13                                        Quantitative Risk Assessment

This section of the EIA presents a summary of the analysis and findings of the Quantitative Risk Assessment (QRA) study undertaken for the proposed LNG Terminal at Black Point and associated facilities.

This section is divided into two sub sections: section 1 relates to the general aspects of the QRA study, and section 2 relates to the LNG Terminal.

Further details of the analysis pertaining to the terminal QRA are contained in Annexes 13A1 through 13A7.

Additional annexes are provided to describe the Safety Management System (Annex 13B) and summarise all the assumptions adopted in the QRA study (Annex 13C).

Sub-Section 1: General

13.1                                  Legislation Requirement and Evaluation Criteria

The key legislation and guidelines that are considered relevant to the development of the proposed LNG Terminal and associated facilities are as follows:

·  Gas Safety Ordinance, Chapter 51

·  Hong Kong Planning Standards and Guidelines (HKPSG), Chapter 12

·  Dangerous Goods Ordinance, Chapter 295

·  Environmental Impact Assessment Ordinance (EIAO), Chapter 499

·  The EIA Study Brief, Section 3.7.9.1

There is some overlap in the requirements of the various pieces of legislation and guidelines. The requirement for a Hazard Assessment (HA) study is contained in the EIAO and HKPSG. Such a study, although not required explicitly in the Gas Safety Ordinance, is implied in the regulations and has been an established practice for similar installations in the SAR.

13.1.1                            EIAO Technical Memorandum (EIAO-TM)

The requirement for hazard assessment of projects involving storage, use and transport of dangerous goods where risk to life is a key issue with respect to Hong Kong Government Risk Guidelines (HKRG) is specified in Section 12 of the EIAO-TM.

The relevant authority for an QRA study relating to an LNG Terminal and associated facilities is the Gas Standards Office (GSO) of the Electrical and Mechanical Services Department (EMSD), as specified in Annex 22 of EIAO-TM.

Annex 4 of EIAO-TM specifies the Individual Risk and Societal Risk Guidelines.

13.1.2                            Risk Measures and Hong Kong Government Risk Guidelines (HKRG)

Individual risk is the predicted increase in the chance of fatality per year to a hypothetical individual who remains 100% of the time at a given stationary point.

The individual risk guidelines require that the maximum level of off-site individual risk associated with a hazardous installation should not exceed 1 in 100,000 per year i.e. 1 x 10-5 per year.

Societal risk expresses the risks to the whole population. The HKRG is presented graphically in Figure 13.1. It is expressed in terms of lines plotting the frequency (F) of N or more deaths in the population from incidents at the installation. Two FN risk lines are used in the HKRG to demark “acceptable” or “unacceptable” societal risks. The intermediate region indicates the acceptability of societal risk is borderline and should be reduced to a level which is “as low as reasonably practicable” (ALARP). It seeks to ensure that all practicable and cost-effective measures which can reduce risks will be considered.

 

Figure 13.1     Hong Kong Government Risk Guidelines

13.2                                  Study Objectives and Methodology

The objective of the QRA study is to assess the risk to life of the general public including the workers of nearby plants from the proposed facilities during its operational phase. The results of the QRA are compared with the HKRG.

The detailed requirements of the study are (see Section 3.7.9.1 of the EIA Study Brief):

·      To identify all credible hazardous scenarios associated with storage, handling and operation of the LNG facility, which has potential to cause fatalities;

·      To carry out the QRA expressing population risks in both individual and societal terms;

·      To compare the individual and societal risks at the proposed development sites with the HKRG;

·      To identify and assess practical and cost effective risk mitigation measures as appropriate;

·      To identify all LNG leakage scenarios and propose a safety management system for the operational phase of the project with an aim to contain any accidental leakage in short notice and to prevent and/or minimise any leakage.

The elements of the QRA are shown schematically in Figure 13.2.

An overview of the methodology employed is provided here to briefly introduce the study approach, while the details are included in the respective sections/ annexes.

Relevant data on the proposed facilities such as their preliminary layout drawings and design basis as well as population data in the vicinity were collected and reviewed.

A Hazard Identification (HAZID) Study was conducted to identify all hazards, both generic and site specific. A review of literature and accident databases were also undertaken. These formed the basis for identifying all hazardous scenarios for the QRA Study.

The frequencies, or the likelihood, of the various outcomes resulting from an LNG/gas release scenario were derived from historical databases and, where necessary, these were modified to take into account local factors.

For all identified hazards assessed as having a frequency of less than 10-9 per year, their frequency assessment will be documented but no quantification of consequences will be performed.

For hazards with frequencies greater than 10-9 per year, the consequences of each release were modelled.

Hydrocarbon releases have been modelled using the PHAST consequence modelling package developed by Det Norske Veritas, Inc. (DNV)

The consequence and frequency data were subsequently combined using ERM’s proprietary software RiskplotTM to produce the required risk calculations.

Finally, the results from the risk assessment were compared with the HKRG and found to be acceptable. No mitigation measures are therefore proposed.

 

Figure 13.2     Schematic Diagram of QRA Process

Sub-Section 2: Terminal

The QRA study for the terminal includes all planned facilities at the site, including unloading operations at the jetty, LNG storage tanks, sendout pumps, LNG vaporisers and the boil-off gas system.

This section presents a summary of the hazard assessment study for the facilities at the terminal while Annex 13A gives further details.

As per the Study Brief, the QRA study for the terminal is also required to include the marine transit risks for LNG carriers within 500m of the jetty. A separate Marine Quantitative Risk Assessment (MQRA) study has been conducted by DNV. The risk results from the MQRA study for the 500m section at the jetty have been combined with the risk results for the facilities at the terminal to produce an overall risk result for the terminal, which is presented in this section. For further details on marine transit risks, DNV’s report may be referred.

13.3                                  Facility Details

13.3.1                            Site Facilities

The proposed LNG Terminal and associated facilities will be built to provide a peak natural gas sendout capacity of 1000 million standard cubic feet per day (MSCFD).

The Terminal will comprise the following primary components:

·      one jetty with a berth for LNG carriers;

·      initially up to two 180,000m3 full containment LNG storage tanks (for Phase I,) followed by one additional tank (for Phase II);

·      two in-tank LNG single stage centrifugal pumps for each tank, capable of delivering LNG at about 7 barg;

·      four High Pressure LNG Booster pumps including one spare for Phase I and three additional pumps for Phase II, to deliver at about 101 barg;

·      four including one spare (plus one additional for Phase II) open-rack seawater vaporisers.

The key features of the proposed LNG Terminal are depicted in the preliminary terminal layout diagram (See Figure 3.1 in Section 3). LNG is transferred by pumps under cryogenic conditions from the carrier to the tanks, where it is stored at near atmospheric pressure. LNG from the tanks is pumped to the vaporisers where the cryogenic LNG is converted into gas phase and the temperature raised to 5 °C for sendout to the adjoining power station.

Figure 13.3 shows a schematic of the overall process in an LNG terminal. A more detailed Process Flow Diagram for the Terminal, including details on the design features and the operating philosophy are included in Annex 13A1. Further details of safety features and the Safety Management System are provided in Annex 13B.

Figure 13.3     Process Overview

 

13.3.2                            Land Use in the Vicinity

The current land use within a 2km radius of the proposed site at Black Point includes Government Land for Temporary Use and the power station at Black Point. Further from the site, there is Lung Kwu Tan village at about 3km. Castle Peak Power Station and the neighbouring industrial sites lie about 4km to the south.

13.3.3                            Population Data

According to data provided by Planning Department, Lung Kwu Sheung Tan and the government land allocated for temporary use are the only areas assumed to hold population within 2km radius of the Black Point site [1]. The population in these areas was taken to be 100 persons for both years 2011 and 2021.

Lung Kwu Tan village is situation 3km form the site and has a population of 753, predicted to rise to 1,297 by the year 2021. To the north lies Ha Pak Nai village with a population of 216.

Marine population in the vicinity has been considered based on the marine traffic data provided by BMT [2]; approximately 3-5 person/km2 is estimated in the vicinity of Black Point.

Further details on land use adjoining the proposed site, as well as the land and marine population surrounding Black Point, are presented in Annex 13A2.

13.3.4                            Weather Data

Weather data for the Black Point site is based on data from Sha Chau weather station which is the closest and most relevant. Details are presented in Annex 13A3.

13.4                                  Hazard Identification

Hazards associated with the LNG terminal have been identified based on a detailed review of known incident records worldwide and experience gained from operations at similar facilities. In addition, a systematic Hazard Identification (HAZID) process was undertaken to identify any local or site specific factors.

13.4.1                            Hazards from LNG

LNG is an extremely cold, non-toxic, non-corrosive and flammable substance. As LNG is released from a temperature-controlled container, it will likely contact warm surfaces and air that transfer heat into the liquid. The heat input begins to vaporise some of the liquid, returning the liquid to the gaseous phase. The relative proportions of liquid and gaseous phases immediately following a release depend on the release conditions. The liquid phase will form an LNG pool on the ground which will begin to “boil”, due to heat input from the surrounding environment.

Immediately following vaporisation, the gas is colder and heavier than the surrounding air and forms a vapour cloud. As the gas disperses, it mixes with the surrounding air and warms up. The vapour cloud will only ignite if it encounters an ignition source while concentrated within its flammability range.

Downstream of the vaporisers the natural gas will be in the gas phase. A release from this piping and equipment will result in a gaseous phase release directly.

13.4.2                            Hazard Effects

In the event of an accidental release of LNG from piping or equipment, the characteristics of the possible hazardous effects are described below.

Pool Fire

A pool fire occurs when a flammable liquid is spilt onto the ground and ignited. A pool formed from the release of liquid LNG will initially spread due to the gravitational and surface tension forces acting on it. As the pool spreads, it will absorb heat from its surroundings causing evaporation from the pool surface. Ignition of this vapour leads to a pool fire.

Jet Fire

Jet fires result from ignited releases of pressurised flammable gas or superheated/pressurised liquid. The momentum of the release carries the materials forwards in a long plume entraining air to give a flammable mixture. Jet fires only occur where the LNG is being handled under pressure or when handled in gas phase and the release is unobstructed.

Flash Fire

Following an LNG release, a large proportion of the liquid will evaporate immediately to form a cloud of methane, initially located around the release point. If this cloud is not ignited immediately, it will move with the wind and be diluted as a result of air entrainment. Similarly, a gas release may not be ignited immediately and will disperse in the air.

The dispersing vapour cloud may subsequently come in contact with an ignition source and burn rapidly with a sudden flash. If the source of material which created the cloud is still present, then the fire will flash back to the source giving a pool fire, or if under pressure, a jet fire. Direct contact with the burning vapours may cause fatalities but the short duration of the flash fire means that thermal radiation effects are not significant outside the cloud and thus no fatalities are expected outside of the flash fire envelope.

Vapour Cloud Explosion

A flash fire is the most likely outcome upon ignition of a dispersing vapour cloud from an LNG release. If ignited in open (unconfined) areas, pure methane is not known to generate damaging overpressures (explode). However, if the gas is ignited in areas where there is significant degree of confinement and congestion, such as the process areas, an explosion may result.

Fireball

Immediate ignition of releases caused by a rupture in a gas piping may give rise to a fireball upon ignition. Fireballs have very high thermal radiation, similar to jet fires although the duration of the event is short.

To summarise, a liquid phase release may result in a flash fire, vapour cloud explosion, pool fire or jet fire. A gas phase release can result in a flash fire, fireball or jet fire.

13.4.3                            Review of Industry Incidents

A review of industry incidents at LNG terminal facilities was carried out. Incident records over the last few decades show small LNG vapour releases and minor fires with impact limited to within the plant boundary. These were associated with leaks from valves and process equipment. There have been no instances of leaks to the environment from full containment tanks. There have been no injuries or fatalities recorded outside the plant boundary since 1944. Other incidents have occurred during the construction and repair of LNG facilities but no LNG was directly involved.

In general LNG facilities have shown an exceptionally high safety record due to the high level of safety features incorporated in an LNG terminal design including the use of full containment tanks and emergency shutdown systems.

13.4.4                            HAZID Study

A Hazard Identification (HAZID) Study was conducted in October 2005 involving representatives from the Project Proponent: CLP and ExxonMobil and their expert consultants: ARUP, Foster Wheeler and ERM. The potential hazards posed by the facility were identified based on the HAZID team’s expert opinion, past accidents, lessons learnt and checklists. The details of the HAZID study can be found in Annex 13A4.

A systematic approach was adopted, whereby the facility was divided into a number of “subsystems” based on the layout and the process; guidewords from the checklist (see Annex 13A4) were then applied to each subsystem as relevant.

 

The Study considered each area of the LNG Terminal and identified any potential hazards that apply to it. The study output served as a basis for identification of scenarios for the QRA study.

13.4.5                            Scenarios for QRA Study

Scenarios for the QRA study were identified based on the HAZID Study as well as a review of incident records. Loss of containment events have been identified for each section of the terminal, corresponding to the relevant process conditions, as listed in Table 13.1.

A detailed discussion on the hazards, particularly in relation to the LNG storage tanks, is given in Annex 13A5.

 

Table 13.1      Scenarios for QRA Study

Plant Section

Initiating Event

Potential Outcome Scenario

Jetty Area

      Unloading arm

      Piping & equipment at the jetty

Leak, rupture

Pool fire/Jet fire, Vapour dispersion/ Flash fire

Transfer Piping on Trestle

      Piping

Leak, rupture

Pool fire/Jet fire, Vapour dispersion/ Flash fire

Tank Area

      Piping on tank roof

 

      Storage Tank

 

 

Leak, rupture

 

Rupture

 

Pool fire/Jet fire, Vapour dispersion/ Flash fire

Pool fire, Vapour dispersion/ Flash fire

Process Area (HP Pumps, Recondenser, Vaporisers)

      Piping/equipment

Leak, rupture

Pool fire/Jet fire, Vapour dispersion/ Flash fire/Vapour cloud explosion

Process Area (Compressors)

      Piping/equipment

Leak, rupture

Jet fire, Gas dispersion/Flash fire, Fireball

Sendout Piping

Leak, rupture

Jet fire, Gas dispersion/ Flash fire, Fireball

 

13.5                                  Frequency Analysis

This includes an assessment of the likelihood or the frequency of events resulting in a hydrocarbon release from piping and equipment and the subsequent potential outcomes such as fires. Details of the frequency analysis are provided in Annex 13A6.

Release frequencies have been derived from generic data on loss of containment events. Reference has been made to a number of sources. A summary is presented in Table 13.2. Release scenarios include a range of hole sizes from small leaks to catastrophic rupture.

The frequency of various outcomes following a loss of containment event is estimated using an event tree model. The various outcomes considered include pool fire, jet fire, flash fire and vapour cloud explosions for liquid releases, jet fire and flash fire for continuous gas releases and fireball and flash fire for instantaneous gas releases.

 


Table 13.2      LNG Release Event Frequencies

Equipment

Release Scenario

Release Phase

Release Frequency

Unit

Reference

Process Vessels

i) 10 & 25mm hole

Liquid

1.00E-05

per year

Crossthwaite et al [3]

 

ii) 50 & 100mm hole

Liquid

5.00E-06

per year

Crossthwaite et al

 

iii) Full bore rupture

 

Liquid

1.00E-06

per year

Crossthwaite et al

Pumps

i) Leak

Liquid

1.00E-04

per year

COVO Study [4]

 

ii) Full bore rupture

 

Liquid

1.00E-05

per year

COVO Study

Unloading Arm

i) Leak

Liquid/ Gas

4.05E-03

per year

COVO Study

 

ii) Full bore rupture

Liquid/ Gas

 

4.05E-05

per year

COVO Study

Pipe size 600mm to 750mm

i) 10 & 25mm hole

Liquid/ Gas

1.00E-07

per meter per year

Hawksley [5]

 

ii) 50 & 100mm hole

Liquid/ Gas

7.00E-08

per meter per year

Hawksley

 

iii) Full bore rupture

Liquid/ Gas

 

3.00E-08

per meter per year

Hawksley

Pipe size 150mm to 500mm

i) 10 & 25mm hole

Liquid/ Gas

3.00E-07

per meter per year

Hawksley

 

ii) 50 & 100mm hole

Liquid/ Gas

1.00E-07

per meter per year

Hawksley

 

iii) Full bore rupture

Liquid/ Gas

5.00E-08

per meter per year

Hawksley

LNG Storage Tank

i) Rupture

Liquid

1.00E-08

per tank-year

“Purple Book” [6]

13.6                                  Consequence Analysis

This section gives a brief summary of the approach adopted to model the consequences of an LNG/natural gas release. Details are given in Annex 13A7.

A range of hole sizes from small leaks to full bore ruptures is considered in the analysis. Discharge rates, dispersion modelling, pool fire modelling, jet fire modelling, fire ball modelling and vapour cloud explosion modelling are considered and are all performed using the PHAST suite of models.

The plant was divided into twenty three isolatable process sections based on the provision of emergency shutdown valves. Physical properties of the fluid (pressure, temperature, density, phase) and equipment dimensions (pipe diameter and length) for each section were applied from the heat and mass balances to estimate the maximum release rate and the inventory in each section.

Fire radiation contours are calculated to 7.3, 14.4, 20.9 and 35.5 kW/m2, and the fatality to people within each contour calculated. Overpressure effects from vapour cloud explosions are calculated to 5psi and 2psi contours. Dispersion of vapour clouds is determined to 0.85 of the lower flammability limit. A range of weather conditions is also considered, to represent a full year of conditions that occur within Hong Kong. Details of the consequence modelling and the results obtained are given in Annex 13A7.

13.7                                  Risk Results

13.7.1                            Individual Risk Results

The individual risk (IR) contours associated with the LNG terminal are shown in Figure 13.4. The maximum off-site risk is less than 1 x 10-5 per year at the site boundary, hence meets the HKRG requirements.

 

Figure 13.4     Individual Risk Contours

13.7.2                            Societal Risk Result

The societal risk for the Black Point site has been estimated based on the land and marine population in the area. Three cases are considered: year 2011, year 2021 “no Tonggu” and year 2021 “with Tonggu”. The potential development of the Tonggu Waterway will reduce the marine traffic along Urmston Road so this possibility was considered in the analysis.

The societal risk results for the onshore terminal facilities have been combined with the risk results for the LNG carrier during berthing manoeuvres within 500m of the jetty to produce the overall societal risk results (Figures 13.5-13.7). The results for the berthing manoeuvres are taken from the Marine Quantitative Risk Assessment (MQRA).

The FN Curve for the 2011 case is shown in Figure 13.5. Most of the points on the curve arise from scenarios involving the catastrophic failure of the LNG storage tanks, which is a very low frequency event. Because of limitations in the modelling, these results are likely conservative. For example, the model is unable to allow for the restrictions in the pool spreading from the coastline and other obstructions. The models simple assume an unconfined isotropic spreading on water. Hence, the model predicts a spreading of the LNG pool towards land populations which is not possible in reality. In any case, Figure 13.5 demonstrates that the risks are well within the acceptable region as per HK EIA Ordinance.

The risks from the carrier berthing manoeuvres within 500m of the jetty are small compared to the risks from the terminal and make negligible contribution to the combined risk.

Compared to 2011, the risks in 2021 (Figures 13.6 and 13.7) are marginally higher, in line with the increase in marine traffic.

The FN curves for 2021 “No Tonggu” (Figure 13.6) and 2021 “With Tonggu” (Figure 13.7) are essentially very similar. The development of the Tonggu Waterway is not predicted to have any effect on the marine population but does affect the collision frequency with the LNG carrier. There are small changes in the carrier manoeuvring risks as a result of this but since this 500m marine risk is small compared to risks from the terminal, there is no discernable difference in the overall risks.

Also shown in the figures are results for large (215,000m3) and small (145,000m3) carriers. If LNG is delivered from smaller carriers, the number of transfers required per year will be higher. The frequency of possible releases therefore increases, but the consequences would be less severe. Again, this only affects the berthing risks and there is negligible difference in the overall risks for large and small carriers.

The risks for all cases are well within the Acceptable Region as per HK EIAO.

The Potential Loss of Life (PLL), or equivalent fatalities per year, are given in Table 13.3. The total PLL for the whole terminal is very low at 6.1 x 10-6 per year, or equivalently, one fatality every 163,000 years.

Table 13.3      Main Contributors to Potential Loss of Life

Section

2011

2021

 

 

PLL

%

PLL

%

L02

T2

T1

T3

L05

L01

G07

 

L03

L06

P20

Liquid unloading arm

LNG tank 2

LNG tank 1

LNG tank 3

Liquid unloading line from shore to tank

Liquid piping from tank to HP pump

Sendout piping from metering station to battery limit

Liquid unloading line from jetty to shore

Recondenser

In-tank pump discharge piping

1.21 x 10-6

9.53 x 10-7

9.43 x 10-7

9.18 x 10-7

7.47 x 10-7

6.53 x 10-7

2.94 x 10-7

 

1.30 x 10-7

7.21 x 10-8

4.5 x 10-8

19.8

15.6

15.4

15.0

12.2

10.7

4.8

 

2.1

1.2

0.7

1.33 x 10-6

1.04 x 10-6

1.02 x 10-6

9.93 x 10-7

8.26 x 10-7

7.20 x 10-7

3.25 x 10-7

 

1.43 x 10-7

7.91 x 10-8

5.05 x 10-8

19.9

15.5

15.3

14.9

12.4

10.8

4.9

 

2.1

1.2

0.8

 

Total

6.11 x 10-6

 

6.68 x 10-6

 

 

 

Figure 13.5     FN Curve for 2011

 

Figure 13.6     FN Curve for 2021 "No Tonggu"

 

Figure 13.7     FN Curve for 2021 "With Tonggu"

13.8                                  Risk from Existing Power Plant

As described in Section 13.3, the proposed LNG Terminal at Black Point will be located adjacent to the existing Black Point Power Station (BPPS). The BPPS is itself classified a Notifiable Gas Installation (NGI) and hence was the subject of a Quantitative Risk Assessment (QRA) prior to commencing operation. This section discusses BPPS and the risks from the site.

13.8.1                            BPPS Description

The BPPS is a gas-fired power plant. The plant receives gas via a subsea pipeline from an offshore platform to a gas receiving station within the premises. The gas receiving station includes:

·       Emergency shutdown valves

·       Pig receiver

·       Slug catcher

·       Heaters

·       Filters

·       Pressure reducing assembly

·       Metering facilities

Gas from the receiving station is fed directly to the power station. The power station includes the following gas holding equipment:

·       Filter separators

·       Fuel gas modules

·       Turbines

13.8.2                            BPPS QRA Study

The BPPS QRA study was conducted by DNV in 1994. The study considered the gas receiving station and power station separately.

The hazards identified in the QRA study at both the receiving station and power station were fire hazards due to a loss of containment of hydrocarbon gas. The study evaluated the scenarios including jet fires, flash fires and vapour cloud explosions following a gas release.

The gas receiving station QRA performed a quantitative analysis considering gas leaks. The analysis considered small, medium, large and full bore ruptures of the major equipment items.

The power station QRA considered small, medium, large and full bore ruptures of the major equipment items. Risks to the offsite populations were evaluated.

13.8.3                            Risk Levels due to BPPS

The BPPS QRA reports show no offsite risk posed by the BPPS.

13.8.4                            Offsite Risk Levels Including BPPS

As the BPPS QRA reports there are no offsite risk posed by the BPPS, the total offsite risk in the vicinity of the LNG Terminal is not affected by BPPS. The results of this study therefore present the total offsite risk posed by the power station/LNG Terminal complex.

Based on the above discussion, the combined risk for the existing Black Point Power Station and the proposed LNG terminal is within the Acceptable Region as per HK EIAO.

13.9                                  Conclusions of QRA Study for Terminal

The results indicate that the societal risks from the proposed facility are within the Acceptable Region of the HK EIAO. The individual risks also meet the requirements of the HKRG.

 

 

References

[1]     Projected Hong Kong Resident Population by TPU, Planning Department, Hong Kong SAR, 2004.

[2]      Marine Impact Assessment for Black Point & Sokos islands LNG Receiving Terminal & Associated Facilities, Pipeline Issues, Working Paper #3, Issue 6, BMT Asia Pacific Ltd, May 2006.

[3]     Crossthwaite, P.J., Fitzpatrick, R.D. & Hurst, N.W., Risk Assessment for the Siting of Developments Near Liquefied Petroleum Gas Installations, IChemE Symposium Series No 110, 1988.

[4]     Rijnmond Public Authority, A Risk Analysis of Six Potentially Hazardous Industrial Objects in the Rijnmond Area – A Pilot Study, COVO, D. Reidel Publishing Co., Dordrecht,1982.

[5]     Hawksley, J.L., Some Social, Technical and Economic Aspects of the Risks of Large Plants, CHEMRAWN III, 1984

[6]     Committee for the Prevention of Disasters, Guidelines for Quantitative Risk Assessment – Purple Book, 1st Edition, 1999.

 

 


Sub-Section 3: Black Point and South Soko LNG Terminal Marine Quantitative Risk Assessment