2                                            comparison of Black Point terminal alternatives

The following section presents a comparison of the alternatives for the Black Point terminal.  The section has been divided into a discussion of the following:

·       Consideration of Different Layouts and Design Options; and

·       Consideration of Alternative Construction Methods.

Based on the above considerations, the Environmental Impact Assessment (EIA) of the preferred Black Point terminal scenario is presented in subsequent sections.

2.1                                      Consideration of Different Layouts and Design Options

In accordance with Clause 3.6.4 of the EIA Study Brief (ESB-126/2005), this section presents considerations of the different layouts and design options that have been assessed as part of the overall assessment of alternatives for the Black Point terminal.  The methodology, criteria and findings are presented.

The assessment was conducted to investigate the environmental considerations of each layout and design option and to examine the engineering aspects for each.  The assessment thus considers both the difficulties of the construction and operation of each facility as well as the associated potential environmental impacts.

2.1.1                                Layout Options

The basic requirements of a LNG receiving terminal in Hong Kong have been described in detail in Part 1 - Section 3.  Justifications for Black Point being considered as one of two sites for a LNG receiving terminal in Hong Kong have been presented in Part 1 – Section 4. 

Several terminal layout options on Black Point have been considered.  As there is limited flat land at Black Point to accommodate the necessary infrastructure, the method of providing sufficient land, either by reclamation or excavation of the existing headland has been considered.  In addition, due to the outline of the coastline, there are options for locating the LNG carrier berth.  These provide differences in dredging requirements but similar approach and berthing issues.

Three layouts have been selected for further assessment in order to provide a comprehensive assessment of different layouts and design options.  The layouts present, as best possible, a wide range of engineering options and subsequent environmental considerations for the construction and operation of the Black Point terminal.  Each of the layouts has been prepared so that the distances between the facilities within the LNG terminal show broad compliance with EN1473.  The three layouts are presented below in terms of the general design and construction methods.

Option 1 – Base Case

Layout Option 1 - Base Case is derived from a combination of reclamation and excavation (Figure 2.1).  The purpose of this combination is to maintain a balance between the cut and fill quantities, and to create cost effective and sustainable site formation.  The area of excavation for the site is limited to provide sufficient land area initially for two tanks to enable them to be founded directly on rock which will permit the use of pad/raft foundations thus negating the need for deep foundations.  The steep rock face behind will also screen the two tanks from any visual sensitive receivers.  A platform at a level of +6mPD will be formed by excavation into the existing hillside.  Land will be reclaimed immediately to the northwest of the Black Point headland to accommodate the third tank and the terminal facilities.

The LNG carrier jetty will be located to the northwest of the reclaimed land.  Although the jetty is close to the Urmston Road fairway, the presence of the headland provides protection from contact by passing traffic.  It also has the advantage that the main components of the facility are screened from the public by the ridgeline of the Black Point headland.

Option 2 – Full Reclamation

Layout Option 2 - Full Reclamation is derived such that no excavation is undertaken in the Black Point peninsula (Figure 2.2).  All the land needed for the three LNG tanks and terminal facilities will be provided by reclamation at the end of the Black Point peninsula.  The platform level will be at +6mPD.  The tanks will be located nearer to the existing hillside as the rock head is shallower which facilitates foundation construction.  As in Option 1, the LNG carrier jetty will be located to the northwest of the reclaimed land. 

Option 3 – Full Excavation

Layout Option 3 - Full Excavation would require no reclamation into the sea such that the required land is generated by excavation only into the Black Point headland.  In order to create a platform of sufficient area at a level of +6mPD to house the three tanks and all the terminal facilities a cutting up to 30m in height will be required.  By cutting into the headland the facility is expected to be more visible from views to the south.

The LNG carrier jetty will be located to the west of the Black Point site. 

Engineering Works Criteria

In order to satisfy each of the terminal requirements described in Part 1 - Section 3, it is necessary to undertake site formation, dredging and reclamation works at each of the layout options at Black Point.  A summary of the key engineering works criteria for each layout option are summarised in Table 2.1.

Table 12.1      Summary of Engineering Works Criteria (based on conceptual indicative site layouts)

Engineering Criteria

Option 1

(Base Case)

Option 2

(Full Reclamation)

Option 3

(Full Excavation)

Site Area (ha)

 

32.0

31.5

35.0

Volume of Dredging for Reclamation (106m³)

 

0.63

0.65

0

Volume of Dredging for Approach Channel & Turning Basin (106m³)

 

2.49

2.49

1.40

Volume of Excavation Disposed (106m³)

 

0

0

14

Volume of Fill Imported (106m³)

 

1.90

3.43

0

Length of Natural Coastline Affected (m)

 

600

580

0

Length of Seawall (m)

 

1,120

1,160

0

Length of Trestle (m)

 

100

100

180

The layouts described above have been considered in terms of a technical comparison and assessment of the engineering works followed by a comparison of the potential for environmental impacts through construction and operation.  Each of these assessments is presented below, followed by a summary of the overall findings.  On the basis of these assessments, the preferred layout and design option for the Black Point terminal is identified.

2.1.2                                Engineering Assessment

Overall Engineering Assessment Criteria

The key engineering assessment criteria have been established to enable a quantitative comparison of the three layout options to be scored and ranked in accordance with their relative merits and demerits.  As each of these assessment criteria do not have an equivalent impact on the overall construction of the terminal facility, a relative importance factor has been applied to each as shown in Table 2.2.


Table 21.2      Overall Engineering Assessment Criteria

Engineering Assessment Criterion

Relative Importance Factor

Construction of site formation works

0.30

Construction of site reclamation works

0.30

Construction of approach channel and turning basin

0.20

Marine navigation

0.10

Construction of facility foundations

0.10

Total

1.00

The rationale for the relative importance factor is given below.

·      It was considered logical for the sum of the relative importance factors to add up to unity.  In this manner each relative importance factor also directly represents the percentage importance to the whole process.

·      The major engineering works for each of the layout options is considered to be the construction of the site formation and reclamation.  These assessment criterions are, therefore, given an equally high relative importance factor of 30% each.

·      The next major engineering works for the layout options is the construction of the approach channel and turning basin.  This assessment criterion is, therefore, assigned a reasonable importance factor of 20%.

·      Black Point is located adjacent to the existing traffic fairway that will be used for construction boats and barges for the import and export of materials to the site.  Similarly marine craft will be employed for the dredging of the approach channel.  The larger the reclamation area, the greater encroachment into the existing waterway north of the jetty for the turning basin.  Since the approach to the site will be relatively similar for each of the layout options, a relatively low importance factor of 10% is, therefore, assigned to this criterion.

·      The construction of the facility foundations and the receiving terminal facility itself will generally employ conventional construction techniques which will be generally similar to all sites with minor differences resulting from accessibility and specific location constraints.  A relatively low weighting of 10% is, therefore, applied to the importance factor for these criteria.

Parameters for Each Engineering Assessment Criterion

In order to make a quantitative assessment of the relative advantages and disadvantages of each layout for each of the engineering assessment criterion defined in Table 2.2, a set of engineering parameters reflecting the main tasks to be undertaken under each activity has been developed.  Each parameter carries a weighting to represent the relative significance and impact on the overall engineering assessment criterion.  It was considered logical for the sum of the relative weighting factors to add up to unity.  In this manner each relative weighting also directly represents the percentage importance to the whole process.  The parameters used in the evaluation of the sites for each engineering assessment criterion is detailed in Tables 2.3 to 2.7.

Construction of Site Formation Works

The engineering assessment criterion for site formation considers nine main parameters. 

Table 21.3      Engineering Assessment Parameters Used for Construction of Site Formation Works

Engineering Assessment Criterion

Parameter

Relative Weighting

Construction of site formation works

Volume of excavation in soil

0.05

Volume of excavation in rock

0.25

Volume of soil to be disposed of

0.20

Volume of rock to be disposed of

0.05

Impact on construction programme

0.10

Slope stabilisation measures required

0.10

Slope maintenance

0.05

Future slope hazard

0.05

Blasting risks

0.15

Total

1.00

The rationale for the selection of each relative weighting factor in Table 2.3 is given below.

·      The most difficult and time consuming activity is usually the excavation of rock material which generally comprises very good quality granite material.  The excavation of this material will require significant effort using blasting and heavy mechanical equipment for which stringent engineering controls will be required.  The excavation works are also generally intimately linked with the construction of the storage tanks, which have a long construction time and are therefore critical path activities.  As such, the rock excavation has a significant impact on the programme.  The highest weighting of 25% is, therefore, assigned to this parameter.

·      The excavation of soil is a relatively easy and quick task utilising mechanical equipment and, therefore, only a low weighting of 5% is assigned.  The volume of soil excavation is also generally small. 

·      The disposal of the soil material is given a high weighting of 20% as it will need to be taken to one of the Public Fill facilities, which should be avoided if possible.  High scores are, therefore, awarded to sites which limit disposal of soil and make the best use of the material which will be apparent with a high weighting.

·      The disposal of rock is given a low weighting of 5% as it will likely be reused for construction in Hong Kong.  The generation of such material is, therefore, not deemed to be as highly negative activity compared to soil.

·      As the site formation works impact directly on the construction programme a medium 10% weighting factor is considered appropriate to favour the sites which can be constructed in the shortest duration.

·      Blasting will need to comply with extensive and stringent regulation requirements. Incorporation of these measures will lengthen the construction programme; therefore, a medium level relative weighting of 15% is applied to these works to favour the sites that do not require blasting.

·      The slope stabilisation works associated with the facility will need to comply with the regulation requirements which are reasonably stringent and can be extensive for large slopes.  The amount of stabilisation works are, therefore, best reduced as far as possible.  A medium relative weighting factor of 10% is therefore applied to these works.

·      Slope maintenance and slope hazards are both events that will be under the control of the LNG facility during operation.  These can, therefore, be reasonably managed and as such a low weighting of 5% has been assigned to each.

Construction of Site Reclamation Works

The engineering assessment criterion for reclamation considers ten main parameters as shown in Table 2.4. 

Table 12.4      Engineering Assessment Parameters Used for Construction of Site Reclamation Works

Engineering Assessment Criterion

Parameter

Relative Weighting

Construction of site reclamation works

Area of reclamation

0.10

Volume of dredging material

0.20

Total volume of fill material required

0.05

Total volume of imported fill (sand + rock)

0.20

Length of natural coastline

0.15

Length of artificial coastline

0.05

Length of seawall required

0.10

Construction time for dredging and filling

0.05

Time for consolidation after construction

0.05

Need for ground improvement

0.05

Total

1.00

The rationale for the selection of each relative weighting factor is given below.

·      The most significant activities are the dredging of soft material beneath and the importation requirements for subsequent filling works.  For the latter case a lower amount of imported material is considered better as it indicates that a better balance is being made with the excavated materials from the site formation works.  A high weighting of 20% is, therefore, assigned to these parameters. 

·      As the volume of imported material has already been considered, the total volume of fill material required is less important if the majority is sourced from within the site, therefore, only a 5% weighting is assigned. 

·      The length of natural coastline affected by the reclamation is a measure of the extent of the engineering works on the natural areas of Hong Kong.  A 15% weighting is, therefore, assigned to this parameter.

·      The length of artificial coastline affected by the reclamation is considered to be less of an effect and a 5% weighting is, therefore, applied.

·      The length of seawall and the area of reclamation are indicators of the extent of the reclamation.  For these parameters a medium weighting of 10% is deemed appropriate.

·      The time for construction, time for consolidation and the need for ground improvement are important but less significant engineering issues.  A lower weighting of 5% is, therefore, assumed for these parameters.

Construction of Approach Channel and Turning Basin

The engineering assessment criterion for the construction of the approach channel and turning basin considers five main parameters as shown in Table 2.5.

Table 12.5      Engineering Assessment Parameters Used for Construction of Approach Channel and Turning Basin

Engineering Assessment Criterion

Parameter

Relative Weighting

Construction of approach channel and turning basin

Total length of approach channel + turning basin

0.20

Volume of dredging

0.35

Rock excavation in dredged zone

0.20

Impact on existing utilities

0.15

Siltation & maintenance dredging

0.10

Total

1.00

The rationale for the selection of each relative weighting factor is given below.

(i)   For approach channel and turning basin the most significant activity is the dredging works.  A high weighting of 35% is therefore assigned to this parameter.

(ii)  The length of the approach channel and the extent of rock excavation  will affects the programme and progress of the overall dredging works and are therefore each assigned a high to medium weighting of 20%.

(iii) The impact on existing utilities is considered to be localised and secondary effects on the overall dredging works and is therefore assigned a medium weighting of 15%.

The siltation/maintenance for the approach channels are factors that affects the long-term operation for which a low to medium weighting of 10% is considered appropriate.

Marine Navigation

The engineering assessment criterion for marine navigation considers four main parameters as shown in Table 2.6. 

Table 21.6      Engineering Parameters and Associated Relative Weighting Used for the Assessment of Marine Navigation

Engineering Assessment Criterion

Parameter

Relative Weighting

Marine navigation

Marine traffic

0.50

Grounding potential

0.10

Striking berth by LNG Carrier

0.10

Striking of the moored carrier by passing traffic

0.30

Total

1.00

The rationale for the selection of each relative weighting factor is given below:

·      Although historically, LNG carriers have had an excellent safety record, the main hazards are the potential for collision with the carrier while in transit to the jetty or from passing traffic striking the carrier while moored.  The probability for such occurrences and consequences will be dependent upon traffic density and discipline of shipboard personnel complying with underway regulations.  As these are the main considerations a weighting of 0.5 and 0.3 are awarded for Marine Traffic and the striking of the moored carrier by passing traffic respectively.

·      The consequence of grounding and striking of the marine berth is significantly lower than the above considerations, therefore, a lower but equal weighting of 10% is assigned to each.

Construction of Facility Foundations

The engineering assessment criterion for the facility foundation considers three main parameters as shown Table 2.7. 


Table 12.7      Engineering Assessment Parameters Used for Construction of Facility Foundation

Engineering Assessment Criterion

Parameter

Relative Weighting

Construction of facility foundations

Terminal facility structures

0.30

Jetty piling works

0.50

Water front access

0.20

Total

1.00

The rationale for the selection of each relative weighting factor in Table 2.7 is given below.

·      The most difficult foundation construction works for the proposed site is the construction of the marine piling works for the jetty structures as it will be undertaken over water.  A weighting of 50% is, therefore, assigned to these works.

·      The land based foundation construction works for the terminal facility structures and the water front access areas are considered to be slightly easier and therefore a weighting factor of 30% and 20% are awarded, respectively.  The slightly higher weighting is given to the terminal facility works as the quantity is significantly greater.

2.1.3                                Site Comparison Scoring System

Parameters and Relative Weighting for Each Engineering Assessment Criterion

In order to make a quantitative assessment of the relative advantages and disadvantages of each site for each of the engineering assessment criterion defined above, a set of engineering parameters reflecting the main tasks to be undertaken under each criterion have been developed.  As with the Assessment Criteria, each parameter carries a relative weighting to represent the significance and impact on the overall engineering assessment criterion that also add up to unity.

Scoring Matrices

Using the parameters described above, each of the different layout options has been evaluated and compared against the base case based upon an assessment of the merits and demerits of each.  For this purpose an options evaluation matrix has been created to compare the Black Point base case layout against each of the two alternative layouts.

Firstly, a relative comparison matrix summarising the quantities associated with each assessment parameter is established within separate matrices for each engineering construction criterion.  The matrices are presented in Annex 2-A.

Using the relative comparison matrices an overall score is established for each layout option and each engineering assessment criterion by assigning a relative score for each parameter of between 0 and 5 which is dependent upon the relative magnitude or impact of the parameter value on the works as compared to the base case as shown in Table 2.8.  The base case will receive an average median score of 3 for each parameter.  For the two option layouts, a higher relative score is given to a site parameter with a lower impact on the construction works when compared to same parameter of the base case, and a lower relative score given to a site parameter with a higher impact on the construction works when compared to the base case.  The best layout site will, therefore, achieve the highest overall score for ease of identification.

Table 12.8      Scoring System Applied to Assessment Criteria

Impact on the Construction of the Works as Compared with Base Case

Score

Significantly lower Impact relative to base case

5

 

 

Slightly lower Impact relative to base case

4

 

 

Similar Level of Impact to Base Case

3

 

 

Slightly higher Impact relative to base case

2

 

 

Significantly higher Impact relative to base case

1

The scores are tabulated in a relative comparison scoring matrix for each engineering criterion.  A total score for each engineering criterion is determined from the sum of the weighted individual scores assigned to each parameter depending upon their relative impact.

The results of the scoring for each engineering assessment criteria are based on the summary quantity matrices shown in Annex 2-A. 

Overall Engineering Ranking of the Layout Options

Having assigned a score to each of the parameters within each of the engineering assessment criteria, the result is multiplied by the relative weighting given in Table 2.8 from which a total score for each site for each engineering assessment criterion is derived.  These scores are then normalised to a maximum value of 5 to enable a quantitative comparison to be made.  These values are referred to as ‘normalised scores’ in Annex 2-A.

These normalised scores for each engineering works activity matrix are applied to the overall ranking matrix.  The relative importance factors given in Table 2.2 are applied to each of the normalised scores within the overall ranking matrix in order to determine an overall score for each option.

Engineering Assessment Results

Having evaluated each layout option for the Black Point terminal separately with respect to each engineering assessment criterion, the results of each individual assessment have been used to produce an overall score for each option.  These scores have then been used to rank the layouts in order of preference to enable selection of the preferred option on the basis of the highest score from the engineering assessment.  The results for each engineering assessment criterion have been collated and are listed in Table 2.9.

Table 12.9      Engineering Comparison of Layout Options at Black Point

Engineering Assessment Criterion

Relative Importance Factor

Option 1

(Base case)

Option 2

(Full Reclamation)

Option 3 

(Full Excavation)

 

 

Score

FS*

Score

FS*

Score

FS*

Site Formation

 

0.30

3.85

1.15

5.00

1.50

1.28

0.38

Site Reclamation

 

0.30

3.00

0.90

2.15

0.65

5.00

1.50

Approach Channel & Turning Basin

 

0.20

3.66

0.73

3.66

0.73

5.00

1.00

Marine Navigation

 

0.10

5.00

0.50

5.00

0.50

5.00

0.50

Facility Foundations

 

0.10

5.00

0.50

4.00

0.40

3.83

0.38

Total Score

 

 

3.79

 

3.78

 

3.77

Site Ranking

 

1

2

3

Note:      *  FS = Factored Score (ie Score x Relative Importance Factor)

On the basis of the engineering assessment for the construction and operation, the result of the site layout comparison is as follows:

·       Preferred layout:           Option 1 – Base Case

·       Second choice:   Option 2 – Full Reclamation

·       Third choice:       Option 3 – Full Excavation

Summary of Engineering Assessment

A comparative engineering study has been made to assess the relative merits and demerits of possible layouts for the proposed LNG receiving terminal at Black Point.  It compared the original base case layout with two other possible layouts – a full reclamation case, and a full excavation case.  The comparisons have been made based on the following engineering assessment criteria:

·       Construction of site formation works;

·       Construction of site reclamation works;

·       Construction of approach channel and turning basins;

·       Marine navigation; and,

·       Construction of the facility foundations.

Several engineering assessment parameters have been derived for each engineering criteria and a scoring system applied to each.  An overall score for each site has then been established by applying an importance factor to each of the assessment criteria.

This assessment procedure has shown that Option 1 Base Case layout is preferred from an engineering standpoint.  The Base Case layout is preferred as it achieves the best balance between reclamation and excavation quantities.

2.1.4                                Environmental Assessment

The three options for the Black Point terminal layout have been assessed in environmental terms through an environmental impact scoping and preliminary assessment exercise (Figures 2.1 to 2.3).  This method allows a high level qualitative comparison of each option through the application of pre-defined impact terminology.  A description of the methodology is presented below ([1]).

Impact Scoping

Potential impacts have been identified using a “Scoping Matrix”.  Identified activities and key potential sources of impacts (i.e., hazards) have been listed down the vertical column of the matrix while environmental resources or receptors are listed across the horizontal axis.  Each square on the scoping matrix represents a potential interaction between an activity and an environmental resource/ receptor (i.e., potential impact).  Resources/ receptors are based on the technical requirements of the EIA Study Brief (ESB-126/2005).

Due to the nature of the construction of each layout option, described above in the engineering assessment, a single scoping matrix has been developed.  Although each layout differs in terms of its design, the functional requirements of the terminal result in similar interactions between activities and environmental resource/ receptors.  Differences appear in the severity of potential impacts.  The scoping matrix is presented in Table 2.10. 

Table 12.10    Impact Scoping Matrix

It should be noted that the list of activities/hazards is not intended to be exhaustive but rather an identification of key aspects of both construction and operation phases of the LNG terminal that have the potential to interact with the environment and subsequently have the potential to cause environmental impacts.  The list of environmental receptors/resources is also a focused list of the key aspects of the environment that are considered vulnerable or important in the context of the construction and operation of the LNG terminal.

Evaluation of Impacts

In evaluating the degree of potential impacts, the following factors have been taken into consideration:

·      Impact Severity:  The severity of an impact is a function of a range of considerations including the following:

o     impact magnitude;

o     impact duration;

o     impact extent;

o     legal and guideline compliance; and,

o     characteristics of the receptor/ resource that is affected.

·      Likelihood of Occurrence:  How likely is the impact to occur?

Severity Criteria for Environmental Impacts

In evaluating the severity of potential environmental impacts, the following factors have been taken into consideration:

·      Receptor/Resource Characteristics:  The nature, importance and sensitivity to change of the receptors or resources that could be affected;

·      Impact Magnitude: The magnitude of the change that is induced;

·      Impact Duration: The time period over which the impact is expected to last;

·      Impact Extent:  The geographical extent of the induced change; and

·      Regulations, Standards & Guidelines: The status of the impact in relation to regulations (e.g. discharge limits), standards (e.g. environmental quality criteria) and guidelines.

Impact severity has been categorised using the following subjective scale:

·      Slight;

·      Low;

·      Medium; and

·      High.

Likelihood of Occurrence

The likelihood (probability) of the pre-identified events occurring has been ascribed using the following qualitative scale of probability categories (in increasing order of likelihood):

A.   Extremely unlikely (e.g. never heard of in the industry);

B.   Unlikely (e.g. heard of in the industry but considered unlikely);

C.  Low likelihood (e.g. such incidents/impacts have occurred but are uncommon);

D.  Medium likelihood (e.g. such incidents/impacts occur several times per year within the industry); and

E.   High likelihood (e.g. such incidents/impacts occurs several times per year at each location where such works are undertaken).

Likelihood is estimated on the basis of experience and/or evidence that such an outcome has previously occurred.  Impacts resulting from routine/planned events (i.e. normal operations) are classified under category (E).

Impact Significance

The significance of each impact is determined by assessing the impact severity against the likelihood of the impact occurring as summarised in the impact significance assessment matrix provided in Table 2.11.

Table 12.11    Impact Significance

Significance criteria for negative/adverse impacts (i.e., relative ranking of importance) are defined in Table 2.12.  It is important to note that impacts are considered without the implementation of mitigation measures.  The need for and appropriate method of mitigation would be determined on the basis of the impact assessment.

Table 21.12    Significance Criteria

 

·      Positive Impacts are classified under a single category; they are then evaluated qualitatively with a view to their enhancement, if practical.

·      Negligible or Low Impacts will require little or no additional management or mitigation measures (on the basis that the magnitude of the impact is sufficiently small, or that the receptor is of low sensitivity). 

·      Medium or High Impacts require the adoption of management or mitigation measures.

·      High Impacts always require further management or mitigation measures to limit or reduce the impact to an acceptable level. 

Evaluation of Potential Environmental Impacts

An evaluation of the above identified potential impacts as a result of the construction and operation of each of the Black Point terminal options has been undertaken using the concepts described above.  The results of these evaluations are presented in detail in Annex 2-B.  The impact assessment matrices for each of the three layout options for the Black Point terminal are presented below in Tables 2.13 to 2.15.  Key impacts, i.e. those activities/ hazards, which may have the potential to result in high impacts to environmental resources/ receptors are highlighted for each option.  Following, environmental impacts that differentiate between the layout options are presented.

Table 21.13    Impact Assessment Matrix: Option 1 - Base Case

Key potential impacts, ie high impacts that are considered to be significant and may require further management or mitigation, associated with the construction and operation of the Black Point terminal according to the Option 1 – Base Case layout have been identified as the following:

·       Construction Marine Dredging and Disposal Impacts to Water Quality; and,

·       Construction Piling Works on Marine Mammals.

Details on each of the above are presented in Annex 2-B.

Table 21.14    Impact Assessment Matrix: Option 2 - Full Reclamation

Key potential impacts associated with the construction and operation of the Black Point terminal according to the Option 2 – Full Reclamation layout has been identified as the following:

·       Construction Marine Dredging and Disposal Impacts to Water Quality; and,

·       Construction Piling Works on Marine Mammals.

Details on each of the above are presented in Annex 2-B.

Table 21.15    Impact Assessment Matrix: Option 3 - Full Excavation

Key potential impacts associated with the construction and operation of the Black Point terminal according to the Option 3 – Full Excavation layout has been identified as the following:

·       Construction Marine Dredging and Disposal Impacts to Water Quality;

·       Construction Piling Works on Marine Mammals; and,

·       Construction Waste Generation and Disposal on Waste Storage Facilities.

Details on the above are presented in Annex 2-B.

Environmental Differentiators

A summary of the key environmental differentiators between the three options is presented below.


Waste Generation and Disposal

All sites will require the excavation of rock from the existing hillsides in order to provide sufficient flat land to meet the functional requirements of the LNG terminal.  However, both Option 1 and Option 2 layouts are expected to utilise all excavated material within the proposed reclamation.  In addition, it is expected that up to 1.90 and 3.43 Mm3 of fill, respectively, will need to be imported from existing construction and demolition (C&D) waste storage facilities.  Hong Kong is currently storing surplus C&D material, thus the necessity to import such material would be considered to be a positive impact for the both layouts.

In contrast to Options 1 and 2, the design of Option 3, the Full Excavation layout, will result in a surplus of approximately 14 Mm3 of rock following excavation and construction works.  This material will be exported to allocated waste storage and disposal facilities and would be considered as a potentially high impact to storage facilities. 

Environmental Assessment Results

The results of the environmental impact scoping and assessment allows a comparison of each layout and design option to be presented based on the number of issues.  Each site has been ranked in order of preference against the other on the basis of the number of impacts compared to the other two sites, ie the lower number of impacts the better.  On the basis of these ranks, the average rank has been determined for each option to determine the order of preference in both the construction and operation phases of the potential Black Point terminal.  The result of the comparison is presented in Table 2.16.

Table 21.16    Comparison of Layout Options at Black Point in terms of Environmental Assessment

On the basis of the environmental assessment for the construction and operation of the potential Black Point terminal, the result of the layout comparison is as follows:

·       Preferred layout:           Option 1 – Base Case


·       Equal second choice:   Option 2 – Full Reclamation or Option 3 – Full

                                           Excavation

The main environmental gains of choosing Option 1 is, on balance, a significant reduction in dredging and excavated volumes when compared to the other options.  The changes have resulted in a reduction in ecological, fisheries and water quality impacts through reduction in reclamation, dredging and natural coastline loss.  The reduction in dredging and excavation will also have a benefit in reducing off site impacts, such as during disposal of dredged muds and ease the burden on the limited capacity remaining at existing marine disposal sites.

Summary of Environmental Assessment

As with the engineering assessment a comparative environmental study has been made to assess the relative merits and demerits of possible layouts for the proposed Black Point terminal.  The study compared the original base case layout with two other possible layouts to identify the preferred layout of the three.  The comparisons have been made based on the potential for impacts to occur to resources/ receptors identified under the EIAO-TM and the technical requirements of the EIA Study Brief (ESB-126/2005).

As it is not considered appropriate to apply an importance factor to environmental criteria, potential impacts to resources/ receptors have been firstly identified through the potential for interaction, followed by a qualitative assessment of the likely severity of impact.

The assessment has determined that the Option 1 – Base Case layout is preferred from an environmental perspective.  This option offers lower excavation requirements as well as a minimal impact to potential landscape and visual sensitive receivers.  The potential for subsequent impacts to the environment have, therefore, been considered to be lower for this layout option.

2.1.5                                Summary of Consideration of Different Layouts and Design Options

The above section has considered different layouts and design options for the Black Point terminal as part of the overall assessment of alternatives.  The assessment has been conducted to investigate not only the environmental considerations of each layout and design options, but to include an examination of the engineering aspects.  The assessment has thus considered both the difficulties of the construction and operation of each facility as well as the potential environmental impacts associated with such.

Both the engineering and environmental assessments have identified layout Option 1 – Base Case as the most preferable for the construction and operation of the Black Point terminal.  This option achieves the best balance between reclamation and excavation quantities.  The location of the two LNG tanks in the Black Point headland also reduces the potential for impacts to landscape and visual sensitive receivers.  The engineering consequences and subsequent environmental impacts are considered to be lower for this layout option.

The Base Case Layout has thus been taken forward as the preferred layout for the Black Point terminal in the Environmental Impact Assessment.

2.2                                      Consideration of Alternative Construction Methods

In accordance with Clause 3.6.5 of the EIA Study Brief (ESB-126/2005), this section presents the consideration of alternative construction methods and sequence of works that have been assessed as part of the overall assessment of alternatives for the Black Point terminal. 

The assessment has been conducted to investigate potential methods and plant for the construction of the proposed terminal as well as associated facilities.  The objective of the assessment is to identify the preferred alternative with a view to avoid the likelihood of unacceptable adverse environmental impacts. 

Alternative construction sequences have been investigated in the EIA , specifically in the water quality section (Section 6) in order to avoid localised cumulative effects and to avoid adverse impacts to the maximum practical extent. 

The basic requirements of a LNG terminal in Hong Kong have been described in Part 2 – Section 3.  Justifications for Black Point being considered as one of the two sites for a LNG receiving terminal in Hong Kong have been presented in Part 1 – Section 4.

On the basis of these requirements, it is considered that the following are the key facilities to be constructed, to which alternative methods have been considered:

·       Reclamation;

·       Seawalls;

·       Jetty; and,

·       Approach Channel and Turning Basin.

As the onsite facilities, such as the LNG storage, regasification plant, administration office, canteen, ancillary buildings and sewerage treatment plants etc., will be constructed to best industry standard, alternatives for construction will not be discussed.

2.2.1                                Reclamation

The preferred layout for the Black Point terminal (see Part 3 – Section 2.1) would involve mainly site formation works and approximately 16 ha of reclamation ([2]).  The layout for the preferred Black Point terminal is presented in Figure 2.1.

Traditionally the method to construct the reclamation area has been to dredge away all soft seabed materials under the entire reclamation area.  This would be considered as a ‘Fully Dredged Method’.  However, recently in Hong Kong there has been an increasing reliance on only dredging soft mud from beneath seawalls and main drainage culverts and leave the soft mud under the proposed reclamations area.  According to the Practice Note for Authorized Persons and Registered Structural Engineers (PNAP) No. 252 issued by the Buildings Department, project proponents must plan projects on the assumption of keep the mud in place.  Time for consolidation and consequential programme constraints shall be allowed for in programming.  In order to reduce the long-term ongoing settlement of the soft mud under the overlying reclamation fill, ground improvement works would be necessary.  Such a construction method would be considered as a ‘Partially Dredged Method’.  In line with local construction practice and government policy, this method will be adopted for the project. 

Partially Dredged Method

For this method, dredging would be limited to only the area beneath the seawall.  The mud is not dredged from beneath the reclamation area but rather sand fill is placed over the soft mud to initially raise the ground level to +2.5 mPD after which, public fill is compacted in layers to the finished level of +6 mPD.    There are two key engineering issues to be considered with this method as follow:

·       The soft marine mud will consolidate significantly under the weight of the overlying fill.  This consolidation may well be up to 3 metres and will take many years to complete if no additional ground improvement works are put in place;

·       The initial layers of sand fill need to be placed very carefully to avoid the generation of mud waves which can significantly affect the long term performance of the reclamation.

The second issue is usually rectified by protecting the mud by a layer of geotextile followed by hydraulically placed sand.

Ground movements due to consolidation settlement have a significant impact on the operation of the facility.  The most sensitive structures will need to be necessarily piled in order to mitigate these effects of ground movement.  However, it will not be cost-effective or practical to support all plant and services at the site on piles.  In these areas ground improvement measures will be essential  to reduce ground movements to acceptable levels.  Two commonly used ground improvement methods suitable for use in reclamation areas include the following: -

·       Installation of vertical drains together with surcharge pre-loading; and

·       Vibro-replacement / vibro displacement.

In view of the tight construction programme, cost-effectiveness and the sensitive nature of cryogenic equipment, the use of vertical drains with surcharge pre-loading is considered the most suitable method of ground improvement.

Vertical Drains with Surcharge Pre-loading

The use of vertical drains (often called band drains) for construction of reclamations has the effect of shortening the drainage paths of the relatively impermeable marine clay and/or alluvial clay.  The consolidation settlement due to the site formation can therefore be achieved within a shorter period.  Drains are typically inserted on a triangular grid at 1.2 to 1.5m spacing down to the interface between marine deposits/alluvial clay layer (sometimes penetrated through the alluvium, depending on its engineering characteristics).

The surcharge preloading serves the following purposes: -

·       To significantly speed up the consolidation;

·       If suitable additional surcharging height or time duration is allowed, it can substantially eliminate the settlement due to the future imposed load from low rise buildings and other light weight structures.

The design height and duration of placement for the surcharge mound will depend upon the time allowed in the construction programme.  For projects with a tight construction programme such as this, the surcharge mound would need to be high.  It is currently estimated that the height of the surcharge mound would need to be approximately 5m above the future formation level of +6mPD, which will achieve acceptable long-term settlement performance of the reclamation.

The cryogenic pipelines and facility structures will require very tight settlement criteria as the movement tolerances are very small.  The proposed foundation schemes for the structures are still under development and thus a detailed settlement / differential settlement analysis shall be carried out at a later stage.

 

2.2.2                                Seawalls

Dredging is required to remove the soft material beneath the seawall to ensure that the seawall is stable and can be built within a optimum timeframe, thereby reducing the potential for environmental impacts to occur.  In addition to the conventional method of carrying out full dredging of the marine deposits before filling up for the seawall, two other alternatives are available. 

The first alternative makes use of ground improvement technique, such as Deep Cement Mixing (DCM), to enhance the strength of the marine deposits before filling up for the seawall.  In DCM, the soft soil is mixed in-situ with an appropriate additive using an auger or other mixing device.  The additive used is typically cement or lime.  No spoil removal is required.  A similar technique called Deep Cement Method was developed in Japan, using cement slurry.  Previous studies have investigated the use of cement stabilization work as part of the ground improvement method, however, these have only been performed on the bench-scale test and such technology has not been taken forward on site with pilot trial ([3]).  The efficiency and cost-effectiveness of the improvement method has not been tested and as such it is not possible to assess the environmental and safety impact attached to this alternative.  The use of Deep Cement Mixing is therefore not the preferred construction alternative for the current study. 

The second alternative requires a long counter fill on the seaward side of the seawall to provide toe stability against slip failure during construction.  The use of this method is, however, considered to be unsuitable for this project as it is likely to lead to significant ongoing settlement of the sea wall after the LNG terminal is in operation.

On the basis of the above, neither of the alternative methods is preferred over the conventional method of dredging beneath the seawall.  As such, the conventional method of carrying out full dredging of the marine deposits before filling up for the seawall is recommended as the preferred alternative for the construction of the seawalls for the LNG terminal.

2.2.3                                Jetty

A piled jetty is required for creation of the berthing facility for the LNG carrier at the Black Point terminal.  For large jetties of this type, piled structures are preferable to blockwork or closed structure designs as they are less likely to result in adverse impacts to water quality and subsequently marine ecology, due to the minimal disturbance to hydrodynamics. 

For the construction of the LNG Jetty, two alternatives are available for the installation of marine piles.  These are bored or percussive piling methods.  A discussion of each of these methods in terms of the environmental advantages and disadvantages is presented below.

Bored Piles

Noise created by bored piling methods tends to be a less intensive continuous noise, rather than the pulsed high power sounds emitted through percussive piling.([4]).  A summary of potential impacts from bored piling methods are presented below.

·       a large casing must be driven into the seabed in order to support the boring equipment which will necessitate a longer construction period

·       socketing into the bedrock will require the use of a chisel (noise impacts from socketing may be mitigated by using the reverse circulation drilling method); and,

·       placing concrete to the bored pile (potential leakage of cementitious materials from sacrificial casing during this process.)

Percussive Piles

The sounds emitted from percussive hammer pile driving activities have their highest energy at lower frequency (20 Hz to 1 kHz) and loud sounds have been identified to cause (short-term) behavioural reactions such as increased swimming speed in cetaceans ([5]).  Studies in Hong Kong have, however, determined that with measures such as bubble jackets and bubble curtains, marine mammal behaviour does not change substantially during percussive piling operations ([6]). 

Based on the well-proven track record for the successful employment of these measures, it is proposed that either method be used for the construction of the LNG Jetty as part of the Black Point terminal.  Detailed assessments of the impacts of both methods are also mentioned in other sections in this EIA Report.

2.2.4                                Approach Channel and Turning basin

An approach channel and turning basin will be required as part of the Black Point terminal in order to allow for the safe transit of the LNG carrier to the jetty.  In order to meet the required draft of the carrier, both the channel and turning basin will be required to be dredged to approximately -15 mPD. 

There are two common dredging plants that are employed for the removal of marine sediments in Hong Kong.  These are grab dredgers or trailing suction hopper dredgers (TSHD).  Each plant would be available as alternatives for the construction of the approach channel and turning basin.  The potential environmental advantages and disadvantages of each are discussed below.

Grab Dredgers

A grab dredger comprises a rectangular pontoon on which is mounted a revolving crane equipped with a grab.  The dredging operation consists of lowering the grab to the bottom, closing the grab, raising the filled grab to the surface and discharging the contents into a barge.  Grab dredgers are usually held in position while working by anchors and moorings but some have a spud or pile, which can be dropped onto the bottom while the dredger is operating.

Grab dredgers may release sediment into suspension by the following mechanisms:

·       Impact of the grab on the seabed as it is lowered;

·       Washing of sediment off the outside of the grab as it is raised through the water column and when it is lowered again after being emptied;

·       Leakage of water from the grab as it is hauled above the water surface;

·       Spillage of sediment from over-full grabs;

·       Loss from grabs which cannot be fully closed due to the presence of debris;

·       Release by splashing when loading barges by careless, inaccurate methods; and,

·       Disturbance of the seabed as the closed grab is removed.

During the transport of dredged materials, sediment may be lost through leakage from barges.  Dredging permits in Hong Kong, however, include requirements that barges used for the transport of dredging materials shall have bottom-doors that are properly maintained and have tight-fitting seals in order to prevent leakage. 

Sediment is also lost to the water column when discharging material at disposal sites.  The amount that is lost depends on a large number of factors including material characteristics, the speed and manner in which it is discharged from the vessel and the characteristics of the disposal sites. 

Trailing Suction Hopper Dredgers

Trailing Suction Hopper Dredgers (TSHD) are designed to use a suction mouth at the end of a long pipe.  As the barge moves, the suction hopper trails along and sucks up the soft seabed sediments.  During dredging the draghead will sink below the level of the surrounding seabed and the seabed sediments will be extracted from the base of the trench formed by the passage of the draghead.  The main source of sediment release is the bulldozing effect of the draghead when it is immersed in the mud.  This mechanism means that sediment is generally lost to suspension very close to the level of the surrounding seabed.

During dredging marine sediments are pumped into the vessel’s hopper.  Once the hopper is loaded the dredging operation will be stopped and the vessel will sail to a designated disposal area.  A TSHD is usually positioned by dynamic positioning, thus they have no anchor wires.  In comparison to grab dredgers, TSHDs generally have a higher production rate.

Both Grab dredgers and Trailing Suction Hopper Dredgers (TSHD) are commonly used in Hong Kong.  As such, the employment of both plants are considered viable options.

2.3                                      Selection of Preferred Scenario

The preferred scenario/alternative to be taken forward to the EIA stage at Black Point is Base Case Layout (Option 1).  Full details of the components of the preferred scenario are detailed in Part 3- Section 3 of this EIA report.

The selection of the preferred scenario has brought about a series of environmental and engineering benefits to the Project as presented in Figures 2.4 and 2.5.  These benefits have arisen through modifications to the engineering layout stimulated by issues raised during consultations with stakeholders in Government, District Councils, Rural Committees, NGOs and the Advisory Council on the Environment, as well as through engineering optimisation.  The main environmental gains are:

·       A significant reduction in dredging volumes from approximately 5 Mm3 to approximately 3 Mm3. 

The above changes have resulted in a reduction in ecological, fisheries and water quality impacts through reduction in reclamation, dredging and natural coastline loss.  The reduction in dredging will also have a benefit in reducing off site impacts during disposal of dredged muds and ease the burden on existing disposal sites.

Further details are presented on Figures 2.4 and 2.5.


Figure 2.4       Base Case Design Adopted in Pre-EIA Studies

 

Base Case Design Adopted in Pre-EIA Studies

Details

The layout initially studied included approximately 16 ha of reclamation to accommodate the LNG terminal facilities.  Total dredging volumes exceeded 5 Mm3.

Layout

Issues

Consultation with stakeholders such as ESMG members, rural committees, NGOs questioned whether dredging volumes could be reduced.


Figure 2.5       Preferred Scenario Design Assessed in this EIA

 

Preferred Scenario Design Assessed in this EIA

Details

During the early stages of this EIA, as described in the sections above the CAPCO team has examined various layouts taking into account:

·         Issues raised during consultations with ACE, NGOs, fishermen, LegCo members;

·         Ongoing process, civil and marine engineering reviews;

·         Updated findings of environmental baseline surveys.

The outcome of this work has been the production of preferred layout as presented below.

Layout

Issues

The resultant layout has a reduction in dredging volumes are reduced to approximately 3 Mm3.  These changes have brought about an overall reduction in water quality, ecological, fisheries and waste impacts.  The positioning of the tanks has resulted in an improvement in visual impacts.

 


 



([1])     It is noted that the methodologies for environmental and engineering comparisons of alternatives differ in this section of the EIA and other such as Part 1 Section 5 and Part 2 Section 2.  This is considered appropriate as the input information in the comparison process has to be treated differently, some of the source information is quantitative and some qualitative and hence the approaches have been tailored to the context of the assessment.

([2])     It is acknowledged that further study may be required to determine if the area for Black Point could be optimised to further reduce the size of the reclamation.

([3])     Aas, PM & Engen A (1993) Hong Kong Seawall Design Study.  GEO Report No. 31. Geotechnical Engineering Office, Civil Engineering and Development Department, Hong Kong SAR Government.

([4])     B Wursig, C.R. Greene, T. A Jefferson (1999) Development of an air bubble curtain to reduce underwater noise of percussive piling. Marine Environmental Research.

([5])     B Wursig, C.R. Greene, T. A Jefferson (2000) Op cit.

([6])     B Wursig, C.R. Greene, T. A Jefferson (2000) Op cit.