1                                            Terminal Design and Operating Details

This section describes briefly the facilities at the LNG terminal.

1.1                                      Marine Facilities

Jetty Structure

A jetty trestle structure, with a berth to moor the carriers. The trestle will be of steel construction with a concrete deck, abutted to a footing of rock. A typical steel trestle jetty is shown in Figure 1.1.

The pier, jetty head and ‘dolphins’ at the berth, will have steel piles founded in the seabed approximately 50m apart. On the jetty head, articulated piping (unloading arms) will be installed to connect the carrier to the piping of the onshore Terminal. The unloading arms are designed with an operating envelope that allows for prescribed carrier movement due to environmental factors while the arms are connected.

Figure 1.1       Typical Steel Trestle Jetty with Berthed Vessel

1.2                                      LNG Storage Tanks

Three LNG storage tanks, each of capacity up to 180,000 m3 will be built.

The tank design will adopt the principle of full containment, with all tank connections made through the roof to maximize mechanical strength and integrity. The double wall construction will comprise an inner wall of low temperature steel and an outer wall of pre-stressed concrete. Full containment tanks provide higher safety standards compared to single containment tanks in view of the intrinsic robustness of the concrete outer structure.

The inner steel container will hold the LNG at -162°C. Cryogenic steels will be used (such as 9% Ni), which can withstand these very low temperatures. The outer concrete wall will include a reinforced concrete bottom slab and roof. The wall will be designed to withstand the cryogenic temperatures involved, ie it will contain any leak from the inner tank. Insulation materials will be applied to the space between the steel inner container and the outer concrete tank to minimise the transfer of heat from the environment to the bulk LNG.  There will inevitably be some ‘boil-off’ of the LNG stored within the tank and this will be compressed and fed into the send out system (see Section 1.4).

Internal tank piping will be designed to enable bottom or top filling without the need to install any connections through the tank wall below the liquid level. Special attention will be given to the instrumentation on the storage tanks. Alarm and shutdown devices will be incorporated in the design to ensure safe tank operation. These alarms and shutdown devices will be sequenced to conform to the requirements of the operating philosophy and the safety failure mode analysis. Tanks will also be provided with pressure relief safety valves with a set of pressure and vacuum breaker relief valves.

Temperature and density measuring devices along the height of the tank will be provided as a mean to help detect stratification (formation of layers of LNG with different densities) and avoid tank rollover. Automatic, continuous level measurement will be provided for the storage tanks. A typical LNG storage tank is shown in Figure 1.2.

The tank design pressure will be 290 millibars (mbar), with all tanks intended to simultaneously send out and to receive LNG discharged by the LNG carrier. The LNG storage tanks will be fitted with pressure-control valves (PCVs), which will prevent excess vapour from accumulating in the tanks.

 

Figure 1.2       Typical LNG Storage Tank

1.3                                      Boil-off Gas (BOG) Handling System

Gas Compressors

Boil-off gases (BOGs) produced during normal Terminal operations as a result of inevitable heat transfer from the atmosphere to the storage tanks and piping as well as those arising from ship unloading operations, will be sent to the BOG compressor and re-condenser for condensing (liquefying) and re‑inclusion into the LNG bulk product stream.

Vent System

The vent system is designed for emergency venting. The vent will not be used under normal operations. 

1.4                                      Sendout Pumps

Because of the high pressures involved, two stages of sendout pumps are required.

First Stage LNG Sendout Pumps

Electrically driven high-capacity (first stage) LNG sendout pumps will be installed in each LNG storage tank. These pumps operate fully submerged in LNG and are located within pump wells, allowing for easy pump removal, maintenance and installation. The pump wells also serve as the discharge piping from the pumps and are connected to the tank-top piping.

LNG from the in-tank pumps is routed directly to the re-condenser. All boil-off vapours during normal sendout or during carrier unloading are routed to this drum, mixed with the LNG, and re-condensed into the bulk LNG fluid. The re-condenser houses a packed bed of stainless‑steel pall rings (or equivalent), which creates additional surface area for vapour-liquid contact.

Second Stage LNG Sendout Pumps

LNG from the re-condenser on level control is directed to the second stage sendout pumps. The second stage sendout pumps are high‑pressure pumps, delivering LNG to the LNG Vaporisers (see Section 1.5) at a pressure of 75 to 80 bar (which could be increased to 100 bar).

1.5                                      LNG Vaporisers

Stored LNG will need to be re-gasified in order for it to be conveyed along the gas transportation pipework. This will be accomplished via LNG Vaporisers, which will either utilise piped seawater (in open-rack vaporisers) or hot combustion gases (in submerged combustion vaporisers) to raise the temperature of the LNG to ambient temperature, thereby causing it to re‑gasify.

·      Open Rack Vaporisers. In open-rack vaporisers (ORVs) seawater flows over aluminium heat exchange panels that contain tubes through which the LNG flows. The seawater falls over the panels to a trough below and is then discharged back to the sea. A typical vaporiser used for LNG Terminals is shown in Figure 1.3.

·      Submerged Combined Vaporisers. Submerged Combustion Vaporisers (SCVs) involve burning off a small amount of gas and using the heat of combustion to maintain the temperature of a water bath. The cold LNG passes through coils within the bath and gets vaporised. 

 

Figure 1.3       Typical Open Rack Vaporiser

1.6                                      Gas Transportation

The gas leaving the LNG Vaporiser will be routed to the sendout gas pipework.

1.7                                      Protective Systems

Fire water

A closed-loop fire water system will be provided to protect the LNG Terminal equipment, utilities, storage and unloading areas. The system will include main pumps and a standby mobile pump, along with hydrants and monitors. Fire water will also be provided to protect the berth.

Security

Security will be designed to prevent unauthorised access and to ensure the safety and integrity of the facilities. The site will be provided with a perimeter fence.

1.8                                      Utilities and Ancillary Facilities

Nitrogen

Nitrogen in the gaseous form will be required at the LNG Terminal for purging of equipment during maintenance as well as during start-up. A facility for onsite nitrogen generation through PSA process or air separation unit will be provided. Details will be finalised during detailed design.

Power

For the Black Point site, power will be supplied from the adjoining power generation plant.

Water

Service and drinking water tanks will be required. Maximum 80m3/hr service water will be required for startup or shutdown operation. Seawater will be used for general washdown purposes.

Sewerage

Sewage will be treated onsite in a packaged plant compliant with relevant local regulations.

Communications

Arrangements will be made for provision of telephone and emergency communications. 

Fuel and Materials Storage

Diesel will be stored on-site in a permanent fuel tank. Diesel will serve as fuel for the emergency generator. Diesel will be transported to site by trucks.

Plant and Instrument Air

Atmospheric air will be compressed by centrifugal compressors (each driven by electric motors) and dried for use as both plant and instrument air.

Plant Buildings

The following permanent buildings will be provided on site for the operational phase:

·       administration building;

·       control room;

·       workshop and store room; and

·       gatehouse.

1.9                                      Site Access

Road for Site access will be provided.

1.10                                  Process Flow Diagram

Detailed process flow diagram of the LNG terminal is shown in Figure 1.4, with details of the process streams indicated.

Figure 1.4       Detailed Process Flow Diagram for Black Point LNG Terminal


 

2                                            Operation and Maintenance of the LNG Terminal Facilities

2.1                                      Commissioning

Upon completion of all control systems testing, the units will be purged of oxygen using nitrogen as the displacement gas. Various Terminal units will then be checked for pressure leaks by pressurising and depressurising over an approximate three-day period. The Terminal will then begin cooldown operations using LNG. In this process, a small continuous flow of LNG will accumulate in the tanks displacing the inert nitrogen to the atmosphere via a vent. The cooldown will continue with LNG being introduced gradually to the piping and other equipment.

2.2                                      Operational Summary

Overview

The facilities that comprise the LNG Terminal are described above. Operation of the Terminal facilities will include the following significant process operations:

·       LNG carrier approach, berthing and departure;

·       LNG unloading from carriers at the marine facility and transfer to shore;

·       LNG storage in onshore storage tanks;

·       Re-gasification of the LNG to natural gas in LNG vaporisers; and

·       Final sendout of natural gas.

2.2.2                                LNG Carrier Approach

In the final segment of the approach fairway, tugboats will assist in controlling the heading and speed of the carrier while entering into and manoeuvring within the turning circle as well as for the final approach towards the jetty.   The tugboats will continue to assist until the mooring operation has been completed. The number and bollard pull of tugboats for such operations will be based on the findings of a simulation study for the safe manoeuvring of the LNG carrier.

LNG will be pumped from the storage tanks of the LNG carriers, through unloading arms on the jetty, to the storage tanks onshore via insulated unloading lines.

2.2.3                                Unloading Operations

It will take approximately 18 hrs to unload an LNG carrier. During cargo discharge the vapour pressure in the LNGC cargo tanks will be maintained by returning vapour from the shore. With this balanced system, under normal circumstances, no hydrocarbons will be released to the atmosphere from ship or shore. Unloading rates vary between 12,000 and 14,000 m3 per hour depending on the size of the carrier.

Before disconnecting the unloading arms, remaining liquid will be drained and the arms purged with Nitrogen. The onshore liquid pipework will be left full and a minor circulation maintained to hold the temperature at approximately -162ºC. This is required to avoid thermal cycling of the piping.

Ballasting operations (i.e. taking on seawater to compensate for the unloaded mass of LNG) will be concurrent with the LNG unloading. Under normal circumstances, the LNG carrier will leave the berth approximately 24 hours after arrival. This includes allowances for the pre-cooling operations, arrival cargo measurements, unloading operations, cargo measurements on completion of discharge and nitrogen displacement of unloading arms prior to disconnection.

To minimise the potential for LNG spillage, the carrier and shore Emergency Shut Down (ESD) systems will be interlinked such that an unusual event on either will automatically activate a transfer system shutdown (ESD I) and in a severe case will also disconnect the unloading arms (ESD II). An ESD I test will be completed before the start of unloading operations. In the event of an ESD II unloading arm disconnection, LNG spillage would be very small due to the activation of isolation valves on either side of the Emergency Release coupler. 

Before and during LNG transfer operations, a safety zone of approximately 250m around the LNG carrier will be maintained.

2.2.4                                Onshore Modes of Operation

The LNG Terminal will operate in two main modes of operation:

·      Unloading Mode – The unloading mode is the period when an LNG carrier is moored to the jetty and is connected via the unloading arms and the jetty piping to the onshore storage tank. The pumps on the LNG carrier will transfer the LNG in both the unloading and the re-circulation lines to the onshore storage tanks. At the end of unloading, pressurised nitrogen gas will be used to purge the arms of LNG before disconnecting.

·      Holding Mode – The holding mode is the period when no unloading takes place. During the holding mode, cryogenic conditions will be maintained in the unloading line by circulating LNG to the jetty head and back to the onshore storage tanks or the sendout system via a dedicated re-circulation line. 

During both of these modes of operation, sendout of LNG to BBPS will continue.

2.3                                      Utilities

Utilities required during the operation of the Terminal facilities are summarised in Table 2.1.

Table 2.1        Utilities

Material

Use

Handling and Transport

Storage quantity

Diesel

 

Operation (for emergency generator)

Truck

20 m3

Liquified nitrogen

 

Maintenance (purging)

Drum to be filled via truck (or ro-ro ferry) every 2 weeks

25 m3

Hydrochloric acid 30% HCl

 

Maintenance; neutralise using caustic and flush to ocean

Aboveground storage on a skid

200 L

Caustic soda 10% NaOH

 

To neutralize the acid from maintenance of the electro-chlorination units

Drum

2 m3

Raw water

 

Fire fighting and for service

Pump

1,500 m3

Seawater

 

Vaporisers

Pump

 

Electricity

 

132 kV or 111 kV