5          WATER QUALITY IMPACT 

5.1          Introduction 

5.2          Environmental Legislation, Standards and Guidelines 

5.3          Baseline Conditions 

5.4          Water Sensitive Receivers 

5.5          Potential Impacts of Different Phases 

5.6          Construction Phase 

5.7          Operation Phase 

5.8          Restoration and Aftercare Phase 

5.9          Cumulative Impacts 

5.10        Residual Impacts 

5.11        Conclusion 

5.12        Reference 

 

Appendices

Appendix 5.1        Groundwater monitoring data of Existing WENT Landfill in 2006 and 2007

Appendix 5.2        Groundwater measurement results for WENT Landfill Extension

Appendix 5.3        Meteorological Data

Appendix 5.4        Leachate Generation for Existing WENT Landfill

 

Figures

Figure 5.1             Groundwater Monitoring Stations at Existing WENT Landfill

Figure 5.2             Marine Water Quality Monitoring Stations (DM4, DM5 and NM5)

Figure 5.3             River Water Monitoring Stations in Deep Bay Water Control Zone

Figure 5.4             Water Sensitive Receivers

Figure 5.4a           Proposed Drainage Layout

Figure 5.5             Groundwater Contours for WENT Landfill Extension

Figure 5.6             Schematic Diagram of the Leachate Treatment Plant

 

 

 

 

 

 

5                  WATER QUALITY IMPACT

5.1                 Introduction

This chapter presents the assessment of potential water quality impacts, which may arise during the construction, operation, restoration and aftercare of the WENT Landfill Extension.  Mitigation measures have been proposed to alleviate the potential water quality impact.  The residual water quality impact was assessed to be acceptable.

The water quality impact assessment has been conducted in accordance with Annexes 6 and 14 of the TM-EIAO and the EIA Study Brief for the Project.

5.2                 Environmental Legislation, Standards and Guidelines

The following relevant legislation and associated guidelines are applicable to the evaluation of water quality impacts associated with the construction, operation, restoration and aftercare of the Project:

·          Environmental Impact Assessment Ordinance (Cap.499, S.16), Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO), Annex 6 and 14 [5-1];

·          Water Pollution Control Ordinance (WPCO, Cap 358) [5-2];

·          Technical Memorandum on Standards for Effluent Discharged into Drainage and Sewerage System, Inland and Coastal Waters (WPCO, Cap. 358, S.21) [5-3];

·          Practice Note for Professional Persons (ProPECC), Construction Site Drainage (PN1/94) [5-4];

·          EPD Pollution Control Clauses for Construction Contract [5-5];

·          Hong Kong Planning Standards and Guidelines (HKPSG) [5-6];

·          Others, e.g., standards of the United Kingdom (UK), European Union (EU), and United States Environmental Protection Agency (USEPA), etc. for those which are not specified in the WQOs.

The Water Pollution Control Ordinance (WPCO, Cap 358) provides the major statutory framework for the protection and control of water quality in Hong Kong. According to the Ordinance and its subsidiary legislation, the entire Hong Kong waters are divided into ten Water Control Zones (WCZs) and four supplementary WCZs. The existing WENT Landfill at Nim Wan and the proposed site for WENT Landfill Extension at some 5 km northwest of Tuen Mun overlooking Deep Bay and the Water Sensitive Receivers which may be affected by the Project works are located within the Deep Bay WCZ and the North Western WCZ.   Their corresponding WQO are listed in Table 5.1 and Table 5.2 respectively.

Table 5.1   Summary of Water Quality Objectives for Deep Bay WCZ

Parameters

Objectives

Sub-Zone

Offensive Odour, Tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved Oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/L for 90% of samples

Outer Marine Subzone excepting Mariculture Subzone

Dissolved Oxygen (DO) within 1 m below surface

Not less than 4.0 mg/L for 90% of samples

Inner Marine Subzone excepting Mariculture Subzone

Not less than 5.0 mg/L for 90% of samples

Mariculture Subzone

Depth-averaged DO

Not less than 4.0 mg/L for 90% of samples

Outer Marine Subzone excepting Mariculture Subzone

Not less than 4.0 mg/L

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone, Water Gathering Ground Subzones and other inland waters of the Zone

5-Day Biochemical Oxygen Demand (BOD5)

Not to exceed 3 mg/L

Yuen Long & Kam Tin (Upper)  Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones

Not to exceed 5 mg/L

Yuen Long & Kam Tin (Lower) Subzone and other inland waters

Chemical Oxygen Demand (COD)

Not to exceed 15 mg/L

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground

Not to exceed 30 mg/L

Yuen Long & Kam Tin (Lower)  Subzone and other inland waters

pH

To be in the range of 6.5 - 8.5, change due to waste discharges not to exceed 0.2

Marine waters excepting Yung Long Bathing Beach Subzone

To be in the range of 6.5 – 8.5

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones

To be in the range of 6.0 –9.0

Other inland waters

To be in the range of 6.0 – 9.0 for 95% samples, change due to waste discharges not to exceed 0.5

Yung Long Bathing Beach Subzone

Salinity

Change due to waste discharges not to exceed 10% of ambient

Whole zone

Temperature

Change due to waste discharges not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by waste discharges and shall not affect aquatic communities

Marine waters

Not to cause the annual median to exceed 20 mg/L

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Ganges Subzone, Indus Subzone, Water Gathering Ground Subzones and other inland waters

Unionized Ammonia (UIA)

Annual mean not to exceed 0.021 mg/L as unionized form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total Inorganic Nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.7 mg/L

Inner Marine Subzone

Annual mean depth-averaged inorganic nitrogen not to exceed 0.5 mg/L

Outer Marine Subzone

Bacteria

Not exceed 610 per 100ml, calculated as the geometric mean of all samples collected in one calendar year

Secondary Contact Recreation Subzones and Mariculture Subzones

Should be zero per 100 ml, calculated as the running median of the most recent 5 consecutive samples taken between 7 and 21 days.

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones

Not exceed 180 per 100ml, calculated as the geometric mean of the collected from March to October inclusive in one calendar year. Samples should be taken at least 3 times in a calendar month at intervals of between 3 and 14 days.

Yung Long Bathing Beach Subzone

Not exceed 1000 per 100ml, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days

Yuen Long & Kam Tin (Lower) Subzone and other inland waters

Colour

Not to exceed 30 Hazen units

Yuen Long & KamTin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones

Not to exceed 50 Hazen units

Yuen Long & KamTin (Lower) Subzone and other inland waters

Turbidity

Shall not reduce light transmission substantially from the normal level

Yuen Long Bathing Beach Subzone

Phenol

Quantities shall not sufficient to produce a specific odour or more than 0.05 mg/L as C6 H5OH

Yuen Long Bathing Beach Subzone

Toxins

Should not cause a risk to any beneficial uses of the aquatic environment

Whole Zone

Should not attain such levels as to produce toxic carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms.

Whole Zone

Source: Statement of Water Quality Objectives (Deep Bay Water Control Zone).

Table 5.2   Summary of Water Quality Objectives for North Western WCZ

Parameters

Objectives

Sub-Zone

Offensive odour, tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/l for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/l

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones, water gathering ground subzones and other inland waters

Not less than 4.0 mg/l for 90 % sample

Marine waters

pH

To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2

Marine waters excepting bathing beach subzones

To be in the range of 6.5 – 8.5

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water gathering ground subzones

To be in the range of 6.0 –9.0

Other inland waters

To be in the range of 6.0 –9.0 for 95% samples

Bathing beach subzones

Salinity

Change due to human activity not to exceed 10% of ambient

Whole zone

Temperature

Change due to human activity not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by human activity

Marine waters

Change due to waste discharges not to exceed 20 mg/l of annual median

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water gathering ground subzones

Change due to waste discharges not to exceed 25 mg/l of annual median

Inland waters

Unionized ammonia (UIA)

Annual mean not to exceed 0.021 mg/l as unionized form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total inorganic nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.3 mg/l

Castle peak bay subzone

Annual mean depth-averaged inorganic nitrogen not to exceed 0.5 mg/l

Marine waters excepting castle peak bay subzone

E.coli Bacteria

Not exceed 610 per 100 ml, calculated as the geometric mean of all samples collected in one calendar year

Secondary contact recreation subzones

Should be less than 1 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken between 7 and 21 days.

Tuen Mun (A) and Tuen Mun (B) subzones and water gathering ground subzones

Not exceed 1000 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken between 7 and 21 days

Tuen Mun (C) subzone and other inland waters

Not exceed 180 per 100 ml, calculated as the geometric mean of all samples collected from March to October inclusive.

Bathing beach subzones

Colour

Change due to waste discharges not to exceed 30 Hazen units

Tuen Mun (A) and Tuen Mun (B) subzones and water gathering ground subzones

Change due to waste discharges not to exceed 50 Hazen units

Tuen Mun (C) subzone and other inland waters

5-Day biochemical oxygen demand (BOD5)

Change due to waste discharges not to exceed 3 mg/l

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water gathering ground subzones

Change due to waste discharges not to exceed 5 mg/l

Inland waters

Chemical oxygen demand (COD)

Change due to waste discharges not to exceed 15 mg/l

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water gathering ground subzones

Change due to waste discharges not to exceed 30 mg/l

Inland waters

Toxins

Should not cause a risk to any beneficial uses of the aquatic environment

Whole zone

Waste discharge shall not cause the toxins in water significant to produce toxic carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms.

Whole zone

Phenol

Quantities shall not sufficient to produce a specific odour or more than 0.05 mg/l as C6 H5OH

Bathing beach subzones

 

Turbidity

Shall not reduce light transmission substantially from the normal level

Bathing beach subzones

Source:   Statement of Water Quality Objectives (North Western Water Control Zone).

5.3                 Baseline Conditions

5.3.1            Groundwater Condition – Existing WENT Landfill

Regular groundwater monitoring along the boundary of the existing WENT landfill site has been conducted since the commencement of the existing WENT Landfill. Groundwater samplings are currently conducted at groundwater monitoring wells. The groundwater sampling locations are shown in Figure 5.1.

According to Development and Management of WENT Landfill Contract Specification Section 35 “Landfill Monitoring”, the target levels of ammonia nitrogen (NH3-N), chemical oxygen demand (COD) and biological oxygen demand (BOD) for groundwater detected through routine monitoring at each groundwater monitoring point of the existing WENT Landfill are listed in the following table:

Table 5.3   Target levels of NH3-N, COD and BOD

Pollutants

Target Level (mg/l)

NH3-N

0.5

COD

20

BOD

5

Groundwater monitoring data presented in existing WENT Landfill’s monthly reports from 2006 to 2007 are shown in Appendix 5.1 and summarised below.  The results were generally in compliance with the specified trigger levels. It is observed that there is no contamination of leachate to the groundwater during the operation of the existing WENT Landfill.  The current engineering design of leachate management system is proven to be effective.

Table 5.3a - Groundwater Monitoring Data (2006 – 2007) for Existing WENT Landfill

Parameters

Unit

2006

2007

EC

mS/cm

0.04 – 25.70

0.04 – 16.60

pH

 

5.20 – 12.20

3.30 – 13.40

Temp

˚C

22.2 – 29.50

22.00 – 28.30

As

mg/L

0.00 – 0.03

0.00 – <0.01

Cr

mg/L

0.00 – 0.05

0.00 – 0.03

Zn

mg/L

0.00 – 0.14

0.00 – 0.09

Pb

mg/L

0.00 – <0.02

0.00 – <0.02

Cd

mg/L

0.00 – <0.001

0.00 – 0.002

Ni

mg/L

0.00 – 0.02

0.00 – 0.05

Fe

mg/L

0.00 – 0.71

0.00 – 1.20

Mn

mg/L

0.00 – 3.20

0.00 – 2.60

Mg

mg/L

0.01 – 400

0.01 - 180

Ca

mg/L

0.27 – 470

0.26 - 310

Cu

mg/L

0.00 – 0.02

0.00 – 0.01

Ag

mg/L

0.00 – <0.01

0.00 – <0.003

Ba

mg/L

0.00 – 0.52

0.00 – 0.21

Na

mg/L

5.90 – 3600

5.60 - 2900

K

mg/L

1.40 – 110

1.70 - 74

Soluble Hg

mg/L

0.00 – 0.0006

0.00 – <0.0003

BOD

mg/L

0.00 – <3

0.00 – <3

COD

mg/L

0.00 – 19.00

0.00 – 16.00

TSS

mg/L

0.00 - 250

0.00 – 88.00

CN-

mg/L

0.00 – <0.2

0.00 – <0.2

F-

mg/L

0.10 – 8.80

0.10 – 9.20

TOC

mg/L

0.00 – 6.00

0.00 – 5.00

CO32-

mg/L

0.00 - 110

0.00 - 130

HCO3-

mg/L

3.80 - 250

2.00 - 150

Ammonia

mg/L

0.00 – 0.40

0.00 – 0.40

Nitrite

mg/L

0.01 – 0.63

0.02 – 0.93

Nitrate

mg/L

0.02 – 5.80

0.02 – 5.60

TKN

mg/L

0.00 – 1.10

0.00 – 1.00

Cl-

mg/L

5.00 - 6300

4.00 - 3700

Reactive Phosphorus

mg/L

0.01 – 0.16

0.01 – 0.23

Sulhpide

mg/L

0.00 – 0.00

0.00 – 0.00

Sulphate

mg/L

2.00 - 840

4.00 - 550

E. Coli.

Count/100mL

0.00 - 1300

0.00 - 700

 

5.3.2            Groundwater Condition –WENT Landfill Extension

Additional groundwater monitoring data within the WENT Landfill Extension had been collected during 2007 and 2008.  The monitoring results are presented in Appendix 5.2 and summarised below.

Table 5.3b - Groundwater Monitoring Data for WENT Landfill Extension

Parameters

Unit

Range

Colour

PtCo

5-60

TSS

mg/L

210-2100

Total LMW PAH

ug/L

0.00-<0.10

Total HMW PAH

ug/L

0.00-<0.10

Total PCB

ug/L

0.00-<0.10

TPH (C6-C9)

ug/L

0.00-<20

TPH (C10-C14)

ug/L

0.00-<25

TPH (C15-C28)

ug/L

0.00-170

TPH (C29-C36)

ug/L

0.00-240

Pesticides

ug/L

0.00-<0.10

Ben

ug/L

0.00-<1.0

Tol

ug/L

0.00-<2

Etb

ug/L

0.00-<2

m,p-Xyl

ug/L

0.00-<4

o-Xyl

ug/L

0.00-<2

BOD5

mg/L

3-23

COD

mg/L

58-460

O&G

mg/L

0.00-23

NH3

mg/L

0.06-0.28

NO3-N

mg/L

0.00-0.43

NO2-N

mg/L

0.00-<0.05

TKN

mg/L

0.00-3.2

PO4-P

mg/L

0.00-<0.01

TP

mg/L

0.00-0.69

SiO2

mg/L

22-53

T.Surf.

mg/L

0.00-<1

F

mg/L

0.30-63

S2-

mg/L

0.03-5.8

CO3

mg/L

0.00-<10

HCO3

mg/L

12-97

SO4

mg/L

0.00-600

Cl

mg/L

9.8-4100

TRCl2

mg/L

0.00-<0.05

Phenol

mg/L

0.00-<0.1

E.coli

CFU /100mL

30-2800

Tri-Butyl Tin

ug/L

0.00-<0.015

Cyanide

ug/L

0.00-<0.05

TOC

ug/L

0.00-15

 

5.3.3            Hydrogeological Information

In addition to the ground water quality, the GI has also collected information on other hydrogeological information which is summarised in Appendix 5.2.

5.3.4            Marine Water Quality

At present, the routine monitoring programme conducted by EPD provides the most comprehensive spatial and temporal marine water quality data, and these data may be used to represent the baseline water quality condition of the concerned water system. The nearest EPD water quality monitoring sampling point located around the existing WENT Landfill is “DM4 and DM5” within the Deep Bay WCZ and “NM5” within the North Western WCZ for marine water monitoring. Figure 5.2 shows the locations of the marine monitoring points, and Table 5.4 shows the results of marine monitoring at the Deep Bay and North Western WCZs in 2007.

Table 5.4     Marine Water Quality of the Deep Bay and North Western WCZs in 2007 [5-7]

Parameter

Water Quality Objective (WQO)

Annual Mean of Monitoring Results at Different Monitoring Stations [1]

DM4               (Outer Deep Bay)

DM5               (Outer Deep Bay)

NM5         (Urmston Road)

Dissolved oxygen (depth-averaged) (mg/l)

³ 4

6.6

6.7

5.7

Dissolved oxygen (bottom) (mg/l)

³ 2

6.2

6.2

5.4

Total inorganic nitrogen (mg/l)

£ 0.5

1.16

0.79

0.64

Unionised ammonia (mg/l)

£ 0.021

0.011

0.007

0.008

pH

6.5 - 8.5

7.6

7.8

8.0

Salinity (ppt)

£ 10% change due to waste discharge

24.1

26.1

28.6

Temperature (ºC)

£ 2ºC change due to waste discharge

24.5

24.4

23.4

Suspended solids (mg/l)

£ 30% increase due to waste discharge

8.1

7.4

11.1

E. coli (cfu/100 ml)

£ 610

120

180

590

Notes:

[1]     Unless otherwise specified, data presented are depth-averaged values calculated by taking the means of three depths, including surface, mid-depth and bottom.

[2]     Data presented are annual arithmetic means of the depth-averaged results except for E. coli which is annual geometric mean.

5.3.5            River Water Quality

At present, the routine monitoring programme conducted by EPD provides the most comprehensive spatial and temporal river water quality data and these data may be used to represent the baseline water quality condition of the concerned water system. The nearest EPD water quality monitoring sampling point located around the existing WENT Landfill are “DB2” & “DB8” on a tributary of Tai Shui Hang Stream and Tsang Kok Stream inside the Deep Bay WCZ (see Figure 5.3). The river water quality monitoring results, as extracted from the “Annual River Water Quality Reports” published by EPD, are summarised in Table 5.5 and 5.6.

Table 5.5  Summary of annual water quality monitoring results at Tai Shui Hang Stream (DB2) [5-8]

 

Annual Average Concentration

DO      (mg/L)

pH

 

TSS      (mg/L)

BOD5    (mg/L)

COD    (mg/L)

E. coli [1] (cfu/100ml)

NH3-N    (mg/L)

WQO

4

6.0-9.0

20

5

30

1000

0.021

2000

8.2

7

3

1

3

31

0.02

2001

8

7.2

4

1

2

54

0.03

2002

8.2

7.5

6

1

2

37

0.03

2003

8.1

7.3

7

1

3

130

0.04

2004

8.2

7.1

3

1

3

85

0.04

2005

8.4

7.1

5

1

3

120

0.03

2006

8

7.4

4

1

3

190

0.03

2007

8.1

7.5

8

1

3

130

0.03

Note : [1] Geometric mean value

Table 5.6  Summary of annual water quality monitoring results at Tsang Kok Stream (DB8) [5-8]

 

Annual Average Concentration

DO      (mg/L)

pH

 

TSS      (mg/L)

BOD5    (mg/L)

COD    (mg/L)

E. coli [1] (cfu/100ml)

NH3-N    (mg/L)

WQO

4

6.0-9.0

20

5

30

1000

0.021

2000

8.0

7.9

6

1

5

50

0.07

2001

8.9

7.6

3

1

3

40

0.03

2002

8.7

7.8

5

1

2

34

0.02

2003

8.8

7.7

4

1

3

87

0.03

2004

9.4

7.8

2

1

4

65

0.03

2005

9.1

7.6

3

1

5

120

0.05

2006

9.5

7.9

4

1

4

310

0.02

2007

10.0

8.4

3

1

3

78

0.03

Note : [1] Geometric mean value

The latest monitoring data in 2007 at Tai Shui Hang Stream and Tsang Kok Stream are generally within the WQOs indicating that the water quality at the stream is relatively good. The river water quality shows no sign of water contamination as indicated by the low inorganic nitrogen level, COD and E. coli levels.

5.3.6            Discharge License for Existing WENT Landfill 

The discharge from the WENT Landfill Extension leachate treatment plant and other facilities shall not exceed the discharge limits specified in the Water Discharge License (EP760/431/009097/T) for existing WENT Landfill (see Table 5.7) issued by EPD under Water Pollution Control Ordinance.

Table 5.7     Discharge limits for effluents

Determinand

Limit for Effluents from EPD Site Office Area, Existing Operator’s Offices, Contaminated Surface Water and Grease Trap Waste Treatment Plant and other facilities

Limit for Effluents of Landfill Leachate

Flow Rate (m3/day)

800

1800

pH (pH units)

6-10 [1]

 6-10 [1]

Temperature (˚C)

43

43

Suspended Solids (mg/L)

800

800

Settleable Solids (mg/L)

100

100

Biochemical Oxygen Demand (5days, 20˚C)

800

800

Chemical Oxygen Demand (mg/L)

2000

2000

Oil and Grease (mg/L)

40

40

Mercury (mg/L)

0.001

0.001

Cadmium (mg/L)

0.001

0.001

Copper (mg/L)

1.5

1

Nickel (mg/L)

1

1

Chromium (mg/L)

0.7

0.7

Zinc (mg/L)

1.5

1.5

Silver (mg/L)

1.5

0.7

Other Toxic Metals individually (mg/L) [2]

0.7

0.7

Total Toxic Metals (mg/L)

2

2

Cyanide (mg/L)

0.5

0.2

Phenols (mg/L)

0.5

0.2

Suphide (mg/L)

5

2

Suphate (mg/L)

1000

800

Total Nitrogen (mg/L)

200

200

Total Inorganic Nitrogen (mg/L) [3]

-

100

Total Phosphorus (mg/L)

50

25

Surfactants (total ) (mg/L)

25

25

Notes :

[1]     Range

[2]     “Toxic metals” include antimony, arsenic, beryllium, cadmium, chromium, copper, lead, mercury, nickel, selenium, silver, thallium, vanadium and any other metals that the EPD specifies.

[3]     Include nitrogen-ammonia, nitrogen-nitrate, nitrogen-nitrite.

5.4                 Water Sensitive Receivers

Water sensitive receivers (WSRs) under this Project include:

·          Tai Shui Hang Stream (WSR-1);

·          Sha Chau Lung Kwu Chau Marine Park (WSR-2);

·          Area of oyster production (WSR-3);

·          A seawater abstraction point for power station cooling (WSR-4); and

·          Tsang Kok Stream outfall (WSR-5).

The locations of the WSRs are shown in Figure 5.4.

5.5                   Potential Impacts of Different Phases

The WENT Landfill Extension will be developed in phases.  Site clearance, excavation and slope formation works will be carried out to develop the ‘landfill bowl’.  The permanent works would comprise cut and fill earthworks, slope formation, earth wall construction and the associated drainage and sewerage works.  The temporary works will involve the formation of temporary ditches along the sides of excavations and material storage areas.

During site formation, sediments will be contained in permanent detention ponds/silt traps that will be constructed according to the landfill phasing.  The final design and location of sediment traps are yet to be decided, but likely to be down gradient of each landfill phase.  Where possible these sediment traps will be maintained during the operation of each phase to ensure the effective control of operational soil erosion problem.  As there will be large-scale site formation, any alteration of the existing water courses, natural streams, catchment types or areas, flow regimes and groundwater level will be identified.

As discussed in Chapter 2, the existing Tsang Kok Stream would need to be removed during the construction phase to facilitate a more efficient waste storage capacity.  For the existing Tsang Kok Stream outfall, a box culvert as shown in Figure 5.4a will be installed.  It would be constructed by first installing temporary sheet piles before any de-watering and construction of box culvert is conducted.  Hence, construction of the box culvert would not have adverse water quality impacts during the construction phase.  During the operation phase, the storm water from the WENT Landfill Extension would be collected and diverted through the box culvert, in a fashion similar to the existing Tsang Kok Stream.  The associated ecological impacts have been separately addressed in Chapter 10. 

For cost effectiveness, the existing berthing facilities of the existing WENT Landfill will be used for the WENT Landfill Extension.  There are no additional berthing facilities / barging points, and thus no capital dredging will be required.  Only very infrequent maintenance dredging as the existing WENT Landfill may be required.

The treated leachate from new leachate treatment plant will be pumped to the rising mains running along the realigned Nim Wan Road and connected to the existing gravity sewerage system discharging to the DSD Lung Kwu Sheung Tan Outfall Chamber. It is then discharged via the Urmston Road Submarine Outfall into marine waters. This submarine outfall serves not only the existing effluent from the existing WENT, but all the effluent from other sources including but not limited to the San Wai Sewage Treatment Works (STW).  According to the information from DSD, the San Wai STW will be upgraded to a capacity of 246,000m³/day for discharge into the existing NWNT Effluent Tunnel and Urmston Road Submarine Outfall.  The quantity of effluent from the existing WENT Landfill (~2,600m³/day) for discharge to the Urmston Road Submarine Outfall only constitutes about 1%.  Table 5.8 summarises the potential water quality impacts during different phases, including construction, operation, restoration and aftercare, of the WENT Landfill Extension.

Table 5.8   Potential Impacts during Different Phases

Impact Source

Potential Impact

Construction Phase

Operation Phase

Restoration and Aftercare Phases

Surface runoff

(i) Construction site runoff and stormwater runoff will carry considerable amount of soil due to excavation and filling.

(ii) Washwater from dust suppression sprays and wheel washing facilities.

(iii) Fuel, oil and chemicals will be generated from maintenance of construction machinery and equipment.

Runoff infiltrated to the active tipping area will result in leachate, which comprises high levels of organics and nutrients arising from the waste materials, particularly during the wet season.

Subject to the nature of aftercare development, runoff should comprise mainly soil in a much smaller-scale than the construction and operation phases.

Capital and maintenance dredging

No capital dredging is involved and thus the impact will be insignificant.

Similar to the current operation, only very infrequent maintenance dredging is anticipated.  Hence, the impacts would be similar to those existing and are not anticipated to be significant. 

Negligible.

Leachate infiltrated / collected by designated collection systems

No leachate generated and thus negligible impact.

Given the implementation of tipping area control and progressive restoration of landfill, the leachate generated from the landfill extension will be minimised.  New leachate treatment works (with adequate design capacity) will be provided to treat the leachate collected.  Hence, impact arising from leachate collected should be minimal.

Leachate will be treated in the new leachate treatment works and effluent will be discharged to the existing submarine outfall in Urmston Road. The leachate discharge will be under controlled and kept same as  the existing Discharge Licence limit for the existing WENT Landfill.

During restoration, the landfill will be restored and vegetated to match the surrounding landform. Final capping with impermeable liner will be provided to prevent infiltration of surface water and hence minimise the leachate generation.  The leachate generated during this period would be much less than the operation phase.  The new leachate treatment works have sufficient capacity to treat the leachate and hence impact arising from leachate infiltrated should be in a much smaller-scale than that in operation phase.

Seepage / leakage of leachate

No leachate generated and thus negligible impact.

Seepage of leachate across the geomembrane, and accidental leakage of leachate from ruptured pipeline, failed pipe joint sealing and damaged geomembrane may result in the discharge of pre-treated leachate to the nearby streams and ultimately groundwater.

Similar nature as the operation phase but in a much smaller-scale.

Sewage generation

Sewage generated by the construction workforce.

Sewage generated by staff working at site office during operation phase.

Sewage generated by staff working at site office during restoration and aftercare period.

 

5.6                   Construction Phase

5.6.1               Potential Impacts from Construction Activities

Potential water pollution sources arising from construction activities include sources mainly from land-based activities, such as:

·          Construction site runoff;

·          Sewage effluent due to workforce on site;

·          Drainage diversion; and

·          Groundwater seepage

5.6.2               Construction Site Runoff

Construction site runoff comprises:

·          Runoff and erosion from excavation areas, drainage channels and stockpiles;

·          Wash water from dust suppression sprays and wheel washing facilities;

·          Fuel, oil, solvent and lubricants from maintenance of construction machinery and equipment.

Construction runoff may cause physical, biological and chemical impacts. Physical impacts include potential blockage of drainage channels and increase of suspended solids concentration in the receiving drainage channel. Local flooding may occur during heavy rainfall if construction runoff is not properly drained. Chemical and biological effects caused by the construction runoff are highly dependent upon the chemical and nutrient contents of the runoff. Runoff containing significant amounts of concrete and cement-derived material may cause primary chemical effects such as increase in turbidity and discoloration, elevation in pH, and accretion of solids. Secondary impacts, such as toxic effects to water biota due to the elevated pH values, and reduction in decay rate of faecal micro-organisms and photosynthetic rate due to the decreased light penetration may result.

5.6.3               Sewage Effluent from Workforce on Site

Sewage generated due to the presence of site staff and construction workers would have the potential to cause water pollution if it was to be discharged directly into adjacent water bodies without appropriate treatment. The characteristics of sewage include high level of BOD5, Ammonia and E. coli counts.

Sufficient temporary sanitary toilets will be provided for on-site construction workforce and will be specified in the contract requirements.  No sewage will be allowed to discharge directly into the surrounding water body without treatment. With this regard, adverse impacts to water quality as a result of handling and disposal of sewage generated by the workforce are not expected.

5.6.4               Drainage Diversion

The potential water quality impact associated with drainage diversion will be from the runoff and erosion from site surfaces and earthwork areas.  All existing upstream channel of Tsang Kok Stream will be diverted off site and discharged to the downstream drainage system.

In order to achieve that, a box culvert as shown in Figure 5.4a will be installed.  It would be constructed by first installing temporary sheet piles before any de-watering and construction of box culvert is conducted.  Hence, construction of the box culvert would not have adverse water quality impacts during the construction phase.  The associated ecological impacts have been separately addressed in Chapter 10. 

5.6.5            Groundwater Seepage

Ground investigation has been carried out to determine the existing groundwater levels within the Project site.  Groundwater seepage is not considered as an issue for the project of WENT Landfill Extension as the landfill will comprise a closed system with liner and leachate collection measures. Additionally, no groundwater sensitive receivers or abstraction points are present in the vicinity of the site.  As such, any changes in groundwater level resulting from the works will have no notable impact.

5.6.6            Cumulative Impacts

Potential concurrent projects in the vicinity of the WENT Landfill Extension are identified, including the following:

·                   Sludge Treatment Facilities;

·                   Integrated Waste Management Facilities; and

·                   Existing / restored WENT Landfill

Sludge Treatment Facilities

To the north of the east lagoon, a Sludge Treatment Facilities (STF) is planned to be built.  According to the best available information, the STF will adopt incineration technology for treating sludge collected from the Stonecutters Island Sewage Treatment Works (STW) and 10 other regional STWs in the territory. 

The construction period is tentatively between 2010 and 2012.  No reclamation work is required.  Hence, potential sources of water quality impact include construction site runoff and drainage, sewage effluent from the construction workforce, and debris, refuse and liquid spillages from general construction activities.

Given that the construction phase is implemented with proper site management and good housekeeping practices, no adverse cumulative water quality impact is anticipated for the STF and therefore no cumulative impact is expected.

Integrated Waste Management Facilities

The other potential concurrent project is the Integrated Waste Management Facilities (IWMF).  It is however still undergoing the site selection process, and the detailed design and works programme are yet to be available.  Hence, it is not considered as a concurrent project under the EIA for the WENT Landfill Extension. 

Even if IWMF is located in the middle lagoon, the construction period is tentatively between 2014 and 2016.  Similar to the STF, given that the construction phase is implemented with proper site management and good housekeeping practices, no adverse cumulative water quality impact is anticipated for the IWMF and therefore no cumulative impact is expected.

Existing / Restored WENT Landfill

During the construction of the WENT Landfill Extension, the existing WENT Landfill would still be operating.  The leachate generated would be treated by the relocated treatment plant and then pumped to the rising mains running along the realigned Nim Wan Road for discharging to the Lung Kwu Sheung Tan Outfall Chamber and then Urmston Road Submarine Outfall.  Even during the operation of the WENT Landfill Extension, the relocated leachate treatment plant would still be operated for the aftercare period of the existing WENT Landfill and hence adverse cumulative water quality impacts are not anticipated.

5.6.7               Precautionary Measures

5.6.7.1        Construction Runoff

In accordance with the Practice Note for Professional Persons on Construction Site Drainage, Environmental Protection Department, 1994 (ProPECC PN 1/94), and DSD Technical Circular TC14/2000, construction phase precautionary measures, where appropriate, will include the following :

·          At the start of site establishment, perimeter cut-off drains to direct off-site water around the site will be constructed with internal drainage works and erosion and sedimentation control facilities implemented. Channels (both temporary and permanent drainage pipes and culverts), earth bunds or sand bag barriers will be provided on site to direct stormwater to silt removal facilities.  The design of the temporary as well as the permanent on-site drainage system will be undertaken by the DBO Contractor prior to the commencement of construction.

·          The dikes or embankments for flood protection will be implemented around the boundaries of earthwork areas. Temporary ditches will be provided to facilitate the runoff discharge into an appropriate watercourse, through a silt/sediment trap. The silt/sediment traps will be incorporated in the permanent drainage channels to enhance deposition rates.

·          The design of efficient silt removal facilities will be based on the guidelines in Appendix A1 of ProPECC PN 1/94, which states that the retention time for silt/sand traps should be 5 minutes under maximum flow conditions.  Sizes may vary depending upon the development phases and associated flow rate, but for a flow rate of 0.1 m3/s a sedimentation basin of 30m3 would be provided and for a flow rate of 0.5 m3/s the basin would be 150 m3.  The detailed design of the sand/silt traps will be undertaken by the DBO Contractor prior to the commencement of construction.

·          Construction works will be programmed to minimize surface excavation works during the rainy seasons (April to September).  All exposed earth areas will be temporarily covered as soon as possible after earthworks have been completed.  If excavation of soil cannot be avoided during the rainy season, or at any time of year when rainstorms are likely, exposed slope surfaces will be covered by tarpaulin or other means.

·          All drainage facilities and erosion and sediment control structures will be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rainstorms.  Deposited silt and grit will be removed regularly and disposed of by spreading evenly over stable, vegetated areas.

·          Measures will be taken to minimise the ingress of site drainage into excavations.  If the excavation of trenches in wet periods is necessary, they will be dug and backfilled in short sections wherever practicable.  Water pumped out from trenches or foundation excavations will be discharged into storm drains via silt removal facilities.

·          Open stockpiles of construction materials (for example, aggregates, sand and fill material) of more than 50m3 will be covered with tarpaulin or similar fabric during rainstorms.  Measures will be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system.

·          Manholes (including newly constructed ones) will always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and storm runoff being directed into foul sewers.

·          Precaution measures will be taken at any time of year when rainstorms are likely, actions to be taken when a rainstorm is imminent or forecasted, and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.  Particular attention will be paid to the control of silty surface runoff during storm events, especially for areas located near steep slopes.

·          All vehicles and plant will be cleaned before leaving the construction site to ensure no earth, mud, debris and the like is deposited on roads.  An adequately designed and sited wheel washing facilities will be provided at every construction site exit where practicable.  Wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process.  The section of access road leading to, and exiting from, the wheel-wash bay to the public road will be paved with sufficient back fall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.

·          Oil interceptors will be provided in the drainage system downstream of any oil/fuel pollution sources. The oil interceptors will be emptied and cleaned regularly to prevent the release of oil and grease into the storm water drainage system after accidental spillage. A bypass will be provided for the oil interceptors to prevent flushing during heavy rain.

·          Construction solid waste, debris and rubbish on site will be collected, handled and disposed of properly to avoid water quality impacts.

·          All fuel tanks and storage areas will be provided with locks and sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank to prevent spilled fuel oils from reaching water sensitive receivers nearby.

By adopting the above precautionary measures with Best Management Practices (BMPs) it is anticipated that the impacts of runoff from the construction site will be reduced to satisfactory levels before discharges.

The construction runoff discharged from the landfill site shall fully comply with the standards stated in Section 5.2, otherwise the discharge shall be collected and conveyed to the on-site leachate treatment and eventually discharged via the existing Urmston Road Submarine Outfall.

5.6.7.2        Accidental Spillage of Chemical

Any service workshops and maintenance facilities will be located within a bunding area, and sumps and oil interceptors will be provided. Maintenance of equipment involving activities with potential for leakage and spillage will only be undertaken within the areas appropriately equipped to control these discharges.  The fuel and waste lubricant oil from the on-site maintenance of machinery and equipment will be collected by a licensed chemical waste collector.

5.6.7.3        Sewage from Workforce

Portable chemical toilets and sewage holding tanks will be provided for handling the sewage generated by the workforce.  A licensed contractor will be employed to provide appropriate and adequate portable toilets and be responsible for appropriate disposal and maintenance.

Notices will be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment during the construction phase of the Project.  Regular environmental audit on the construction site can provide an effective control of any malpractices and can achieve continual improvement of environmental performance on site.  It is anticipated that sewage generation during the construction phase of the Project would not cause water quality impact after undertaking all required measures.

5.6.8               “What if IWMF not proceed”

The feasibility of IWMF is still being conducted and there is no decision on the implementation programme and site selection. In case the IWMF is not located at the middle ash lagoon, the boundary of the proposed WENT Landfill Extension would be further expanded to include the middle lagoon. Since the additional landfill area will be all land based and all the proposed precautionary and mitigation measures will be extended to that area, there would not have additional impacts on the water quality on neighbouring sensitive receivers.

5.7                 Operation Phase

5.7.1            Surface Water Management

5.7.1.1        Potential Impacts of Surface Runoff from Site

Surface runoff of the WENT Landfill Extension during its operation phase will be collected through the installation of site drainage system and be discharged through the storm drains and eventually via various new box culverts including the new box culvert at Tsang Kok Stream outfall.  The proposed site drainage including the new Tsang Kok Stream box culvert will be designed with adequate capacity.  Since the existing Tsang Kok Stream is also carrying stormwater already and the existing downstream has been channelised already, it is anticipated that the surface runoff to be collected and discharged via the new box culvert will not have adverse water quality impact on the environment.

5.7.1.2        Potential Impacts of Surface Runoff from Realigned Nim Wan Road

Surface runoff from the realigned Nim Wan Road may include heavy metals, oil and grease and inorganic matters.  Similar to other approved EIA practices on roadwork project (e.g., Deep Bay Link), the most effective mitigation measure to prevent the vehicle-generated pollutants from entering the water bodies is to remove the pollutants from road surface prior to the occurrence of a rainstorm.  Vacuum air sweepers/trucks could be deployed to remove the pollutants deposited on the road surface at appropriate time intervals.

Standard road gullies with silt traps could be installed to intercept and enable the removal of residual grit, particulate matters and pollutants in road runoff.  Regular cleaning of rubbish and sediments from the drainage system following the normal road maintenance practices is required to maintain the normal operation of the systems at all times.

5.7.2            Groundwater Management

5.7.2.1        Potential Impacts on Groundwater Regime

The formation of a fully-lined and capped landfill within the WENT Landfill Extension will mean that any infiltration that currently occurs within WENT Landfill Extension will be removed from the hydrological system. Although upon completion of the landfill operation this volume of water will be diverted to the surface water, there will be some resultant loss of recharge to the main groundwater body beneath the site area as the main recharge source at upstream will have been lost.

We have carried out groundwater investigation and based on the results from groundwater investigation, the groundwater contours for WENT Landfill Extension have been developed.  The direction of groundwater flow, based on the groundwater contours, has been developed and it directs to the sea (see Figure 5.5), thus no adverse impact on the downstream watercourses is anticipated.

5.7.2.2        Generation of Leachate due to Groundwater Infiltration

The extension site will be designed and constructed as a containment facility incorporating a multi-layer composite liner system covering the entire land formation of the extension site where waste will be deposited. This will not only prevent infiltration of groundwater into the waste and hence minimising leachate generation, and also prevent off-site migration of leachate and contamination of the groundwater. Construction quality assurance/control procedures will be implemented to ensure that the liner system is proper constructed (ie avoiding puncture of the impermeable HDPE liner by construction equipment during installation, and proper seaming of the joints, etc). It is hence expected that the groundwater will be isolated from the extension site and as a result leachate generation from groundwater infiltration will be negligible.

5.7.2.3        Groundwater Contamination due to Leachate Seepage

A geocomposite groundwater drainage layer will be constructed underneath the lining system. The compacted soil underneath the groundwater drainage layer will inhibit the downward infiltration of leachate into the groundwater and hence the drainage layer (with an adequate gradient) could allow the collected groundwater to flow horizontally by gravity. Since the groundwater drainage layer will also be connected to leachate treatment plant, the operation of the WENT Landfill Extension would not impact the groundwater quality.

5.7.2.4        Groundwater Contamination due to Accidental Leakage

While the WENT Landfill Extension has been installed with precautionary measures such as double-layered geomebranes, there is a possible chance of accidental leaking of leachate from the rupture of the leachate pipeline, failure of the pipe joint and the damage of geomembrane.  Based on the historical groundwater monitoring data for the existing WENT Landfill, it is considered such a chance is considered as low.  In addition, a contingency plan will also be developed to ensure effective mitigation measures are put in place in a timely manner.  Hence any associated impacts are considered insignificant.

5.7.3            Leachate Generation

5.7.3.1        Rainfall Data in Nim Wan, Tuen Mun

 

Leachate quantity is usually determined using a simple water balance approach taking into account the amount of water entering the landfill (ie precipitation) and the amount of water leaving the landfill (ie water consumed in biochemical reactions and evaporation).

Rainfall data from the Hong Kong Observatory Rain Gauge at Tap Shek Kok and Lau Fau Shan between 1993 and 2007 had been reviewed for estimating the precipitation in Nim Wan.

Table 5.8a           Average Monthly Rainfall in Tap Shek Kok and Lau Fau Shan

 

Average monthly rainfall in Tap Shek Kok (mm)

Average monthly rainfall in Lau Fau Shan (mm)

Jan

26.6

24.1

Feb

35.8

34.5

Mar

44.4

38.0

Apr

132.4

115.7

May

218.8

181.4

Jun

358.5

291.1

Jul

275.6

258.5

Aug

379.7

313.8

Sep

215.8

181.1

Oct

46.1

40.3

Nov

50.7

39.3

Dec

29.0

30.3

Total

1813.5

1540.4

 

It is noted from the above table that the average annual rainfall recorded in Tap Shek Kok is about 20% higher than that of Lau Fau Shan. To plan for the worst, the average rainfall of 1813.5 mm was adopted for the estimation of leachate generation in WENT Landfill Extension.

Reference is also made to Table 6.2 of Waste Management Paper 26B, Department of the Environment, London. Effective rainfall should be adopted for the estimating the leachate flow. It is also noted that the rainfall recorded in Tap Shek Kok Rain Gauge has not taken into account the evaporation effect. Evaporation data from King’s Park Meteorological Station had been reviewed as enclosed in Appendix 5.3. It is noted that minimum evaporation is recorded in 2006 as 1157mm per year. Thus, the effective rainfall in Tap Shek Kok is estimated to be 902mm/year which is only 50% of the average rainfall. Thus the following leachate estimation based on the average rainfall will be on high side.

5.7.3.2        Estimation of Leachate Flow

The leachate generated from the landfill site in different year can be calculated by :

Leachate generation = runoff coeff. * operation area * effective rainfall

where runoff coefficient for different type of landfill is shown in Table 5.8b.

Table 5.8b          Runoff Coefficient for Different Type of Landfill

Landfill Type

Runoff coeff.

Remarks

Active tipping face

1.00

100% of surface water infiltrated into leachate collection system of landfill

Temporary restored area

0.30

70% of surface water will be convey to surface channel / stormwater system

Permanent restored area

0.10

90% of surface water will be convey to surface channel / stormwater system

Notes :

1.    Reference is made to DSD Stormwater Manual Clause 7.5.2. “The value of C depends on the impermeability, slope and retention characteristics of the ground surface. It also depends on the characteristics and conditions of the soil, vegetation cover, the duration and intensity of rainfall, and the antecedent moisture conditions, etc. In Kong Kong, a value of C =1.0 is commonly used in developed urban areas. In less developed areas, the following C values may be used.” Table below extracted from DSD Stormwater Drainage Manual Page 42.

 

Surface Characteristics

Runoff coefficient, C

Asphalt

0.70 – 0.95

Concrete

0.80 – 0.95

Brick

0.70 – 0.85

Grassland (heavy soil)

 

Flat

0.13 – 0.25

Steep

0.25 – 0.35

Grassland (sandy soil)

 

Flat

0.05 – 0.15

Steep

0.15 – 0.20

2.    As per the recommendation of DSD Manual, a value of C =1.0 is commonly used in developed urban areas, which conveys all the surface face to the adjacent drainage system. Similarly, a runoff coeff. of 1.0 is used for the tippling face in order to convey all leachate to the treatment plant. Runoff coeff. of 0.30 for heavy steep soil is adopted for site formation work. Runoff coeff. of 0.10 for sandy flat soil is adopted for the permanent restored surface with top soil and plantation.

 

3.     The same value had been adopted in the Approved EIA Report for NENT Landfill Extension (Register No. AEIAR-111/2007).

To minimise the leachate generation, it is necessary to control the active tipping area and to start restoration as early as practicable. A Phasing Plan A1 was developed with the following leachate minimisation control measures :

-          Operation life of 15 years (with IWMF implemented in mid 2010s);

-          active tipping face to be controlled within 3 to 6 ha;

-          restoration start in Year 8; and

-          leachate recirculation to landfill for leachate storage where necessary.

The proposed phasing sequence for Phasing Plan A1 is shown in Table 5.8c. Table 5.8d shows the leachate generation for Phasing Plan A1.

Table 5.8c        WENT Landfill Extension Phasing Plan A1

Year

 

Active tipping area (ha)

Temporary working area (ha)

Permanent restored area (ha)

Total Area

(ha)

0

0

10

0

10

1

6

20

0

26

2

6

30

0

36

3

6

40

0

46

4

6

50

0

56

5

6

60

0

66

6

6

70

0

76

7

6

80

0

86

8

5

90

0

95

9

5

100

0

105

10

4

90

20

114

11

4

90

40

134

12

3

90

60

153

13

3

80

80

163

14

3

75

100

178

15

3

65

120

188

16

0

48

140

188

17

0

28

160

188

18

0

0

188

188

19

0

0

188

188

Table 5.8d        Leachate Generation for Phasing Plan A1

Year

Calculation of Infiltration

Leachate Generation

 

Working Area

(m³/year)

Temporary Restored Area

(m³/year)

Permanent Restored Area

(m³/year)

(m³/year)

(m³/day)

1

108,810

108,810

0

217,620

596

2

108,810

163,215

0

272,025

745

3

108,810

217,620

0

326,430

894

4

108,810

272,025

0

380,835

1,043

5

108,810

326,430

0

435,240

1,192

6

108,810

380,835

0

489,645

1,341

7

108,810

435,240

0

544,050

1,491

8

90,675

489,645

0

580,320

1,590

9

90,675

544,050

0

634,725

1,739

10

72,540

489,645

36,270

598,455

1,640

11

72,540

489,645

72,540

634,725

1,739

12

54,405

489,645

108,810

652,860

1,789

13

54,405

435,240

145,080

634,725

1,739

14

54,405

408,038

181,350

643,793

1,764

15

54,405

353,633

217,620

625,658

1,714

16

0

261,144

253,890

515,034

1,411

17

0

152,334

290,160

442,494

1,212

18

0

0

340,938

340,938

934

19

0

0

340,938

340,938

934

5.7.3.3        Existing WENT Landfill After Restoration

During the restoration period, a final capping system will be provided to prevent infiltration into the waste body and minimise the leachate generation. After the closure of the existing WENT Landfill, there will still be some leachate generated from the restored landfill. The estimated leachate after closure is about 550m³/day as shown in Appendix 5.4.

During the restoration and aftercare period, the workforce in the site office will be significantly reduced, the refuse reception area, vehicle washing facility will also be removed. However, afteruse facilities and visitor centre will be provided during the aftercare period.  The wastewater and sewage generated from the restored WENT Landfill will consist of:

(1)                       Sanitary wastewater from EPD Site Office and Swire-SITA Site Office toilet and canteen, which is estimated to be 32m³/day (say 25% of operation phase).

(2)                       Sanitary wastewater from aftercare facilities and visitor centre, which is estimated to be 16m³/day (assuming 200 staff/visitors with commercial unit flow rate of 0.08m³/day).

The wastewater and sewage generated from the restored WENT Landfill is estimated to be 50m³/day. Together with the pre-treated leachate flows, the total effluent to be discharged is estimated to be 600m³/day.

5.7.3.4        Other Wastewater from WENT Landfill Extension

Similar to the existing WENT Landfill, there are other wastewater generated from the WENT Landfill Extension during the operation period, which includes :

(1)                       Sanitary wastewater from EPD Site Office and future operator Site Office including toilet and canteen, which is estimated to be 103m³/day for both dry and wet season, see breakdown below.

Table 5.8e               Sewage generated from Site Office in WENT Landfill Extension

Source

Quantity

Unit flow rate

Sewage flows

Staff

500 person

0.08 m³/person/day [a]

40 m³/day

Canteen GFA 600 m²

(kitchen area = 21% of Restaurant GFA)

126 m²

0.5 m³/m² kitchen area/day [b]

63 m³/day

 

 

Total

103 m³/day

Notes :      [a] Unit flow factors of commercial employee extracted from EPD Technical Paper Report No. EPD/TP 1/05.

[b]  Unit flow factors for canteen extracted from EPD Guidelines for the design of Small Sewage Treatment Plants Appendix 2.

 

(2)                       Wastewater from vehicle wash area, assumed to be 75m³/day.

(3)                       Wastewater from vehicle maintenance facility, assumed to be 50m³/day.

(4)                       Wastewater from refuse reception area, assumed to be 50m³/day.

The total wastewater and sewage generated from the WENT Landfill Extension during the operation phase is estimated to be 278m³/day.

During the restoration and aftercare period, the workforce in the site office will be significantly reduced, the refuse reception area, vehicle washing facility will also be removed. However, afteruse facilities and visitor centre will be provided during the aftercare period.  The wastewater and sewage generated from the restored WENT Landfill Extension will consist of :

(1)                       Sanitary wastewater from EPD Site Office and Swire-SITA Site Office toilet and canteen, which is estimated to be 26m³/day (say 25% of operation phase).

(2)                       Sanitary wastewater from aftercare facilities and visitor centre, which is estimated to be 16m³/day (assuming 200 staff/visitors with commercial unit flow rate of 0.08m³/day).

The wastewater and sewage generated from the restored WENT Landfill Extension is estimated to be 50m³/day.

5.7.3.5        Total Leachate Generated during Operation Phase

During operation of WENT Landfill Extension, the existing WENT Landfill will be restored with total effluent of 600m³/day.

Under the “No Net Increase in Pollution Loads Requirement in Deep Bay”, the existing Discharge Licence of 2,600m³/day will be kept remain unchanged. Thus, it is proposed that the restored WENT Landfill will have a Discharge Licence of 600m³/day while the WENT Landfill Extension will have a Discharge Licence of 2,000m³/day.

As the wastewater and sewage generated from the site office and reception area are about 278m³/day, thus the discharge limit for pre-treated leachate will be limited to 1,800m³/day (or 657,000m³/year).

As shown in Table 5.8d, exceedance to Discharge Licence limit will not occur during the operation life of the WENT Landfill Extension. The maximum leachate flow generated is estimated to be 1,789m³/day in Year 12. As the leachate estimated is based on an average rainfall data without taking into account the evaporation effect of leachate volume, the actual leachate generated should be less than 1,789m³/day. It is therefore concluded that with the implementation of leachate minimisation control measures, the leachate generated from the WENT Landfill Extension would be within control and no exceedance to the Discharge Licence would be allowed.

5.7.4            Leachate Management

The volume of leachate generated by a landfill depends on the amount of precipitation getting into the landfill. Operating landfills generate more leachate than closed landfills, because closed landfills have been capped and vegetated. This reduces the amount of water getting into the waste body, and thus lesser amount of leachate being produced.

The leachate management system comprises the following components:

•     leachate collection system;

•     leachate extraction system;

•     leachate treatment system; and

•     leachate disposal.

5.7.4.1        Leachate Collection

A low permeability composite liner system will be placed at the base of the WENT Landfill Extension to reduce the discharge to the underlying hydrogeologic environment. The liner system will be designed as a barrier to intercept leachate so that the contained leachate can be abstracted for treatment prior to discharge from the WENT Landfill Extension.

The proposed liner system of the WENT Landfill Extension consists of a 2 mm high density polyethylene (HDPE) liner, a 6 mm bentonite matting and a leachate collection system.  Similar liner and leachate collection systems had been adopted in the existing WENT Landfill and proven to be effective. 

Leachate will be collected by the gravity leachate collection pipe to the proposed leachate treatment works. The treated leachate will be pumped to the rising mains running along the realigned Nim Wan Road and connected to the existing gravity sewerage system discharging to the DSD Lung Kwu Sheung Tan Outfall Chamber. It is then discharged via the Urmston Road Submarine Outfall into marine waters.

5.7.4.2        Leachate Extraction

Leachate will be extracted from the extension via a series of collection sumps around the perimeters of the extension site.  

The leachate collection sumps will be constructed of pre-cast concrete and will be equipped with submersible pumps to enable leachate to be pumped from the base of the landfill to the leachate collection main, which will transfer leachate to the new leachate treatment plant near the waste reception area.  The leachate collection sumps will be accessed by upslope risers along the toe bund of the extension, and therefore will not be prone to damage due to movements of the waste mass.

5.7.4.3        Leachate Minimisation

The WENT Landfill Extension will adopt even more strengthen operation mode to control the leachate generation.  The leachate generation rate is greatly dependent on the meteorological conditions and phasing of the WENT Landfill Extension. In order to minimise leachate generation, the phasing of WENT Landfill Extension will be controlled with detailed planning.  The following leachate minimization program will be specified in the DBO Contract for implementation by the DBO Contractor:

-          Phased development and closure to minimize the active area footprint;

-          Temporary geosynthetic covers to minimize infiltration in active cells;

-          Run-on and runoff control systems for active and inactive tipping areas;

-          Sub-surface drainage systems to control groundwater seepage;

-          Low permeability final cover systems to minimize infiltration during post-closure, and

-          Cell construction techniques that promote surface runoff rather than infiltration.

Nevertheless, progressive restoration is encouraged where practicable.  With detailed planning on temporary and permanent restored area, leachate generation rate could be under control and greatly reduced.  No discharge or overflow of leachate to the adjacent streams, rivers and culverts is anticipated.

5.7.4.4        Leachate Treatment

Leachate from the WENT Landfill Extension will be collected and diverted to a new treatment plant.  The collected leachate will be diverted to ammonia stripping plant for the removal of high ammonia concentration.  After the stripping process, the leachate will be diverted to SBR plant for COD, BOD and SS removal.  The effluent will be discharged off-site to the pumping station for onward pumping to DSD Lung Kwu Sheung Tan Outfall Chamber.  A schematic diagram showing the tentative process design is given in Figure 5.6 for information.  The design of the treatment plant has considered the worst case scenario of extreme rainfall incident described in Section 5.7.3.5. Nevertheless, the proposed leachate treatment process will be designed by the future operator to suit its landfill development phasing and sequence. It is up to the future operator to determine which treatment process is preferred to enhance cost-effective. 

In general, the objective of leachate treatment at all landfill sites is to attain the required standards for discharge. It is noted that the Discharge License for the existing WENT Landfill EP760/431/009097/T has set out the following limits for the effluent discharge. Due to the 'No Net Increase in Pollution Loads Requirement in Deep Bay', it is reasonable to assume the same standards to be applied for the WENT Landfill Extension.

Table 5.9     Treatment Objectives

Determinand

Limit

Flow rate for total effluent

2,600

m³/day

pH

6 - 10

 

Suspended Solids

< 800

mg/l

Biochemical Oxygen Demand (5 days)

< 800

mg/l

Chemical Oxygen Demand

< 2,000

mg/l

Total Nitrogen

< 200

mg/l

5.7.4.5        Leachate Disposal

Leachate generated from the WENT Landfill Extension will be collected and conveyed to the new leachate treatment plant within the Waste Reception Area. The treated effluent will be pumped to the new rising mains along the realigned Nim Wan Road and connected to the existing gravity sewerage system discharging to the DSD Lung Kwu Sheung Tan Outfall Chamber and then Urmston Road Submarine Outfall.

To facilitate the future maintenance and emergency repair of Lung Kwu Sheung Tan Outfall Chamber and the Urmston Road Outfall, the proposed leachate treatment plant shall be able to have a minimum retention time of 8 hours. The proposed new pumping station and rising main shall equip with gate valve to cut off the leachate flows to downstream system during maintenance / emergency repair period. DSD will notify EPD in case of emergency, a communication channel between DSD / EPD / Landfill Extension Contractor will be set up.

The discharge limit of treated leachate set out in the licence for the existing WENT Landfill is 2,600 m3/day.  To minimise the environmental impacts to surrounding and the drainage impact to downstream DSD Lung Kwu Sheung Tan Outfall Chamber and Urmston Road Outfall, the discharge limit for the combined existing WENT Landfill and its extension will be the same as existing Discharge Licence, ie 2,600 m³/day.

Under the 'No Net Increase in Pollution Loads Requirement in Deep Bay', the pollution loading currently discharged from the existing WENT Landfill will be kept remain unchanged. 

The disposal of treatment effluent, which meets the discharge standards stipulated in the Discharge License, from the leachate treatment plant to the rising mains leading to the Lung Kwu Sheung Tan Outfall Chamber and then Urmston Road Submarine Outfall will not cause adverse water quality impacts to the identified WSRs downstream.

5.7.4.6        Cumulative Impacts

Similar, new pumping station will also be provided at the reprovisioned leachate treatment plant for the restored WENT Landfill.  New rising mains will also be provided and connected to the pumping station of the WENT Landfill Extension.  The combined leachate with total flows of 2,600m³/day will then be discharged to the proposed rising mains along the realigned Nim Wan Road.

For STF, an on-site wastewater treatment plant would be provided to treat the wastewater generated for reuse at the facility for washdown water and landscape irrigation.  In addition, all on-site wastewater will be incinerated and there will be no discharge into the Deep Bay or pose any adverse impact on water quality [5-10].  Hence, no adverse cumulative impact on water quality is expected during its operation.

5.7.5            Potential Impacts from Seepage and Leakage of Leachate

It is assumed that the total leachate generated from the existing WENT Landfill and its extension will be under controlled and within the Discharge License limit as the existing WENT Landfill.  Leachate to be collected and treated prior to discharge through the submarine outfall is discussed in Section 5.7.3.

Suitable liner and leachate collection systems of the WENT Landfill Extension will be recommended in accordance with local and international practices to prevent leachate seeping / leaking into the natural groundwater system. 

In the assessment of potential seepage of leachate across a composite liner, the following assumptions will be made:

·         The bentonite matting has a maximum placed hydraulic conductivity of 1 × 10-10 m/s in any direction, which is the specified performance requirement in the existing WENT Landfill Contract. The HDPE is assumed to have a maximum placed hydraulic conductivity of 1 x 10-11 m/s in accordance to the NENT Landfill Extension EIA Report.

·         4 defects are assumed in every hectare, which represents “Good” installation quality. (Schroeder et al., 1994 [5-11])

·         Contact qlity factor of 0.21 (i.e. good contact conditions) is assumed. It corresponds to a geomembrane installed, with as few wrinkles as possible, on top of low permeability soil layer that has been adequately compacted and has a smooth surface. (Bonaparte et al., 1989 [5-12])

·         Giroud et al. [5-13] (1997)’s equation for calculating the flow through a composite liner having circular defect with diameter of 2mm.

 

 

 


                                                              

where

Q

=

seepage rate through the considered geomembrane defect (m3/s)

 

A

=

considered geomembrane area (m2)

 

N

=

number of defects per considered geomembrane area (A)

 

Cqo

=

contact quality factor

 

H

=

hydraulic head on top of the geomembrane (m)

 

ts

=

thickness of the low-permeability soil layer of the composite liner (m)

 

D

=

diameter of circular defect (m)

 

ks

=

conductivity of liner

 

It is known that the diameter of circular defect should not be less than 0.5 mm or greater than 25 mm when applying this Giroud’s equation to predict seepage of leachate through a defect [5-12] as the limitation.

The liquid head on top of the geomembrane would be in the order of 0.3 m, based on the existing WENT Landfill practice.

Accidental leakage of leachate from the rupture of leachate pipeline, the failure of pipe joint sealing and the damage of geomembrane will cause water quality impact.  These may result in the discharge of pre-treated leachate to the nearby streams and ultimately groundwater.  There is no known water abstraction of groundwater for drinking, its impact to human health is therefore minimal.  The preliminary predicted groundwater flow paths in the vicinity of the site show that the groundwater flows towards the sea (i.e. northward).  Hence, it is unlikely that the pre-treated leachate will migrate towards the west to Tai Shui Hang Stream through the natural groundwater transmission path.   

Assessment results show that for a composite liner with good contact condition between geomembrane and bentonite matting which has a saturated hydraulic conductivity of
1x10-10
m/s, the rate of seepage would be 1.4 litres per hectare per day. The flow rate could be further reduced by lowering the conductivity of the bentonite matting and the number of defects per unit area through better QA/QC programme to improve the installation quality to “Excellent” [5-11].  According to USEPA 1997 [5-14] ,a conductivity of 1x10-11 m/s could generally be adopted for bentonite in a modern landfill.  This would significantly reduce the seepage rate to 0.26 litres per hectare per day.  In addition, composite liner had been proposed for the WENT Landfill Extension (HPDE and Bentonite Mat), thus the resulting conductivity for this composite liner shall be much less then 1x10-11 m/s.

The potential amount of leaked leachate from the WENT Landfill Extension site reaching the groundwater collection layer would be 0.26 litres per hectare per day, if conductivity of 1x 10-11 m/s is assumed for the composite liner. The depth of leaked leachate mixing with groundwater would be 0.009mm per year. The groundwater monitoring results show that the groundwater depth outside the site is greater than 5000mm above rock head. As a conservative approach to cater for the fluctuation of the groundwater, 500mm is assumed. For leachate with typical COD, NH3-N and BOD concentrations of 7,952mg/L, 4,028mg/L and 2,276mg/L 5-[1], the increase in COD, NH3-N and BOD concentrations of the groundwater will be 0.149mg/L, 0.075mg/L and 0.043 respectively, which are negligible and well within the respective trigger levels of 20mg/L, 0.5mg/L and 5mg/L. Table 5.10 shows the potential impact on groundwater quality under various defect conditions.

Table 5.10   Potential Impacts of Leachate Seepage on Groundwater Quality

No. of Defects (ha)

Conductivity (m/s)

Rate of seepage (l/ha/d)

Depth infiltrated (mm/yr)

Groundwater Quality

COD (mg/L)

NH3-N (mg/L)

BOD (mg/L)

4

1 x10-11

0.26

0.0093

0.149

0.075

0.043

3

1 x10-11

0.19

0.0070

0.112

0.056

0.032

2

1 x10-11

0.13

0.0047

0.074

0.038

0.021

1

1 x10-11

0.06

0.0023

0.037

0.019

0.011

In case of seepage / leakage, the leaked leachate will be collected via the groundwater collection layer and will be drained to the on-site leachate treatment plant.  The impact on groundwater quality due to seepage / leakage of leachate is therefore assessed to be unlikely.

A network of groundwater boreholes will be established to monitor any leachate leakage.  Details of the monitoring, such as locations, frequency and parameters tested, will be proposed in the EM&A Manual.  The existing contingency plan, including groundwater extraction, interception and diversion, will also be reviewed and amended to prevent water quality impact on the nearby sensitive receivers, if necessary.

5.7.6            Potential Impacts from Sewage

Sewage will be generated from both staff working on active construction/tipping area and staff working in the site office. Permanent toilet with flushing system will be provided at the site office. The sewage collected will be conveyed to leachate treatment plant for treatment and the treated effluent will be pumped to existing gravity sewerage system for discharging to Lung Kwu Sheung Tan Outfall Chamber and then Urmston Road Submarine Outfall.  The DBO Contractor will provide temporary sanitary toilets for their own staff at the landfill development areas.  These toilets will be cleaned on a regular basis to comply with the relevant sanitary requirements. For other areas on the site where no temporary toilets are provided, workers on the sites will use the toilets at the site office. The characteristics of the sewage generated during this stage will be very much similar to that generated during construction stage. No sewage impact on the surrounding water systems is anticipated during operation phase.

5.7.7            Cumulative Impacts

Cumulative impact on leachate treatment would occur during the initial operation of the WENT Landfill Extension (Phase 1) and restoration of the existing landfill.  During restoration of the existing landfill, small amount of leachate will still be generated due to the decomposition of waste body.  However, the amount of leachate generated would be greatly reduced when compared with an active landfill.  For the WENT Landfill Extension, given the fact that the WENT Landfill Extension will be developed in phases, leachate generated in the early stage of the WENT Landfill Extension would be small.  The new on-site treatment facilities will be designed to cater leachate from both existing WENT Landfill and its extension.  Cumulative impact during the restoration of existing WENT Landfill and operation of WENT Landfill Extension is considered minimal.  As new leachate treatment plant (reprovision) will also be provided at the restored WENT Landfill.  New rising mains will also be provided and connected to the new pumping station of the WENT Landfill Extension.  The combined leachate with total flows of 2,600m³/day will then be discharged to the proposed rising mains along the realigned Nim Wan Road.

For STF, an on-site wastewater treatment plant would be provided to treat the wastewater generated for reuse at the facility for washdown water and landscape irrigation.  In addition, all on-site wastewater will be incinerated and there will be no discharge into the Deep Bay or pose any adverse impact on water quality [5-10].  Hence, no adverse cumulative impact on water quality is expected during the operation phase.

If IWMF is proposed in the middle lagoon, it is assumed that similar on-site wastewater treatment plant as STF will be provided and hence no adverse cumulative impact on water quality is expected during the operation phase.

5.7.8            Precautionary Measures

5.7.8.1        Surface Water Management

Erosion Control

There are lots erosion control methods available.  The DBO Contractor shall devise a soil erosion control plan during the detailed design stage so as to define the site-specific measures and procedures (including the specific operation plan, implementation frequency, monitoring procedures, maintenance schedules, etc). Such requirement shall be specified in contract documents. The followings summarize the most popular erosion control methods for reference:

a.             Preserve Natural Vegetation

This Best Management Practices will involve preserving natural vegetation to the greatest extent possible during the construction process and after construction where appropriate. Maintaining natural vegetation is the most effective and inexpensive form of erosion prevention control.

b.             Provision of Buffer Zone

A buffer zone consists of an undisturbed area or strip of natural vegetation or an established suitable planting adjacent to a disturbed area that reduces erosion and runoff. The rooted vegetation holds soils acts as a wind break and filters runoff that may leave the site.

c.             Seeding (Temporary/Permanent)

A well-established vegetative cover is one of the most effective methods of reducing erosion. Vegetation should be established on construction sites as the slopes are finished, rather than waiting until all the grading is complete. Besides, Hydroseeding will be applied on the surface of stockpiled soil and on temporary soil covers for inactive tipping areas to prevent soil erosion during rainy season.

d.             Ground Cover

Ground Cover is a protective layer of straw or other suitable material applied to the soil surface. Straw mulch and/or hydromulch are also used in conjunction with seeding of critical areas for the establishment of temporary or permanent vegetation. Ground cover provides immediate temporary protection from erosion. Mulch also enhances plant establishment by conserving moisture, holding fertilizer, seed, and topsoil in place, and moderating soil temperatures.

e.             Hydraulic Application

Hydraulic application is a mechanical method of applying erosion control materials to bare soil in order to establish erosion-resistant vegetation on disturbed areas and critical slopes. By using hydraulic equipment, soil amendments, mulch, tackifying agents, Bonded Fiber Matrix (BFM) and liquid co-polymers can be uniformly broadcast, as homogenous slurry, onto the soil. These erosion and dust control materials can often be applied in one operation.

f.               Sod

Establishes permanent turf for immediate erosion protection and stabilizes rainageways.

g.             Matting

There are numerous erosion control products available that can be described in various ways, such as matting, blankets, fabric and nets. These products are referred as matting. A wide range of materials and combination of materials are used to produce matting including, but not limited to: straw, jute, wood fiber, coir (coconut fiber), plastic netting, and Bonded Fiber Matrix. The selection of matting materials for a site can make a significant difference in the effectiveness of the Best Management Practices.

h.             Plastic Sheeting

Plastic Sheeting will provide immediate protection to slopes and stockpiles. However, it has been known to transfer erosion problems because water will sheet flow off the plastic at high velocity. This is usually attributable to poor application, installation and maintenance.

i.               Dust Control

Dust Control is one preventative measure to minimize the wind transport of soil, prevent traffic hazards and reduce sediment transported by wind and deposited in water resources.

Apart from above erosion control methods, it should be noted that the greater the volume and velocity of surface water runoff on landfill sites, the more sediment and other pollutants are transported to streams. Diverting runoff away from exposed soils can greatly reduce the amount of soil eroded from a site. Decreasing runoff velocities reduces erosion and the amount of pollutants carried off-site. For the division of run-off from exposed areas, the common practices include the use of pipe slope drains and diversion swales. For the reduction of runoff velocities, the common practices will include check dams and sediment traps.

Surface Water Drainage System

A temporary surface water drainage system to manage runoff will be adopted during construction and operation phases. This system will consist of channels as constructed around the perimeter of the site area. This system will collect surface water from the areas of higher elevations to those of lower elevations and ultimately to the point of discharge.  Erosion will therefore be minimised.

The temporary surface water management system will include the use of a silt fence around the soil stockpile areas to prevent sediment from entering the system. Regular cleaning will be carried out to prevent blockage of the passage of water flow in silt fence.

Intermediate drainage system will be installed for filled cell/phase. The major purpose of the intermediate drainage system is to prevent the clean surface water run-off from the filled phases coming into contact with the waste mass in active cell and to prevent excessive surface water infiltration through the intermediate cover, thus contribute to increasing volume of leachate.

The intermediate drainage system will collect the clean surface water run-off and divert it to the permanent discharge channels connected to the proposed box culvert for final discharge.

In addition, surface flow from the haul road (especially near the wheel washing facility) will be collected to a dry weather flow interceptor and conveyed to the leachate treatment plant for further treatment.

The surface flow discharge from the landfill site shall fully comply with the standards stated in Section 5.2, otherwise the contaminated surface flow shall be collected and disposed of to the on-site leachate treatment plant and eventually discharged via the Urmston Road Submarine Outfall.

Inspection and Monitoring

Inspections of the drainage system, sand traps, settlement ponds and surface water channels should be performed regularly to identify areas necessary for maintenance, cleaning or repair. Regular maintenance and replacement, if required, of the HDPE liner should be conducted to prevent degradation from affecting the performance of the capping system. 

Monthly monitoring of the surface water discharges will form part of the environmental monitoring programme. The results of the monitoring will show if contamination of surface water by leachate is occurring. If surface water is contaminated, further monitoring will be undertaken to locate the source of contamination, and remediation measures will then be carried out. Once the source of contamination has been identified, various remediation measures will be considered, for example, conveying the contaminated surface water runoff directly to the leachate treatment plant.

Detailed monitoring plan including sampling locations, parameters and frequency will be presented in the EM&A Manual for this Project.

5.7.8.2        Groundwater Management

The groundwater management facilities including the groundwater monitoring wells and the groundwater collection sumps will be inspected regularly during the routine groundwater monitoring programme.  Monitoring of groundwater quality will be conducted on a regular basis.  Details for the monitoring are given in the EM&A Manual.

5.7.8.3        Leachate Management

Contingency Plan for Accidental Leakage of Leachate

Under the existing contingency plan (under Landfill Monitoring Plan) for existing WENT Landfill, groundwater within and around the site will be monitored in accordance with the groundwater monitoring programme proposed in the EM&A Manual. The parameters to be monitored include groundwater level and groundwater quality. The objective of the monitoring programme is to ensure that the trigger levels in Table 5.11 below are not exceeded.

Table 5.11  Trigger levels for groundwater monitoring

Parameter

Trigger Level

Ammonia Nitrogen

0.5 mg/L

COD

20 mg/L

BOD

5 mg/L

In the event that the above trigger levels are exceeded, the DBO Contractor will implement a Corrective Action Programme, which shall include:

·          Groundwater interception and diversion; and

·          Groundwater extraction (by active pumping of leachate from leachate and groundwater collection layers) and treatment prior to discharge.

The existing Contingency Plan is comprehensive and well-developed. It will be used as basis for developing the Contingency Plan for the WENT Landfill Extension.

Potential actions to be taken in case of identification of groundwater contamination should also include:

·          Installation of additional ground-water monitoring well;

·          Increased frequency of ground-water quality testing;

·          Installation of ground-water extraction wells to remove contaminated groundwater for treatment;

·          Installation of subsurface barriers, such as bentonite;

·          Detailed investigation of the potential impact to be performed within six months of the first detection of the justified impact.

Contingency Plan for Surface Water Contamination

Surface water monitoring will be conducted to keep the ammonia-nitrogen and COD below the following trigger levels:

Table 5.11a  Trigger levels for surfacewater monitoring

Parameter

Trigger Level

Ammonia nitrogen

0.5 mg/L

COD

30 mg/L

BOD

20 mg/L

In the event that any one of the above parameters was exceeded, the landfill operation should implement a Corrective Action Programme. The key elements shall include:

·          Surface water interception and temporary storage of the contaminated surface water;

·          Installation of surface barriers, such as sand bund along the surface water channel / site boundary to avoid overflow off-site; 

·          Active pumping of the contaminated surface water to the leachate lagoons / leachate recirculation system / on-site leachate treatment plant;

·          Additional monitoring locations will be selected to determine the pollution source;

·          Installation of surface barriers, such as intercepting bund to separate the active and inactive tipping area. 

·          Change of working methods to prevent surface water contamination; and

·          Implementation of diversionary works.

5.7.9            “What if IWMF not proceed”

Similar to the construction phase, since all the proposed precautionary and mitigation measures will be extended to that area, there would not have additional impacts on the water quality on neighbouring sensitive receivers.

5.8                 Restoration and Aftercare Phase

Upon completion of final filling and site restoration, the period of aftercare will begin and last for 30 years. During this period, leachate will continue to be generated. The established leachate control measures and treatment will continue to operate throughout the aftercare period. 

Subject to the nature and scale of aftercare development, potential sources of water quality impact during the restoration and aftercare phases include surface runoff, seepage/leakage of leachate and sewage generation.  Water quality impact in restoration and aftercare phases would be even smaller than those in the operation phase.

In view of the similar nature but smaller scale in water quality impact generated during this phase, water quality assessment methodologies adopted in the construction and operation phases can be made reference to in the restoration and aftercare phases.

5.8.1            Potential Impacts on Surface Runoff

Subject to the nature of aftercare development, surface runoff should comprise mainly soil in a much smaller-scale than the construction and operation phases. Surface runoff from the restored WENT Landfill Extension will be collected to the new stormwater drainage system and discharge to Deep Bay via box culvert outfall.  No adverse water quality impact is expected during restoration and aftercare period.

5.8.2            Potential Impacts on Seepage / Leakage of Leachate

Potential risks to groundwater quality will be associated with leakage of leachate from the WENT Landfill Extension through the base liner and side slope lining systems.   With the presence of the multi-layer capping and liner systems, proper site maintenance and regular monitoring, the probability of the leachate leakage to groundwater system from the base liner system and containment system is expected to be very low.   

During restoration, the landfill will be restored and vegetated to match the surrounding landform. Final capping with impermeable liner will be provided to prevent infiltration of surface water and hence minimise the leachate generation.  The leachate generated during this period would be much less than the operation phase.  The new leachate treatment works have sufficient capacity to treat the leachate and hence impact arising from leachate infiltrated should be in a much smaller-scale than that in operation phase.  Seepage/leakage of leachate for a restored landfill would have less impact than an operating landfill. 

5.8.3            Potential Impacts on Sewage Generation

Sewage generated from the after use facilities will be collected by new sewerage system and conveyed to the leachate treatment plant for treatment.  The treated effluent will be pumped to the existing gravity sewerage system for discharging to Lung Kwu Sheung Tan Outfall Chamber and then Urmston Road Submarine Outfall. Similar to the operation phase, all site staff will use the permanent toilet provided at the site office. No sewage impact on the surrounding water systems is anticipated. 

5.8.4            Cumulative Impacts

As discussed in Section 5.7.7, no adverse cumulative water quality impact is expected from the concurrent projects during the restoration and aftercare phases.

5.8.5            Precautionary Measures

A permanent surface water drainage system will be provided to convey the surface water running through the final restoration slopes to the perimeter channels.  The design of the diversion channels located on the final cover is such that their construction involves no disturbance below the cap cover soil. 

Regular groundwater quality monitoring should be carried out to monitor the performance of the leachate containment system. Maintenance and replacement of the capping system should be carried out, if necessary, to prevent leachate seepage in the event of a damaged cap.

In addition, long term measures to prevent any surface breakout of leachate include maintaining control of the leachate level through extraction; and/or maintaining the engineered capped system to control infiltration.

5.8.6            “What if IWMF not proceed”

Similar to other phases, since all the proposed precautionary and mitigation measures will be extended to that area, there would not have additional impacts on the water quality on neighbouring sensitive receivers.

5.9                 Cumulative Impacts

Two possible potential concurrent projects in the vicinity of the WENT Landfill Extension are identified, including the following:

·                   Sludge Treatment Facilities; and

·                   Integrated Waste Management Facilities.

5.9.1            Construction Phase

As discussed in Section 5.6.6, the construction of the STF, IWMF and WENT Landfill Extension will fall into different timeframe, initial development of the WENT Landfill Extension will be after the completion of the above two projects. 

Given that the construction phase is implemented with proper site management and good housekeeping practices, no adverse cumulative water quality impact is anticipated.

5.9.2            Operation Phase

Cumulative impact on leachate treatment would, however, occur during the initial operation of the WENT Landfill Extension (Phase 1) and restoration of the existing landfill.  During restoration of the existing landfill, small amount of leachate will still be generated due to the decomposition of waste body.  However, the amount of leachate generated would be greatly reduced when compared with an active landfill.  For the WENT Landfill Extension, given the fact that the WENT Landfill Extension will be developed in phases, leachate generated in the early stage of the WENT Landfill Extension would be small.  The new on-site treatment facilities will be designed to cater leachate from both existing WENT Landfill and its extension.  Cumulative impact during the restoration of existing WENT Landfill and operation of WENT Landfill Extension is considered minimal.   With leachate minimisation control measures to be implemented in the extension site, the combined leachate from restored WENT Landfill and the WENT Landfill Extension will be kept same as the existing discharge limit of existing WENT Landfill (with total flows of 2,600m³/day).  The combined leachate will then be discharged to the proposed rising mains along the realigned Nim Wan Road and finally disposed to Lung Kwu Sheung Tan Outfall Chamber and then Urmston Road Submarine Outfall.

Besides, there is contract provision in the extension site to provide temporary leachate storage to cater one-off event during extreme rainfall incident.  The size of the storage tank will be sufficient to cater the contaminated surface water for corrective action. The quantity of leachate discharged to the on-site leachate treatment plant will be controlled and will not overload the treatment system.

As discussed in Section 5.7.7, on-site wastewater treatment plant would be provided in STF to treat the wastewater generated for reuse at the facility for washdown water and landscape irrigation.  In addition, all on-site wastewater will be incinerated and there will be no discharge into the Deep Bay or pose any adverse impact on water quality.  Hence, no adverse cumulative impact on water quality is expected during the operation phase.

5.9.3            Restoration and Aftercare Phase

During the aftercare phase of the WENT Landfill Extension, leachate will continue to be generated from both restored WENT Landfill and its extension, but the leachate quantity is expected to be sufficiently reduced. The established leachate control measures and treatment will continue to operate throughout the aftercare period of the WENT Landfill Extension.

Proper site maintenance will be undertaken during the aftercare period to ensure that the capping system, leachate collection and treatment systems will be performed to comply with the design requirements. Surface water, groundwater and effluent quality monitoring will also be undertaken during the aftercare period in accordance to the monitoring plan. With the provisions of all these control and monitoring systems, no cumulative impacts are expected to occur during the aftercare phase.

5.10             Residual Impacts

Construction site runoff will be managed in accordance with the guidelines specified in ProPECC PN 1/94, no residual water quality impact during construction phase is anticipated.

All site staff will either use portable toilets provided on site or the permanent toilets provided at the site office. No residual sewage impact on the surrounding water systems is anticipated.

The rate of leachate seepage is assessed to be negligible. With the implementation of the contingency plan on leachate seepage, no residual groundwater quality impact is anticipated.

The surface drainage management system is designed to collect, carry and discharge the clean surface water run-off from WENT Landfill Extension and its immediate surroundings to the public drainage network. The discharge of surface water from the landfill drainage system will not have any adverse impacts on the water quality of the surrounding streams and rivers.

No residual water quality impact is envisaged during the construction, operation, restoration and aftercare of the WENT Landfill Extension.

5.11             Conclusion

The potential water quality impacts of the Project have been assessed.

5.11.1        Construction Phase

With proper implementation of construction site runoff control measures, adverse water quality impact during construction phase is not expected.

Sewage will be generated by workforce on-site during the construction period.  Temporary sanitary toilets will be provided for on-site construction workforce.  No sewage will be allowed to discharge directly into the surrounding water body without treatment.   It is anticipated that sewage generation during the construction phase of the Project would not cause water quality impact after undertaking all required measures.

5.11.2        Operation Phase

Given that the WENT Landfill Extension will only be in operation after the closure of the existing landfill, no cumulative water quality impact due to the operation of the two landfills will occur.  Nonetheless, cumulative impact will occur when restoration in existing landfill and operation in the extension take place concurrently.

With the implementation of surface water and groundwater management control measures, adverse water quality impact on surface water and groundwater during operation phase is not expected.

Leachate generated from the landfill will be treated at the leachate treatment plant. The treated leachate will be pumped to the rising mains running along the realigned Nim Wan Road and connected to the existing gravity sewerage system discharging to the DSD Lung Kwu Sheung Tan Outfall Chamber. It is then discharged via the Urmston Road Submarine Outfall into marine waters.  Given that the discharge limit of the leachate treatment will be maintained, the impact of leachate on the environment will be minimal.

Under normal installation condition, the rate of leachate seepage is potentially 0.26 litres per hectare per day, which is considered to be insignificant.  With the implementation of the measures proposed in the Contingency Plan on Accidental Leakage of Leachate (including active pumping of leachate from leachate and groundwater collection layers to the on-site leachate treatment plant), impact on the groundwater quality is insignificant.

Nevertheless, monthly monitoring of the surface and groundwater discharges will form part of the EM&A programme.  If groundwater or surface water is contaminated, further monitoring will be undertaken to locate the source of contamination, and remediation measures will then be carried out.

Sewage will be generated by workforce on site during operation phase. Adverse impact is not anticipated as both portable toilets and permanent toilets at the site office will be provided to collect all sewage generated.

For STF and IWMF, wastewater generated will be reused within the facilities for washdown water and landscape irrigation.  Hence, there would be no discharge into the Deep Bay and no adverse cumulative impact on water quality is anticipated.

5.11.3        Restoration and Aftercare Phases

During the restoration and aftercare phases, leachate will continue to be generated but the amount of leachate generated is expected to be sufficiently reduced.  The established leachate control measures and treatment will continue to operate throughout the restoration and aftercare periods of the WENT Landfill Extension.

Proper site maintenance will be undertaken during the restoration and aftercare periods to ensure that the capping system, leachate collection and treatment systems will be performed to comply with the design requirements. Surface water, groundwater and effluent quality monitoring will also be undertaken during the restoration and aftercare periods in accordance to the monitoring plan. With the provisions of all these control and monitoring systems, no cumulative impacts are expected to occur during the restoration and aftercare phases.

5.12             Reference

[5-1]           Environmental Protection Department (EPD). 1997. Environmental Impact Assessment Ordinance (Cap.499, S.16), Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO). HKSAR.

[5-2]           HKSAR Government. 1997. Water Pollution Control Ordinance (WPCO) (Cap. 358). HKSAR.

[5-3]           HKSAR Government. 1997. Technical Memorandum - Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters. HKSAR.

[5-4]           EPD. 1994. Practice Note for Professional Persons - Construction Site Drainage (ProPECC PN 1/94). EPD, HKSAR.

[5-5]           EPD. Pollution Control Clauses for Construction Contract. EPD, HKSAR.

[5-6]           PlanD.  Hong Kong Planning Standards and Guidelines (HKPSG), PlanD, HKSAR.

[5-7]           EPD. 2008. Marine Water Quality in Hong Kong 2007. EPD, HKSAR.

[5-8]           EPD. River Water Quality in Hong Kong 2000 - 2007. EPD, HKSAR.

[5-9]           EPD. 2007. North East New Territories (NENT) Landfill Extension Environmental Impact Assessment Final Report. EPD, HKSAR.

[5-10]        EPD. Sludge Treatment Facilities - Project Profile. EPD, HKSAR.

[5-11]        Schroeder PR, TS Dozier, PA Zappi, BM McEnroe, JW Sjostorm and RL Peton. 1994. The Hydrologic Evaluation of Landfill Performance (HELP) Model: Engineering Documentation for Version 3 (EPA/600/R-94/168b). United States Environmental Protection Agency (USEPA), US.

[5-12]        Giroud JP and R Bonaparte. 1989. Leakage through Liners Constructed with Geomembranes, Part I. Geomembrane Liners, Geotextiles and Geomembranes 8: 27-67.

[5-13]        Giroud JP, TD King, TR Sanglerat, T Hadj-hamou and MV Khire. 1997. Rate of Liquid Migration through defects in a Geomembrane placed on a Semi-permeable Medium. Geosynthetics International 4: 349-372.

[5-14]        Geosynthetic Clay Liners used in Municipal Solid Waste Landfills, United States Environmental Protection Agency, Solid Waste and Emergency Response, EPA530-F-97-002, July 1997.

 



5-[1] Data from WENT Monthly Reports, 2003-2007