all sites with only minor differences resulting from accessibility and specific location constraints.  A relatively low weighting of 10% is therefore applied for these criteria.

Parameters for Each Engineering Assessment Criterion

In order to make a quantitative assessment of the relative advantages and disadvantages of each layout for each of the engineering assessment criterion defined in Table 2.2, a set of engineering parameters reflecting the main tasks to be undertaken under each activity have been developed.  Each parameter carries a weighting to represent the relative significance and impact on the overall engineering assessment criterion.  It was considered logical for the sum of the relative weighting factors to add up to unity.  In this manner each relative weighting also directly represents the percentage importance to the whole process.  The parameters used in the evaluation of the sites for each engineering assessment criterion is detailed in Tables 2.3 to 2.7 and described below.

Construction of Site Formation Works

The engineering assessment criterion for site formation considers nine main parameters as shown in Table 2.3. 

Table 2.3        Engineering Parameters and Associated Relative Used for the Assessment of the Construction of Site Formation Works

Engineering Assessment Criterion

Parameter

Relative Weighting

Construction of site formation works

Volume of excavation in soil

0.05

Volume of excavation in rock

0.25

Volume of soil to be disposed of

0.20

Volume of rock to be disposed of

0.05

Impact on construction programme

0.10

Slope stabilisation measures required

0.10

Slope maintenance

0.05

Future slope hazard

0.05

Blasting risks

0.15

Total

1.00

The rationale for the selection of each relative weighting factor is given below

·      The most difficult and time consuming activity is usually the excavation of rock material, which generally comprises very good quality granite.  The excavation of this material will require significant effort using blasting and heavy mechanical equipment for which stringent engineering controls will be required.  The excavation works are also generally intimately linked with the commencement of construction of the storage tanks, which have a long construction duration and are therefore critical path activities.  As such the rock excavation has a significant impact on the construction programme.  The highest weighting of 25% is therefore assigned to this parameter.

·      The excavation of soil is a relatively easy and quick task utilising mechanical equipment and therefore only a low weighting of 5% is assigned.  The volume of soil excavation is also generally small. 

·      The disposal of the soil material is given a high weighting of 20% as it will need to be taken to one of the Public Fill facilities, which should be avoided to the extent practicable or possible.  High scores are therefore awarded to sites which limit disposal of soil and make the best use of the material.

·      The disposal of rock is given a low weighting of 5%, as it will likely be reused for construction in Hong Kong.  The generation of such material is therefore not deemed to be as highly negative activity compared to soil, which may have limited beneficial use.

·      The construction period for the terminal facility needs to be minimised to meet the required project operational target date.  As the site formation works impact directly on the construction programme, a medium weighting factor of 10% is considered appropriate to favour the sites that can be constructed in the shortest duration.

·      Blasting will need to comply with extensive and stringent regulation requirements.  Incorporation of these measures will impact on the construction programme; and therefore, a medium level relative weighting of 15% is applied to these works to favour the sites that do not require blasting.

·      The slope stabilisation works associated with the facility will need to comply with the regulation requirements which are reasonably stringent and can be extensive for large slopes.  The quantity of stabilisation works therefore needs to be reduced as far as possible.  A medium relative weighting factor of 10% is applied to these works.

·      Slope maintenance and slope hazards are both events that will be under the control of the LNG terminal facility during operation.  These can therefore be reasonably managed and as such a low weighting of 5% has been assigned to each.

 

Construction of Site Reclamation Works

The engineering assessment criterion for reclamation considers ten main parameters as shown in Table 2.4. 

Table 2.4        Engineering Parameters and Associated Relative Used for the Assessment of the Construction of Site Reclamation Works

Engineering Assessment Criterion

Parameter

Relative Weighting

Construction of site reclamation works

Area of reclamation

0.10

Volume of dredging material

0.20

Total volume of fill material required

0.05

Total volume of imported fill (sand + rock)

0.20

Length of natural coastline affected

0.15

Length of artificial coastline affected

0.05

Length of seawall required

0.10

Construction time for dredging and filling

0.05

Time for consolidation after construction

0.05

Need for ground improvement

0.05

Total

1.00

 

The rationale for the selection of each relative weighting factor is given below.

·      The most significant activities are the dredging of the underlying soft material and the importation requirements for subsequent back filling works.  For the latter case a lower amount of imported material is considered more favourable as it indicates that a better balance is being made with the excavated materials from the site formation works.  A high weighting of 20% is therefore assigned to these parameters. 

·      As the volume of imported material has already been considered, the total volume of fill material required is less important if the majority is sourced from within the site and therefore only a 5% weighting is assigned. 

·      The length of natural coastline affected by the reclamation is a measure of the extent of the engineering works on the natural site areas.  A 15% weighting is therefore assigned to this parameter.

·      The length of artificial coastline affected by the reclamation is considered to be less of an effect and therefore a 5% weighting is applied.

·      The length of seawall and the area of reclamation are indicators of the extent of the reclamation.  For these parameters a medium weighting of 10% is deemed appropriate.

·      The time for construction, time for consolidation and the need for ground improvement are important but less significant engineering issues.  A lower weighting of 5% is therefore assumed for these parameters.

Construction of Approach Channel and Turning Basin

The engineering assessment criterion for the construction of the approach channel and turning basin considers five main parameters as shown in Table 2.5. 

Table 2.5        Engineering Parameters and Associated Relative Used for the Assessment of the Construction of Approach Channel and Turning Basin

Engineering Assessment Criterion

Parameter

Relative Weighting

Construction of approach channel and turning basin

Total length of approach channel + turning basin

0.20

Volume of dredging

0.35

Rock excavation in dredged zone

0.20

Impact on existing utilities

0.15

Siltation & maintenance dredging

0.10

Total

1.00

The rationale for the selection of each relative weighting factor is given below.

(i)      For approach channel and turning basin the most significant activity is the dredging works.  A high weighting of 35% is therefore assigned to this parameter.

(ii)          The length of the approach channel and the extent of rock excavation will affects the programme and progress of the overall dredging works and are therefore each assigned a high to medium weighting of 20%.

(iii)         The impact on existing utilities is considered to be localised and secondary effects on the overall dredging works and is therefore assigned a medium weighting of 15%.

(iv)        The siltation/maintenance for the approach channels are factors that affects the long-term operation for which a low to medium weighting of 10% is considered appropriate.

Marine Navigation

The engineering assessment criterion for marine navigation considers four main parameters as shown in Table 2.6. 

Table 2.6        Engineering Parameters and Associated Relative Weighting Used for the Assessment of Marine Navigation

Engineering Assessment Criterion

Parameter

Relative Weighting

Marine navigation

Marine traffic

0.50

Grounding potential

0.10

Striking berth by LNG Carrier

0.10

Striking of the moored carrier by passing traffic

0.30

Total

1.00

The rationale for the selection of each relative weighting factor is given below:

·      Although historically, LNG carriers have had an excellent safety record, the main hazards are the potential for collision with the carrier while in transit to the jetty or from passing traffic striking the carrier while moored.   The probability for such occurrences and consequences will be dependent upon traffic density and discipline of shipboard personnel complying with underway regulations.   As these are the main considerations a weighting of 0.5 and 0.3 are awarded for marine traffic and the striking of the moored carrier by passing traffic respectively

 

·      The consequence of grounding and striking of the marine berth is significantly lower than the above considerations, therefore, a lower but equal weighting of 10% is assigned to each.

Construction of Facility Foundations

The Engineering assessment criterion for construction of facility foundations considers three main parameters as shown in Table 2.7 below. 


Table 2.7        Engineering Parameters and Associated Relative Weighting Used for the Assessment of the Construction of Facility Foundation

Engineering Assessment Criterion

Parameter

Relative Weighting

Construction of facility foundations

Terminal facility structures

0.30

Jetty piling works

0.50

Water front access

0.20

Total

1.00

The rationale for the selection of each relative weighting factor is given below

·      The most difficult foundation construction works for the proposed site is the construction of the marine piling works for the jetty structures, as it will be undertaken over water.  A weighting of 50% is therefore assigned to these works.

·      The land based foundation construction works for the terminal facility structures and the water front access areas are considered to be slightly easier and therefore a weighting factor of 30% and 20% are awarded respectively.  The slightly higher weighting is given to the terminal facility works, as the quantity is significantly greater.

2.1.3                               Site Comparison Scoring System

Parameters and Relative Weighting for Each Engineering Assessment Criterion

In order to make a quantitative assessment of the relative advantages and disadvantages of each site for each of the engineering assessment criterion defined above, a set of engineering parameters reflecting the main tasks to be undertaken under each criterion have been developed as described above.  Each of the engineering criterion and their associated parameters are assigned a relative weighting as shown in Tables 2.2 to 2.7.

Scoring Matrices

Using the parameters described above, each of the different layout options has been evaluated and compared against the base case based upon an assessment of the merits and demerits of each.  For this purpose an options evaluation matrix has been created to compare the South Soko Island base case layout against each of the two alternative layouts.

Firstly, a relative comparison matrix summarising the quantities associated with each assessment parameter is established within separate matrices for each engineering construction criterion.  The matrices are presented in Annex 2-A.

Using the relative comparison matrices an overall score is established for each layout option and each engineering assessment criterion by assigning a relative score for each parameter of between 0 and 5 which is dependent upon the relative magnitude or impact of the parameter value on the works as compared to the base case as shown in Table 2.8.  The base case will receive an average median score of 3 for each parameter.  For the two option layouts, a higher relative score is given to a site parameter with a lower impact on the construction works when compared to same parameter of the base case, and a lower relative score given to a site parameter with a higher impact on the construction works when compared to the base case.  The best layout site will, therefore, achieve the highest overall score for ease of identification.

Table 2.8        Scoring System Applied to Assessment Criteria

Impact on the Construction of the Works as Compared with Base Case

Score

Significantly lower Impact relative to base case

5

 

 

Slightly lower Impact relative to base case

4

 

 

Similar Level of Impact to Base Case

3

 

 

Slightly higher Impact relative to base case

2

 

 

Significantly higher Impact relative to base case

1

The scores are tabulated in a relative comparison scoring matrix for each engineering criterion.  A total score for each engineering criterion is determined from the sum of the weighted individual scores assigned to each parameter depending upon their relative impact.

The results of the scoring for each engineering assessment criteria are based on the summary quantity matrices shown in Annex 2-A. 

Overall Engineering Ranking of the Layout Options

Having assigned a score to each of the parameters within each of the engineering assessment criteria, the result is multiplied by the relative weightings given in Tables 2.3 to 2.7 from which a total score for each site for each engineering assessment criterion is derived.  These scores are then normalised to a maximum value of 5 to enable a quantitative comparison to be made.  These values are referred to as ‘normalised scores’ in Annex 2-A.

These normalised scores for each engineering works activity matrix are applied to the overall ranking matrix.  The relative importance factors given in Table 2.2 are applied to each of the normalised scores within the overall ranking matrix in order to determine an overall score for each option.

Engineering Assessment Results

Having evaluated each layout option for the South Soko Island terminal separately with respect to each engineering assessment criterion, the results of each individual assessment have been used to produce an overall score.  These scores have then been used to rank the layouts in order of preference to enable selection of the preferred option on the basis of the highest score from the engineering assessment.  The results for each engineering assessment criterion developed in Annex 2-A have been collated and are summarised in Table 2.9.

Table 2.9        Engineering Comparison of Layout Options at South Soko Island

Engineering Assessment Criterion

Relative Importance Factor

Option 1

(Base case)

Option 2

(Full Reclamation)

Option 3 

(SE Jetty)

 

 

Score

FS*

Score

FS*

Score

FS*

Construction of Site Formation Works

 

0.30

3.57

1.07

5.00

1.50

2.98

0.89

Construction of Site Reclamation Works

 

0.30

5.00

1.50

2.08

0.63

5.00

1.50

Construction of Approach Channel & Turning Basin

 

0.20

3.66

0.73

3.66

0.73

5.00

1.00

Marine Navigation

 

0.10

4.69

0.47

4.69

0.47

5.00

0.50

Construction of Facility Foundations

 

0.10

5.00

0.50

4.00

0.40

4.17

0.42

Total Score

 

 

4.27

 

3.73

 

4.31

Site Ranking

 

2

3

1

Note:          *  FS = Factored Score (i.e., Score x Relative Importance Factor)

On the basis of the engineering assessment for the construction and operation of the proposed LNG receiving terminal at South Soko Island, the result of the site layout comparison is as follows:

·       Preferred layout:           Option 3 – SE Jetty

·       Second choice:   Option 1 – Base Case

·       Third choice:       Option 2 – Full Reclamation

Alternative Layout for Option 3 – South East Jetty

A variation on the alternative site layout for the preferred layout Option 3 is shown in Figure 2.4, which has been developed to explore the possibility of achieving further engineering merit.  The layout is similar to that of the preferred Option 3 layout with the jetty at the south eastern side of South Soko Island.  However, for the alternative layout the provisional third tank is moved slightly to the southwest onto the reclaimed platform area at +6mPD thus reducing the quantity of rock excavation required.  The alternative layout option is termed Option 3D.

In order to undertake a technical comparison and assessment of the engineering works required for Option 3 and Option 3D, a quantitative comparison of the two layouts has been undertaken to score and rank each of the engineering assessment criteria according to their relative merits and demerits as shown in Table 2.2.  The outcome for all engineering assessment criteria, with the exception of Site Formation, is the same for the two layouts as they are unchanged.  In view of this, the two layout options have been assessed and compared using the Site Formation criterion only.  The detailed comparison of the site formation requirements for Option 3 and Option 3D is presented in Annex 2-A.

The results of the engineering comparison are shown below in Table 2.10.  The total weighted score for each layout has been derived using the weightings given in Table 2.3.  For comparison purposes Option 3 is given a score of 3.0 for each parameter and the Option 3D layout is scored relative to it for each parameter.  For the Option 3D site layout, a higher relative score is given to a site parameter with a significantly lower impact on the construction works when compared to same parameter of the Option 3 layout case, and similarly a lower relative score is given to a site parameter with a significantly higher impact on the construction works.  The best layout site will therefore achieve the highest overall score.

Table 2.10      Scoring for Option 3 and 3D at South Soko Island for Construction of Site Formation Works

Parameter

Weight

Option 3

(SE Jetty – 3 tanks within cutting)

Option 3D

(SE Jetty – 2 tanks within cutting)

 

 

Score

WS*

Score

WS*

Volume of excavation in soil

 

0.05

3.00

0.15

4.00

0.20

Volume of excavation in rock

 

0.25

3.00

0.75

4.00

1.00

Volume of soil to be disposed of

 

0.20

3.00

0.60

4.00

0.80

Volume of rock to be disposed of

 

0.05

3.00

0.15

3.00

0.15

Impact on construction programme

 

0.10

3.00

0.30

4.00

0.40

Slope stabilisation measures required

 

0.10

3.00

0.30

5.00

0.50

Slope maintenance

 

0.05

3.00

0.15

5.00

0.25

Future slope hazard

 

0.05

3.00

0.15

5.00

0.25

Blasting risks

0.15

3.00

0.45

5.00

0.75

Total Weighted Score

 

 

3.00

 

4.30

 

From the comparison of the site formation construction criteria, it is found that the Option 3D site layout is preferred to the Option 3 site layout for South Soko Island.  It also offers significant programme savings due to the reduced quantity of rock excavation.

Summary of Engineering Assessment

Two comparative engineering assessments have been made to study the relative merits and demerits of possible layouts for the proposed South Soko Island terminal.  The first assessment compared the original base case layout with two other possible layouts to identify the preferred layout of the three.  The second assessment investigated the benefits of modifying the preferred layout to consider an alternative design.  The comparisons have been made based on the following engineering assessment criteria:

·       Construction for the site formation;

·       Construction of any reclamation that may be required;

·       Construction of the approach channel and turning basins;

·       Marine navigation; and,

·       Construction of the facility foundations.

Several engineering assessment parameters have been derived for each engineering criteria and a quantitative scoring system applied to each.   An overall score for each site has then been established by applying an importance factor to each of the assessment criteria.

The assessment has determined that the Option 3D – South East Jetty layout is preferred from an engineering standpoint.  This option achieves the best balance between reclamation and excavation quantities.  The location of the jetty at the southeast corner also reduces the dredging volumes for the approach channel and turning basin.

2.1.4                               Environmental Assessment

The three options for the South Soko terminal layout have been assessed in environmental terms through an environmental impact scoping and preliminary assessment exercise (Figures 2.1 to 2.3).  This method allows a high level qualitative comparison of each option through the application of pre-defined impact terminology.  A description of the methodology is presented below ([1]) .

Impact Scoping

Potential impacts have been identified using a “Scoping Matrix”.  Identified activities and key potential sources of impacts (i.e., hazards) have been listed down the vertical column of the matrix while environmental resources or receptors are listed across the horizontal axis.  Each square on the scoping matrix represents a potential interaction between an activity and an environmental resource/ receptor (i.e., potential impact).  Resources/receptors are based on the technical requirements of the EIA Study Brief (ESB-126/2005).

Due to the nature of the construction of each layout option, described above in the engineering assessment, a single scoping matrix has been developed.  Although each layout differs in terms of its design, the functional requirements of the terminal result in similar interactions between activities and environmental resource/ receptors.  Differences appear in the severity of potential impacts.  The scoping matrix is presented in Table 2.11.

Table 2.11      Impact Scoping Matrix

 


It should be noted that the list of activities/ hazards is not intended to be exhaustive but rather an identification of key aspects of both construction and operation phases of the LNG terminal that have the potential to interact with the environment and subsequently have the potential to cause environmental impacts.  The list of environmental receptors/ resources is also a focused list of the key aspects of the environment that are considered vulnerable or important in the context of the construction and operation of the LNG terminal.

Evaluation of Impacts

In evaluating the degree of potential impacts, the following factors have been taken into consideration:

·      Impact Severity:  The severity of an impact is a function of a range of considerations including the following:

-      impact magnitude;

-      impact duration;

-      impact extent;

-      legal and guideline compliance; and,

-      characteristics of the receptor/ resource that is affected.

·      Likelihood of Occurrence:  How likely is the impact to occur?

Severity Criteria for Environmental Impacts

In evaluating the severity of potential environmental impacts, the following factors have been taken into consideration:

·      Receptor/ Resource Characteristics:  The nature, importance and sensitivity to change of the receptors or resources that could be affected;

·      Impact Magnitude:  The magnitude of the change that is induced;

·      Impact Duration:  The time period over which the impact is expected to last;

·      Impact Extent:  The geographical extent of the induced change; and

·      Regulations, Standards & Guidelines: The status of the impact in relation to regulations (eg. discharge limits), standards (eg. environmental quality criteria) and guidelines.

Impact severity has been categorised using the following subjective scale:

·      Slight;

·      Low;

·      Medium; and

·      High.

Likelihood of Occurrence

The likelihood (probability) of the pre-identified events occurring has been ascribed using the following qualitative scale of probability categories (in increasing order of likelihood):

A.        Extremely unlikely (eg never heard of in the industry);

B.       Unlikely (eg heard of in the industry but considered unlikely);

C.       Low likelihood (eg such incidents/impacts have occurred but are uncommon);

D.       Medium likelihood (eg such incidents/impacts occur several times per year within the industry); and

E.       High likelihood (eg such incidents/impacts occurs several times per year at each location where such works are undertaken).

Likelihood is estimated on the basis of experience and/ or evidence that such an outcome has previously occurred.  Impacts resulting from routine/planned events (i.e., normal operations) are classified under category (E).

Impact Significance

The significance of each impact is determined by assessing the impact severity against the likelihood of the impact occurring as summarised in the impact significance assessment matrix provided in Table 2.12.

Table 2.12       Impact Significance

 

 

Significance criteria for negative/adverse impacts (i.e., relative ranking of importance) are defined in Table 2.13.  It is important to note that impacts are considered without the implementation of mitigation measures.  The need for and appropriate method of mitigation would be determined on the basis of the impact assessment.

Table 2.13      Significance Criteria

·      Positive Impacts are classified under a single category; they are then evaluated qualitatively with a view to their enhancement, if practical.

·      Negligible or Low Impacts will require little or no additional management or mitigation measures (on the basis that the magnitude of the impact is sufficiently small, or that the receptor is of low sensitivity). 

·      Medium or High Impacts require the adoption of management or mitigation measures.

·      High Impacts always require further management or mitigation measures to limit or reduce the impact to an acceptable level. 

Evaluation of Potential Environmental Impacts

An evaluation of the above identified potential impacts as a result of the construction and operation of each of the South Soko terminal options has been undertaken using the concepts described above.  The results of these evaluations are presented in detail in Annex 2-B.  The impact assessment matrices for each of the three layout options for the South Soko terminal are presented below in Tables 2.14 to 2.16.  Key impacts, i.e., those activities/ hazards which have the potential to result in high impacts to environmental resources/ receptors are highlighted for each option.  Following this, environmental impacts that differentiate between the layout options are presented.

 

Table 2.14      Impact Assessment Matrix: Option 1 - Base Case

 

Key potential impacts, i.e., high impacts that are considered to be significant and must be mitigated, associated with the construction and operation of the South Soko terminal according to the Option 1 – Base Case layout have been identified as the following:

·       Construction Marine Dredging and Disposal Impacts to Water Quality;

·       Construction Piling Works on Marine Mammals;

·       Construction Waste Generation and Disposal on Waste Storage Facilities; and,

·       Construction Excavation to Archaeological Site.

Details on each of the above are presented in Annex 2-B.

Table 2.15      Impact Assessment Matrix: Option 2 - Full Reclamation

 

Key potential impacts associated with the construction and operation of the South Soko terminal according to the Option 2 – Full Reclamation layout have been identified as the following:

·       Construction Marine Dredging and Disposal Impacts to Water Quality;

·       Construction Piling Works on Marine Mammals;

·       Construction Excavation to Archaeological Site;

·       Operation Layout Characteristics on Hydrodynamics; and,

·       Operation Layout Characteristics on Visual (Aesthetics).

Details on each of the above are presented in Annex 2-B.

 

 

Table 2.16      Impact Assessment Matrix: Option 3 - South East Jetty

 

Key potential impacts associated with the construction and operation of the South Soko terminal according to the Option 3 – SE Jetty layout have been identified as the following:

·       Construction Waste Generation and Disposal on Waste Storage Facilities; and,

·       Construction Excavation to Archaeological Site.

Details on the above are presented in Annex 2-B.

Environmental Differentiators

A summary of the key environmental differentiators between the three options is presented below.

Marine Dredging and Disposal

According to the engineering design of the three layouts for the South Soko terminal one of the major differences appears to be in the dredging and subsequent disposal requirements of marine sediments.  Table 2.1 above indicates that both Option 1 – Base Case and Option 2 – Full Reclamation have been estimated to require approximately 3.36 Mm3 of marine sediments to be removed in order to dredge the approach channel and turning basin to the required depth for safe LNG carrier passage (approximately -15 mPD).  In contrast, Layout 3 – SE Jetty will only require approximately 1.07 Mm3 of marine sediments to be removed. 

The primary difference is the shorter length of the approach channel and turning basin for this layout has been designed to only come into the southeastern side of South Soko Island, which is in contrast to Options 1 and 2 where the channel circumnavigates the southern, eastern and northern sides of the island before ending at the northwest near Sai Wan bay.

The increased dredging requirements of Options 1 and 2 will have subsequent increases in potentially adverse consequences to resources and receptors, such as those to water quality, marine habitats (both intertidal and subtidal), marine mammals, as well as fisheries resources and operations.  These differences have been reflected in the impact severity and likelihood assessments.

Piling

Piling operations will be required for all layouts in order to construct the jetty and trestle for the LNG carrier.  Piling operations have the potential to result in adverse impacts to underwater noise and subsequently marine mammals.  Layout Options 1 and 2 of the South Soko terminal would require the jetty to be constructed in the northwestern Sai Wan Bay of South Soko Island, whereas, Option 3 will have the jetty located on the southeastern side of the island. 

Recent monitoring by CAPCO as well as long-term monitoring of marine mammal abundance and distribution in these waters (Part 2 – Section 9) indicates that marine mammal sightings are more frequent in the waters in the vicinity of Options 1 and 2, in comparison to those in the waters surrounding the jetty in Option 3.  As a result, it would be expected that the potential for adverse impacts to occur to marine mammals as a result of marine piling operations would be considered likely to be higher for Options 1 and 2 when compared to Option 3. 

Reclamation

The engineering design of Option 2 – Full Reclamation will require the reclamation of approximately 13 hectares (ha) of existing marine habitats.  The majority of reclamation will occur to the west of the existing platform to house the proposed turbine substation, utility area and laydown area.  The area to the east of the platform will be used for the service berth. 

In comparison, both Options 1 and 3, Base Case and SE Jetty respectively, will require only approximately 1.7 ha of marine habitats to be reclaimed.  This will primarily be needed for the utility pier on the west of the platform (or for Tank 3 for the SE Jetty layout) and to the east for the service berths.

The differences in reclamation area will result in subsequent increases in potential impacts to resources and receptors, such as those to water quality, marine habitats (both intertidal and subtidal), marine mammals, fisheries resources and operations as well as visual and aesthetics.  These differences have been reflected in the impact severity and likelihood assessments.

Waste Generation and Disposal

All options will require the excavation of rock from the existing hillsides in order to provide sufficient flat land to meet the functional requirements of the LNG terminal.  However, as the Option 2 layout design will involve the construction of a comparatively large area of reclamation, it has been estimated that all excavated material under this design will be able to be reused in the reclamation.  In addition, it is expected that up to 1,261,000 m3 of fill will need to be imported, possibly from existing construction and demolition (C&D) waste storage facilities.  Hong Kong is currently storing surplus C&D material, thus the necessity to import such material would be considered to be a positive impact for the Option 2 layout.

In contrast to Option 2, the design of Options 1 and 3, the Base Case and SE Jetty, respectively, will result in a smaller requirement for import of fill than Option 2. 

Layout Characteristics

The reclamation requirements for layout Option 2, Full Reclamation, may be expected to potentially change the hydrodynamics in the surrounding waters.  Impacts as a result of these changes may occur to water quality, marine ecological and fisheries sensitive receivers.  In addition, the extended footprint of the site would likely increase the exposure to visual sensitive receivers, such as those on Lantau Island.  Such operational impacts are considered to be a disadvantage of this layout in comparison to the others under investigation.

Environmental Assessment Results

The results of the environmental impact scoping and assessment allows a comparison of each layout and design option to be presented based on the number of issues.  Each option has been ranked in order of preference against the other on the basis of the number of impacts compared to the other two options, i.e., the lower number of impacts the better.  On the basis of these ranks, the average rank has been determined for each option to determine the order of preference in both the construction and operation phases of the potential South Soko terminal.  The result of the comparison is presented in Table 2.17.

Table 2.17      Comparison of Layout Options at South Soko Island in terms of Environmental Assessment

 

On the basis of the environmental assessment for the construction and operation of the potential South Soko terminal, the result of the layout comparison is as follows:

·      Preferred layout:            Option 3 – SE Jetty

·      Second choice:             Option 1 – Base Case

·      Third choice:                 Option 2 – Full Reclamation

Option 3 is preferred based on the following reasons:

·      Reduced reclamation size;

·      Reduced amount of natural coastline disturbed as a result of reduction in reclamation works; and

·      Significantly reduced dredging volumes by orientating the LNG jetty to the southeast of South Soko Island. 

·      Option 3 avoids having to site the jetty (and therefore not have to dredge the turning basin and approach channel) in the area between the North and South Soko Islands which has been highlighted by EPD in the Study Brief as an area where impacts should be avoided/reduced.

Option 3 layout has resulted in a substantial reduction in ecological, fisheries and water quality impacts through reduction in reclamation, dredging and natural coastline loss.  The reduction in dredging will also have a benefit in reducing off site impacts during disposal of dredged muds and ease the burden on the capacity of existing disposal sites.

Alternative Layout for Option 3 – South East Jetty

As with the engineering assessment, an alternative layout for the preferred option has been examined in terms of comparing the layout from an environmental perspective (see Figure 2.4).  As the design of the alternative option for the SE Jetty, termed Option 3D, is similar to that of the original Option 3, with principal changes being on-land configuration, the impact scoping and assessment methodology applied for the comparison of the three layout options would not be sensitive enough to differentiate between the two options.  A comparative methodology of preference is therefore presented below (Table 2.18).  As above, resources/ receptors have been based on the technical requirements of the Study Brief (ESB-126/2005).

Table 2.18      Comparison of Environmental Preference between Option 3 (SE Jetty -3 Tanks) and Option 3D (SE Jetty - 2 Tanks)

On the basis of the above, the indication is that the layout for Option 3D (SE Jetty – 2 Tanks) would be preferable from an environmental perspective.  With the exception of cultural heritage and hazard to life, Option 3D would be preferred for all environmental resources/ receptors under the EIAO-TM.  Rationale for each assessment is presented below.

Air

According to the engineering assessment, the combined volume of soil and rock to be excavated from Option 3 during construction works would be approximately 2.3 Mm3, whereas, for Option 3D an estimated combined volume of 2.06 Mm3 of material would be required to be excavated.  Assuming the material would be removed through similar processes, air quality impacts associated with the excavation of this material through construction works, such release of particulates and dust, would therefore be expected to be lower for Option 3D.  Operational impacts would be expected to be similar for both options.  As a result, Option 3D would be preferred over Option 3 from an air quality perspective.

Noise

Given that the sensitive receivers at Shek Pik are located at approximately 6 km away from the site, the construction and operational noise would be expected to be similar for both options.

Water

Due to the relocation of the utility pier to Tung Wan bay to the east of the platform, Option 3D would not require a dredged approach channel in Sai Wan bay when compared to Option 3.  Refinements to the approach channel for the LNG Carrier to the south east of the island would also reduce dredging requirements. 

In addition to the above, the layout of Option 3D proposes that the outfall for the cooled water be located to the south east of the island, with the discharge point approximately 10 m offshore and in close proximity to the jetty for the LNG carrier.  For Option 3 the outfall has been located directly south of Yuen Kong Chau, the small island to the east of Tung Wan Bay.  The relocation of the outfall to the south of the island in Option 3D allows the discharge point to be located in an area of increased current flows, thereby potentially allowing more immediate dispersion and assimilation of the cooled water.  In addition, the installation of a 10 m outfall for Option 3D in comparison to an approximate 400 m outfall for Option 3 would result in lower dredging requirements.

The reduction in dredging requirements described above would result in a decrease in the potential for impacts to water quality to occur through the sediment plumes as a result of the release of suspended solids and through any changes in general hydrodynamics.  On this basis, Option 3D would be preferred over Option 3 from a potential impacts to water quality perspective.

Terrestrial Ecology

As with the comparison for air and noise impacts, the reduction in excavation requirements at Fei Kei Teng and Sheung Tsuen will result in a reduced impact to terrestrial ecology.  Assuming excavation methods will be similar between options, the total area of habitat loss, and therefore potential to impact terrestrial flora and fauna, will be less for Option 3D than for Option 3 (for approximately 1 ha).  Based on this, Option 3D would be preferred over Option 3 from a terrestrial ecology perspective.

Marine Ecology

As impacts to water quality are likely to be lower with Option 3D when compared to Option 3, it would be reasonable to assume that indirect impacts to marine ecology would also be lessened.  Similarly, direct impacts would be lower due to a reduction in disturbed habitat through dredging works. 


Fisheries

The potential to limit impacts to Sai Wan Bay and Pak Tso Wan through a reduction in dredging works would be considered to be favoured in terms of reducing the potential for impacts to occur to fisheries resources.  These waters have previously been identified as an area supporting fish fry habitat, and as such, unacceptable impacts to water quality in this bay may have the potential to result in consequences to fish fry (see Part 2 – Section 10).  Option 3D would, therefore, be preferred over Option 3 in terms reducing the potential to impact fisheries resources, and subsequently fishing operations.

Landscape and Visual

The configuration of the on-land facilities associated with layout Option 3 would result in excavation of the majority of the southern slope of Fei Kei Teng.  Whilst this natural slope will provide some degree of shielding for Tanks 1 and 2 of the design, the top of future Tank 3 would remain visible from a number of visual sensitive receivers to the south of Lantau, albeit predominantly from the south east of Lantau and at some considerable distance from the source.  In contrast, Option 3D, by leaving a larger portion of the natural southern slope of Fe Kei Teng intact, the future Tank 3, which would be located south of Tank 2 would likely be shielded from view from the majority of sensitive receivers.  In addition, from an aesthetic point of view, it would be considered favourable to leave the natural terrain in place as much as possible.  As a result, Option 3D would be considered to be preferred from a Landscape and Visual perspective.

Cultural Heritage

Recent surveys of areas or deposits of potential archaeological interest or cultural heritage importance (Part 2 – Section 12) indicate that the majority of deposits of archaeological potential or existing graves are located in areas that are in common for both Option 3 and Option 3D.  As such, similar mitigation measures would be proposed for each of the two layouts to limit any impacts to cultural heritage and as a result, there would be no preference between the two sites from a cultural heritage perspective.

Hazard to Life

As with potential impacts to cultural heritage, the design of each site is similar such that the potential hazard to life would be considered no different between the two.  A minor difference may be in that potentially less blasting would be required during the construction of Option 3D when compared to Option 3, however, as both would require blasting neither site is considered to be preferable over the other from a Hazard to Life perspective. 

Summary of Environmental Assessment

As with the engineering assessment, two comparative environmental studies have been made to assess the relative merits and demerits of possible layouts for the proposed South Soko terminal.  The first study compared the base case layout with two other possible layouts to identify the preferred layout of the three.  The second study investigated the benefits of modifying the preferred layout to consider an alternative design.  The comparisons have been made based on the potential for impacts to occur to resources/ receptors identified under the EIAO-TM and the technical requirements of the Study Brief (ESB-126/2005).

As it is not considered appropriate to apply an importance factor to environmental criteria, potential impacts to resources/ receptors have been firstly identified through the potential for interaction, followed by a qualitative assessment of the likely severity of impact.

The assessment has determined that the Option 3D – South East Jetty layout is preferred from an environmental perspective.  This option offers lower excavation requirements as well as a reduction in dredging volumes.  The potential for subsequent impacts to the environment have, therefore, been considered to be lower for this layout option.

2.1.5                               Summary of Consideration of Different Layouts and Design Options

The above section has considered different layouts and design options for the South Soko terminal as part of the overall assessment of alternatives.  The assessment has been conducted to investigate not only the environmental considerations of each preliminary layout and design options, but to include an examination of the engineering aspects for various layouts.  The assessment has thus considered both the difficulties of the construction and operation of each facility as well as the potential environmental impacts associated with such.

Both the engineering and environmental assessments have identified layout Option 3D – South East Jetty as the most preferable for the construction and operation of the South Soko terminal.  This option achieves the best balance between reclamation and excavation quantities.  The location of the jetty at the southeast corner also reduces the dredging volumes for the approach channel and turning basin.  The engineering consequences and subsequent environmental impacts are considered to be lower for this layout option.

The South East Jetty Option 3D Layout was therefore taken forward as the preferred layout for the South Soko terminal in the Environmental Impact Assessment.  However, it should be noted that a further revision to the layout was made during the EIA as a result of information gathered from the baseline environmental surveys.  This layout change and the resulting adopted layout are presented in Section 2.5. 

 

2.1.6                               Tank Technology Selection

The Hong Kong LNG Terminal Project has selected the above-ground full containment LNG tank system for the import re-gasification terminal in Hong Kong SAR (as discussed in Part 1 Section 3).  This selection is applicable to either South Soko Island or Black Point, the two sites being considered for the LNG terminal.  A technical note has been prepared that discusses the main reasons for selecting an above-ground full containment LNG storage tank system over other methods, such as an in-ground system and this is presented in full in Annex 2D. 

2.2                                      Consideration of Alternative Construction Methods & Sequences

In accordance with Clause 3.3.5 of the EIA Study Brief (ESB-126/2005), this section presents the consideration of alternative construction methods and sequence of works that have been assessed as part of the overall assessment of alternatives for the South Soko terminal. 

The assessment has been conducted to investigate potential methods and plant for the construction of the proposed terminal as well as associated facilities such as the submarine cable, water main and natural gas pipeline.  The objective of the assessment is to identify the preferred alternative with a view to avoid the likelihood of unacceptable adverse environmental impacts.

Alternative construction sequences have been investigated in the EIA , specifically in the water quality section (Section 6) in order to avoid localised cumulative effects and to avoid adverse impacts to the maximum practical extent. 

The basic requirements of a LNG terminal in Hong Kong have been described in Part 1 – Section 3.  Justifications for South Soko Island being considered as one of the two sites for a LNG receiving terminal in Hong Kong have been presented in Part 1 – Section 4.

On the basis of these requirements, it is considered that the following are the key facilities to be constructed, to which alternative methods have been considered:

·       Reclamation;

·       Seawalls;

·       Jetty;

·       Approach Channel and Turning Basin; and

·       Submarine Gas Pipeline, Water Main and Power Cable.

As the onsite facilities, such as the LNG storage, gasification plant, administration office, canteen, ancillary buildings and sewerage treatment plant etc, will be constructed to best industry standard, alternatives for construction will not be discussed.

2.2.1                               Reclamation

The preferred layout for the South Soko terminal (see Part 2 – Section 2.1) would involve mainly site formation works and approximately 1.7 ha of reclamation.  The relatively small-scale reclamation is predominantly for the construction of breakwater and service berths.  The layout for the preferred South Soko terminal is presented in Figure 2.4.

Traditionally the method to construct the reclamation area has been to dredge away all soft seabed materials under the entire reclamation area.  This would be considered as a ‘Fully Dredged Method’.  However, recently in Hong Kong there has been an increasing reliance on only dredging soft mud from beneath the seawall and main drainage culverts and to leave the soft mud under the proposed reclamation area.  According to the Practice Note for Authorized Persons and Registered Structural Engineers (PNAP) No. 252 issued by the Buildings Department, project proponents must plan projects on the assumption of keeping the mud in place.  Time for consolidation and consequential programme constraints shall be allowed for in programming.  In order to reduce the long term ongoing settlement of the soft mud under the overlying reclamation fill, ground improvement works would be necessary.  Such a construction method would be considered as a ‘Partially-dredged Method’.  In line with local construction practice and government policy, this method will be adopted for the project.  It is noted that the partially dredged option minimises the quantities of materials dredged on site and therefore disposal offsite resulting in a net environmental benefit.

Partially-dredged Method

For this method, dredging would be limited to only the area beneath the seawall.  The mud is not dredged from beneath the reclamation area but rather sand fill is placed over the soft mud to initially raise the ground level to +2.5 mPD after which, public fill is compacted in layers to the finished level of +6 mPD.  There are two key engineering issues to be considered with this method as follow:

·      The soft marine mud will consolidate significantly under the weight of the overlying fill.  This consolidation may well be up to 3 metres and will take many years to complete if no additional ground improvement works are put in place;

·      The initial layers of sand fill need to be placed very carefully to avoid the generation of mud waves which can significantly affect the long term performance of the reclamation.

The second issue is usually rectified by protecting the mud by a layer of geotextile followed by hydraulically placed sand.

Ground movements due to consolidation settlement have a significant impact on the operation of the facility.  The most sensitive structures will need to be necessarily piled in order to mitigate these effects of ground movement.  However, it will not be sensible to support all plant and services at the site on piles.  In these areas ground improvement measures will be essential to reduce ground movements to acceptable levels.  Two commonly used ground improvement methods suitable for use in reclamation areas include the following: -

·       Installation of vertical drains together with surcharge pre-loading; and

·       Vibro-replacement / vibro displacement.

In view of the tight construction programme, cost-effectiveness and the sensitive nature of cryogenic equipment, the use of vertical drains with surcharge pre-loading is considered the most suitable method of ground improvement.

Vertical Drains with Surcharge Pre-loading

The use of vertical drains (often called band drains) for construction of reclamations has the effect of shortening the drainage paths of the relatively impermeable marine clay and/or alluvial clay.  The consolidation settlement due to the site formation can therefore be achieved within a shorter period.  Drains are typically inserted on a triangular grid at 1.2 to 1.5m spacing down to the interface between marine deposits/alluvial clay layer (sometimes penetrated through the alluvium, depending on its engineering characteristics).

The surcharge preloading serves the following purposes: -

·      To significantly speed up the consolidation;

·      If suitable additional surcharging height or time duration is allowed, it can substantially eliminate the settlement due to the future imposed load from low rise buildings and other light weight structures.

The design height and duration of placement for the surcharge mound will depend upon the time allowed in the construction programme.  For projects with a tight construction programme such as this, the surcharge mound would need to be high.  It is currently estimated that the height of the surcharge mound would need to be approximately 5m above the future formation level of +6mPD which will achieve acceptable long-term settlement performance of the reclamation.

 

The cryogenic pipelines and facility structures will require very tight settlement criteria as the movement tolerances are very small.  The proposed foundation schemes for the structures are still under development and thus a detailed settlement / differential settlement analysis shall be carried out at a later stage.

2.2.2                               Seawalls

Dredging is required to remove the soft material beneath the seawall to ensure that the seawall is stable and can be built within an optimum timeframe, thereby reducing the potential for environmental impacts to occur.  In addition to the conventional method of carrying out full dredging of the marine deposits before filling up for the seawall, two other alternatives have been considered. 

The first alternative makes use of ground improvement technique, such as Deep Cement Mixing (DCM), to enhance the strength of the marine deposits before filling up for the seawall.  In DCM, the soft soil is mixed in-situ with an appropriate additive using an auger or other mixing device.  The additive used is typically cement or lime.  No spoil removal is required.  A similar technique called Deep Cement Method was developed in Japan, using cement slurry.  Previous studies have investigated the use of cement stabilization work as part of the ground improvement method, however, these have only been performed on the bench-scale test but such technology has not been taken forward on site with pilot trial ([2]).  The efficiency and cost-effectiveness of the improvement method has not been tested and as such it is not possible to assess the environmental and safety impact attached to this alternative.  The use of Deep Cement Mixing is therefore not the preferred construction alternative for the current study.

The second alternative requires a long counter fill on the seaward side of the seawall to provide toe stability against slip failure during construction.  The use of this method is, however, considered to be unsuitable for this project as it is likely to lead to significant ongoing settlement of the sea wall after the LNG terminal is in operation.

On the basis of the above, neither of the alternative methods is preferred over the conventional method of dredging beneath the seawall.  As such, the conventional method of carrying out full dredging of the marine deposits before filling up for the seawall is recommended as the preferred alternative for the construction of the seawalls for the LNG terminal.

2.2.3                               Jetty

A piled jetty is required for creation of the berthing facility for the LNG carrier at the South Soko terminal.  Piled structures are preferable to blockwork or closed structure designs as they are less likely to result in adverse impacts to water quality and subsequently marine ecology, due to the minimal disturbance to hydrodynamics. 

For the construction of the LNG Jetty, two alternatives are available for the installation of marine piles.  These are bored or percussive piling methods.  A discussion of each of these methods in terms of the environmental advantages and disadvantages is presented below.

Bored Piles

Noise created by bored piling methods tends to be a less intensive continuous noise, rather than the pulsed high power sounds emitted through percussive piling ([3]).  A summary of potential impacts from bored piling methods are presented below.

·       a large casing must be driven into the seabed in order to support the boring equipment which will necessitate a longer construction period;

·       socketing into the bedrock will require the use of a chisel (noise impacts from socketing may be mitigated by using the reverse circulation drilling method); and,

·       placing concrete to the bored pile (potential leakage of cementitious materials from sacrificial casing during this process).

Percussive Piles

The sounds emitted from percussive hammer pile driving activities have their highest energy at lower frequency (20 Hz to 1 kHz) and loud sounds have been identified to cause (short-term) behavioural reactions such as increased swimming speed in cetaceans ([4]).  Studies in Hong Kong have, however, determined that with measures such as bubble jackets and bubble curtains, marine mammal behaviour does not change substantially during percussive piling operations ([5]). 

Based on the well-proven track record for the successful employment of these measures, it is proposed that either method be used for the construction of the LNG Jetty as part of the South Soko terminal.  Detailed assessments of the impacts of both methods are also mentioned in other sections in this EIA Report.

2.2.4                               Approach Channel and Turning Basin

An approach channel and turning basin will be required to allow for the safe transit of the LNG carrier to the jetty.  In order to meet the required draft of the carrier, both the channel and turning basin will be required to be dredged to approximately -15 mPD.  There are two common dredging plant that are employed for the removal of marine sediments in Hong Kong.  These are grab dredgers or trailing suction hopper dredgers (TSHD).  Each plant would be available as alternatives for the construction of the approach channel and turning basin.  The potential environmental benefits and dis-benefits of each are discussed below.

Grab Dredgers

A grab dredger comprises a rectangular pontoon on which is mounted a revolving crane equipped with a grab.  The dredging operation consists of lowering the grab to the bottom, closing the grab, raising the filled grab to the surface and discharging the contents into a barge.  Grab dredgers are usually held in position while working by anchors and moorings but some have a spud or pile, which can be dropped onto the bottom while the dredger is operating.

Grab dredgers may release sediment into suspension by the following mechanisms:

·       Impact of the grab on the seabed as it is lowered;

·       Washing of sediment off the outside of the grab as it is raised through the water column and when it is lowered again after being emptied;

·       Leakage of water from the grab as it is hauled above the water surface;

·       Spillage of sediment from over-full grabs;

·       Loss from grabs which cannot be fully closed due to the presence of debris;

·       Release by splashing when loading barges by careless, inaccurate methods;

·       Disturbance of the seabed as the closed grab is removed.

During the transport of dredged materials, sediment may be lost through leakage from barges.  However, dredging permits in Hong Kong include requirements that barges used for the transport of dredging materials shall have bottom-doors that are properly maintained and have tight-fitting seals in order to prevent leakage. 

Sediment is also lost to the water column when discharging material at disposal sites.  The amount that is lost depends on a large number of factors including material characteristics, the speed and manner in which it is discharged from the vessel, and the characteristics of the disposal sites. 

Trailing Suction Hopper Dredgers

Trailing Suction Hopper Dredgers (TSHD) are designed to use a suction mouth at the end of a long pipe.  As the barge moves, the suction hopper trails along and sucks up the soft seabed sediments.  During dredging the drag head will sink below the level of the surrounding seabed and the seabed sediments will be extracted from the base of the trench formed by the passage of the draghead.  The main source of sediment release is the bulldozing effect of the draghead when it is immersed in the mud.  This mechanism means that sediment is generally lost to suspension very close to the level of the surrounding seabed.

During dredging marine sediments are pumped into the vessel’s hopper.  Once the hopper is loaded the dredging operation will be stopped and the vessel will sail to a designated disposal area.  A TSHD is usually positioned by dynamic positioning, thus they have no anchor wires. In comparison to grab dredgers, TSHDs generally have a higher production rate.

Both Grab dredgers and Trailing Suction Hopper Dredgers (TSHD) are commonly used in Hong Kong.  As such, the employment of both plant are considered viable options.

2.2.5                                Gas Pipeline, Water Main and Power Cable

Due to the geological profile of the proposed alignments for the natural gas pipeline, water main and power cable (each of which are discussed further in the following sections), the installation of these facilities will require dredging/trenching operations for the offshore and nearshore sections.  Dredging will be employed at each of the associated facilities launching and landing sites, due to the proximity of these locations to the shoreline requiring accurate removal of potential marine muds and rock fill.  In addition, dredging and backfilling with a combination of gravel and rock armour will be required when these facilities cross fairways and other specific locations in order to provide adequate protection from third party damage. 

Offshore, along the routes of each installation, there is the potential to employ jetting in order to trench these facilities to the required depths.  Whilst dredging methods are discussed above, a description of the jetting method is presented below.

Jetting

The jet machine will either be self-propelled or be towed by barge.  The self-propelled machine has wheels resting on the pipeline and uses the pipe for traction.  Stability is achieved with the use of buoyancy aids.  A ‘Non-conventional’ jetting machine may be utilised, as it does not use air to assist with discharge of the sediment.  This results in less adverse effect on the water quality of the surrounding areas. 

From the soil data, a nozzle configuration that best suits the in-situ soil characteristics will be determined.  The method is based on fluidising the muds allowing the pipe to sink to the chosen depth. 

During the installation of the submarine utilities using jetting technology, it would be expected that seabed sediment would be released close to the seabed and will settle out relatively quickly.  The sediment would therefore only be in suspension for a short period of time and as such, the potential for impacts to occur, such as through the exertion of the oxygen demand on the receiving waters, will be limited.

Preferred Installation Techniques for Submarine Gas Pipeline

Data gathered during the EIA on marine ecological resources along the submarine gas pipeline route indicated that there were two key sensitive areas ie, West Lantau where dolphins are abundant and along the boundary of the Sha Chau Lung Kwu Chau Marine Park.  Consequently, during the preliminary engineering design of the submarine pipeline an analysis of different techniques was undertaken to select the method that produced the better overall environmental performance.

West Lantau

In West Lantau there were two options for the route, one was aligned inshore and the other offshore close to the boundary of Hong Kong waters.  The option to use jetting was only available inshore as the offshore route required a larger dredged trench with additional armour rock backfill as protection from anchor drop and drag.  For this reason for the offshore option it was proposed that a trailing suction hopper dredger (TSHD) be employed.  The impact on water quality was examined for both of the options as shown in Figure 2.5. 

TSHD Dredging Maximum SS Elevation in the Dry Season

JettingMaximum SS Elevation in the Dry Season (jetting has to be carried out on a inshore route)

TSHD Dredging Maximum SS Elevation in the Wet Season

JettingMaximum SS Elevation in the Wet Season (jetting has to be carried out on a inshore route)

Figure 2.5      Contour plots of maximum suspended solids elevations generated in West Lantau using Jetting (45 m hr-1 working 24 hours per day) or TSHD Dredging (4,600 m3 trip-1 working 24 hours per day) ([6])

The results show the spread of suspended sediment generated by the jetting machine extends further and is more concentrated than the TSHD.  It is noted from the plots that in both the wet and dry seasons the SS elevations exceed 30 mg L-1 along some of the coastal areas of West Lantau some areas of which would be within the boundary of the Proposed Southwest Lantau Marine Park (eg Peaked Hill) whereas for the TSHD the plumes generated do not touch the coastline areas.  The areal exceedance of the water quality objective is also larger for the jetting machine than the TSHD.  The impacts produced by the inshore jetting option are unlikely to be acceptable without additional mitigation measures whereas the impacts of the TSHD are not unacceptable.

The jetting machine does not generate any mud to be disposed offsite unlike the TSHD.  However, given the expected water quality impacts of the inshore jetted route this concern is considered to be secondary.

For this section of the gas pipeline a grab dredger was not considered a suitable engineering solution to form a trench of the required size at the given location compared to a TSHD.  The advantages of using a TSHD over grab dredgers are summarised as follows :

1)   In this region the water depth is deeper and the current velocities much higher than along other sections of the pipeline route.  The grab, which is connected only by winches to the derrick barge, would be affected by these marine conditions, which will result in a less accurate dredging profile.  The barges also use only simple global positioning systems, which leads to crude positioning and depth control, typically resulting in over-dredging of the channel. 

  The TSHD has an attached trailer which is lowered onto the seabed when dredging.  The greater rigidity of the trailer typically results in more accurate dredging even in strong currents and deep water.  The vessel is also equipped with sophisticated satellite positional (DGPS) and depth control systems and hence they are able to cut the trench profile more accurately.

2)   The dredged profile in this section requires a much larger trench width than elsewhere along the route.  It is therefore more suited towards the more efficient TSHD operation which can dredge more than 4 times the daily volume of mud compared to a single grab dredger.

  Due to their slower work rate, there is also a concern that the use of grab dredgers could lead to slumping of the trench sides as pore water pressures recover within the low permeability clay material.  Slumping of the trenches would lead to additional remedial dredging, and hence mud disposal needs, as well as additional impacts on water quality and marine ecology that could otherwise be avoided through the use of the TSHD.

3)   A grab dredger needs to work with a split-bottom barge to store the dredged mud, and also tug boats, hoppers, pontoons, etc.  To make up for the grab’s smaller capacity, more of these vessels would be required which increases the risks to marine traffic.  The TSHD is a self-contained barge with a container to store the dredged mud sucked up by the trailer via pipelines.  Therefore only one vessel will be required at the dredging location which reduces the marine traffic risk.

Northwest Lantau

The pipeline alignment in Northwest Lantau passes along the corridor between the Sha Chau Lung Kwu Chau Marine Park and the western boundary of Hong Kong waters.  The water depths in the areas are too shallow to utilise a TSHD and hence the options for burying the pipeline were to jet following pipelay or to use grab dredgers to pre-trench.  The impact on water quality was examined for both of the options as shown in Figure 2.6.

The results show the spread of suspended sediment generated by the jetting machine extends further and is more concentrated than the grab dredgers.  It is noted from the plots that in both the wet and dry seasons the SS elevations exceed 10 mg L-1 inside the boundary of the Marine Park whereas for the grab dredgers the SS elevations meet the allowable WQO exceedance just inside the boundary of the Marine Park.  The areal exceedance of the water quality objective is also much larger for the jetting machine than the grab dredgers.  Although the impacts from the jetting machine can be mitigated to an extent, through the adoption of movable standing silt curtains, the WQO would still be marginally exceeded inside the park.  It is noted that the practicalities of installing a movable silt curtain in the narrow corridor between the pipeline works area and the boundary of the Marine Park where current velocities are high would require investigation.

The jetting machine does not generate any mud to be disposed offsite unlike the grab dredging.  Should grab dredgers be adopted for the section of the alignment along the Marine Park boundary it would be uneconomical and not practical to utilise a jetting machine for the remaining areas close to Black Point and South Soko (ie less than 8 km).  Consequently, the adoption of grab dredging would signify that the dredged mud volumes would increase by 0.62 Mm3.  Of this mud approximately 50% would require Type 2 disposal (ie at East of Sha Chau) and 37% would require unconfined open sea disposal. 

Figure 2.6       Contour plots of maximum suspended solids elevations generated in West Lantau using Jetting (21 m hr-1 working 12 hours per day) or Grab Dredging (4,000 m3 hr-1 per dredger with 4 dredgers working 12 hours per day) ([7])

Taking the above into consideration it was considered that the preferred approach for Northwest Lantau would be to adopt grab dredging and for West Lantau dredging using TSHD.

Remaining sections of the pipeline route

For the remaining sections of the submarine gas pipeline route, ie the sections that approach the landing points at Black Point and South Soko the decision was taken that grab dredgers would be used.  The rationale behind the selection of equipment along these sections is that the spread of suspended sediment can be controlled through adjusting dredging rates and employing silt curtains if considered necessary.  Also these two sections of the gas pipeline route are relatively shallow and hence suitable for grab dredgers to work in.

Construction Sequencing

The water quality modelling results for the TSHD and grab dredging has indicated that the works can proceed in either dry or wet season without there being appreciably different levels of impact.  From a marine ecological perspective it is noted that the density of sightings of marine mammals in the Northwest and West Lantau do not appreciably differ between seasons in the year (see Annex 9 – Figure 9.4).  However, it has been noted that research on the Indo-Pacific Humpback Dolphin has indicated, based on stranding information, that in these two areas although calving occurs throughout the year the peak period would appear to be between March and August with the highest frequency in May and June ([8]). 

The EIAO-TM specifies the priorities for addressing ecological impacts is avoidance and minimization.  This philosophy was referred to in designing the marine works construction programme.  There was a consensus among the leading local marine mammal specialists (Würsig, Jefferson, Hung pers comm.) that reducing the overall duration of marine works is the most effective approach to reduce impacts on marine mammals. 

The marine mammal assessment (Section 9.7) has indicated that there is little risk of the gas pipeline installation works causing either physical harm or water quality related impacts to dolphin mothers and their calves and hence no apparent technical basis to avoid the March through August peak calving period.  However, the submarine gas pipeline programme was reviewed and it became apparent that the dredging works for the submarine gas pipeline could be scheduled to take place during the period September through February in West and Northwest Lantau.  Consequently, the preferred programme for the Project has adopted this scheduling measure.

The other issue concerning the sequencing of works is whether they would be scheduled to take place over 24 hours or just during daylight hours.  Grab dredging works in Hong Kong typically take place during daylight hours and the same approach will be adopted for this project in West and Northwest Lantau.  TSHDs usually would operate round the clock as they are not available in Hong Kong and have to be brought in from overseas so they therefore try to maximise production rates over each day.  For this project the schedule for dredging works in West and Northwest Lantau can accommodate daylight hour dredging and hence this measure will be adopted.  Because of marine traffic constraints, grab dredgers may need to operate 24 hours on the pipeline section which crosses the Urmston Road channel off Black Point enabling completion in the shortest possible time. 

It is important to note that adoption of the above two measures in Northwest and West Lantau (ie 12 hour dredging during daylight hours and dredging only during September though February) is for dredging only.  In order to achieve the master construction programme for the South Soko option all other activities associated with the pipeline installation, ie pipelaying and the placement of armour rock protection will operate over 24 hour periods and throughout the year.  Neither of these works activities cause adverse impacts to the marine environment as discussed in Section 3.3.4.

2.3                                      Consideration of Pipeline Alignment

This Section of the EIA for the proposed LNG terminal at South Soko Island describes the criteria that have been used for establishing the routing of the gas pipeline connection to Black Point.  As specified in the EIA Study Brief (No. ESB-126/2005, Clause 3.3.6), the EIA shall explore different pipeline options including underground pipeline option.  Construction options for the submarine pipeline have been discussed in Section 2.2 above.  The Study Area for the routing exercise covers western Hong Kong, including Lantau Island.

2.3.1                                Connection to the Existing Yacheng Pipeline

Connecting to the existing Yacheng Pipeline is one of the alternatives that has been examined for the LNG supply from South Soko to Black Point.  The gas pipeline route would depart South Soko Island via the Sai Wan launching point and head generally west, crossing the HKSAR boundary to the north of Guishan Dao and passing to the north of Niutao Dao and Qing Zhou.  The route would continue in a WNW direction, intersecting the Yacheng Pipeline in an area north of the Qing Zhou Traffic Separation Scheme.  The total length of the submarine connection would be approximately 22 km and is displayed in Figure 2.7 below.

Figure 2.7      Connection to the Existing Yacheng Pipeline

This route was considered as a technically possible option; however, several associated issues make it impractical in terms of the overall project objectives which are detailed below ([9]) . 

Technical Approach

It would be possible to install a connection to the existing 28” Yacheng pipeline that supplies natural gas to BPPS, using currently available technology.

A simple hot-tap would be insufficient because it would be necessary to install a check valve preventing gas from flowing back towards the Yacheng production facilities.  Accordingly, the line would need to be cut and a piping assembly that incorporates a check valve (or non-return valve) would have to be installed.  To achieve this, the following activities would need to be undertaken:

·      The pipeline does not belong to CAPCO and therefore a commercial agreement would have to be reached with the pipeline owner (CNOOC/BP/Kufpec) enabling the modifications to the pipeline and its ongoing use by CAPCO to transport regasified LNG.

·      Implementing the modifications would entail significant engineering and advance planning culminating in the following actions:

-       Design, procure and construct an insert assembly comprising a tee piece with associated isolation and check valves.  These items will be special designs suited to subsea service.

-       Plan an outage of BPPS enabling the shut down of the Yacheng pipeline and evacuation of gas enabling safe working whilst installing the insert assembly.

-       Detailed planning of the construction work using above-water methods.  It is considered that whilst underwater methods are available for pipeline intervention work, the water depth and visibility conditions in the PRD would make such methods impractical.

-       Locate and expose the Yacheng pipeline at the chosen site (a recent survey confirmed that the pipeline is buried along the entire Pearl River Delta section) using suction dredging methods.  A long length of the pipeline would need to be exposed to provide sufficient “slack” enabling lifting the line to the surface to facilitate performance of the work above water.  Comprehensive marine traffic control measures would have to be adopted for the duration of the work for safety of the worksite and passing vessels.

-       The pipeline would be cut in two places and the prefabricated, pre-tested assembly welded in.  The tie-in welds would be subject to rigorous non-destructive testing ensuring they are free from defects.  At this stage a “stub” would be provided for later connection of the LNG line.

-       The assembly would then be coated with anti-corrosion material, compatible with the existing pipeline protection system and lowered to the seabed.

-       The pipeline, complete with the new assembly, would be jetted into the seabed, achieving the same depth of cover as previously.

-       The LNG pipeline would be laid and tied-in to the subsea assembly and commissioned.

-       Gas supply could be resumed.

·      Consideration could be given to performing the intervention work subsea; however, the conditions are estimated to be even more difficult using that approach, including a complete lack of visibility, as shown by recent survey work in the area.

Important Considerations and Constraints

Whilst the above concept is technically possible, there are a number of constraints that would have a significant impact on CAPCO’s ability to supply power from BPPS:

1)   BPPS Fuel Shutdown

  It is estimated that the work would involve a shutdown of the gas supply to BPPS of approximately two months.  During that time BPPS would not be able to sustain operations even on liquid fuel, because the liquid fuel supply system was not designed to cater for an extended outage.  The current practical limit of operation on liquid fuel is estimated to be in the order of 6 – 7 days and a significant cost impact would occur as a result of the higher cost of liquid fuel.  Arrangements could be made to increase the capability of BPPS to burn liquid fuel over an extended period.  Issues that would require resolution include:

·      Increasing the liquid fuel import capacity to enable replenishment of the tanks at BPPS meeting the fuel demand of the generation units burning liquid fuel on a continuous basis.  The existing fuel unloading berth at BPPS would need to be dredged and enlarged to cater for larger fuel barges/tankers and the existing fuel unloading system would have to be modified to increase the delivery and offloading capacity.

·      Increasing the demineralised water treatment capacity enabling the use of liquid fuel on a continuous basis while meeting emissions standards.  The use of LSIDO in the BPPS generator units requires a 1:1 ratio of demineralised water to fuel to keep NOX emissions at an acceptable level.  Arrangements would have to be made with WSD to increase the water supply to BPPS and the existing demineralization facilities would need to be expanded.

Both of these actions would require considerable lead time and require a significant capital investment to implement.

2)   Yacheng Supply Shutdown

  Shutting down the Yacheng supply would have a significant impact on the production facilities owned and operated by CNOOC/BP/Kufpec, and a new commercial arrangement would be necessary covering the situation. 

3)   Wastage of Gas

  Depressurizing and evacuating the Yacheng pipeline would result in a significant wastage of gas by venting to atmosphere or flaring.  The quantity would be equivalent to several days’ supply to BPPS and it would be necessary because whilst much of the inventory in the pipeline could be used to fuel the power station in the initial phase of depressurization, ultimately the line pressure would fall below the practical minimum required to supply the power station (2,800 kPa or 400 psi) and therefore the remaining gas would need to be vented to a low pressure vent/flare.

4)   Gas Characteristics

  BPPS gas turbines have been engineered specifically to burn Y13 gas (Modified Wobbe index = 43+/-5%) with a narrow range of variation of gas composition.  The existing combustors cannot burn regasified LNG (Wobbe index = 51 +/- 5%) directly or any mixture of Y13/LNG without modification because combustion characteristics of LNG differ from those of Y13 gas significantly.  The simple mixing of the two gases will result in unstable combustion performance and frequent tripping of generator units therefore replacement combustors will be required.  A phased transition is planned to convert generating units one or two at a time from Y13 gas fuel to LNG fuel as the Y13 gas supply is depleted.  Use of the Yacheng pipeline to deliver LNG gas to BPPS would necessitate conversion of all units at once and prevent the further use of Yacheng gas.  Again, there is no provision for this in the existing gas supply contract and a variation would need to be negotiated with the suppliers.

5)   Generator Unit Conversion

  The replacement of combustors of all Black Point units will require advance planning and require a shutdown of several months.  This could be performed in parallel with the required modification to the Yacheng pipeline; however, CAPCO would be required to burn an increased amount of coal at CPPS to satisfy power demand over that period.  An alternative approach would be to convert units one at a time whilst keeping BPPS operational on liquid fuel, however, this would carry a significant cost penalty as a result of the higher cost of liquid fuel.  There are also limitations as to how much liquid fuel can be burned over a period of time due to supply constraints as discussed above.

6)   High Risk Operation

   The work required to modify the Yacheng pipeline constitutes a major intervention that carries a very high risk of unforeseen events occurring.  The exercise would be very complex and there are many factors that could give rise to in an extended shutdown greatly in excess of that planned for the work.  This would leave BPPS without a viable fuel supply for a long period of time and carry commercial, environmental and social impacts including:

·      the requirement to burn more coal at CPPS satisfying the demand for power,

·      contractual impacts related to postponing the supply of LNG pending the ability to transport gas to BPPS,

·      liability for any damage to the Yacheng pipeline,

·      standing down the operations workforce at BPPS for an extended period.

7)   Multiple Jurisdictions

  It is anticipated that constructing the BPPS supply pipeline across the HKSAR border would necessitate a complex approvals process that could impose significant schedule risk on the project.

Accordingly this option was excluded from the detailed assessment.

2.3.2                                Routes within Hong Kong

Although the routing corridors have been broadly defined (see Figure 2.8), the environmental and physical constraints within, and in proximity to, the corridors have been reviewed to further define the pipeline routes.

2.3.3                                Route Selection Criteria

As part of the route selection exercise, environmental, physical and risk constraints within the three corridors were reviewed to determine the most appropriate pipeline corridor and landing areas where environmental impacts can be managed and mitigated. 

Environmental Issues

Areas of known environmental importance that have been identified during the route selection process.  Although not possible to avoid all environmentally important areas the design process has sought to reduce impacts to the extent practicable.  The environmentally important areas and issues for the pipeline routing are illustrated in Figures 2.9& 2.10 and discussed in Table 2.19.

Table 2.19      Environmental Issues

Issues

Notes

Land Based

 

·       Sites of Special Scientific Interest (SSSIs)

There are several SSSIs located within the Study Area which have been designated for a variety of reasons.  Some of the SSSIs support important vegetation population, eg No 32 Ma Cheung Po and No 61 San Chau on Lantau island, whereas others have been designated for the wildlife, eg No 38 Lung Kwu Chau, Tree island, Sha Chau for bird and No 62 Ngong Ping for Romers’ Tree Frog.

 

·       Designated Country Parks

There are two Country Parks at North and South Lantau and one proposed Country Park Extension at North Lantau in the Study Area, both of them abut the coastline.  Country Parks are gazetted for conservation, recreation and educational purposes and are under the control of the Country and Marine Parks Authority (CMPA). 

 

·       Coastal Protection Areas/ Conservation Areas/Green Belt

The Planning Department has designated several areas as Coastal Protection Areas (CPA) and Conservation Areas (CA) on the Outline Zoning Plans for specific locations within the Study Area. 

 

·       Land sites of cultural heritage (declared monuments and archaeological sites)

There are declared monuments located throughout the Study Area.  Consultation should be initiated if necessary with the Antiquities & Monuments Office of the Leisure & Cultural Services Department.

 



Marine Based

 

·       Marine Parks

There is one designated Marine Park at Sha Chau and Lung Kwu Chau and two proposed Marine Park at Fan Lau and Soko in the Study Area.  Marine Parks are gazetted for conservation, recreation and educational purposes and are under the control of the Country and Marine Parks Authority (CMPA). 

 

·       Potential Marine Parks

There are two potential marine parks in the Study Area at Fan Lau and around the Soko Islands.  Neither of these parks has statutory status.

·       Fish Culture Zones

There is one small Fish Culture Zone within the Study Area, which is located at Cheung Sha Wan.  Impacts to FCZs are controlled by the Water Pollution Control Ordinance and the Marine Fish Culture Ordinance.  Developments within 500m of an FCZ are subject to claims for ex gratia allowances.  FCZs can be regarded as water quality sensitive receivers.

 

·       Seawater intake points

Seawater intake points are located at Tuen Mun (WSD Intake), Airport, the Black Point Power Station and the Castle Peak Power Station.  Intakes have their own water quality standards that have to be met during construction.

 

·       Gazetted bathing beaches

There are several gazetted bathing beaches in South Lantau and near Tuen Mun. 

 

·       Sites of Special Scientific Interest (SSSIs)

There are two marine SSSIs located within the Study Area which have been designated for ecological reasons.  The SSSI at San Tau Beach (No 58) was established because of the seagrass bed, whereas Tai Ho stream (No 63) was established because of the natural stream, seagrass and mangrove stands at the southern end of Tai Ho Wan. 

 

·       Gazetted artificial reef deployment sites

Artificial reefs (ARs) have been deployed in the Sha Chau and Lung Kwu Chau Marine Parks and Airport.  ARs are deployed to enhance fisheries and marine ecological resources and are under the jurisdiction of AFCD. 

 

·       Spawning ground of commercial fisheries resources

Spawning ground of commercial fisheries resources is located in the North Lantau Waters. 

 

·       Nursery area of commercial fisheries resources

Nursery area of commercial fisheries resources is located in the Southern Hong Kong Waters covering a large area.

 

·       Seagrass

Seagrasses are located mainly in San Tau, Tai Ho Bay, Yam O and Deep Bay. 

 

·       Mangrove

Mangrove stands are located mainly in sheltered bays, i.e., Tung Chung, Tai Ho Bay, Tai O, Yam O and Deep Bay. 

 

·       Intertidal mudflat

Intertidal mudflats are located mainly in sheltered bays, i.e., Tung Chung, Tai Ho Bay, Tai O, Yam O and Deep Bay. 

 

·       Horseshoe crab breeding habitat

Horseshoe crabs are known to breed within the Study Area. 

 

·       Marine mammal habitats

There are two resident species of cetacean in Hong Kong’s waters, the Finless Porpoise and the Indo-Pacific Humpback Dolphin.  The Finless Porpoise only occurs in the southern and eastern waters of Hong Kong.  The Indo-Pacific Humpback Dolphin can be observed mainly in the western waters of Hong Kong.  The sighting density of both dolphin and porpoise with corrected survey effort per km2 is presented in Figure 2.10.  The highest marine mammal sightings are recorded in West Lantau.  

 

2.3.4                                Physical Constraints

The physical constraints that were considered during the route selection included those shown in Figure 2.11 and discussed in Table 2.20.

Table 2.20      Physical Constraints

Constraints

Notes

Land

 

·          Areas of steep topography/ hillslopes

Avoidance of such geographical features is recommended in order to limit the amount of slope cutting required and to limit the risks of boulder falls or landslides damaging the pipelines. 

 

·          Areas requiring multiple bends/ curves

From engineering perspective, planning a pipeline with a minimum number of bends is preferable as it reduces the construction difficulties. 

 

·          Areas close to present or planned utilities that may require maintenance.

Utilities are present on land which may have to be avoided during the route planning.  These include water pipes, electricity cables and gas pipelines.

 

·          Reservoir

The Shek Pik Reservoir is considered to be a constraint to the pipeline and Water Supplies Department (WSD) are the lead authority for the reservoir.

 

·          Shek Pik Prison

The Shek Pik Prison is considered to be a constraint to the pipeline.

 

·          Shek Pik Fault, Sha Lo Wan Fault and Sham Wat Fault

Seven geological faults cross the proposed tunnel alignment.  Major faults include Shek Pik Fault, Sha Lo Wan Fault and Sham Wat Fault.  The nature of each fault is uncertain and requires geological site investigation.

 

·          Habitation

Populated areas may have to be avoided to the extent practical during the route planning.

 

Marine

 

·          Designated areas of marine dredging and mud disposal

Although there are no active dredging areas within the Study Area there are several mud disposal sites located in North Lantau, including the new contaminated mud pits at the east and north of the Hong Kong International Airport, which should be avoided to limit disturbance to the disposed dredged muds.  West Soko marine sand borrow area is located to the west of the North Soko Island.  South Cheung Chau Disposal area is located to the east of the South Soko Island.

 

·          Restricted areas

There are three types of restricted areas in Hong Kong waters, based on restrictions in vessel air-draught.  These areas should be avoided.

 

·          Existing and proposed anchorage

An Immigration Anchorage (IA) is located close to Tuen Mun.  The IA should be avoided due to the potential for damage to the pipelines.  If the IA cannot be avoided then pipeline protection measures will be required.

 

·          Heavily trafficked marine vessel fairways

The South Lantau Channel is a busy fairway mainly used by smaller cargo vessels to and from the southwest and the high speed ferries to and from Macau.  If the fairway cannot be avoided, then pipeline protection measures will be required.

 

·          Zhujiang Estuary Vessel Routing System (Trial)

The Zhujiang Estuary Vessel Routing System (Trial) is located in the southwest of Hong Kong Waters and may have to be avoided during the route planning. 

 

·          Potential bridge/ highway development

The potential Northshore Lantau Highway Corridor and Hong Kong-Zhuhai-Macau Bridge may have to be avoided during the route planning.  Where crossings are necessary, these are preferably conducted at right angles to limit the chances of disturbance to the potential bridge/ highway development.

 

·          Areas of current, future or proposed reclamation

There are several areas that are proposed to be reclaimed at North Lantau, including proposed Logistics Park and Container Terminal 10.  This area should be avoided where possible.  If these possible development areas cannot be avoided then robust pipeline protection measures will be required.

 

·          Typhoon shelters

The Tuen Mun Typhoon Shelters should be avoided because these are anchorage areas.

 

 

·          Utilities (cables, pipelines and outfalls)

Utilities may have to be avoided during the route planning.  These include water pipes, electricity cables and gas pipelines.  Where crossings are necessary, these are preferably conducted at right angles to limit the chances of disturbance to the existing utility.

In addition, general risk constraints were also identified along the route corridors to reduce the potential risk to the public during the operation of the pipeline.  The potential risk constraints that were considered during the route corridor selection process include the following:

·                the general avoidance of populated areas;

·                the avoidance, where practical, of areas that were considered to have a high degree of risk associated with their activities (e.g. anchorage areas, major fairways); and

·                the selection of the most direct route between the two sites, to reduce the length of pipeline required.

A summary map illustrating all of the environmental issues and physical constraints is presented in Figure 2.12.  The map also illustrates the four options highlighted for examination following the review of potential constraints.

2.3.5                                Routes Selected for Review

Base Case Marine Route (Entirely Offshore Route Passing West of Lantau)

The Base Case route departs South Soko Island and heads generally west, turning north to stay within the HKSAR boundary.  The route follows the boundary (nominally 100 - 200 m to the east) passing to the west of the proposed Marine Park at the western extremity of Lantau Island, at Fan Lau, the potential port development area, across the planned route of the Hong Kong – Zhuhai – Macau Bridge and between the HKSAR waters boundary and the western boundary of the Sha Chau and Lung Kwu Chau Marine Park.  The route then curves to the east, maintaining a nominal 100 m clearance south, of the existing Yacheng pipeline and lands at Black Point Power Station in the vicinity of the existing gas receiving station.  The total length of the route is approximately 38 km.

Option 1 (Route Crossing Lantau Island Overland to the West)

The Option 1 (A and B) pipeline route begins at the PIG launching facility at the LNG terminal on South Soko Island with an offshore section from the western side of South Soko Island to a landfall on west Lantau Island in the vicinity of Tai Long Wan.  From Tai Long Wan the route generally parallels the existing steep narrow Keung Shan mountain road until a fork. Option 1A turns to the west and on to the Tai O Road and Option 1B proceeds from the fork directly north to Sham Wat Wan.  Then before reaching the coast, the pipeline route proceeds east outside the Country Park boundary until it reaches Sham Wat Wan (Option 1B joins here) where it crosses the shore northward and skirts the western side of the Sha Chau and Lung Kwu Chau Marine Park generally following (within) the HKSAR boundary.  The route approaches the existing Yacheng pipeline, turning east to land at a shore crossing within the existing gas receiving station at Black Point.  The length of the marine based segment for Option 1 is approximately 29 km and the land based segment for Options 1A and 1B are approximately 10 km and 7 km respectively.

Option 2 (Route Crossing Lantau Island Through a Tunnel)

The South Soko Island onshore portion and the marine portions of Option 2 route are the same as for Option 1.  However, the Lantau onshore portion of the route is replaced by a straight tunnelled crossing between the two landfalls at Tai Long Wan and Tit Tak Shue (Sham Wat Wan) with potentially an intermediate access at Keung Shan.  As for Option 1, the length of the marine based segment for Option 2 is approximately 29 km and the land based segment (mainly tunnel with diameter of approximately 3.5 m) for Option 2 is approximately 6 km.

Option 3 (Route Crossing Lantau Island Overland to the East)

The proposed Option 3 pipeline route with an overland crossing of Lantau Island features an offshore section departing South Soko Island on the eastern side and passing east of North Soko to a landing point in the vicinity of upper Cheung Sha Beach.  The route then generally follows Tung Chung Road north through the South Lantau and North Lantau Country Parks and across the Lantau Expressway (North Lantau Highway) to a shore (near Tai Ho) crossing point east of Tung Chung new town and Hong Kong International Airport (HKIA).  The final offshore portion would be required to avoid the airport exclusion zone and follow the Urmston Road, crossing a sewerage line and past Castle Peak Power Station to Black Point Power Station.  It is possible that this route would have to cross pipelines/cables servicing HKIA and seven cables at South Lantau waters.  The total length of the route is approximately 41 km comprising about 29 km marine based segment and about 12 km land based segment.

The options as identified above are further reviewed in terms of their potential for environmental and risk impacts in Sections 2.3.4 and 2.3.5. 

2.3.6                                Environmental Review of Route Options

This section provides a preliminary review of the environmental impacts associated with each option.  A description of the potential impacts associated with each option has been provided in the following sections and classified in accordance with the above categories.

Land Use Constraints

Base Case (Entirely Offshore Route Passing West of Lantau)

There is no land use constraint as the route is entirely offshore passing to the west of Lantau.  The project would be subject to the EIAO, and an EP would be required prior to construction.  Furthermore, the project would be subject to the Foreshore and Seabed (Reclamations) Ordinance (Cap 127) (FSRO) and would require approval from the Director of Lands for the gazettal of the affected area of the seabed in which the pipeline is to be installed.

Option 1 - Route Crossing Lantau Island Overland to the West

The Option 1 (A and B) pipeline route begins at the PIG launching facility at the LNG terminal on South Soko Island with an offshore section from the western side of South Soko Island to a landfall on west Lantau Island in the vicinity of Tai Long Wan.  From Tai Long Wan the route generally parallels the existing steep narrow Keung Shan mountain road until a fork.  Option 1A turns to the west and on to the Tai O Road and Option 1B proceeds from the fork directly north to Sham Wat Wan.  Then before reaching the coast, the pipeline route proceeds east outside the Country Park boundary until it reaches Sham Wat Wan (Option 1B joins here) where it crosses the shore northward and skirts the western side of the Sha Chau and Lung Kwu Chau Marine Park generally following (within) the HKSAR boundary.  The route approaches the existing Yacheng pipeline, turning east to land at a shore crossing within the existing gas receiving station at Black Point. 

The segment of the pipeline that traverses from Tai Long Wan Tsuen to Sham Wat, Option 1A would pass through areas designated by the Town Planning Board (TPB) as “Green Belt” (GB) and “Site of Special Scientific Interest” (SSSI) and the Country and Marine Park Board as “Country Park” (CP), while Option 1B would pass through areas designated by the Town Planning Board (TPB) as “Green Belt” (GB) and the Country and Marine Park Board as “Country Park” (CP), shown in Figures 2.13 & 2.14.  The land use planning designations have been assigned to these areas for multiple purposes, amongst which include retaining their existing natural character and to provide a high degree of protection based on their conservation value.

The project would be subject to the EIAO, and an EP would be required prior to construction.  Further, the project would be subject to the Foreshore and Seabed (Reclamations) Ordinance (Cap 127) (FSRO) and would require approval from the Director of Lands for the gazettal of the affected area of the seabed in which the pipelines are to be installed.  Prior to development within these areas, permission for the routing of the pipelines would need to be obtained in advance from the Country and Marine Parks Authority (CMPA), under the Country Parks Ordinance, and from the TPB under the Town Planning Ordinance.  In addition, approvals from relevant government departments (i.e., Highway Department and Lands Department) should also be obtained for the road sections.

Option 2 - Route Crossing Lantau Island Through a Tunnel

Option 2 has similar routing as Option 1 except that the segment between Shek Pik and Tit Tak Shue (Sham Wat Wan) uses a tunnel.

The option would be subject to the EIAO, and an EP would be required prior to construction.  Furthermore, the project would be subject to the Foreshore and Seabed (Reclamations) Ordinance (Cap 127) (FSRO) and would require approval from the Director of Lands for the gazettal of the affected area of the seabed in which the pipelines are to be installed and reclamation required for access for portal construction and spoil handling during tunnel excavation. 

For the land based portion of the project, similar approvals would be required those specified above for Option 1.  In order to investigate the geological conditions and rockhead levels along the proposed tunnel alignment (the proximity and quantities of the existing geotechnical information available are considered insufficient), site-specific ground investigation will be required.  Prior to the ground investigations within Country Park, permission would need to be obtained in advance from the Country and Marine Parks Authority (CMPA), under the Country Parks Ordinance.

In addition to the land right required for a potential intermediate access, the subsurface rights may also need to be obtained from the owners of each of the lots that are affected by the tunnel.  Given the density of lots within the Keung Shan area stakeholder issues would need to be resolved before land applications could be processed.  In addition, approvals from relevant government departments (i.e., Highways Department and Lands Department) should also be obtained for the intermediate shaft as well as approvals for access and associated road strengthening or extension.

Planning approvals will be required at both of the landing points.  The landfall at Tai Long Wan will require a Section 16 application as the land is zoned as Green Belt.  The northern landing point is not within an area controlled by a town plan but is potentially within an SSSI, depending on the final alignment, and this would require clearance from Planning Department.

Option 3 - Route Crossing Lantau Island Overland to the East

Similar approvals would be required for Option 3 as described for the land based segment of Option 1. 

The segment of the pipeline that traverses from Cheung Sha to Tai Ho would pass through areas designated by the Town Planning Board (TPB) as “Green Belt” (GB) and “Coastal Protection Area” (CA) and the Country and Marine Park Board as “Country Park” (CP), as shown on Figure 2.13 & 2.14.  The land use planning designations have been assigned to these areas for multiple purposes, amongst which include retaining their existing natural character and for providing a high degree of protection based on their conservation value.

Option 3 would cross a number of submarine utilities (more than 10 cables and a pipeline), consents from each utility owner would be required before Lands Department can gazette the submarine route.

Water Quality Impacts

Base Case (Entirely Offshore Route Passing West of Lantau)

The proposed route for the submarine pipelines would pass through the Southern Water Control Zone (WCZ), the Second Southern Supplementary WCZ, the North Western WCZ, the North Western Supplementary WCZ and Deep Bay WCZ.  In accordance with the Water Pollution Control Ordinance (WPCO), the project would be required to comply with the Water Quality Objectives for this area and all discharges during the project implementation and operation phases would be required to comply with the Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM) issued under Section 21 of the WPCO, which defines acceptable discharge limits for different receiving waters.

The Southern Hong Kong Waters are influenced by the semi diurnal tidal regime of the South China Sea and dominated by the freshwater flows of the Pearl River Delta, particularly during the wet season.  The riverine influence is generally stronger in the western and northern parts of the southern waters.

In the North Western part of Hong Kong marine waters at the mouth of the Pearl River Estuary are heavily influenced by the freshwater flows from the hinterland.  The estuarine influence is especially pronounced in the wet summer months when the freshwater flows are greatest and strong salinity and temperature stratification is prominent.  During winter months water conditions are more typically marine (with lower nutrient levels and higher DO levels) and salinity and other parameters vary less with depth.  Ebb tide currents are towards the southeast where the flood tide currents move to the northwest.  Current velocities in areas near to Sha Chau can reach up to 2.0 ms-1.

In Deep Bay, the hydrodynamic regime of the Deep Bay area is unidirectional and the current direction reverses during ebb and flood tides.  Tidal flow is dynamic and complex in the Deep Bay areas due to the seasonal influx of freshwater from the Pearl River to the Urmston Road.  The water quality of Deep Bay is poor in general, characterised by high organic and inorganic pollutants and low dissolved oxygen levels. 

For those areas in which the pipeline is to be laid into a pre-dredged trench, during the dredging process, some quantity of the sediment removed from the sea bed would be lost to suspension and would be dispersed through tidal currents.  For the section of the pipeline that would be installed by jetting, a fluidised mixture of water and sediment would be formed close to the sea bed and dispersed by tidal currents.  Although, the suspended sediments are expected to settle rapidly, there is the potential for impacts to occur to nearby sensitive ecological receivers as a result of elevated suspended solids.

The water quality sensitive receivers identified along the proposed pipeline route include: water intake at Black Point Power Station, Artificial Reefs at Sha Chau and Lung Kwu Chau Marine Park, fisheries spawning and nursery areas and other areas of ecological interest (including the Sha Chau and Lung Kwu Chau Marine Park, proposed Fan Lau Marine Park, proposed Soko Islands Marine Park, Finless Porpoise and Indo-Pacific Humpback Dolphin habitats, intertidal mudflat, seagrass, mangrove and horseshoe crab breeding habitat).  The pipeline corridor has been defined to avoid these areas, where practical.

As such, it is expected that the potential impacts to water quality could be controlled through measures such as defining equipment requirements (requiring the use of watertight grabs, bottom sealed barges, etc) and through programme modification (controlling the dredging and jetting rates).  The need for such measures would be determined by detailed computer modelling of water quality.  It is believed that with the implementation of the necessary mitigation measures, impacts to water quality can be controlled to within acceptable levels.  Successful examples of gas pipeline installation in Hong Kong include the recently installed gas pipelines for Hongkong Electric and Towngas, both of these pipelines have been installed in areas of high ecological value.

Option 1 - Route Crossing Lantau Island Overland to the West

For the marine based aspects of Option 1, the proposed route for the submarine pipelines, similar to the Base Case, would pass through the designated Southern, North Western and Deep Bay WCZs and compliance with the same regulations would be required. 

The water quality sensitive receivers identified along the proposed pipeline route include: water intake at Black Point Power Station, Artificial Reefs at Sha Chau and Lung Kwu Chau Marine Park, fisheries spawning and nursery areas and other areas of ecological value (including the Sha Chau and Lung Kwu Chau Marine Park, Finless Porpoise and Indo-Pacific Humpback Dolphin habitats, intertidal mudflat, seagrass, mangrove and horseshoe crab breeding habitat).  The pipeline corridor has been defined to avoid these areas to the extent practical.

Similar to the Base Case, it is expected that the potential impacts to water quality could be controlled through measures and through programme modification.  However, the major difference from the Base Case is that there would be two additional landing/ launching points.  Additional measures may be required to control the water quality impacts due to the construction works at the landing/ launching points at Lantau.  The need for such measures would be determined by detailed computer modelling of water quality.

For the land based segment of Option 1, it is expected that extensive slope cutting and stabilisation will be required along the roads (Keung Shan Road and Tai O Road for Option 1A, and Keung Shan Road and Sham Wat Road for Option 1B), in particular the segment at the northern end (between Hang Mei and Sai Tso Wan for Option 1A, and along Sham Wat Wan for Option 1B) due to the narrow, torturous and steep gradient nature of the roads.  Before the pipeline installation, the existing roads may require considerable upgrading to enable pipeline transport and stringing.

Water quality impacts may occur during construction works as a result of runoff and drainage containing increased loads of suspended solids and other contaminants (such as oil and chemical waste from heavy machinery and cement derived materials used for road pavement).  The runoff may result in physical effects including the blockage of drainage channels, increased suspended solids concentrations in receiving waters and accretion of suspended solids with high pH from cement derived materials in the catchwaters and Shek Pik Reservoir.  Potential biological effects may also occur from these activities which may affect aquatic life within the receiving water courses, in particular Sham Wat Stream and Tai O Stream.

It is expected that with good site management, runoff may be controlled from entering the surrounding waters.  The types of measures that may be required to reduce the impacts include: containment of stockpiled materials, proper collection of spent cement mix or other paving materials, undertaking extensive slope cutting work outside the wet season as well as other measures to prevent runoff from occurring.  Because of the marine and aquatic potential water quality issues, Options 1A and 1B may require extensive mitigation measures (i.e., taking extensive land within the Country Parks for site runoff treatment and slope stabilisation to prevent erosion or slope slippage) to reduce impacts to an acceptable level and may result in residual impacts, even with the implementation of mitigation measures.

Option 2 - Route Crossing Lantau Island Through a Tunnel

The marine based segment of Option 2 shares largely the same routing as Option 1, and therefore the water quality issues would be the same for both of the Options 1 and 2. 

During the construction stage, temporary reclaimed platforms would need to be formed along the shoreline of each of the portal locations (ie at Sham Wat Wan and Tai Long Wan to provide sufficient working area for machine launching, spoil handling, stockpiling, barging, loading of tunnel segments, allocation of the blast doors and noise barriers (for drill and blast method only) and settlement treatment/treatment tanks for water discharge (Figures 2.15 & 2.16([10]) .  The required reclamation areas at each of the selected portal locations (either end of the tunnel) are expected to be approximately 15,000 m2 each (100 m wide x 150 m long).  The reclamations would be formed within shallow water typically less than 2 m depth, which will not permit the access of marine barges.  Vertical seawalls would therefore be required along the farthest edge of the reclamation in conjunction with associated dredging works to form a channel with at least 3 m draft.  Additional measures will expect to be required to control the water quality impacts due to the dredging and reclamation works at the landing/ launching points at Lantau.  The need for such measures would be determined by detailed computer modelling of water quality.  Upon completion of the works the platforms would then be decommissioned and removed from the sites.  Impacts of the decommissioning activities would need to be examined.

It is expected that the land-based segment of Option 2 (through a tunnel), which avoids most of the sensitive receivers (including most of the catchwaters, Shek Pik Reservoir and Sham Wat Stream), has relatively lower water quality impacts compared with the land based segment of Option 1.  However, in the event that the construction of the intermediate portal and access is required this may have potential impacts on the catchwaters and Tai O Stream, as well as the rural areas in Keung Shan (Figure 2.17).  In addition, the ground investigations during detailed design stage may cause water quality and ecological impacts on the sensitive receivers (including catchwaters, Shek Pik Reservoir, Sham Wat Stream and Tai O Stream).  At least 32 vertical land drillholes (with 13 located within Country Park), 15 inclined land drillholes (with 7 located within Country Park), 7 horizontal drillholes (with 2 located within Country Park) and 4 vertical marine drillholes will be required for the ground investigations.  It is expected that similar measures as those described for Option 1 could be adopted to control land-based water quality impacts to an acceptable level. 

Option 3 - Route Crossing Lantau Island Overland to the East

For the marine based aspects of Option 3, the proposed route for the submarine pipelines, similar to Option 1, would pass through the designated Southern, North Western and Deep Bay WCZs.  The water quality sensitive receivers identified along the proposed pipeline route include: water intakes (at Airport and along the southwest coastline of New Territories), Artificial Reefs at Sha Chau and Lung Kwu Chau Marine Park and Airport, fisheries spawning and nursery areas, gazetted bathing beaches in South Lantau and Tuen Mun and other areas of ecological value (including the Sha Chau and Lung Kwu Chau Marine Park, Finless Porpoise and Indo-Pacific Humpback Dolphin habitats, intertidal mudflat, seagrass, mangrove and horseshoe crab breeding habitat). 

Similar to Option 1, it is expected that the potential impacts to water quality could be controlled through measures and through programme modification.  The need for such measures would be determined by detailed computer modelling of water quality. 

For the land based segment of Option 3, water quality impacts addressed in Option 1 could be limited due to the potential reduction of slope cutting and stabilisation after the improvement of Tung Chung Road (currently the subject of improvement works) if the gas pipeline route can be followed with the alignment of the improved road.  However, the ecologically sensitive Tung Chung and Cheung Sha Streams would still potentially be affected during the construction.  In general, Option 3 is expected to have higher impacts than those described above for Option 1 (considering the longer length).

Ecological Impact

Base Case (Entirely Offshore Route Passing West of Lantau)

The marine ecological sensitive receivers in the area include:

 

·           Numerous intertidal habitats in West Lantau including Yi O, Tai O, Sham Wat, San Tau and Tung Chung, in general, which have been reported as supporting intertidal mudflat, seagrass and mangrove;

·         Horseshoe crab breeding ground reported along the north western coastline of Lantau Island from Yi O to Tung Chung;

·         Finless Porpoise and Indo-Pacific Humpback Dolphin habitat;

·         Sha Chau and Lung Kwu Chau Marine Park;

·         Proposed Fan Lau Marine Park;

·         Proposed Soko Islands Marine Park;

·         Fisheries spawning and nursery areas; and

·         Artificial Reef Deployment Areas at Sha Chau and Lung Kwu Chau Marine Park.

The marine ecological sensitive receivers for this option have been taken into consideration, to the extent practical, during the route selection process; therefore, direct disturbance to these areas would be either avoided or reduced.  During the installation of the gas pipeline, short term elevations (in the order of hours or days) in suspended solids concentrations would occur as a result of dredging/jetting operations associated with the pipeline deployment.  The suspended sediment generated during dredging will cause a short-term increase in turbidity in the water column and result in higher rates of deposition on the seabed.  Such elevated suspended sediment levels may cause sediment deposition onto benthic organisms.

It is expected that water quality impacts can be controlled through standard measures (described above) which would in turn control impacts to ecological and fisheries resources.  Marine ecological impacts are expected to be short-term in nature and mitigated through standard practices.  Successful examples include the recently installed gas pipelines for Hongkong Electric (total length of 92 km, 20 inches diameter pipe) and Towngas (total length of 31.5 km, 18 inches diameter twin pipes), both of which have been installed in areas of high ecological value.  The Hongkong Electric pipeline route passes through Finless Porpoise habitat (southern Lamma waters) and close to coral habitats (which are sensitive to elevated suspended solids and sediment deposition) in particular at Tung Ping Chau and Po Toi.  As reported in the Monthly EM&A Reports, there was no Action/Limit Level exceedance recorded in the ecological sensitive receivers (Tung Ping Chau, southern Po Toi and Lamma) for all of the water quality parameters during the Hongkong Electric pipeline installation works (4th June to 19th July 2005) ([11]).  

The Towngas pipeline route is located close to (most within 500 m) high ecological value sessile hard coral and black coral communities along the subtidal shores of Tolo Channel as well as proximal to the Marine Parks of Tung Ping Chau and Hoi Ha Wan.  No exceedances of environmental performance limits (both water quality and coral criteria) attributable to the Towngas pipeline installation works were recorded ([12]).  The Towngas pipeline environmental monitoring results over the period 1 April 2005 to 25 May 2006 indicated that the works did not cause any significant impacts on the water quality and marine ecology in the works areas.

Option 1 - Route Crossing Lantau Island Overland to the West

The marine ecological sensitive receivers in the area include:

·         Intertidal habitats at Sham Wat which have been reported as supporting Intertidal mudflat, mangrove and horseshoe crab nursery ground;

·         Horseshoe crab breeding ground reported along the coastline of Sham Wat;

·         Finless Porpoise and Indo-Pacific Humpback Dolphin habitat;

·         Sha Chau and Lung Kwu Chau Marine Park;

·         Proposed Soko Islands Marine Park;

·         Fisheries spawning and nursery areas; and

·         Artificial Reef Deployment Areas at Sha Chau and Lung Kwu Chau Marine Park.

The sensitive areas of marine ecological value have been avoided, to the extent practical, during the route selection process.  However, indirect impacts to marine ecology may occur, as described for the Base Case, due to impacts to water quality, in particular to the Sha Chau and Lung Kwu Chau Marine Park.  Although sediment plume modelling would be required to more accurately predict potential impacts, it is expected that water quality impacts can be controlled through standard measures (see Base Case) which will in turn control impacts to ecology and fisheries resources.  Therefore, impacts have been classified as moderate potential for the marine portion of this project.

The terrestrial ecological sensitive receivers along the land based segment of Option 1 between Tai Long Wan Tsuen and Sham Wat Wan, include:

Option 1A

·       South Lantau Country Park;

·       North Lantau Country Park;

·       San Chau SSSI (support the largest known population of Rhododendron championae in Hong Kong);

·       Numerous stream courses segmenting the roadway; and

·       Tai O Stream.

Option 1B

·       South Lantau Country Park;

·       North Lantau Country Park;

·       Numerous stream courses segmenting the roadway; and

·       Sham Wat Stream.

Except for the northern end of the land based segment (the segment between Hang Mei to Sai Tso Wan for Option 1A and the segment at Sham Wat Wan for Option 1B), most of the pipeline route runs along the existing roads with dense woodland situated on both sides.  As the roads, as well as the proposed pipeline route, directly pass through or run along the Country Park, it is expected that direct impacts (including potentially extensive tree cutting and subsequent disturbance to wildlife would occur during construction.  Due to the importance of this area for local flora and fauna, protection measures would be required as well as extensive mitigation measures for any areas directly affected. 

For Option 1A, a significant amount of land may be disturbed during the installation of the pipelines between Hang Mei to Sai Tso Wan where only a narrow footpath exists.  Land would also be required along the pipeline corridor (3m either side) to act as a reserve for maintenance access.  Potential impacts may also result from development within the San Chau SSSI which may affect the population of Rhododendron championae, which is considered as one of the rarest native rhododendrons in Hong Kong.  All wild rhododendrons are protected species in Hong Kong.

For Option 1B, the segment at the northern end of Lantau is situated on or next to the intertidal mudflat, mangrove and horseshoe crab nursery ground at Sham Wat Wan. Such habitats are considered to be of high ecological value (see Figure 2.14). 

It is expected that any development situated along the proposed route (both Options 1A and 1B) would require disturbance to the natural vegetation in the area which comprises mainly secondary woodland and shrubland which are classified as being of high and medium ecological value, respectively (see Figure 2.14).

Option 2 - Route Crossing Lantau Island Through a Tunnel

The marine based segment of Option 2 shares the same routing as Option 1, but the temporary platforms that would need to be constructed (and later decommissioned) would directly disturb the natural shorelines (mainly rocky shore) at Tai Long Wan and Sham Wat Wan and soft-bottomed subtidal habitats at the portal areas (at least 100 m at either end of the tunnel).  It is noted that the shallow subtidal habitat at the Sham Wat Wan portal is considered to be habitat and spawning grounds of the Horseshoe Crab.  As a consequence, the marine ecological impacts of Option 2 would be higher compared with the Option 1. 

It is expected that the land based segment of Option 2 (through a tunnel), which avoids most of the land-based sensitive receivers (including SSSI, Country Parks, Sham Wat Stream and Tai O Stream), has relatively lower ecological impacts compared with the land based segment of Option 1 although in the event the intermediate portal and access is required this will have potential impacts on the rural habitats and associated wildlife in Keung Shan.  In general, Option 2 is expected to have less land-based ecological impacts when compared to those described for Option 1.

Option 3 - Route Crossing Lantau Island Overland to the East

The marine ecological sensitive receivers in the area include:

·         Numerous intertidal habitats in South and North Lantau including Shui Hau, Cheung Sha, San Tau, Tung Chung and Tai Ho, in general, which have been reported as supporting sandy beach, intertidal mudflat, seagrass, mangrove and horseshoe crab nursery ground;

·         Horseshoe crab breeding ground reported Tung Chung Bay and coastal areas near Tong Fuk;

·         Finless Porpoise and Indo-Pacific Humpback Dolphin habitat;

·         Sha Chau and Lung Kwu Chau Marine Park;

·         Proposed Soko Islands Marine Park;

·         Fisheries spawning and nursery areas; and

·         Artificial Reef Deployment Areas Sha Chau and Lung Kwu Chau Marine Park and Airport.

The sensitive areas of ecological value have been avoided, to the extent practical, during the route selection process.  However, indirect impacts to marine ecology have the potential to occur, as described for the Base Case, due to impacts to water quality.  Although water quality modelling would be required to more accurately predict potential impacts, it is expected that such impacts can be controlled through standard measures (see Base Case) which will in turn control impacts to ecological and fisheries resources.

For the land based segment of Option 3, ecological impacts addressed in Option 1 could be limited if the gas pipeline route can be followed with the alignment of the improved Tung Chung Road (currently under improvement).  The extent of the slope cutting and stabilisation could be reduced if managed properly.  However, the North Lantau and South Lantau Country Parks, woodlands located along the Tung Chung Road, Tai Ho and the ecologically sensitive Tung Chung Stream and Cheung Sha Stream and habitats for wildlife and plant species of conservation interest (including Hong Kong Newt Paramesotriton hongkongensis, Lesser Spiny Frog Paa (Rana) exilispinosa, Romer's Tree Frog Philautus romeri, Beijiang Thick-lipped Barb Acrossocheilus beijiangensis, the tree Artocarpus hypargyreus, the shrub Pavetta hongkongensis, the orchids Liparis viridiflora and Acampe rigida) are still potentially affected.  In general, Option 3 is expected to have similar impacts as those described above for Option 1 and it is expected that similar measures as those described for Option 1 could be adopted to control ecological impacts to acceptable levels.

Landscape/Visual Impacts

Base Case (Entirely Offshore Route Passing West of Lantau)

There are no expected landscape and visual impacts associated with the marine works for the implementation of the Base Case.  The pig launching facility at the South Soko site and gas receiving station at Black Point are common to all options and so are not discussed here. 

Option 1 - Route Crossing Lantau Island Overland to the West

There are no expected landscape and visual impacts associated with the marine works for the implementation of Option 1, aside from construction of landing sites, which are not considered to be of major significance. 

The land based pipeline route from Tai Long Wan Tsuen to Sham Wat, is expected to be located within rural areas which, due to the topography of the area, would require extensive slope cutting and stabilisation works for installation.  The pipeline would traverse either near or within areas designated on the Outline Zoning Plan as “Green Belt” (GB), “Site of Special Scientific Interest” (SSSI) and “Country Park” (CP) for Option 1A and “Green Belt” (GB) and “Country Park” (CP) for Option 1B.  These areas are considered to be important in terms of their landscape value and visual amenity and are considered to be areas of high landscape and recreational value.

During installation of the pipelines, direct removal of vegetation is expected to be required which, due to the project requirements for a maintenance reserve area, will not be reinstated back to the original condition.  Furthermore, depending upon the area selected, tree felling and vegetation removal may be required for slope cutting and stabilisation. 

In order to develop within this area, prior approval would be required from the CMPA and TPB.  The impacts associated with these works, particularly if undertaken within the North and South Country Parks, are considered to be significant.

Option 2 - Route Crossing Lantau Island Through a Tunnel

Similar to the case for Option 1, there are no expected landscape and visual impacts associated with the marine works for the implementation of Option 2, aside from the construction of a tunnel portal at both ends of the tunnel and the temporary reclaimed platform.  The natural landscape would be modified due to the construction of the tunnel portals including slope cutting and stabilisation works.  The visual impacts associated with the tunnel portals and the temporary reclaimed platforms (each of approximately 1.5 ha) at South and North of Lantau, as well as any required intermediate portal, are considered to be significant due to the close proximity to populated areas particularly at Tai Long Wan and Keung Shan.

During construction of the portals and associated access particularly in Keung Shan, direct removal of vegetation is expected to be required which will not be reinstated back to the original condition due to the requirement of provision of maintenance access.  Furthermore, depending upon the area selected, tree felling and vegetation removal may be required for slope cutting and stabilisation.  In addition, the land based construction works associated with Option 2 would be similar to those identified at the southern end (near Tai Long Wan Tsuen and designated on the Outline Zoning Plan as “Green Belt” (GB)) for Option 1.

Option 3 - Route Crossing Lantau Island Overland to the East

There are no expected landscape and visual impacts associated with the marine works for the implementation of Option 3, aside from construction of landing sites, which are not considered to be of major significance. 

The majority of the land based pipeline route from Cheung Sha to Tai Ho, is expected to be located within rural areas which, due to the topography of the area, may require extensive slope cutting and stabilisation works for installation (subject to the compatibility of the improved Tung Chung Road).  The pipeline would traverse either near or within areas designated on the Outline Zoning Plan as “Green Belt” (GB), “Coastal Protection Area” (CPA) and “Country Park” (CP).  These areas are considered to be important in terms of their landscape value and visual amenity and are considered to be areas of high landscape and recreational value.

During installation of the pipeline, direct removal of vegetation is expected to be required which, due to the project requirements for a maintenance reserve area, could not be reinstated back to the original condition.  The extent of the impacts is subject to the final design.  Furthermore, depending upon the area selected, tree felling and vegetation removal may be required for the slope cutting and stabilisation. 

In order to develop within this area, prior approval would be required from the CMPA and TPB.  The impacts associated with these works, particularly if undertaken within the North and South Lantau Country Parks, are considered to be significant.

Waste

Base Case (Entirely Offshore Route Passing West of Lantau)

Waste materials likely to be generated by the proposed option include dredged marine sediment, minor quantities of chemical waste generated from machinery, and minor quantities of solid waste from the construction workers.

Marine sediments will be required to be dredged to provide protection to the pipelines crossing the Urmston Road, Adamasta Channel and potentially on the western edge of the Port Development and eastern side of the Zhujiang Estuary Vessel Routing System.  The sediments in this area are not expected to be contaminated but would require verification as part of the sediment classification scheme under ETWBTC 34/2002; Management of Dredged/ Excavated Sediment.  Furthermore, sediments would be likely to be required to be dredged at the shore ends at Black Point and South Soko.  The disposal of these sediments would be undertaken in accordance with the ETWBTC. 

The impacts associated with dredging marine sediments are addressed in the water quality and ecology sections of this review.  Potential impacts are expected to be controlled through standard mitigation measures. 

Option 1 - Route Crossing Lantau Island Overland to the West

The potential waste impacts associated with the marine based work described for Option 1 would be similar to those for the Base Case.  However, it is expected that there would be a comparatively smaller amount of sediment that would be required to be dredged and disposed due to the shorter marine route. 

Land based waste impacts would be limited to the construction phase of the project and are expected to be significant.  Due to the nature of the terrain (steep) along the land based route, extensive slope cutting may be required and adequate temporary storage areas may not be permitted.  As a consequence, most of the excavated material would not be used on site.  It is expected that Option 1A would generate more excavated materials than Option 1B due to the longer land based route (approximately 3.2 km longer than Option 1B).  Small amounts of construction and demolition waste would be produced from the projects, such as wood from form work, broken asphalt, equipment and vehicle maintenance parts and unusable surplus concrete grouting mixes.  Chemical wastes would also be produced in small quantities from equipment maintenance and small quantities of solid waste would be generated by construction workers.  It is expected that these waste materials can be controlled by the contractor through standard waste management procedures. 

Option 2 - Route Crossing Lantau Island Through a Tunnel

The impacts associated with waste materials from marine based construction works are the same as those described for Option 1 but additional dredging for the marine barge access for the spoil transport and equipment loading at the temporary reclaimed platforms would be required.

Depending on the design, Option 2 tunnelling, may generate large amounts of excavated materials that would necessitate disposal.  Further to the preliminary estimation based on approximate 3.5 m excavated diameter, the total volume of the in-situ rock spoil to be excavated from the tunnel is approximately 75,000 m3.  All rock spoil from the tunnel would be temporarily stored in a muck bin on the Tai Long Wan reclamation and double handled onto a barge for periodic removal.

Option 3 - Route Crossing Lantau Island Overland to the East

The potential waste impacts associated with the marine based work described for Option 3 would be similar for Option 1.  However, it is expected that there would be a comparatively smaller amount of sediment that would be required to be dredged and disposed due to the shorter marine route due to avoidance of West Lantau, although there would be a number of utilities crossings required. 

The impacts associated with waste material disposal from land based construction works are similar to those described for Option 1 but with more excavated materials due to the longer length (approximately 12 km).

Noise/Air Quality Impacts

Base Case (Entirely Offshore Route Passing West of Lantau)

The noise sensitive receivers along the proposed marine route include Fan Lau Tsuen, Yi O San Tsuen, village/ residential houses in Tai O and Sham Shek Tsuen.  The background noise levels in the area are considered to be generally low and are dominated by aircraft and road traffic at Tai O.

Based on the expected equipment requirements, noise levels are expected to comply with noise criteria as nearest sensitive receivers would be situated more than 200 m from the proposed pipeline route.  Noise levels (induced only during construction) can be controlled by standard measures and do not impose major project constraints.

Air quality impacts are not expected to arise from the marine based portion of the pipeline during installation.  The pig launching facility at the South Soko site and gas receiving station at Black Point are common to all options and so are not discussed here.

Option 1 - Route Crossing Lantau Island Overland to the West

Sensitive receivers located along the Option 1 pipeline route include Tai Long San Tsuen, Sha Tsui Detention Centre, Shek Pik Prison, rural village developments along Keung Shan Road (Shek Pi Garden), rural village/ residential development areas along Tai O Road (San Tsuen, Lung Tin Estate, Tai O sheds and Hang Mei, only apply for Option 1A) and rural village developments at Sai Tso Wan and Sham Wat Wan.  As standard measures are expected to be able to control noise to an acceptable level under the EIAO TM, impacts are not considered to be significant for the marine section. 

For the land based segment, the potential for noise and dust impacts would be limited to the construction phase of the project.   

Sensitive receivers are located along the Option 1 pipeline route include Tai Long San Tsuen, Sha Tsui Detention Centre, Shek Pik Prison, rural village developments along Keung Shan Road (Shek Pi Garden), rural village/ residential development areas along Tai O Road (San Tsuen, Lung Tin Estate, Tai O sheds and Hang Mei, only apply for Option 1A) and rural village developments at Sai Tso Wan and Sham Wat Wan. 

The background noise levels of areas along the route are generally low and will be limited to vehicles travelling along the local road system.  Based on experience from similar projects, noise generated from powered mechanical equipment required for the installation of the pipelines and associated facilities (including: hand held breakers, excavators, generators, lorries, compactors, etc.) are the major noise sources affecting the sensitive receivers.  It is expected that noise levels can be mitigated to within the EIAO-TM limit and in accordance with the Technical Memorandum for the Assessment of Noise from Places Other Than Domestic Premises, Public Places or Construction Sites (IND-TM).

The potential air quality impacts arising from the construction of the pipeline are related to dust nuisance from slope cutting and excavation activities.  It is expected that these sources of nuisance can be controlled through measures stipulated in the Air Pollution Control (Construction Dust) Regulations employed in the worksite.

Option 2 - Route Crossing Lantau Island Through a Tunnel

The potential for air and noise impacts for both of the marine and land based segments would be the same as the Option 1, but with fewer sensitive receivers as the majority of the route is underground.  Sensitive receivers include Tai Long San Tsuen, Sha Tsui Detention Centre, Shek Pik Prison and rural village developments at Sai Tso Wan and Sham Wat Wan.  Standard measures are expected to be able to control noise and dust impacts to an acceptable level under the EIAO TM.

Option 3 - Route Crossing Lantau Island Overland to the East

The potential for air and noise impacts would be similar to those identified for the marine based aspects of Base Case.  Sensitive receivers include Cheung Sha Ha Tsuen, Butterfly Crest, South Lantau Hospital and Pak Mong.  Standard measures are expected to be able to control noise to an acceptable level under the EIAO TM. 

For the land based segment, the potential for noise and dust impacts would be limited to the construction phase of the project.  Noise and dust would be generated during the excavation of the trenches for the pipeline.  Sensitive receivers are located along the pipeline route include Cheung Sha Ha Tsuen, Butterfly Crest, South Lantau Hospital, rural village developments along Tung Chung Road (Shek Mun Kap, Lung Tseng Tau and Wong Ka Wai), Tung Chung New Town (Yat Tung Estate, Fu Tung Estate, Caribbean Coast, etc) and Pak Mong.

The background noise levels of areas along the route are generally low (in South Lantau rural areas) to moderate (in highly developed areas, i.e., Tung Chung New Town) and are dominated by aircraft noise and road traffic.  It is expected that the noise levels generated during the construction can be mitigated to within the EIAO-TM and in accordance with the Technical Memorandum for the Assessment of Noise from Places Other Than Domestic Premises, Public Places or Construction Sites (IND-TM).

It is expected that dust nuisance can be controlled through measures stipulated in the Air Pollution Control (Construction Dust) Regulations being employed in the worksite.

Cultural Heritage

Base Case (Entirely Offshore Route Passing West of Lantau)

There are some shipwrecks of marine archaeological interest recorded in western Hong Kong waters (database maintained by the United Kingdom Hydrographic Office in Taunton).  Geophysical surveys along the Base Case alignment identified six anomalies, which on further investigation, proved not to be of archaeological potential.  Furthermore, there is a known archaeological site on land at South Soko (the landing site and the proposed PIG station location), though this has been disturbed in the past (due to the construction of the detention centre which has be demolished).

Option 1 - Route Crossing Lantau Island Overland to the West

As noted above, there are no shipwrecks of marine archaeological interest recorded in western Hong Kong waters.  For both Options 1A and 1B, the area of potential constraint to the project is the potential impact on a declared monument named Shek Pik Rock Carving, and three archaeological sites, comprising Tai Long Wan Archaeological Site, Sham Wat Archaeological Site and Nam Tin Archaeological Site.  The project must avoid the impact to the Shek Pik Rock Carving.  As the pipeline and associated development was located within Tai Long Wan Archaeological Site and Sham Wat Archaeological Site, archaeological survey would be required to obtain field data for subsequent impact assessment to evaluate the extent of impact and recommend appropriate mitigation measures to reduce the impact.

Option 2 - Route Crossing Lantau Island Through a Tunnel

As for Option 2, there are no shipwrecks of marine archaeological interest recorded in western Hong Kong waters.  For this Option, the area of potential constraint to the project is the potential impact on a declared monument named Shek Pik Rock Carving, and three archaeological sites, comprising Tai Long Wan Archaeological Site, Sham Wat Archaeological Site and Nam Tin Archaeological Site.  The project must avoid the impact to the Shek Pik Rock Carving.  As the pipeline and associated development was located within Tai Long Wan Archaeological Site and Sham Wat Archaeological Site, archaeological survey would be required to obtain field data for subsequent impact assessment to evaluate the extent of impact and recommend appropriate mitigation measures to reduce the impact.

The access portal at Keung Shan would have to be constructed in a careful manner in order to avoid disturbances to the heritage sites in this area.

Option 3 - Route Crossing Lantau Island Overland to the East

Shipwrecks of marine archaeological interest recorded in western Hong Kong waters may be located close to the proposed pipeline route.  There is one known area of archaeological significance (Tung Chung Fort) situated next to Tung Chung Road.  Protective measures would be required if the pipelines were located close to this area. 

Summary/ Ranking of Potential Impacts

The potential impacts associated with each Option are summarised in Table 2.21.

 


Table 2.21       Summary of Potential Environmental Impacts

Issue Area

Impact Type

Base Case (Marine)

Option 1A & B (Marine + Road)

Option 2 (Marine + Tunnel)*

Option 3 (Marine + Road)

Water Quality

Short-term

Moderate/High

Moderate/High

Moderate/High

High

 

Long-term

Negligible

Negligible

Moderate

Negligible

Terrestrial Ecology

Short-term

Negligible

High

Moderate/High

Moderate/ High or High

 

Long-term

Negligible

Low/Moderate

Low

Low/Moderate

Marine Ecology

Short-term

Moderate/High

Moderate

Moderate/High

Moderate

 

Long-term

Negligible

Negligible

Moderate

Negligible

Landscape/Visual

Short-term

Negligible

High

Moderate/High

High

 

Long-term

Negligible

Low

Moderate/High

Low

Waste

Short-term

Moderate

Moderate/High

High

Moderate/High

 

Long-term

Negligible

Negligible

Low

Negligible

Noise/Air Quality

Short-term

Low

Moderate

Low/Moderate

Moderate

 

Long-term

Negligible

Negligible

Negligible

Negligible

Cultural Heritage

Short-term

Low

Moderate/High

Moderate/High

Low/Moderate

 

Long-term

Negligible

Moderate

Moderate

Negligible

Notes: The categories of the severity of potential impact shown in the table above are defined as follows:

·                 Negligible potential = impacts not expected to occur.

·                 Low potential for adverse impacts and represents impacts that are not considered to be unacceptable without mitigation.

·                 Low/moderate potential for adverse impacts which can be mitigated through good working practices without residual impacts.

·                 Moderate potential for adverse impacts which are slightly greater than low/moderate impacts and can likely be mitigated through the application of standard measures and working practices.

·                 Moderate/high potential for adverse impacts which, although resulting in a greater impact than those of moderate potential, could still be mitigated through the application of mitigation measures.

·                 High potential for adverse impacts which would require extensive mitigation measures to reduce impacts to an acceptable level and may result in residual impacts, even with the implementation of mitigation measures.

·                 Long-term refers to an impact that may last for several months/years or is permanent – whereas short-term refers to impacts that are transient and are on the scale of weeks/months

·                 * higher rating would apply if the intermediate portal is required

 


On the basis of the environmental assessment for the construction and operation of the gas pipeline, the result of the route comparison is as follows:

·      Preferred layout:            Base Case (Marine)

·      Second choice:             Option 2 (Marine + Tunnel)

·      Third choice:                 Option 3 (Marine + Road)

·      Fourth choice:               Option 1 A & B (Marine + Road)

The route crossing Lantau Island overland to the west, Option 1A and 1B, and the route crossing Lantau Island overland to the east, Option 3, are the least preferred.  Both options have greater potential for water quality, ecological and landscape impacts within the Country Parks (North Lantau and South Lantau) and along the roads in Lantau. 

Option 2, the route crossing Lantau Island through a tunnel, would avoid most of the land based sensitive receivers but generate more waste materials.  The portals would cause the permanent loss of natural habitats, long term landscape and visual impacts and potential impacts on the Tai Long Wan Archaeological Site and Sham Wat Archaeological Site.  The construction of the pipeline section passing through the tunnel will have a longer duration, which has a greater potential to delay project completion.  The dredging and reclamation due to the construction of the tunnel portals have greater water quality impacts, and therefore additional measures (determined by detailed computer modelling of water quality) will expect to be required to control the impacts.  In addition, the ground investigations for the tunnel option during detailed design stage may cause water quality and ecological impacts on the sensitive receivers (including catchwaters, Shek Pik Reservoir, Sham Wat Stream and Tai O Stream). 

With consideration of the programme and scale of the Base Case submarine pipeline, as well as the previous similar pipeline installation works in Hong Kong (ie Hongkong Electric and Towngas pipelines), water quality and marine ecological impacts are expected to be short-term in nature and mitigated through standard practices.  A discussion on the acceptability of ecological impacts with reference to previous pipeline installation projects in Hong Kong is given in Section 9.7.1.  No long term and operation impacts would be expected.  The pipeline installation works within the dolphin habitats in West Lantau will use jetting method to avoid dredging and reduce the water quality impacts, and the construction period for such section are predicted to last for not more than 2 months.  The Base Case is preferred as it also avoids impacts to land based sensitive receivers (i.e., Country Parks) and the potential terrestrial ecological impacts and other environmental impacts (i.e., noise, air, cultural heritage, waste, landscape and visual impacts). 

The preferred route is, therefore, the Base Case from the perspective of overall environmental impacts and impact duration.

2.3.7                                Preliminary Risk Review

Risk Constraints

This Section provides a qualitative review of the potential risks associated with each option and identifies the preferred option which would result in the least risk to the public.

Land Based Risk

As part of the pipeline system a Pipeline Inspection Gauge (PIG)  launching/receiving facility and a Gas Receiving Station (GRS) are also proposed to be developed.  A buffer area would be required around these components of the project and the potential risks associated with their operation are considered to be localised to within the required separation distance and would need to meet the relevant standards imposed by the GSO.  Therefore, the risks associated with this aspect of the project are considered to be common for all options.

For gas pipelines installed on land, there are two constraining requirements listed in the Hong Kong Planning Standards and Guidelines (HKPSG), Chapter 7, Section 3.3.4.  These are:

·       a restriction on development within 3 m of high pressure pipelines; and

·       a requirement to perform a Hazard Assessment for gas works to ensure that risks to the public are limited. 

Thus, a major constraint on the routing of the pipelines relate to the required compliance with the Hong Kong Risk Guidelines (HKRG).

Based on an analysis of the consequences of a pipeline release using standard correlations for various releases ([13]) ([14]),pipelines should typically maintain a distance of more than 125 m from developments, to the extent practical.

Pipeline Tunnel Option

Option 2 involves laying a 30” gas pipeline at about 100 barg in a tunnel about 6 km long beneath the Lantau hills.  This tunnel option presents construction safety, operational and maintenance challenges.  Maintenance and repair of the pipeline as well as maintenance of the tunnel could also pose significant constraints.  Provision of leak detection and ventilation systems, employment of equipment of electrical classification requirement and external pipe corrosion protection will be required.  During operation, confined space entry and ventilation would also be required.  Considering other factors such as maintenance and repair constraints, the tunnel option is less preferable than other options.

Land Based Option

Option 3 involves traversing the island.  Locating the pipeline above land or buried on land introduces potential fire and explosion hazards.  The hazard to life aspects of this option make it less preferable. 

Marine Based Risks

The route selection should seek to avoid passing through the Immigration Anchorage and other anchorage areas, where practicable.

Hazard to Life due to Pipeline Failure

A review of shipping traffic information demonstrates that there is less population on the sea as compared with on the land (Table 2.22).  In terms of the location of the pipelines for the Base Case the pipeline would be laid in the sea bed and thus avoid areas of high population. 

Table 2.22      Estimated Population Density - Marine Vessels / Land

Type

Density

Length of Segment (km)

 

(Population per m2)

Base Case

Option 1A

 

Option 1B

Option 2

Option 3

Rural population

0.005

0

10

7

6

10

Urban population

0.01

0

0

0

0

2

Shipping population

 

 

 

 

 

 

  High

1.2x10-7

6.4

6

6

6

5

  Moderate

1. 2x10-8

13

11

11

11

17

  Low

4x10-9

19.5

12

12

12

7

On the basis of the hazard to life due to pipeline failure, the result of the route comparison is as follows:

·      Preferred layout:            Base Case (Marine)

·      Second choice:             Option 2 (Marine + Tunnel)

·      Third choice:                 Option 1 A & B (Marine + Road)

·      Fourth choice:               Option 3 (Marine + Road)

 

It can be concluded, therefore, that Option 3 would be the least preferable, as it is largely land based.  It should also be noted that, as discussed above, the tunnel option (Option 2) is considered less preferable.  Therefore the Base Case is considered to be the preferred option.

2.3.8                                Technical Considerations concerning the Tunnel and the Marine Route

The information above concerning environmental and safety issues has indicated that the marine route and the tunnel routes have advantages over the on land routes across Lantau.  As described above the marine route is considered to have environmental and safety advantages over the tunnel route and is preferred by CAPCO.  The marine route has significant advantages over the tunnel route, many of which are related to engineering complexity, planning, schedule and air emission benefits.

Despite the above, the Study Brief in clause 2.1 (v) indicates that alternatives should be examined with a view to avoiding and minimising the potential impacts on marine waters and ecologically sensitive areas.  The following presents information as to why the tunnel is not a practical or reasonable alternative to avoiding potential impacts to the western Lantau area of dolphin habitat.

Design Considerations

·      In order to investigate the geological conditions in more detail specific site investigation would need to be carried out.  At least 32 vertical, 15 inclined and 7 horizontal drillholes would need to be carried out.  In-situ tests, including standard Penetration Testing, falling head permeability tests, water adsorption, impression packer survey, acoustic borehole televiewer survey and chemical tests for groundwater samples as well as laboratory tests for each of the drill holes would have to be carried out.  Part of the site investigation works would need to be carried out in the Lantau North and Lantau South Country Parks to allow for a full interpretation of the geological conditions along the proposed tunnel alignment.  It is expected that difficulty will be encountered with the permit applications due to environmental concerns and regulations. There is no existing access to the proposed site investigation stations, which will necessitate access by helicopter.  Several of the proposed boreholes will be in the range of 200-300m deep.  To locate the drill rods and related plant, site areas of approximately 10m x 10m will be required for each site investigation station, which will present a significant constraints to these operations within a protected country park area.

·      In order to access the site and commence preliminary excavation working platforms, formed through reclamation, would be required.  The reclaimed platforms would occupy around 1.5 ha each.  Alternative piled structures would have a more adverse environmental impact and floating platforms would not be able to withstand the weight of a Tunnel Boring Machine. Each reclamation would be formed in an area of natural coastline and some dredging would be required to access the site.

Planning Considerations

·      Liaison will be required with Highways Department concerning the potential alignment and landing point facilities for the Hong Kong Zhuhai Macau Bridge.

·      At the Shek Pik end the tunnel runs underneath the catchment area of the Shek Pik Reservoir and hence water drawdown will be an issue requiring careful consideration and detailed discussions with Water Supplies Department.

·      There remain planning uncertainties if a tunnel option is to be adopted. Planning approvals for the Southern Portal are not believed to impact the critical path of the project as it is to be constructed within the existing South Lantau Coast OZP.  Uncertainties relate to approvals for the Northern Portal, the Intermediate Ventilation Shaft Building (if adopted) and a permanent pier.  Both the Northern Portal and Ventilation Shaft Building are significant structures of size 50m wide x 20m high x 20m deep and 15m wide x 10m high x 15m deep respectively.  The Northern pier would be some 3m wide x 50 m long to cater for the limited depth of the existing approach.  To date it is still not clear whether an OZP would or would not be required.

Construction Issues

·      As noted above working platforms would be required to provide access to the Tunnel Boring Machine (TBM).  The TBM would operate 24 hours per day and would require a power supply.  During construction 11kV power supply would be from Tai Long Wan supplied via OHL lines.  During the operational phase dual 132kV supply from both ends would be required.  These could be supplied via overhead lines or submarine cables.

·      Analysis of geological maps obtained from the GEO indicates that at least 7 geological faults cross the proposed tunnel alignment.  Extended weakness zones with highly to completely decomposed materials, shear planes with soft clay infill and high water seepage could be anticipated as the tunnel excavation approaches any fault zone.  Soft ground tunnelling techniques could need to be adopted when excavating through these fault zones.  The tunnel option adopts a construction methodology which safety statistics and the insurance market confirm as having a high risk.  The impact of a tunnel fire due to the limited egress points for line workers would be severe.

·      Some 75,000 m3 of in situ excavated rock material would have to be disposed off site. Although not a huge quantity by itself the number of projects presently in the inception stage means that this could be a major logistical issue.  Unfortunately the excavated tunnel material could not be used as backfill material for the reclamation, as the reclamation has to be constructed first to allow access to commence tunnel construction. 

Operation and Maintenance Issues

·      The tunnel after it is completed is classified as a confined space.  Safety mitigation measures need to be taken to regularly purge the tunnel of gases before workers go into the tunnel.

·      In the permanent condition ventilation fans would need to be adopted.  Large fans housed in a ventilation building would be required as up to 3 air changes an hour are required to initially purge the tunnel of gases.  Such fans have a noise impact even though dampers will have to be used.

·      Diesel, grease, oils and chemicals (e.g. admixtures) would need to be stored on each of the sites.  All of these items need to adopt the use of drip trays and in the case of chemicals, self closing enclosures in the case of fire.  There is also the issue of disposal of chemical waste, sewage and general refuse.

Schedule Issues

The installation works for the submarine pipeline are scheduled to take place over 3-5 months in the West Lantau area (which is the key area avoided by the tunnel option).  It is to be noted that these works are undertaken in sequences (pre-trenching, pipelay and backfilling) and in specific areas at a time.  The tunnel option would, however, take around 49 months to construct.  A breakdown of the key schedule differentiators is presented in Table 2.23. 

Table 2.23      Key Schedule Differentiators: Marine vs Tunnel

 

Marine Route

Tunnel

Temporary reclamations

n/a

5 months

Portal construction

n/a

5 months

Tunnel Boring machine setup

n/a

2 months

Tunnel Excavation

n/a

22 months

Tunnel E&M Fitout

n/a

6 months

Onshore Pipeline Installation

n/a

2 months

Jetting

28 - 48 days

(not on critical path)

n/a

- Lay pipeline (W. Lantau/Tunnel Section)

8 - 16 days

(not on critical path)

n/a

- Rock dumping

40 days

n/a

Hydrotesting and pre-commissioning

(included in overall)

2 months

Tie-in to offshore pipeline

n/a

1 month

Remove Reclamation Platforms

n/a

3 months

BD Occupation Permit

(included in overall)

1 month

Total Lantau Area Construction

3 – 5 months

49 months

Total Delay in First Gas

0 months

15 to 26 months

Implications for Meeting Government Policy on Air Emissions

The LNG project schedule delays presented above that would arise with the tunnel option of 15 to 26 months would have a significant impacts on air emissions and CAPCO’s ability to comply with the Government’s policy on emission reductions.  With the tunnel option additional use of coal will be required through the startup of the LNG terminal and the incremental emission of pollutants will total over 100,000 tons as shown in Table 2.24 below.

Table 2.24      Incremental emission of pollutants as a result of a delay in first gas

Pollutant (Kilotonnes - KT)

18 Months

24 Months

Total Suspended Particulates

2.34

3.1

Sulphur Dioxide

46.5

59.0

Nitrogen Oxides

29.5

38.9

Total

78.3

100.0

A summary of the key differentiators between these options is presented in Table 2.25.  It is clear from the table that in terms of meetings the need for this project, ie a replacement gas source for Black Point Power Station that allows CAPCO to meet the Government’s emission objectives, the tunnel option is not a reasonable or practical alternative to the marine option via West Lantau.

Table 2.25      Summary of Key Differentiators between the Tunnel and Marine Option

Issue

Marine Route

Tunnel Route

Construction Safety/Risk

 

Operational Safety

 

Lower Risk Construction Methodology

 

Protected to reduce risk of damage/leak

Higher Risk Construction Methodology

 

Gas detectors present in tunnel. Tunnel in both construction and operation modes is classified as a confined space

 

Cost

No Impact

Increases Overall Pipeline cost by ~ 30% (HK$0.5 billion) 

 

Duration of West Lantau Occupation

 

3 – 5 months

49 months

Impact on LNG Delivery Schedule

First gas in 4Q 2011

Overall Schedule Impact of 15 – 26 months assuming no complications in EIA, town planning procedures or FSRO gazettal

 

Community Position

Concerns regarding the pipeline routing have been focused on marine issues

Potential for additional objections from local communities and Green Groups due to disturbances to remote sections of Lantau Island and Country Parks

 

Environment

·           No reclamations

·           No areas of natural coastline related to the marine option

·           Two dredged approaches

·           No impacts to land based sensitive receivers

 

·           Two reclamations (3 ha)

·           Two areas of natural coastline loss

·           Four dredged approaches

·           Additional land based construction impacts on air, noise, landscape, visual, terrestrial ecology and heritage sensitive receivers

·           Tunnel excavation creates an additional spoil handling and disposal issues ~  75,000m3

·           18 months delay causes an increase of SOX emissions of 46 KT and NOX emissions of 29 KT

·           24 month delay causes an increase of SOX emissions of 59 KT and NOX emissions of 39 KT

·           2010 Emissions targets cannot be met

2.3.9                                Summary

The tunnel option is a more uncertain undertaking resulting in a minimum delay to the LNG Receiving facility of 15 - 26 months and an additional cost of HK$0.5 billion.  There are significant uncertainties inter alia unexpected ground conditions, planning issues, community issues related to private lots and potential extra EIA studies which could increase the delay further.  The conclusion is that when compared to the pipeline option, the tunnel (and other land based options) are not practicable alternatives when the risks and schedule uncertainties are all considered. 

Considering the environmental constraints and safety issues, as well as the physical constraints, presented in the discussions above it is concluded that the Marine Route remains the preferred gas pipeline route option.  From a scheduling aspect the marine route can be installed without resulting in delays in commissioning of the LNG terminal whereas the other options will lie on the critical path and introduce significant delays to project start-up.  The schedule delays brought about by the non-marine option will mean that CAPCO cannot meet the Government’s 2010 emission initiatives.

2.4                                      Consideration of Power and Water Supply

Power and water supplies are required for the routine operation of the LNG terminal.  Historically, one submarine cable and one water main connected South Soko Island to South Lantau, via Shek Pik, providing power and water to the Detention Centre.  The capacity of decommissioned cable system is insufficient to meet the electricity demand for the LNG Terminal during construction and operation.  Due to poor condition, the cable system must be replaced.  New power cables would therefore be required to be installed for the South Soko LNG terminal. 

The conditions of the existing water main are unknown.  In order to determine the integrity of the pipeline a number of detailed tests would be required which would take time and may prove the lack of integrity of the water main.  It is also of note that ownership of the water main remains unclear.  For the purposes of this EIA, it is therefore considered that in order to examine the potential worst case scenario, the installation of a new water main will be investigated.

The purpose of this section is to present the considerations of alternative routes for the power cables and water main.  The assessment has been conducted to investigate not only the environmental considerations of each route, but to include an examination of potential engineering aspects.  The assessment thus considers both the difficulties of the construction and operation of each route as well as the potential environmental impacts.

2.4.1                                Route Options

The basic requirements of a LNG receiving terminal in Hong Kong have been described in detail in Part 1 – Section 3.  Justifications for South Soko Island being considered as one of two sites for a LNG receiving terminal in Hong Kong have been presented in Part 1 – Section 4. 

On the basis of the requirements, both a reliable power and water supply must be provided to the proposed terminal.  Due to the island location of the potential South Soko terminal there are a number of potential routes that the necessary power cables and water main may traverse (Figure 2.18).  Typical Sections through the submarine water main and power line are shown in Figures 2.19 and 2.20. 

2.4.2                                Power and Water Supply Route Selection Process

Selecting the Launching Site

The selection of launching site was based on avoidance to the extent practical of the following considerations (Figure 2.21):

·      Gazetted bathing beaches;

·       Country Park;

·       Coastal Protection Areas and Green Belt;

·       Locations with conservation interest;

·       Archaeological Site; and,

·       Selecting technically feasible areas (i.e., soft muds) to limit the construction difficulties.

Marine Route Planning Consideration

There are some existing physical constraints to the proposed cable and water main route, which have confined the alignment of the cable (Figure 2.21).  As it is allowed to lay submarine utilities within the gazetted marine borrow area, the Soko Marine Borrow Area is not considered to be a constraint for the routing.  The following constraints have, however, been taken into consideration:

·      Minimising crossing or encroaching on the existing submarine cable or water main to South Soko, thereby ensuring that cable laying operations do not cause any disturbance to the existing utility systems should they still be viable for future use;

·       Avoiding locations with high ecological interest, high dolphin and porpoise sighting density in South Lantau waters;

·       Avoiding the existing sand deposit area as it would pose installation difficulties; and,

·       Avoiding shallow sediment areas or areas with rock outcrops to facilitate burial requirements.

   In addition to the avoidance of the aforementioned constraints, the following considerations have also been taken into account:

·       For simultaneous cable burial/laying operation it is necessary to avoid sharp bends of the cable alignment and try to ensure that the power and water pipe routes are as straight as possible; and,

·       To provide the shortest interface with the major marine vessel fairway (South Lantau Channel), the existing water main and cable and seawalls, keep the cable circuit/ water pipe crossing the fairway, utilities and seawalls perpendicular as far as possible.

Preferred Route for the Power Cable and Water Main

With consideration of the route selection process as discussed above, Option 1 is the preferred route for the power cable and water main (nearly parallel to each other).  Option 1 has the shortest route and avoids most of the major elements including the Country Park, Green Belt, existing sand deposit area locations of high dolphin and porpoise sighting density. 

2.5                                      Selection of Preferred Scenario

The preferred scenario/alternative to be taken forward to the EIA stage at South Soko is Layout Option 3D, the Base Case submarine gas pipeline alignment and Option 1 for the proposed power cable and water main.  Full details of the components of the preferred scenario are detailed in Part 2- Section 3 of this EIA report.

The selection of the preferred scenario has brought about a series of environmental and engineering benefits to the Project as presented in Figures 2.22 to 2.25.  These benefits have arisen through modifications to the engineering layout stimulated by issues raised during consultations with stakeholders in Government, District Councils, Rural Committees, NGOs and the Advisory Council on the Environment, as well as through engineering optimisation. 

One of the main environmental outcomes of this process was the orientation of the LNG jetty to the southeast of South Soko Island has brought about a significant reduction in dredging volumes from approximately 4 Mm3 to approximately 1.07 Mm3. 

Following discussions with NGO groups and feedback from various Government departments concerning findings of the Marine Ecology baseline surveys presented in Annex 9, CAPCO has re-examined the layout of the site to determine whether the amount of reclamation can be reduced further in the eastern bay of Tung Wan.  The purpose of the reduction in reclamation is to reduce the disturbance to the marine habitats in Tung Wan and in particular the habitat of amphioxus (Branchiostoma belcheri).  The layout review concluded the following:

·      By removing the jetty in Tung Wan marine vessels during construction and operation of the terminal will need to access the site in Sai Wan during periods of adverse weather.  This will result in reduction in dredging in Tung Wan but a slight increase in dredging in Sai Wan to allow for access by construction barges.  Overall though there is a net decrease in dredging of 60,000 m3.

·      The northern coastline in Tung Wan will not require reclamation by relocating the Control Room, Maintenance Workshop and Administration building to the southern side of the terminal.  The relocation will result in a reduction in coastline loss but moving the process areas will necessitate additional excavation into the hillside.  The excavation works are not expected to cause unacceptable impacts to terrestrial ecology as they will take place in areas of low to moderate ecological value shrubland.  No rare or protected fauna or flora have been recorded in this area.

·      The changes above will necessitate, in order to comply with the safety codes for the terminal design a minor relocation of facilities within the existing footprint of the site.  No significant changes in environmental (eg air, noise, waste, landscape visual) or risk issues are expected from these modifications.

·      The net reduction in reclamation arising from the above changes is 1.1 ha resulting in a overall reclamation area of 0.6 ha.

·      The net reduction in natural coastline loss is 150 m resulting in a overall loss of natural coastline of 300 m.

The above changes have resulted in a reduction in ecological, fisheries and water quality impacts through reduction in reclamation, dredging and natural coastline loss.  The reduction in dredging will also have a benefit in reducing off site impacts during disposal of dredged muds and ease the burden on existing disposal sites.

·      Improvement in visual impacts through relocation of LNG tanks to the western side of the Island and behind prominent topographical features.

Further details are presented on Figures 2.22 to 2.25.


Figure 2.22     Design Adopted in Pre-EIA Studies

 

Design Adopted in Pre-EIA Studies

Details

The layout initially studied included approximately 13 ha of reclamation to accommodate the LNG terminal facilities.  Total dredging volumes exceeded 4 Mm3.

Layout

Issues

Field work conducted on the island revealed the generally low ecological value of the terrestrial habitats.  Consequently members of the ESMG and various NGOs questioned whether less reclamation could be involved and more land on the island utilised.


Figure 2.23     Design Presented in the Project Profile

 

Design Presented in the Project Profile

Details

A modified layout was presented in the Project Profile which reduced reclamation (< 5 ha) and utilised more land of the Island.

Layout

Issues

The Study Brief identified the need to avoid permanent impacts to habitats in between the North and South Soko Islands.  NGOs and ACE members questioned whether the LNG jetty could be located in the deeper waters to the south of the island to reduce dredging and avoid the waters between the North and South Soko Islands.

 


Figure 2.24     Scenario Design at the commencement of the EIA

 

Scenario Design at the commencement of the EIA

Details

During the early stages of this EIA, as described in the sections above the CAPCO team has examined various layouts taking into account:

·          Issues raised during consultations with ACE, Rural Committees, District Councils, NGOs, Fishermen, LegCo members;

·          Ongoing process, civil and marine engineering reviews; and,

·          Updated findings of environmental baseline surveys. 

The outcome of this work was the production of a layout as presented below for examination during the EIA.

Layout

Benefits

The resultant layout has a reduction in reclamation to approximately 1.7 ha in Sai Wan and Tung Wan.  The relocation of jetty to southeast has meant that dredging volumes are reduced to approximately 1.4 Mm3 at the terminal.  These changes have brought about an overall reduction in water quality, ecological, fisheries and waste impacts.  The positioning of the tanks has resulted in an improvement in visual impacts.

 


Figure 2.25     Preferred Scenario Design Finalised as part of this EIA

 

Preferred Scenario Design Assessed in this EIA

Details

During the later stages of the EIA, as described in the sections above the CAPCO team has examined various layouts taking into account:

·          Ongoing process, civil and marine engineering reviews; and,

·          Updated findings of environmental baseline surveys including the identification of the presence of Amphioxus in Tung Wan. 

The outcome of this work has been the production of preferred layout as presented below.

Layout

Benefits

The resultant layout has a reduction in reclamation to approximately 0.6 ha in Sai Wan and no reclamation in Tung Wan.  The new layout serves to reduce the magnitude of impacts on the coastal resources of South Soko Island.

 


 



([1])     It is noted that the methodologies for environmental and engineering comparisons of alternatives differ in this section of the EIA and other such as Part 1 Section 5 and Part 3 Section 2.  This is appropriate as the input information in the comparison process has to be treated differently, some of the source information is quantitative and some qualitative and hence the approaches have been tailored to the context of the assessment.

([2])     Aas, PM & Engen A (1993) Hong Kong Seawall Design Study.  GEO Report No. 31. Geotechnical Engineering Office, Civil Engineering and Development Department, Hong Kong SAR Government.

([3])     B Wursig, C.R. Greene, T. A Jefferson (2000) Development of an air bubble curtain to reduce underwater noise of percussive piling. Marine Environmental Research (49), 79-93.

([4])     B Wursig, C.R. Greene, T. A Jefferson (2000) Op cit.

([5])     B Wursig, C.R. Greene, T. A Jefferson (2000) Op cit.

([6])      It should be noted that these plots show the highest level recorded in each model grid cell over the entire 15 day cycle and are hence a worse case image.  They do not represent simultaneous snap shots and therefore should not be interpreted against the WQO as the SS elevations in one grid cell (ie area) will occur during a different day/hour than in another grid cell.

([7])      It should be noted that these plots show the highest level recorded in each model grid cell over the entire 15 day cycle and are hence a worse case image.  They do not represent simultaneous snap shots and therefore should not be interpreted against the WQO as the SS elevations in one grid cell (ie area) will occur during a different day/hour than in another grid cell.

([8])      Jefferson, T. A. (ed.). 2005.  Monitoring of Indo-Pacific humpback dolphins (Sousa chinensis) in Hong Kong waters – data analysis: final report.  Unpublished report submitted to the Hong Kong Agriculture, Fisheries and Conservation Department

([9])      Aker Kvaerner Yacheng Connection Study for CAPCO. 2006

([10])    Aker Kvaerner & ARUP 2006 Tunnel Reports to CAPCO

([11])    Cinotech Consultants Limited (2005) Lamma Power Station Extension – Supply and Installation of Submarine Gas Pipeline. Water Quality Monitoring During Post-trenching Works. Impact Monitoring Report (June & July 2005).

([12])    Meinhardt Infrastructure and Environment Limited (2006) FEP-01B/167/2003/D Proposed Submarine Gas Pipeline from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plant, Hong Kong. Final EM&A Summary Report.

([13])    Chamberlain (July 1987) Developments in Design Methods for Predicting Thermal Radiation from Flares Chem Eng Res Des Volume 65

([14])    CCPS (1994) Guidelines for Evaluating the Characteristics of Vapour Cloud Explosions, Flash Fires and BLEVEs