1                                            INSTALLATION OF PIPELINE AND BURIAL USING JETTING

1.1                                      Introduction

This Annex presents information on the potential installation method for the proposed submarine water main from South Soko Island to Shek Pik.  The submarine water main is proposed as part of the construction of a Liquefied Natural Gas (LNG) Terminal on South Soko Island.

The intention of the paper is to provide background information on typical jetting works associated with the follows:

·      Pipelay and pre-test;

·      Jetting “spead”;

·      Deployment and operation of jetting; and

·      Post trench rock dumping.

1.2                                      Pipelay and Pre-Test

In sections of the route where burial is proposed using a water jetting technique, the pipeline will first be laid on the seabed using the pipe lay barge.  Prior to trenching, the pipeline will be pre-tested to ensure its strength and leak integrity, enabling easier rectification (rarely necessary) of any faults exposed by the test.  The pipeline will be left flooded with water to increase its weight and aid its settlement into the trench as the jetting progresses.

1.3                                      Jetting “Spread”

The jetting “spread” is typically based on a flat barge that will be towed into position over the pipeline at the start point and then anchored using a 4-anchor pattern.  The forward anchors will be deployed some distance ahead of the barge and the stern anchors will be positioned close to the stern of the barge.  These distances are variable depending on water depth, current conditions and the presence of any constraints.  The contractor will determine these details in the course of its detailed design and will continually verify/update its practices and procedures in response to the results being obtained on site and any unforeseen or changed conditions.

The jetting machine will be chosen by the contractor based on its past experience with site conditions comparable to those existing along the pipeline route.  There are many different designs of jet sled that have been developed by a number of general and specialist contractors operating in the pipeline industry.  Whilst they all operate using the same principles, each one features several variables including:

·       number and positioning of water jets;

·       water pressure operating range;

·       arrangement of eductor tubes;

·       airlift or water venturi eductor tubes;

·       depth of “cut” per pass and number of passes required for required depth;

·       length of route “blocks”; and

·       speed of forward travel.

These variables are adjusted to suit specific site conditions.  While Contractors can predict reasonable starting values for the site based on site investigation results, it is probable that adjustments will be required on commencement of work and even in the course of work to obtain optimum trenching performance and/or to ensure that water quality standards are met.

Because designs of jetting machines are proprietary to the various specialist contractors, design details are not given out for fear of copying of designs by competitors.  CAPCO consulted several contractors, including Saipem and Leighton, both of which constructed offshore pipelines in Hong Kong within the last two years.  The following (limited) details were provided by OES, Leighton’s subcontractor for jetting on the Towngas project (an approved EIA), in which a submarine gas pipeline was installed successfully under a comprehensive EM&A programme ([1]). 

Known:

Pump pressure:  400 psi

Pump flow rate:  4000 USG min-1 => 15,140 L min-1

Eductors output:  20,000 L min-1 with 1.5 m head @~3.5 psi

Assumed:

That all liquefied soils are ejected from the trench.

Trench area:  2 m2 => 1 m deep and 2 m wide per pass

Jetting speed:  0.35 m min-1

Trench Volume:  0.7 m3 min-1

Eductor discharge Soil/water %:  10 %=> 2 m3 min-1 soil

Output to environment:

Pump pressure:  400 psi

Pump flow rate:  4000 USG min-1 => 15,140 L min-1

Eductors output:  20,000 L min-1

Water output:  36,000 L min-1

Eductor discharge height above seabed:  2 m

Volume of soil in water column:  0.7 m3 min-1

Potential volume @ 10% soil in water column:  2 m3 min-1

It is found that the monitoring results of jetting operations were comparable to the model results predicted for the EIA for the Towngas project.  The LNG project used the similar approach to the Towngas project in the modelling and hence it is expected that the assumptions in the water quality assessment and model would be realistic.

From previous experience in HKSAR the soils were dispersed in a 70 m radius with 80% of the material falling from the water column.  By the 150 m radius the SS concentrations were consistently below the EPD requirements, even when there was a 1.5 m s-1 current effecting greater dispersion.


1.4                                      Deployment and Operation of Jetting Spread (including anchoring)

 

The jetting spread will be deployed at the start location of the section to be jetted and the support barge will be pulled forward on its forward anchors, towing the jet sled behind.  The position of the barge will be controlled by maintaining tension on the stern anchors as the forward anchor cables are winched in.  The progress of this activity is similar to that of pipe laying, with the exception that there is no need to pause at each pipe joint.  The barge can be moved ahead continuously, with anchor handling tugs working to recover and relocate bow and stern anchors (duplicate sets of anchors are used) as the limits of anchor cable movement are reached.  The contractor may elect to perform jetting over limited “block” lengths of the route, completing a number of passes to achieve the required depth in one area before moving to the next.  Alternatively, it is possible that for the site conditions on this project, completing each pass over the entire section will produce better overall results.

1.1                                      Post Trench Rock Dumping

The pipeline protection design concept for this project identifies the need to protect the pipeline from third party contact, particularly dropped and dragged anchors.  Where jetting is used for trenching, there are some areas where it was assessed that natural backfill may be either insufficient or might not occur sufficiently rapidly after construction, to provide the necessary protection.  Accordingly, supplementary protection may be provided by partially backfilling the jetted trench with a layer of rock, nominally 1m over the top of the pipe.  The requirement for all subsea constructions in Hong Kong waters to be finished level with the surrounding seabed is noted and this requirement will be specified and noted on the drawings in the design of the pipeline.

This design has been assessed as suitable to protect the pipeline from small vessel activity.  In areas where larger vessels (and therefore larger anchors) are expected, a completely different design will be utilized, incorporating a pre-dredged trench and a larger rock mound protecting the pipeline.  In such cases, the design requirement to finish the construction level with the surrounding seabed will be maintained.

1.2                                      HKLNG Project Construction Approach

The pipeline construction will be contracted to an experienced, reputable offshore pipeline contractor on the basis of a detailed construction specification.  Included in the specification will be the requirement to follow the environmental management plan developed for the project and, particularly, an obligation to meet the defined water quality standards (and other standards) mandated by the relevant HKSARG departments.  Also included will be a requirement for the contractor to utilize proven equipment and work methods. 

1.3                                      Water Quality Control

Water quality modelling was performed as part of the EIA to enable a selection of acceptable technologies in terms of meeting water quality standards and to provide guidance on developing environmental management plans and mitigation methods.  Ultimately, it will be the responsibility of CAPCO and its Contractor/s to monitor the work closely and adjust the work procedures as required to ensure that water quality standards are met to the satisfaction of EPD and other relevant authorities.

A series of images show the variations in design of jetting equipment.

Figure 1.1      “Arabian Leopard” 12 – 30 inch pipeline Jet Sled (OES Equipment)

Figure 1.2       Bengal Tiger” 30 – 60 inch pipeline Jet Sled (OES Equipment)

 

Figure 1.3       “Sumatran Tiger” 20 to 42 inch pipeline Jet Sled (OES Equipment)

 

Figure 1.4       “Canyon Horizon” Pipe Jetting Barge(Horizon Offshore equipment)

            

Figure 1.5       “Canyon Horizon” Pipe Jetting Barge (Horizon Offshore equipment)

 

Figure 1.6       “Castoro 10” Pipelay and trenching barge (Saipem Equipment)

 

 

Figure 1.7       “DJS 1” Diverless Jet Sled for up to 60 inch pipelines (Saipem Equipment)


 



([1]) The project refers to the submarine gas pipelines from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plant, Hong Kong.