Environmental Protection Department

 

Agreement No. CE20/2004 (EP)

North East New Territories (NENT) Landfill Extension

 

Environmental Impact Assessment Report  

 

May 2007

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Contents

                                                                                                                                                                                                     

1          Introduction   1

1.1        Project Background  1

1.2        Purpose and Scope of the EIA Study  1

1.3        EIA Study Area  1

1.4        The Approach  2

1.5        Structure of the EIA Report 3

2          Description of the Project   1

2.1        General Description of the Project 1

2.2        Key Project Requirements  1

2.3        Need for the Project 2

2.4        Consideration of Alternatives  3

2.5        Site Location and Site History  11

2.6        Nature, Scope and Benefits of the Project 12

2.7        Size, Scale, Shape and Design of the Project 12

2.8        Project Timetable  14

2.9        Related Projects  15

2.10      “No Project” Scenario  15

3          Air Quality Impact   1

3.1        Introduction  1

3.2        Environmental Legislation, Standards and Guideline  1

3.3        Description of the Existing NENT Landfill and the Extension  5

3.4        Air Sensitive Receivers  11

3.5        Identification of Air Pollution Source and Environmental Impact 12

3.6        Assessment Methodology  18

3.7        Prediction and Evaluation of Air Quality Impact 30

3.8        Precautionary Measures  42

3.9        Residual Environmental Impact 44

3.10      Implication of IWMF Implementation  44

3.11      Conclusion  44

4          Noise Impact   1

4.1        Introduction  1

4.2        Environmental Legislation, Standards and Guidelines  1

4.3        Description of the Environment 4

4.4        Noise Sensitive Receivers  5

4.5        Assessment Methodologies  6

4.6        Construction, Restoration & Aftercare Noise Impact Assessment 7

4.7        Operational Noise Impact Assessment 9

4.8        Residual Environmental Impact 15

4.9        Conclusion  15

5          Water Quality Impact   1

5.1        Introduction  1

5.2        Environmental Legislation, Standards and Guidelines  1

5.3        Baseline Conditions  2

5.4        Water Sensitive Receivers  6

5.5        Assessment Methodology  7

5.6        Identification and Evaluation of Water Quality Impacts  7

5.7        Cumulative Impacts  23

5.8        Precautionary Measures  23

5.9        Residual Impacts  30

5.10      Conclusion  30

5.11      Reference  32

6          Waste Management Implications   1

6.1        Introduction  1

6.2        Legislation, Standards and Guidelines  1

6.3        Assessment Methodology  1

6.4        Identification and Evaluation of Waste Management Implications  2

6.5        Mitigation Measures  6

6.6        Residual Impacts  6

6.7        Environmental Audit 7

6.8        Implication of IWMF Implementation  7

6.9        Conclusion  7

7          Landfill Gas Hazards   1

7.1        Introduction  1

7.2        Legislation, Standards and Guidelines  1

7.3        Background Information  1

7.4        LFG Hazard Assessment 3

7.5        Protective and Precautionary Measures  13

7.6        Monitoring Requirement 20

7.7        Implication of IWMF Implementation  21

7.8        Conclusion  21

8          Landscape and Visual Impact   1

8.1        Introduction  1

8.2        Legislation, Standards and Guidelines  1

8.3        Landscape And Visual Impact Assessment Methodology  2

8.4        Baseline Study Frameworks  5

8.5        Planning and Development Control Review   11

8.6        Source of Impacts and Impact Assessment 11

8.7        Conclusion  22

9          Impact on Cultural Heritage   1

9.1        Introduction  1

9.2        Environmental Legislation & Standards  1

9.3        Description of the Study Area  1

9.4        Archaeology  2

9.5        Built Heritage  7

9.6        Identification and Evaluation of Impacts  13

9.7        Mitigation Recommendations  15

9.8        Conclusions  16

9.9        References  17

10         Ecological Impact   1

10.1      Introduction  1

10.2      Relevant Legislation and Guidelines  1

10.3      Field Survey Scope and Methodology  2

10.4      Key Ecological Issues  3

10.5      Results of Literature Review   4

10.6      Results of Field Surveys  6

10.7      Evaluation of Habitats and Species  14

10.8      Impact Identification and Evaluation  19

10.9      Impact Avoidance and Mitigation Measures  27

10.10    Residual Ecological Impacts  30

10.11    Ecological Monitoring and Audits  31

10.12    Conclusion  31

10.13    Reference  31

11         Summary of Environmental Outcome   1

11.1      Population and Environmental Sensitive Areas Protected  1

11.2      Environmental Friendly Design and Benefit 1

11.3      Key Environmental Problem Avoided  1

11.4      Environmental Protection Measures and Precautionary Measures  1

12         Environmental Monitoring and Audit Requirements   1

12.1      Introduction  1

12.2      Project Organisation  1

12.3      EM&A Manual and Implementation Schedule  1

12.4      EM&A Programme  2

12.5      Method Statements  2

13         3-Dimensional EIA   1

14         Conclusion   1

14.1      Option Evaluation  1

14.2      Air Quality Impact 1

14.3      Noise Impact 2

14.4      Water Quality  2

14.5      Waste Management 3

14.6      Landfill Gas Hazards  3

14.7      Landscape and Visual Impact 3

14.8      Cultural Heritage Impact 4

14.9      Ecological Impact 4

14.10    Environmental Monitoring and Audit 5

14.11    3D-EIA Tools  5

14.12    Overall Conclusion  5

 

 

 

Drawings

24315/01/001        Location Plan

24315/01/005        Existing NENT Landfill and Proposed Landfill Extension

24315/01/101        Landfill Extension Layout Option 1

24315/01/102        Landfill Extension Layout Option 1a

24315/01/103        Landfill Extension Layout Option 1b

24315/01/104        Landfill Extension Layout Option 2

24315/01/105        Landfill Extension Layout Option 2a

24315/01/106        Landfill Extension Layout Option 3

24315/01/107        Landfill Extension Layout Option 4

24315/13/101        Location of Air Sensitive Receivers (Assessment Points)

24315/13/102        Dust Emission Source Location (Existing NENT Landfill Final Capping + NENT Landfill Extension Phase 1)

24315/13/103        NO2, SO2 & VOC Emission Source Location

24315/13/104        Odour Emission Source Location

24315/13/105        Predicted 1-hour TSP Contour (mg/m³) at 1.5m Above Ground (Worst-case Scenario)

24315/13/106        Predicted 24-hour TSP Contour (mg/m³) at 1.5m Above Ground (Worst-case Scenario)

24315/13/107        Predicted 1-hour Averaged NO2 Contour (mg/m³) at 10m Above Ground (Worst-case Scenario : ASP ON))

24315/13/108        Predicted 1-hour Averaged SO2 Contour (mg/m³) at 10m Above Ground (Worst-case Scenario : ASP ON)

24315/13/109        Predicted 1-hour Averaged Benzene Contour (mg/m³) at Worst Affected Location (Worst-case Scenario : ASP ON)

24315/13/110        Predicted Annual Averaged Benzene Contour (mg/m³) at Worst Affected Location (Worst-case Scenario : ASP ON)

24315/13/111        Predicted 1-hour Averaged Vinyl Chloride Contour (mg/m³) at Worst Affected Location (Worst-case Scenario : ASP ON)

24315/13/112        Predicted Annual Averaged Vinyl Chloride Contour (mg/m³) at Worst Affected Location (Worst-case Scenario : ASP ON)

24315/13/113        Predicted 5-second Averaged Odour Contour at 1.5m Above Ground (Northern Tipping)

24315/13/114        Predicted 5-second Averaged Odour Contour at 1.5m Above Ground (Western Tipping)

24315/13/201        Location of Noise Sensitive Receivers

24315/13/202        Proposed Planter Wall at Wo Keng Shan Road

24315/13/203        Location of Fixed Noise Sources

24315/13/301        Location of Groundwater Monitoring Point for Existing NENT Landfill

24315/13/302        Boreholes Location Plan

24315/13/303        Location of Water Sensitive Receivers and Sampling Points for Stream Water Baseline Survey           

24315/13/304        Catchment Areas near the NENT Landfill Extension Site

24315/13/501        Geological Map of NENT Landfill Extension Site

24315/13/502        LFG Consultation Zone

24315/13/503        Monitoring of Background CO2 Levels at 25 Boreholes

24315/13/504        Existing Landfill and Landfill Extension Monitoring Plan

24315/14/001        NENT Landfill Extension & Source of Impact

24315/14/002        Landscape Character Areas (LCAs) Plan & Impact Assessment (Without Mitigation)

24315/14/003        Aerial Photograph of the Project Site and the Surroundings

24315/14/004        Landscape Resources (LRS) Plan & Impact Assessment (Without Mitigation)

24315/14/005        Tree Survey Plan

24315/14/006        Visual Envelope and Visual Sensitive Receivers (VSRs) Plan & Impact Assessment (Without Mitigation)

24315/14/007        Typical View of Visual Sensitive Receivers to Proposed Development (Sheet 1 of 2)

24315/14/008        Typical View of Visual Sensitive Receivers to Proposed Development (Sheet 2 of 2)

24315/14/009        Mitigation Plan

24315/14/010        Photo Montage of Selected View (Sheet 1 of 3)

24315/14/011        Photo Montage of Selected View (Sheet 2 of 3)

24315/14/012        Photo Montage of Selected View (Sheet 3 of 3)

24315/13/601        CHIA Issues

24315/13/602        Study Area of Option 4 (Divided into Four Sub-sections for Ease of Reference)

24315/13/603        Solid and Superficial Geology (Sheung Shui) Hong Kong Geological Survey

24315/13/604        Location of Auger Holes and Test Pits

24315/13/605        Contexts of Test Pits

24315/13/606        Archaeological Findings

24315/13/701        Location of Site of Conservation Importance and Sampling Transects and Points for Fauna

24315/13/702        Habitat Map Location of Species of Conservation interest overlaid with Option 4

24315/13/703        Photos of Habitat and Species of Conservation interest

 


 

Appendices

Appendix 2.1      EIA Study Brief ESB-114/2004

Appendix 2.2      Tentative Outline Programme

Appendix 3.1       Construction Dust Assessment

Appendix 3.2      Gaseous Emission Assessment

Appendix 3.3A    Identification of Worst Weather Condition for Odour Assessment

Appendix 3.3      Odour Emission Assessment

Appendix 3.4      Odour Emission Strength and Modelling Parameters

Appendix 3.5      Surface Roughness Calculation in the area

Appendix 3.6      Odour Hourly Emission Concentration

Appendix 3.7      Predicted 1-hour and 24-hour TSP concentration

Appendix 3.8      Predicted 1-hour, 24-hour and annual averaged NO2 and SO2 concentration (mg/m3) at ASRs under various modes of operations

Appendix 3.9      Predicted 1-hour and annual averaged VOC concentration (mg/m3) at ASRs under various modes of operations

Appendix 3.10     Predicted odour concentration

Appendix 4.1      Sound Power Level of PMEs  

Appendix 4.2      Construction Plant Inventory

Appendix 4.3      Locations of Notional Sources and Distance to NSRs

Appendix 4.4      Detail Calculation of Construction Noise Assessment

Appendix 4.5      Detail Calculation of Cumulative Construction Noise Assessment

Appendix 4.6      Compute Plot of Road Traffic Noise Model

Appendix 4.7      Noise Measurement Results of Aeration Lagoon

Appendix 4.8      Noise Measurement Results of Ammonia Stripping Plant

Appendix 4.9      Noise Measurement Results of Refuse Vehicle

Appendix 4.10     Detail Calculation of On-site Operation Noise (Un-mitigated Scenario)

Appendix 4.11     Detail Calculation of On-site Operation Noise (Mitigated Scenario)

Appendix 4.12     Detail Calculation of Existing Landfill Operational Noise

Appendix 5.1      Groundwater Monitoring Data for Existing NENT Landfill from January 2005 to March 2006

Appendix 5.2      Leachate Generated from Landfill

Appendix 7.1      LFG Protection Measures in Existing NENT Landfill

Appendix 7.2      Specific LFG Protection Measures for Building Services

Appendix 9.1      Plates

Appendix 9.2      Grave Catalogue

Appendix 9.3      Cultural Landscape Feature Recording Form

Appendix 9.4      Methodology for Preservation by Record

Appendix 10.1     Freshwater Fish known to be present in Lin Ma Hang Stream

Appendix 10.2     Bat species recorded in Ling Ma Hang or in the vicinity of the Study Area

Appendix 10.3     Plant species recorded within the Study Area

Appendix 10.4     Bird species and their abundance in the Project Area

Appendix 10.5     Bird species and their abundance in the Study Area

Appendix 10.6     Dragonfly species and their abundance in the Project Area

Appendix 10.7     Butterfly species and their abundance in the Project Area

Appendix 10.8     Dragonfly species and their abundance in the Study Area

Appendix 10.9     Butterfly species and their abundance in the Study Area


Abbreviation

 

 

ASR

Air Sensitive Receiver

BMP

Best Management Practice

BOD5

5-Day Biochemical Oxygen Demand

COD

Chemical Oxygen Demand

CRTN

Calculation of Road Traffic Noise

DIA

Drainage Impact Assessment

DO

Dissolved Oxygen

DP

Designated Project

EIA

Environmental Impact Assessment

EIAO

Environmental Impact Assessment Ordinance

EPD

Environmental Protection Department

ETWBTC

Environment, Transport and Works Bureau Technical Circular

GCL

Geosynthetic clay liner

HDPE

High density polyethylene

HKPSG

Hong Kong Planning Standards and Guidelines

IWMF

Integrated Waste Management Facilities

MSW

Municipal solid waste

NCO

Noise Control Ordinance

NENT

North East New Territories

NSR

Noise Sensitive Receiver

OZP

Outline Zoning Plan

PCB

Polychlorinated Biphenyl

ProPECC

Environmental Protection Department Practice Note for Professional Persons

SBA

Stockpile and Borrow Area

SBR

Sequencing Batch Reactor

SENT

South East New Territories

SPL

Sound Pressure Levels

SS

Suspended Solid

SWHSTW

Shek Wu Hui Sewage Treatment Works

SWL

Sound Power Levels

TKN

Total Kjeldahl Nitrogen

TM-EIAO

Technical Memorandum on Environmental Impact Assessment Process (Environmental Impact Assessment Ordinance, Cap. 499, S.16)

TM-Places

TM for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites

TM-PP

Technical Memorandum on Noise from Percussive Piling

TM-DA

Technical Memorandum on Noise from Construction Work in Designated Areas

TM-GW

Technical Memorandum on Noise from Construction Work other than Percussive Piling

TM-Water

Technical Memorandum on Standards for Effluent Discharged into Drainage and Sewerage System, Inland and Coastal Waters

TN

Total Nitrogen

TOC

Total Organic Carbon

TSS

Total Suspended Solid

TTSAS

Tong To Shan Archaeological Site

USEPA

United State Environmental Protection Agency

WCZ

Water Control Zone

WENT

West New Territories

WHO

World Health Organization

WPCO

Water Pollution Control Ordinance

WRFP

Waste Reduction Framework Plan

WSR

Water Sensitive Receiver

WQI

Water Quality Indexes

WQO

Water Quality Objective

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


1                  Introduction

1.1                 Project Background

Currently, about 6 million tonnes of waste are disposed each year at the three strategic landfills in Hong Kong, including the West New Territories (WENT) Landfill, the South East New Territories (SENT) Landfill, and the North East New Territories (NENT) Landfill.

At time of commissioning, the three landfills with a total capacity in the order of 140 Mm³ were expected to be able to meet the waste disposal needs of Hong Kong until 2020 or beyond.  The actual waste disposal rate at the landfills has been, however, higher than expected.  It is thus projected that the three existing landfills would last only until early-to-mid next decade.

To tackle the problem, further efforts have been taken to reduce and recycle waste.  Also, the HKSAR Government has planned to develop Integrated Waste Management Facilities (IWMF) to substantially reduce the volume of waste requiring landfill disposal.  Yet these measures could not obviate totally the need for new landfill capacity in Hong Kong, especially as the implementation of IWMF will take time and as its residues will still need to be disposed.

The Environmental Protection Department (EPD) of the HKSAR Government therefore commissioned a Study in Year 2000 on the Extension of Existing Landfills and Identification of Potential New Waste Disposal Sites.  Amongst the potential sites recommended in this territory-wide study is an extension of the existing NENT Landfill, with a target capacity of about 19 Mm³.  As shown in the attached Drawing No. 24315/01/001, the proposed Extension, of about 70 ha, is located immediately east of the existing NENT Landfill.  A large proportion of the Extension area is in fact the borrow/stockpiling area of the existing landfill.  Drawing No. 24315/01/005 depicts the general topography at/around the Extension site, showing that it is generally in the form of a bowl bounded by Robin’s Nest and Wo Keng Shan.

In February 2005, EPD appointed Ove Arup & Partners Hong Kong Ltd. to undertake a detailed feasibility study for the NENT Landfill Extension (hereafter referred to “the Project”), with the following key tasks: formulation and evaluation of layout options for the landfill extension; EIA study; and conceptual design of landfill facilities.

1.2                 Purpose and Scope of the EIA Study

The purpose of this EIA Study is to provide information on the nature and extent of environmental impacts arising from the construction, operation, restoration and aftercare stages of the NENT Landfill Extension, and to contribute to decisions on the overall acceptability of the Project, after the implementation of environmental mitigation measures.

The NENT Landfill Extension is a Designated Project under Schedule 2, G.1, of the EIAO : “A landfill for waste as defined in the Waste Disposal Ordinance (Cap. 354)”.  The EIA study, undertaken under the NENT Landfill Extension Feasibility Study, has therefore been carried out in strict accordance with the EIAO, including the requirements stipulated in EIA Study Brief No. ESB-114/2004 issued under the EIAO.

Drawing No. 24315/01/001 shows the location of the Project site.

1.3                 EIA Study Area

The EIA study areas for the impact assessments on air quality, noise, water quality, landfill gas, ecology, landscape & visual and cultural heritage as defined in accordance with the requirements in the EIA Study Brief and are presented in Table 1.1 below.

Table 1.1: Study areas for various assessments

Aspect

Study Area

Remarks

Air Quality

within 500m from the Project Boundary

According to the study brief requirements with additional ASRs selected between 500 to 2000m.

Noise

within 300m from the Project Boundary

According to the study brief requirements with additional NSRs selected between 300 to 1800m.

Water Quality and

Aquatic Ecology

within 500m from the Project Boundary

According to the study brief requirements, with additional WSRs such as nearby watercourses, the associated water systems and the coastal water of Deep Bay and Starling Inlet.

Landfill gas

within 250m from the Project Boundary

According to the study brief requirements

Landscape

within 500m from the Project Boundary

According to the study brief requirements

Visual

visual envelope

According to the study brief requirements

Cultural Heritage

within 50m from the Project Boundary

According to the study brief requirements

Terrestrial Ecology

within 500m from the Project Boundary

According to the study brief requirements.

1.4                 The Approach

The EIA study has been prepared in accordance with the guidelines provided in Annex 11 of the TM-EIAO for the report contents and Annexes 12 to 19 for the impact assessments of various environmental issues. The general approaches and methodologies adopted for this EIA study are described below.

1.4.1            Description of the Environment

The characteristics of the existing environment were reviewed for identification and prediction of environmental impacts. Baseline surveys were conducted to determine the existing environmental conditions on the Project site and in any environs likely to be affected by the Project. The baseline conditions of the key issues as identified in the EIA Study Brief including air quality, noise, water quality, landscape & visual, cultural heritage and ecology are described in the assessment.

1.4.2            Impact Prediction

The EIA Study was undertaken in accordance with the guidelines on assessment methodologies given in Annexes 12 to 19 of the TM-EIAO. Quantitative predicting tools were employed for assessing the environmental impacts in respect of construction dust, operational air quality, construction noise, operational noise and water quality. The predictions were conducted based on well-recognized methods such as Arup plant noise impact analysis for construction activities, CRTN for evaluating operational road traffic noise impact, ISCST3 for evaluating fugitive and odorous source impacts, and hydrogeological model for evaluating the change of groundwater flow regime.

The applied methodologies for the Project had previously been adopted in other EIA studies. They have been generally accepted for use in predicting environmental impacts and for comparison of assessment results with the TM-EIAO requirements. Limitations are however envisaged of these methodologies. The accuracy of the prediction result will be affected by the degree of uncertainty in input data such as construction plant, air emission inventories and predicted traffic flow. Quantitative uncertainties in the prediction have been considered when drawing conclusion from the assessment results. In carrying out the prediction, realistic worst-case assumptions have been made in order to provide a conservative assessment of environmental impacts.

1.4.3            Impact Evaluation

The predicted changes and effects as a result of the Project were evaluated with respect to the criteria described in Annexes 4 to 10 of the TM-EIAO, and were in quantitative terms as far as practicable.

1.4.4            Impact Mitigation

Mitigation measures have been identified and evaluated to avoid, minimize or remedy the impacts. Priority was given to avoidance of impacts as a primary means of mitigation. The effectiveness of mitigation measures was assessed and the residual environmental impacts identified. Evaluation of impact was made with respect to the criteria described in Annexes 4 to 10 of the TM-EIAO, in quantitative terms as far as practicable.

1.5                 Structure of the EIA Report

The structure of this EIA Report is outlined below for ease of reference:

Chapter

Title

Aims

1

Introduction

To provide project background, purpose and scope of the EIA Study and to define the EIA study area.

2

Description of the Project

To describe the project requirements, consideration of alternative and major activities in the Project.

3

Air Quality Impact

To assess the potential air quality impact of the Project and suggest mitigation measures.

4

Noise Impact

To assess the potential noise impact of the Project and suggest mitigation measures.

5

Water Quality Impact

To assess the potential water quality impact of the Project and suggest mitigation measures.

6

Waste Management Implications

To assess the potential waste management implications of the Project and suggest mitigation measures.

7

Landfill Gas Hazards

To assess the potential hazards arising from landfill gas migration and suggest precautionary measures.

8

Landscape and Visual Impact

To assess the potential landscape and visual impacts of the Project and suggest mitigation measures.

9

Impact on Cultural Heritage

To assess the potential impacts of the Project on cultural heritage and suggest mitigation measures.

10

Ecological Impact

To assess the potential ecological impacts of the Project and suggest mitigation measures.

11

Summary of Environmental Outcome

To summarise the key environmental outcomes arising from the EIA Study.

12

Environmental Monitoring and Audit Requirements

To define the scope of the EM&A requirements for the Project.

13

3-Dimensional EIA

To describe the 3-Dimensional EIA for this Study.

14

Conclusion

To conclude the assessment results of the EIA Study.


2                  Description of the Project

2.1                 General Description of the Project

The development of the NENT Landfill Extension (hereafter referred to “the Project”) will involve the following works:

·         Site formation and preparation.

·         Installation of liner system.

·         Installation of leachate collection, treatment and disposal facilities.

·         Installation of gas collection, utilization and management facilities.

·         Utilities provisions and drainage diversion.

·         Operation of landfill.

·         Restoration and aftercare in subsequent stages.

·         Measures to mitigate environmental impacts as well as environmental monitoring and auditing to be implemented.

2.2                 Key Project Requirements

The key project requirements for the NENT Landfill Extension are:

·         Development of a sanitary landfill that covers an area of about 70 ha with an estimated void space (landfill capacity) of 19Mm3;

·         Provision of a liner system for the landfill to prevent contamination of land and water resources;

·         Provision of a leachate collection, treatment and disposal facilities with sufficient capacity for handling the leachate arising from the landfill extension;

·         Provision of landfill gas collection, utilisation and management facilities;

·         Provision of utilities, drainage and road network necessary for the proper operation of the Project;

·         Provision of facilities (both civil works and electrical & mechanical equipment) for waste reception, inspection, charging, handling and compaction, and plant maintenance;

·         Provision of facilities for site administration;

·         Operation of the landfill in compliance with all relevant engineering, geotechnical and environmental standards;

·         Restoration of the landfill in compliance with all relevant engineering, geotechnical and environmental standards;

·         Provision of aftercare for the landfill for a period of about 30 years;

·         Carrying out environmental monitoring and audits throughout construction, operation, restoration and aftercare of the landfill; and

·         Implementation of environmental measures necessary for the protection of the surrounding environment.

2.3                 Need for the Project

2.3.1            Growing Wasteloads

Waste is a common problem of affluent societies. Especially when people can afford greater convenience and more purchases, they tend to generate a higher volume of waste per capita. Hong Kong is no exception to this. Like many other modern cities, Hong Kong has seen its wasteloads increase following the economic growth.  Municipal wasteloads have grown on average of about 3% per year since 1986.  With the population growth at 0.9% each year, the waste generation rate has risen from 1.96 kg per person per day in 1996, to 2.27 kg in 2004 (Figure 2.1).

Text Box:

 

 

MSW Generation: 3% average annual growth

Population: 0.9% average annual growth

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Figure 2.1  Waste line grew from 1996 to 2004 [extracted from EPD” Policy Framework for the Management of MSW (2005-2014)”]

 

Hong Kong’s waste arising have exceeded the expected amount. At the time when the three existing strategic landfills, SENT Landfill, NENT Landfill and WENT Landfill, were planned, it was forecasted that the daily amount of waste to be disposed of at landfills would rise from 12,500 tonnes in 1989, to 14,000 tonnes in 1997 and 16,700 tonnes by 2001. By 1997 the three strategic landfills were already taking in 16,000 tonnes of waste every day. Should this trend continue, the landfills will be full by 2015, instead of lasting until 2020 as they were originally designed for.

Although all measures outlined in the Policy Framework for the Management of Municipal Solid Waste (2005-2014) including source separation, MSW charging, waste recycling, IWMF, etc. would help extend the lives of the three landfills, the residues from the IWMF will still require sites for final disposal and landfill site is therefore necessary. 

 

The reality is that HK, like all other developed cities around the world, will need landfills as the final means of disposal.  Assuming the Government’s target of reducing the waste going to landfill site from 60% in 2004 to 25% by 2014 will be achieved, some 4000 tonnes per day of waste still needs to be disposed of at landfill sites. Therefore, outlets for landfill sites for final disposal of solid waste are still required.  Extensions of existing landfill sites have been identified as an indispensable element for the management of waste in Hong Kong.  Justifications of the need for providing additional void space for waste disposal by developing extension at the existing NENT Landfill are provided in the following sections.

2.3.2            Justification of Developing Extension at NENT Landfill

With a clear Government strategy to achieve sustainable management of the MSW in the next 10 years, it is anticipated that the amount of solid waste requiring landfill disposal will start to reduce gradually.  Having said that, there will still be millions of tonnes of un-recyclable or unrecoverable waste requiring disposal each year. With the three existing strategic landfills envisaged to be exhausted between Year 2011 to 2015 and the long lead time required for developing new landfills, there is a need to identify an intermediate solution.

EPD had therefore commissioned a study in February 2000 to explore the potential of extending the existing landfills and identify potential new landfill sites.

Given that it will take many years to confirm suitability of a new landfill location, extensions of the existing landfills were considered a practicable, necessary and urgent intermediate solution.  Key advantages of the extension schemes include:

·         Availability of existing supporting infrastructure and therefore less lead time for the development.

·         Availability of existing supporting infrastructure and therefore more cost effective for the development.

·         Availability of accurate information and hence lower level of risk in capital and operating costs estimation.

·         Availability of existing environmental monitoring data and hence more reliable for confirming environmental acceptability of the Project.

·         Availability of existing supporting infrastructure and therefore less requirements on land resumption for the development.

·         Availability of existing supporting infrastructure and therefore potentially less impact on the environment in comparison with a new green field site scheme.

·         Established site specific procedures for operation and environmental impact control.

These key advantages are recognised at the NENT Landfill for the proposed extension.

2.4                 Consideration of Alternatives

2.4.1            Alternative Extension Layout

In working out the most desirable layout for NENT Landfill Extension, a number of layout options were formulated, evaluated and then compared for selection, based on various evaluation criteria and an evaluation framework agreed with relevant stakeholders in advance.

The key issues and constraints identified during the course of study were taken into account in formulation of landfill extension layout options.  A total of 4 broad options (as well as related sub-options) were thoroughly evaluated and discussed at a Value Management Workshop on 2 December 2005, attended by relevant stakeholders. Key features of the various options are recapitulated below.

2.4.2            Broad Layout Option 1

2.4.2.1       Option 1

Option 1 adopts a similar rationale as the proposed conforming scheme in the EPD’s preliminary study under “Agreement No. CE45/99, Extension of Existing Landfills and Identification of Potential Waste Disposal Sites, Final Strategic Environmental Assessment Report”.  It achieves a landfill capacity of 17Mm³, and infringes a minor part of the Tong To Shan Archaeological Site (TTSAS). The area of built heritage affected will only be limited to the secondary features of boulder paths and stone terraces.  The main archaeological features will be untouched (see Drawing No. 24315/01/101 for layout).  The key parametric indicators of this option are outlined below in Table 2.1.

Table 2.1: Summary of Option 1

Waste receiving area

60 ha

Maximum fill level

+245 mPD

Site formation complexity

Cut volume 5.9 Mm³, Fill volume 2.3 Mm³

Landfill capacity

17.4 Mm³

2.4.2.2       Option 1a

Option 1a is similar to Option 1 except with the slight extension to the southern boundary and the increase in fill level to meet the target landfill capacity of 19Mm³.  The design is achieved by raising the eastern part of the landfill extension by approximate 10m relative to the original design to reach a maximum level of +255mPD (see Drawing No.  24315/01/102).  The maximum height of the adjacent Wo Keng Shan is about +297mPD.  It is envisaged that the visual impact due to a 10m raise would be insignificant.  The key parametric indicators of this option are outlined in Table 2.2.

Table 2.2: Summary of Option 1a

Waste receiving area

61 ha

Maximum fill level

+255 mPD

Site formation complexity

Cut volume 6.0 Mm³, Fill volume 2.2 Mm³

Landfill capacity

20.2 Mm³

2.4.2.3       Option 1b

Option 1b is derived based on Options 1 and 1a, with the same encroachment to TTSAS, to further increase the landfill capacity. The design is achieved by the slight extension to the south boundary and the increase in fill level to +300mPD (see Drawing No. 24315/01/103).  This roughly matches with the maximum elevation of +297mPD of the adjacent Wo Keng Shan.  The key parametric indicators of this option are outlined in Table 2.3.

Table 2.3: Summary of Option 1b

Waste receiving area

61 ha

Maximum fill level

+300 mPD

Site formation complexity

Cut volume 6.0 Mm³, Fill volume 2.2 Mm³

Landfill capacity

25.2 Mm³

 


2.4.3            Broad Layout Option 2

2.4.3.1       Option 2

Option 2 avoids the encroachment on TTSAS and keeps the peak level the same as Option 1 (i.e. +245mPD).  This will reduce the actual landfill capacity to 16.8Mm³ (see Drawing No. 24315/01/104).  The key parametric indicators of this option are outlined in Table 2.4.

Table 2.4: Summary of Option 2

Waste receiving area

55 ha

Maximum fill level

+245 mPD

Site formation complexity

Cut volume 4.7 Mm³, Fill volume 2.0 Mm³

Landfill capacity

16.8 Mm³

2.4.3.2       Option 2a

Similar to Option 2, Option 2a also avoids the encroachment on TTSAS and again falls short of meeting the target capacity of 19Mm³.  The design deviates from Option 2 by raising the eastern part of the landfill extension by approximate 10m to reach a maximum level of +255mPD (see Drawing No. 24315/01/105).  The key parametric indicators of this option are outlined in Table 2.5.

Table 2.5: Summary of Option 2a

Waste receiving area

55 ha

Maximum fill level

+255 mPD

Site formation complexity

Cut volume 4.7 Mm³, Fill volume 2.0 Mm³

Landfill capacity

18.4 Mm³

2.4.4            Broad Layout Option 3

Archaeological survey conducted on the site has identified a number of large graves in the heart of the landfill extension. Option 3 is developed with extensive reinforced earth wall at the northern boundary to avoid the need for clearance of these existing large graves (Drawing No. 24315/01/106). The landfill capacity will however be reduced to only 11.1Mm³.  The key parametric indicators of this option are outlined in Table 2.6.

Table 2.6: Summary of Option 3

Waste receiving area

50 ha

Maximum fill level

+245 mPD

Site formation complexity

Cut volume 3.7 Mm³, Fill volume 2.8 Mm³

Landfill capacity

11.1 Mm³

2.4.5            Broad Layout Option 4

Option 4 is developed with the northwestern and southeastern boundary extended to reach the ridgeline to maximize the landfill capacity.  The northern boundary is also set back to minimize the impact to woodland as well as TTSAS (see Drawing No. 24315/01/107).   The landfill capacity can achieve 21.4Mm³ while encroachment on the Lin Ma Hang catchment can be totally avoided.  The key parametric indicators of this option are outlined in Table 2.7.

Table 2.7: Summary of Option 4

Waste receiving area

63 ha

Maximum fill level

+255 mPD

Site formation complexity

Cut volume 6.2 Mm³, Fill volume 2.2 Mm³

Landfill capacity

21.4 Mm³

 

2.4.6             Selection of Preferred Scenario

2.4.6.1             Evaluation Criteria

These options were evaluated / assessed in accordance with the following factors and main criteria :

·         Waste management needs of 19Mm3 void space for the NENT Landfill Extension;

·         Engineering considerations including site formation complexity, constructability, drainage impact and maintenance;

·         Environmental issues such as noise, air quality, ecology, landscape and visual, waste management, cultural heritage, water quality, etc.

·         Social issues such as afteruse flexibility, cost of disposal, land resumption and graves clearance. 

2.4.6.2       Waste Management Needs

Under the previous study ”Agreement No. CE45/99, Extension of Existing Landfills and Identification of Potential Waste Disposal Sites, Final Strategic Environmental Assessment Report”, the “Strategic Plan” for the development of NENT Landfill Extension required a void space (landfill capacity) of 19Mm3 to be provided.  Options 1, 2, 2a and 3 cannot achieve this target volume.  Options 1a, 1b and 4 can achieve this target and are therefore preferred.

2.4.6.3       Engineering Considerations

The major engineering considerations relate to construction practicability, drainage impact to downstream rivers and requirements on operation and maintenance of the various facilities are discussed as follows:

 

Construction Practicability

The optimum engineering design of a landfill site is to maintain a balance in cut and fill material over the entire construction and operation periods. Importing or exporting construction material is not preferred.  In this regard, all the four broad options including sub-options can achieve this requirement.

According to the recent ground investigation (GI) data, there is no particular geological constraint in the proposed landfill extension site.  Site formation and retaining structures for all options are feasible to construct. All options will experience the same founding condition and reinforced fill slopes will be adopted for retaining structures taller than 10m

Although Options 1, 1a, 1b, 2, 2a and 4 require the construction of reinforced earth wall, they do not affect the site formation planning and are therefore preferred.  By contrast, Option 3 requires construction of a long reinforced earth wall at the north within a small site area, hence imposing great difficulties on the phasing and sequencing of the site formation works.  Option 3 is therefore less preferable.

Drainage Impact to Downstream

All options affect the existing landform and may have impact to the adjacent drainage systems at both Lin Ma Hang Stream and Ping Yuen River.   

According to the Drainage Impact Assessment (DIA) conducted for this Project, the diversion of catchment in some options will result in increased water level in Ping Yuen River and decreased water level in Lin Ma Hang Stream. In other words, the less the impact on stream and river, the more preferable the option.

Options 2, 2a, Option 3 and Option 4 that have no drainage impact to Lin Ma Hang Stream are therefore preferred.  Option 1, 1a and 1b have drainage impact to both Lin Ma Hang Stream and Ping Yuen River and are therefore less preferable.

Operation and Maintenance

The operation and maintenance requirements for various facilities such as treatment facilities, drainage system, E&M equipment, water quality, leachate and landfill gas monitoring equipment, etc. are similar for all the 4 options.

Option 1, 1a and 1b are preferred as they have only a small section of reinforced earth wall, which requires less maintenance works.  Options 2, 2a, 3 and 4 require more substantial maintenance works for the reinforced earth wall and the associated drainage system, and are therefore less preferable.

2.4.6.4       Environmental Issues

The major environmental considerations relate to water quality, ecology, archaeology and cultural heritage, landscape and visual etc. at various project phases are discussed as follows:

Water Quality Impact

Some of the landfill extension options may encroach to both Lin Ma Hang and Ping Yuen Catchments.  There may be certain degree of influence of water flow/yield on Lin Ma Hang Stream and Ping Yuen River.  In case of any accidental overflow from the treatment plant or accidental leakage through the liner, there might be short-term impact on the adjacent streams.

Options 2, 2a, 3 and 4 with no encroachment to Lin Ma Hang Catchment are therefore preferred whereas, Option 1, 1a and 1b with encroachment to both Lin Ma Hang Catchment and Ping Yuen Catchment are less preferable.

Ecological Impact

Some of the landfill extension options may cause minor ecological impacts to the Lin Ma Hang Stream due to reduction in water level and loss of woodland and shrubland.  Option 1, 1a and 1b will cause minor ecological impacts to Lin Ma Hang Stream due to a 15mm drop in water level and are therefore less preferable.  Options 2, 2a, 3 and 4 will have neither encroachment nor ecological impacts on Lin Ma Hang Stream, and are preferred options.    

Woodland of over 1 ha is considered as an important habitat.  Option 1, 1a and 1b will cause a significant loss of woodland of more than 5ha and are thus less preferable.  For other options, the impact on loss of woodland, ranging from 2 to 4 ha, are considered to be moderate in term of ecological value. Compensatory woodland planting would be provided.  These options are therefore preferred with mitigation measures being in place.

With consideration of a cumulative combination of ecological impacts (drop in water level and loss in woodland), Options 1, 1a, 1b and 4 are less preferable.  Options 2, 2a and 3 are preferred.

Archaeological and heritage Impact

Some of the landfill extension options may encroach into TTSAS affecting secondary features such as boulder paths and boulder terraces.  A total of 21 graves including 10 old graves will be affected and will need to be removed. In terms of impacts to graves, all options have the same grade as these can be mitigated by detailed preservation by record as agreed with AMO, LCSD.

Option 1, 1a and 1b will encroach into TTSAS by about 5 ha, affecting of 200m boulder paths and 2 numbers of boulder terraces. Nonetheless, these affected areas comprise mainly secondary features and can be mitigated by detailed preservation by record (as agreed with AMO).  Therefore, these options are less preferable.

Options 2, 2a and 3 will have no impact to the TTSAS and are therefore preferred.  Similarly, Option 4 affects only 30m of boulder path (secondary feature only) which can be mitigated by detailed preservation by record.  The impact on Option 4 is therefore also minimal and this option is preferred. 

Landscape and Visual Impact

Option 1a will have a total area of about 61 ha which encroaches into about 5.16 ha of woodland near the ridge of Wong Mau Hang Shan, Shui Ngau Tso and northeast of Wo Keng Shan.  The final height of the landfill is about +255mPD.  

Option 2a will have a total area of about 54 ha which encroaches into about 3.08 ha woodland near the ridge of Shui Ngau Tso and northeast of Wo Keng Shan.  The final height of the landfill is about +255mPD.

Option 3 will have a total area of about 50 ha which encroaches into about 3.05 ha of woodland near Shui Ngau Tso and northeast of Wo Keng Shan.  The final height of the landfill is about +245mPD which is similar to the adjacent Wong Mau Hang Shan. 

Option 4 will have a total area of about 63 ha and encroach into about 3.7ha of woodland near the ridge of Shui Ngau Tso and northeast of Wo Keng Shan.

In fact, the visual impact to the adjacent areas for all options is similar with slight impact (also see Chapter 8).

Other environmental considerations

Other environmental considerations, including air, noise, waste, landfill gas, have been reviewed.  The potential impacts for all options are similar in order and can all be mitigated by suitable mitigation measures. 

2.4.6.5             Impact on Community

The major community considerations relate to flexibility for aftercare, unit cost per disposal, needs for land resumption and needs for graves clearance at various project phases are discussed as follows:

Flexibility for Afteruse

The proposed extension is expected to last for about 10 to 12 years.  Options that can offer higher flexibility to the potential afteruse of the landfill are preferred.

Options 1, 1a, 1b and 4 will cover areas of 60 ha to 63ha in size.  The gradients of the final landfill profile for these options are gentle and suitable for all type of afteruse activities.  These options would not impose any restriction/limitation to the afteruse planning. They are the preferred options.

Option 2 and 2a will cover an area of 55 ha only. The gradient of the final landfill profile is gentle with slight variation.  This option would not impose any restriction/limitation to the afteruse planning.  However, this option has less planning flexibility in view of the smaller landfill area and is therefore less preferable.

Similarly, Option 3 has the smallest landfill area of only 50 ha with steep gradient at certain locations.  The steep slope may inevitably impose additional constraints to the potential afteruse and the planning flexibility of other facilities such as bowling greens and multi-purposes grass pitches. This option is therefore also less preferable.

Unit Cost per Disposal

The unit cost per disposal is the capital cost divided by the actual landfill capacity, which is the cost required to produce a 1m3 landfill capacity.  The higher the unit cost per disposal, the higher the chance of illegal dumping.

The anticipated unit cost per disposal (m³) for Options 1, 1a, 1b, 2, 2a and 4 are of similar order, which is about half of that for Option 3. Based on the above cost estimation, Options 1, 1a, 1b, 2, 2a and 4 are “preferred”; while Option 3 is “less preferable”.

Needs for Land Resumption

All Options will affect the same number of private lots.  Nonetheless, Option 1, 1a and 1b affect a Government Hilltop Survey Tri-Station (GLA) and are therefore less preferable.  Hence, Options 2, 2a, 3 and 4 are preferred.

Needs for Graves Clearance

According to recent survey, there are a large number of graves including some old graves lying within the extension site.  All options affect almost the same number of graves including old graves except for Option 3 which affect a much smaller number of graves (9 to 10 graves less).  Option 3 is therefore preferred.  All other options are less preferable since a longer lead time would be required on liaison in the graves clearance process.

2.4.6.6       Overall

Amongst the three options in Broad Layout Option 1, Option 1a is the most preferred.  Similarly, Option 2a is the most preferred option under Broad Layout Option 2.  Accordingly, Option 1a and Option 2a were therefore directly compared with Option 3 and Option 4, so as to arrive at the most favourable layout for NENT Landfill Extension.  A summary of the final round of layout options selection is tabulated below.

Table 2.8: Summary of reasons for option evaluation

Criteria 

Option 1a

Option 2a

Option 3

Option 4

(A) Waste Management Needs

20.2 Mm³ - achieving the target requirement of 19Mm3 .

(Preferred)

18.4 Mm³ - marginally falls short of meeting target requirement of 19Mm3 .

(Less Preferred)

 

11.1 Mm³ - falls short of meeting target requirement of 19Mm3 .

(Less Preferred)

21.4 Mm³ - achieving the target requirement of 19Mm3 .

(Preferred)

(B) Engineering

Construction Practicability

No imported fill material is required for the site formation works;

Require short (100m) reinforced earth wall with max. height of 15m.

(Preferred)

No imported fill material is required for the site formation works;

Require relatively long (400m) reinforced earth wall with max. height of 25m.

(Preferred)

No imported fill material is required for the site formation works;

Require relatively long reinforced earth wall (with max. height of 25m) in a relatively small site and impose difficulties in site formation phasing.

(Less Preferred)

 

No imported fill material is required for the site formation works;

Require relatively long reinforced earth wall (with max. height of 25m) but will not impose difficulties in site formation phasing.

(Preferred)

Drainage Impact to Downstream

Impact to both Lin Ma Hang Stream and Ping Yuen River.

(Less Preferred)

Impact to Ping Yuen River (no impact on Lin Ma Hang).

(Preferred)

Impact to Ping Yuen River (no impact on Lin Ma Hang).

(Preferred)

Impact to Ping Yuen River (no impact on Lin Ma Hang).

(Preferred)

 

Operation and Maintenance

Require maintenance of a short reinforced earth wall and associated drainage system (100m).

(Preferred)

Require maintenance of a relatively long reinforced earth wall and associated drainage system (400m).

(Less Preferred)

Require maintenance of a relatively long reinforced earth wall and associated drainage system (510m).

(Less Preferred)

Require maintenance of  a relatively long reinforced earth wall and associated drainage system (590m).

(Less Preferred)

(C) Environmental

Water Quality Impact

Impact to both Lin Ma Hang Stream and Ping Yuen River

(Less Preferred)

Impact to Ping Yuen River (no impact on Lin Ma Hang)

(Preferred)

Impact to Ping Yuen River (no impact on Lin Ma Hang)

(Preferred)

 

Impact to Ping Yuen River (no impact on Lin Ma Hang)

(Preferred)

Ecology Impacts

Minor impact to the Lin Ma Hang Stream & its catchment;

Relatively large scale  of woodland loss (5.16ha);

No impact to Lin Ma Hang Lead Mines;

Minor impact to the  Robin’s Nest countryside;

 (Less Preferred)

No impact to the Lin Ma Hang Stream & its catchment;

Small scale of woodland loss (3.08ha)

No impact to Lin Ma Hang Lead Mines;

Minor impact to the Robin’s Nest countryside;

 (Preferred)

 

No impact to the Lin Ma Hang Stream & its catchment;

Small scale of woodland loss (3.05ha)

No impact to Lin Ma Hang Lead Mines;

Minor impact to the Robin’s Nest countryside;

(Preferred)

No impact to the Lin Ma Hang Stream & its catchment;

Medium scale of woodland loss (4.01ha)

No impact to Lin Ma Hang Lead Mines;

Minor impact to the Robin’s Nest countryside;

 (Less Preferred)

Archaeological and Heritage Impact

Encroach into small (non-core) portion  of TTSAS (5ha).

Affect 21 graves including 10 old graves (no impact on cultural heritage value).

(Less Preferred)

No impact to TTSAS.

Affect 20 graves including 9 old graves (no impact on cultural heritage value).

(Preferred)

No impact to TTSAS.

Affect only 9 graves and avoid all old graves (no impact on cultural heritage value).

(Preferred)

Encroach into very small (non-core) portion  of TTSAS (2ha).

Affect 20 graves including 9 old graves (no impact on cultural heritage value).

(Preferred)

Landscape & Visual

Total landfill area is 61ha; final fill level at +255mPD.

(Insignificant landscape & visual impact)

Total landfill area is 55ha; final fill level at +255mPD.

(Insignificant landscape & visual impact)

Total landfill area is 50ha; final fill level at +245mPD.

(Insignificant landscape & visual impact)

Total landfill area is 63ha; final fill level at +255mPD.

(Insignificant landscape & visual impact)

Other Environmental Considerations, such as air, noise, landfill gas, waste

Neutral to various options – minor impact which can be mitigated by suitable mitigation measures.

(similar impact to other options)

Neutral to various options – minor impact which can be mitigated by suitable mitigation measures.

(similar impact to other options)

Neutral to various options – minor impact which can be mitigated by suitable mitigation measures.

(similar impact to other options)

Neutral to various options – minor impact which can be mitigated by suitable mitigation measures.

(similar impact to other options)

(D) Impact on Community

Flexibility for afteruse

Largest landfill area (61ha) with gentle slopes/ gradient – good for all kinds of afteruse.

(Preferred)

Smaller landfill area (55ha) with gentle slopes/gradient, but vary in landfill profile and hence less planning flexibility.

(Less Preferred)

Smallest landfill area (50ha) with steep slope and extensive earth wall.  Hence, impose constraints to the potential afteruses.

(Less Preferred)

Highest landfill area (63ha) with gentle slopes/ gradient – good for all kinds of afteruse.

(Preferred)

Unit Cost per Disposal

Comparable with other options except Option 3.

(Preferred)

Comparable with other options except Option 3.

(Preferred)

Higher disposal cost leading to higher chance of illegal dumping.

(Less Preferred)

Comparable with other options except Option 3.

(Preferred)

Need for Land Resumption

Affect private lands and survey station

(Less Preferred)

Affect only private lands (no impact on survey station)

(Preferred)

Affect only private lands (no impact on survey station)

(Preferred)

Affect only private lands (no impact on survey station)

(Preferred)

Need for Graves Clearance

Affect 21 graves including 10 old graves (no impact on cultural heritage value)

(Less Preferred)

Affect 20 graves including 9 old graves (no impact on cultural heritage value)

(Less Preferred)

Affect 9 graves and aovid all old graves (no impact on cultural heritage value)

(Preferred)

Affect 20 graves including 9 old graves (no impact on cultural heritage value)

(Less Preferred)

As Option 4 was evaluated as a preferred option for the largest number of aspects, it was selected as the overall most preferred option.  See Drawing No. 24315/01/107 for the layout of Option 4.

2.4.7            Alternative Construction Methods and Sequences of Works 

Different construction methodology and sequences of works were studied, giving careful consideration on environmental impacts including noise, ecology, archaeology, etc.

It is recommended to adopt a balanced cut-and-fill site formation for constructing the landfill bowl within the existing valley.

The NENT Landfill Extension will be developed in three phases to allow progressive use of the overall landfill area.  Each phase will be constructed, operated and restored at a rate dependent on the delivery of waste.  Simultaneous construction, operation and capping activities will therefore occur in different parts of the site.

During the construction stage, mobilisation & preparation / establishment will be carried out by the DBO Contractor.  A balance between cut-and-fill quantities will be adopted to optimise the reuse of excavated materials, i.e. to minimise import or export of materials.  The process involves temporarily stockpiling of excavated materials on site for use as daily cover during the operation phase and final capping during the restoration phase.  This will reduce construction materials / waste to be delivered to public fill bank.  Where necessary (to be triggered by EM&A programme), daily cover and temporary cover will be provided to reduce potential impact on air and water qualities during the operation phase of the Project.

Alternative construction methods such as blasting have also been evaluated but found to be not desirable from an engineering perspective.  The balancing of cut-and-fill limits the usable area of the landfill site and therefore the amount of stockpiled materials.  Blasting will generate a significantly larger volume of excavated and stockpiled materials, and the usable area of the landfill site will be much reduced.  There is also a safety concern if blasting is conducted in close proximity to the tipping area, as refuse collection vehicles and operators might be at risk if the buffer distance provided is not sufficient. 

2.5                 Site Location and Site History

2.5.1            Site Location

The landfill extension site of the selected layout is approximately 70 ha in size and located in a valley to the south of the existing NENT Landfill. The valley is encircled by three ridgelines and exits to the southwest through a small gorge, at approximately +50mPD.

On its south-eastern side, the site is enclosed by a major ridgeline, which runs from Wo Keng Shan (+297mPD) to Robins Nest (+492mPD). A smaller ridge intersects this main ridgeline and forms the northern flank of the Project area. This ridge overlooks To Tong Shan Settlement District and Lin Ma Hang Village. It reaches an elevation of +205mPD at its western end, just beyond the boundary between the existing NENT Landfill and the extension site. Two saddles, with minimum elevations of approximately +120mPD, are located about half way along this smaller ridge.

The ridge separating the site from the existing NENT Landfill forms the north-western boundary of the Project area. This ridge runs from an elevation of +205mPD at its northern end to a level of +65mPD at the point where it intersects the existing haul road in the south-western corner of the site (Drawing No. 24315/01/001).

The slopes overlooking the main valley of the site are sparsely vegetated with a cover of grass and shrubland. Occasional groups of pine trees and localised dense vegetation are also found along stream courses.

2.5.2            Site History

The proposed extension is mainly covered by the existing NENT Landfill Stockpile and Borrow Area that was formed to the east of the existing landfill as part of the original landfill development.  The aerial photographs of the site reveals that several large cut slopes, many of which have been subsequently covered with stockpiled material, and a haul road (Shek Tsai Ha Road) have been formed within. The stockpile area is mostly located within the eastern portion of the site and is bound by concrete drainage channels. Other than the haul road and scattered gravesites, the remaining site area comprises natural terrain that has seen little interference from human activity.

2.6                 Nature, Scope and Benefits of the Project

2.6.1            Nature of the Project

The nature of the Project is to develop a landfill extension for waste as defined in the Waste Disposal Ordinance (Cap. 354).

2.6.2            Scope of the Project

The scope of the Project is to provide a landfill extension of about 70 hectares with a target void space of at least 19 million cubic metres on the eastern side of the existing NENT Landfill. On top of site formation and preparation works; there will be provision of installation of liner system; leachate collection, treatment and disposal; gas collection and management; utilities provisions; drainage diversion; restoration and aftercare. Environmental mitigation measures, monitoring and auditing are provided.

2.6.3            Benefits of the Project

The development of NENT Landfill Extension ensures the continued provision of final disposal site for solid waste after the three existing landfills are full by 2015.

It also avoids illegal dumping of construction waste and municipal waste that may cause serious environmental problems.

With waste-to-energy facility (such as Landfill Gas Export Scheme), landfill gas can be converted to reusable energy that brings benefits to the community.

The Project site is equipped with waste handling facilities at NENT Landfill, waste recycling factories in the nearby area, sewage treatment facility at Shek Wu Hui Sewage Treatment Works, and a landfill gas waste-to-energy facility nearby. The availability of these existing supporting facilities can shorten the lead time and land resumption requirement for a new landfill development in a green field site. 

Substantial saving in cost can also be achieved by pooling together the existing NENT Landfill infrastructure and facilities by carrying out suitable conversion works under suitable contractual arrangement.

There are some small-scale waste recycling factories around the existing NENT Landfill, skilful workers and special equipments have been allocated in the region. Therefore, there will be social and economic benefit of the Project, if these workers and equipments can be tied in with the NENT Landfill Extension (e.g. sustainable for local employment).

2.7                 Size, Scale, Shape and Design of the Project

The landfill extension site is a bowl-shape area with a large void space in the middle for waste filling. The northwestern and southeastern boundaries of the landfill extension site follow the ridgelines to maximize the landfill capacity.  Some set back of the northern boundary is included to minimize the impact to woodland and Lin Ma Hang Catchment. The total site area is about 70 ha and the final height of the landfill would be +255mPD (see Drawing No. 24315/01/107).

The key design features are listed as follows and summarised in Table 2.10:

·         Bottom liner system - to separate rubbish and leachate from groundwater;

·         Landfill cells – to store waste within the unit;

·         Storm water drainage system - to collect rain water run off on the landfill;

·         Leachate collection system - to collect liquid leaching from the waste mass and convey it to a leachate treatment plant prior to discharging to Shek Wu Hui Sewage Treatment Works;

·         Gas collection system - to collect gases formed during the decompositon of waste. These gases will be treated and utilised for production of electricity on site.

·         Covering and capping - to seal off the top of the landfill with a gas venting layer, an impermeable mineral layer, a drainage layer of at least 0.5 metre and at least one metre of top soil.

Table 2.10: Summary of key design elements

Total size

63 ha

Final height

+255 mPD

Shape

Bowl shape at the existing NENT Landfill Stockpile and Borrow Area

Site formation complexity

Cut volume 6.2 Mm³, Fill volume 2.2 Mm³

Actual waste capacity

21.4 Mm³

Key elements of design

•     Site formation and preparation

•     Installation of liner system

•     Installation of leachate collection, treatment and disposal facilities

•     Installation of gas collection, utilization and management facilities

•     Utilities provisions and drainage diversion        

 

Various activities during construction, operation, restoration and aftercare of landfill are discussed in the following sub-sections.

2.7.1            Construction Phase and Activities 

Simple excavation and slope formation works will be carried out during the construction stage.  The permanent works comprise cut and fill earthworks, slope formation and earth wall construction.  The temporary works will involve the formation of temporary ditches along the sides of the excavations and associated drainage works, and material storage areas.

During site formation, sediment will be contained in permanent detention ponds/silt traps that will be constructed according to landfill phasing. Final design and location of sediment traps are yet to be decided, but are likely to be down gradient of each landfill phase or in the downstream valleys near the existing waste reception area.  Where possible they will be maintained during the operation of each phase to ensure the effective control of operational soil erosion problem.

2.7.2            Operation Phase and Activities 

During operation, waste will be disposed of at individual landfill cells.  Deposited waste will be compacted to thin layers.  The works will be maintained at a gradient of not greater than 1 in 3 to ensure the effectiveness of the compaction equipment.  Daily cover (about 150mm if soil cover used) will be applied to control environmental nuisances such as windblown litter, odour, vermin, flies and birds.

There are other more effective alternative biodegradable materials for use as daily cover. They include:

·         heavy duty reusable and biodegradable sheets;

·         non reusable plastic films;

·         geotextiles; and

·         foams and sprays.

Advantages of using alternative daily cover over traditional methods include preservation of landfill capacity and soil material; biodegradable and less permeable to water and gas (reduce water infiltration, odour and dust emission).

2.7.3