Section                                  Title                                                                                        Page

4.1              Introduction________________________________________________________________ 4-1

4.2              Environmental Legislation, Standards and Guidelines_______________________________ 4-1

4.3              Assessment Area, Noise Sensitive Receivers and Background Noise Climate_____________ 4-5

4.4              Construction Phase Impact____________________________________________________ 4-8

4.5              Operation Phase Impact_____________________________________________________ 4-22

4.6              Environmental Monitoring and Audit_____________________________________________ 4-35

4.7              Conclusion_______________________________________________________________ 4-35

 

Tables

Table 4.1:__ Noise Standards for Daytime Construction Activities_ 4-2

Table 4.2:__ Ground-borne Noise Criteria (Leq 30min, dB(A)) 4-3

Table 4.3:__ Relevant Noise Standards for Planning Purposes_ 4-4

Table 4.4:__ Acceptable Noise Level for Fixed Plant Noise_ 4-4

Table 4.5:__ Area Sensitivity Rating_ 4-5

Table 4.6:__ Representative Noise Sensitive Receivers_ 4-7

Table 4.7__ Measured Noise Levels_ 4-8

Table 4.8:__ Unmitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A) 4-9

Table 4.9__ Unmitigated Construction Airborne Noise Impact from Lin Ma Hang to Wo Keng Shan, Leq (30mins) dB(A) 4-10

Table 4.10_ Unmitigated Construction Airborne Noise Impact at  Wo Keng Shan, Leq (30mins) dB(A) 4-10

Table 4.11_ Unmitigated Construction Airborne Noise Impact near Sha Tau Kok Road, Leq (30mins) dB(A) 4-11

Table 4.12_ Unmitigated Construction Airborne Noise Impact near Po Kat Tsai, Leq (30mins) dB(A) 4-11

Table 4.13_ Unmitigated Construction Airborne Noise Impact near Fanling, Leq (30mins) dB(A) 4-11

Table 4.14_ Quieter PME Recommended for Adoption during Construction Phase_ 4-12

Table 4.15_ Noise Mitigation Measures for Certain PME during Construction Phase_ 4-13

Table 4.16:_ Mitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A) 4-14

Table 4.17_ Mitigated Construction Airborne Noise Impact from Lin Ma Hang to Wo Keng Shan, Leq (30mins) dB(A) 4-14

Table 4.18_ Mitigated Construction Airborne Noise Impact at Wo Keng Shan, Leq (30mins) dB(A) 4-15

Table 4.19_ Mitigated Construction Airborne Noise Impact near Sha Tau Kok Road, Leq (30mins) dB(A) 4-15

Table 4.20_ Mitigated Construction Airborne Noise Impact near Po Kat Tsai, Leq (30mins) dB(A) 4-16

Table 4.21_ Mitigated Construction Airborne Noise Impact near Fanling, Leq (30mins) dB(A) 4-16

Table 4.22:_ Cumulative Mitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A) 4-17

Table 4.23_ Cumulative Mitigated Construction Airborne Noise Impact at Lin Ma Hang to Frontier Closed Area Boundary, Leq (30mins) dB(A) 4-17

Table 4.24:_ Reference Vibration Level based on Measurements_ 4-19

Table 4.25:_ Source Vibration Velocity of Octave Band Frequency for Hydraulic Breaker 4-19

Table 4.26: _ Wave Propagation Properties of Soil 4-19

Table 4.27:_ Adjustment Factor for Building Coupling Loss (BCF) 4-20

Table 4.28:_ Adjustment Factor for Building Structure Attenuation (BSA) 4-20

Table 4.29:_ Building Structure Attenuation (BSA) 4-20

Table 4.30:_ Building Structure Resonance (BSR) 4-21

Table 4.31:_ Room Correction Factors_ 4-21

Table 4.32_ Unmitigated Construction Ground-borne Noise_ 4-22

Table 4.33_ Comparison between With and Without Project in Year 2018 from Lin Ma Hang to North Tunnel (Existing Receivers) 4-23

Table 4.34_ Comparison between With and Without Project in Year 2018 from Lin Ma Hang to North Tunnel (Planned Receivers) 4-24

Table 4.35_ Comparison between With and Without Project in Year 2018 near Sha Tau Kok Road Section (Existing Receivers) 4-25

Table 4.36_ Comparison between With and Without Project in Year 2018 near Fanling Highway (Existing Receivers)4-25

Table 4.37_ Unmitigated Road Traffic Noise Impact in Year 2033 near Lin Ma Hang to Wo Keng Shan (Existing Uses4-26

Table 4.38_ Unmitigated Road Traffic Noise Impact in Year 2033 near Lin Ma Hang to Wo Keng Shan (Planned Uses) 4-27

Table 4.39_ Unmitigated Road Traffic Noise Impact in Year 2033 near Sha Tau Kok Road Section (Existing Uses) 4-27

Table 4.40_ Unmitigated Road Traffic Noise Impact in Year 2033 near Fanling Highway (Existing Uses) 4-27

Table 4.41_ Summary of Exceedance of Road Traffic Noise Criteria_ 4-28

Table 4.42_ Proposed Location of Noise Barrier for Existing Uses_ 4-29

Table 4.43:_ Mitigated Road Traffic Noise Levels of Existing Uses_ 4-30

Table 4.44_ Noise Criteria of Fixed Plant Noise_ 4-31

Table 4.45:_ Summary of Fixed Plant Noise Sources_ 4-33

Table 4.46:_ Maximum SWLs of the Fixed Plant 4-33

 

 

Figures

Figure 1.1                              Project Layout Plan

Figure 4.1.1                          Assessment Area and Outline Zoning Plan

Figure 4.1.2                          Recommended Development Plan (Sheet 1 of 2)

Figure 4.1.3                          Recommended Development Plan (Sheet 2 of 2)

Figure 4.2                              Representative Noise Sensitive Receivers (Sheet 1 of 11)

Figure 4.3                              Representative Noise Sensitive Receivers (Sheet 2 of 11)

Figure 4.4                              Representative Noise Sensitive Receivers (Sheet 3 of 11)

Figure 4.5                              Representative Noise Sensitive Receivers (Sheet 4 of 11)

Figure 4.6                              Representative Noise Sensitive Receivers (Sheet 5 of 11)

Figure 4.7                              Representative Noise Sensitive Receivers (Sheet 6 of 11)

Figure 4.8                              Representative Noise Sensitive Receivers (Sheet 7 of 11)

Figure 4.9                              Representative Noise Sensitive Receivers (Sheet 8 of 11)

Figure 4.10                           Representative Noise Sensitive Receivers (Sheet 9 of 11)

Figure 4.11                           Representative Noise Sensitive Receivers (Sheet 10 of 11)

Figure 4.12                           Representative Noise Sensitive Receivers (Sheet 11 of 11)

Figure 4.13                           Photos of Noise Sensitive Receivers

Figure 4.14                           Photos of Noise Sensitive Receivers

Figure 4.15                           Photos of Noise Sensitive Receivers

Figure 4.16                           Photos of Noise Sensitive Receivers

Figure 4.17                           Photos of Noise Sensitive Receivers

Figure 4.18                           Schematic Diagram of Movable Noise Barrier

Figure 4.19                           Schematic Diagram of Full Noise Enclosure for PME

Figure 4.20.1                        Proposed Location of Noise Barriers (Sheet 1 of 4)

Figure 4.20.2                        Proposed Location of Noise Barriers (Sheet 2 of 4)

Figure 4.20.3                        Proposed Location of Noise Barriers (Sheet 3 of 4)

Figure 4.20.4                        Proposed Location of Noise Barriers (Sheet 4 of 4)

Figure 4.20.5                        Cross-section Plans of Proposed Barriers

Figure 4.21.1                        Fixed Plant of Boundary Control Point

Figure 4.21.2                        Fixed Plant of North Tunnel North Portal

Figure 4.21.3                        Fixed Plant of North Tunnel South Portal

Figure 4.21.4                        Fixed Plant of Administration Building

Figure 4.21.5                        Fixed Plant of South Tunnel North Portal

Figure 4.21.6                        Fixed Plant of Mid-Ventilation Building

Figure 4.21.7                        Fixed Plant of South Tunnel South Portal

 

Appendices

Appendix 4.1                         Unmitigated Construction Plant Inventory

Appendix 4.2                         Unmitigated Construction Airborne Noise Impacts

Appendix 4.3                         Mitigated Construction Plant Inventory

Appendix 4.4                         Mitigated Construction Airborne Noise Impacts

Appendix 4.5                         Unmitigated Construction Ground-borne Noise Impacts

Appendix 4.6                         Traffic Data and Road Traffic Network

Appendix 4.7                         Comparison Scenario Between With and Without Project

Appendix 4.8                         Unmitigated Road Traffic Noise Level

Appendix 4.9                         Mitigated Road Traffic Noise Level

Appendix 4.10                      Sample Calculation of Fixed Plant Noise

 

 



4.1               Introduction

This section presents the assessment of the potential noise impacts associated with the construction and operation phases of the proposed BCP and associated facilities, according to section 3.4.4 of the Study Brief (ESB-199/2008) and Annexes 5 and 13 of the Technical Memorandum to the EIAO. Mitigation measures, where necessary, have been recommended accordingly to reduce the identified noise impacts to an acceptable level.

Potential noise impacts associated with the construction and operational phases of the Project have been assessed.  Noise generated from various construction activities is the primary concern during the construction phase. Road traffic noise from the proposed connecting roads, fixed plant noise from ventilation shafts, as well as noise from fixed plant of the BCP are major noise impacts during the operational phase.  Representative Noise Sensitive Receivers (NSRs) within 300m of the subject site have been identified and the worst case impacts on these receivers have been assessed.  Suitable mitigation measures, where necessary, have been recommended to protect the NSRs and to ensure that the legislative criteria and guidelines can be satisfied.

4.2               Environmental Legislation, Standards and Guidelines

4.2.1           Construction Phase

Control over the generation of construction noise in Hong Kong is governed by the Noise Control Ordinance (NCO) and the EIAO and their subsidiary requirements. Various Technical Memoranda (TMs) have been issued under the NCO and the EIAO to stipulate control approaches and criteria.  These TMs prescribe the maximum permitted noise levels for the use of Powered Mechanical Equipment (PME) and certain construction activities and processes, according to the type of equipment or activity, the perceived noise climate of the area, and the working hours of equipment operation and usage.  The TMs applicable to the control of noise from construction activities of proposed construction works are:

¡      TM on Environmental Impact Assessment Process (EIAO-TM)

¡      TM on Noise from Construction Work other than Percussive Piling (GW-TM)

¡      TM on Noise from Construction Work in Designated Areas (DA-TM)

4.2.1.1         General Construction Activities during Non-Restricted Hours

Noise impacts arising from general construction activities other than percussive piling during the daytime period (07:00-19:00 hours of any day not being a Sunday or general holiday) are assessed against the noise standards tabulated in Table 4.1 below.

Table 4.1:      Noise Standards for Daytime Construction Activities

Noise Sensitive Uses

0700 to 1900 hours on any day not being a Sunday or general holiday, Leq (30 min), dB(A)

All domestic premises including temporary housing accommodation

75

Hotels and hostel

Educational institutions including kindergarten, nurseries and all others where unaided voice communication is required

70

65 during examination

Source: EIAO-TM, Annex 5, Table 1B - Noise Standards for Daytime construction Activities

Note:        The above noise standards apply to uses, which rely on opened windows for ventilation

The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external facade             

The above standards shall be met as far as possible.  All practicable mitigation measures shall be exhausted and the residual impacts are minimised

4.2.1.2         General Construction Activities during Restricted Hours

Noise impacts arising from general construction activities (excluding percussive piling) conducted during the restricted hours (19:00-07:00 hours on any day and anytime on Sunday or general holiday) and percussive piling during anytime are governed by the Noise Control Ordinance (NCO).

For carrying out of any general construction activities involving the use of any Powered Mechanical Equipment (PME) within restricted hours, a Construction Noise Permit (CNP) is required from the Authority under the NCO. The noise criteria and the assessment procedures for issuing a CNP are specified in Technical Memorandum on Noise from Construction Work Other Than Percussive Piling (GW-TM) under the NCO.

The use of Specified PME (SPME) and/or the carrying out of Prescribed Construction Work (PCW) within a Designated Area (DA) under the NCO during the restricted hours are also prohibited without a CNP. The relevant technical details in Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM) under NCO can be referred. 

Designated areas, in which the control of SPME and PCW shall apply, are established through the Noise Control (Construction Work Designated Areas) Notice made under Section 8A(1) of the NCO.  According to the Designated Area defined under the NCO (effective from 1 January 2009), only a small part of the works area of this project will fall within these areas where underground tunnelling works would be carried out. 

As such, the application for CNP for any general construction activities involving the use of any PME shall refer to the GW-TM only. However, the Contractor has the responsibility to check the latest status and coverage of the Designated Areas at time of construction of the Project.

Regardless of any description or assessment made in this section, in assessing a filed application for a CNP the Authority will be guided by the relevant Technical Memoranda.  The Authority will consider all the factors affecting their decision taking contemporary situations/ conditions into account. Nothing in this Report shall pre-empt the Authority in making their decisions, and there is no guarantee that a CNP will be issued.  If a CNP is to be issued, the Authority may include any conditions they consider appropriate and such conditions are to be followed while the works covered by the CNP are being carried out. Failing to do so may lead to cancellation of the permit and prosecution action under the NCO.

According to the construction programme, the proposed construction works would be carried out during non-restricted hours.  In case of any construction activities during restricted hours, it is the Contractor’s responsibility to ensure compliance with the NCO and the relevant TMs. The Contractor will be required to submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued.

4.2.1.3         Ground-borne Noise

Noise arising from general construction works during normal working hours is governed by the EIAO-TM under the EIAO as shown in Table 4.1.  The Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM) under the NCO stipulates that noise transmitted primarily through the structural elements of building, or buildings, shall be 10 dB(A) less than the relevant Acceptable Noise Level (ANLs).

Based on the same principle for the ground-borne noise criteria (i.e. ANL-10 dB(A) under the IND-TM), the ground-borne construction noise levels inside domestic premises and schools shall be limited to 65 dB(A) and 60 dB(A) respectively when compared to the EIAO-TM. 

For construction works conducted on general holidays, Sundays and weekdays during evening (1900-2300 hrs) and night time (2300-0700 hrs) the following day, the ground-borne construction noise level shall be limited to 10 dB(A) below the respective ANLs for the Area Sensitivity Rating appropriate to those NSRs affected by the Project.  A summary of these criteria is given in Table 4.2.

Table 4.2:      Ground-borne Noise Criteria (Leq 30min, dB(A))

NSR type

Ground-borne Noise Criteria (1), dB(A)

Daytime (0700-1900) except general holidays and Sunday

Daytime (0700-1900) during general holidays and Sundays and all days during Evening (1900-2300 hrs)

Night-time (2300 – 0700 hrs)

All domestic premises including temporary housing accommodation

65

50/55/60(2,3)

35/40/45(2,3)

Hotels and hostel

Educational institutions including kindergarten, nurseries and all others where unaided voice communication is required

60

55 (for during examination)

N/A(4)

N/A(4)

Notes:

(1)      Noise descriptor for daytime noise except general holidays and Sunday and other periods are Leq (30min) and Leq (5min) respectively.  Measurement shall be carried out at an internal location representative of normal occupancy of the building. For residential building, measurement shall be conducted in the bedroom of the apartment.

(2)      Based on the Basic Noise Level for NSRs with Area Sensitivity Ratings of A, B, and C detailed in the Technical Memorandum on Noise From Construction Work Other Than Percussive Piling.

(3)      Construction Noise Permit is required for works during this period.

(4)      No sensitive use in Education institutions during evening and night-time period is assumed except specified.

4.2.1.4         Blasting

There are no statutory procedures and criteria under the NCO and EIAO for assessing the airborne noise impacts of blasting, hence the airborne noise impact assessment generated by this activity is beyond the scope of the EIA. However, it is expected that the impact due to blasting shall be minimal as the blasting location is deep underground (about 40m below ground level of the identified ground-borne NSRs) and far away from the noise sensitive receivers and most of the blasting will be carried out inside tunnel. Nevertheless good site practices such as installation of blasting door at tunnel portals or equivalent measures and proper schedule of blasting time (e.g. during non sensitive hours) shall be implemented by the Contractor so to avoid the potential disturbance that may be caused.

4.2.2           Operation Phase

4.2.2.1         Road Traffic Noise

The Technical Memorandum (TM) published under Section 16(5) of the Environmental Impact Assessment Ordinance (EIAO) gazetted in 1997, is the fundamental legislation of noise criteria for evaluating noise impact of designated projects.  The summary of noise criteria is given in Table 4.3. 

Table 4.3:      Relevant Noise Standards for Planning Purposes             

Uses

Road Traffic Noise Peak Hour Traffic

L10 (1hour), dB(A)

All domestic premises including temporary housing accommodation

70

 

Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required

65

 

Notes:      (i)             The above standards apply to uses which rely on opened windows for ventilation

(ii)            The above standards should be viewed as the maximum permissible noise levels assessed at 1m from the external façade

4.2.2.2         Fixed Plant Noise

For the fixed plant noise assessment, the ANLs for the NSRs are determined based on the Area Sensitivity Rating (ASR).

Fixed plant noise is controlled under the NCO and shall comply with the ANLs laid down in the Table 2 of the IND-TM. For a given ASR, the ANL is given by Table 4.4.

Table 4.4:      Acceptable Noise Level for Fixed Plant Noise

Time Period

Area Sensitivity Rating

A

B

C

Day (0700 to 1900 hours)

60

65

70

Evening (1900 to 2300 hours)

Night (2300 to 0700 hours)

50

55

60

As stipulated in Annex 5 of the EIAO-TM, the noise standard for planning purposes for fixed noise source are (a) 5 dB(A) below the appropriate ANL, or (b) the prevailing background noise levels (For quiet areas with level 5 dB(A) below the ANL).

4.2.2.3         Area Sensitivity Rating (ASR)

ASR is defined in the IND-TM.  The ASR depends on the type of area and the degree of impact that Influencing Factors (IFs) have on the NSRs and is determined from Table 4.5.  Industrial area, major road or the area within the boundary of Hong Kong International Airport shall be considered to be an IF.

Table 4.5:      Area Sensitivity Rating

Type of Area Containing NSR

Degree to which NSR is affected by IF

Not Affected

Indirectly Affected

Directly Affected

(i) Rural area, including country parks or village type developments

A

B

B

(ii) Low density residential area consisting of low-rise or isolated high-rise developments

A

B

C

(iii) Urban area

B

C

C

(iv) Area other than those above

B

B

C

4.3               Assessment Area, Noise Sensitive Receivers and Background Noise Climate

4.3.1.1         Assessment Area

The Assessment Area is defined as within 300m of the site boundary of the Project for noise impact assessment. This assessment area is identified and shown in Figure 4.1.1.

4.3.1.2         Noise Sensitive Receivers (NSRs)

Noise Sensitive Receivers (NSRs) have been identified in accordance with Annex 13 of the EIAO-TM. The NSRs have included existing, planned/ committed noise sensitive developments and relevant uses earmarked on the relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans, including plans and drawings published by Lands Department.  The Outline Zoning Plans within the assessment area are shown in Figure 4.1.1.

There are numerous village houses situated along the proposed BCP and the connecting road which are identified as NSRs.  For the purpose of noise assessment, the first layer of houses of each village located close to the site boundary have been selected as assessment points/ identified representative NSRs within the Study Area for prediction of noise impact levels.

According to the Outline Zoning Plans (S/NE-TKL/13 – Ping Che & Ta Kwu Ling, S/NE-WKS/10 – Wo Keng Shan, S/NE-MUP/11 – Man Uk Pin, S/NE-KLH/11 – Kau Lung Hang) located within the works area, there are Village Type Development zoning (“V” zone) near Nga Yiu Ha, Ping Yeung, Wo Keng Shan, Tai Tong Wu, Loi Tung and Kau Lung Hang.  Construction of New Territories Exempted House is permitted in this zoning.  Existing NSRs in those “V” zone located close to the site boundary have been identified and selected as representative NSRs.  It is identified that the first layer of existing NSRs does not cover the worst affected location of the “V” zone at Wo Keng Shan. Hence an assessment point i.e. WKS8 has been selected to represent a planned NSR in the area.

It is noted that some of the existing NSRs along the proposed road alignment are located in the Agriculture and Green Belt zonings.  Construction of new New Territories Exempted House outside the 'V' Zones would require planning permission from the Town Planning Board under Section 16 of the Town Planning Ordinance.  At the time of preparation of this Report, no approved application for such planned development was identified along the site boundary of the Project.

According to the North East New Territories New Development Areas (NENT NDAs) Planning and Engineering Study – Investigation (2009), part of the Ping Che/ Ta Kwu Ling NDA is located within the Study Area.  However, the study is still in progress and land uses within the NDA has not been finalised.  As first layer of NSRs have been selected as assessment points, no additional assessment point has been selected for the NDA.

According to the planned programme (see Appendix 2.2), the Chuk Yuen Village Resite will be completed in early 2012 for population intake by early 2013, and construction of this Project will commence in around mid 2013.  Therefore, the existing Chuk Yuen Village that is within the BCP site will have been relocated to the Resite (as represented by NSR CY3) before commencement of construction of this Project.  Hence, the existing Chuk Yuen Village located within the future BCP site will not be subject to any construction or operational phase impacts of this Project, and is not included in this assessment.   However, the Chuk Yuen Village Resite (NSR CY3) will be subject to both construction and operational phase impacts, and is included in the assessment.

Based on the Recommended Development Plan in the Final Report (July 2010) of Planning Department’s Land Use Planning for the Closed Area – Feasibility Study (see Figures 4.1.2 and 4.1.3), areas of Tsung Yuen Ha, Chuk Yuen and Kan Tau Wai fall within the Study Area of this noise impact assessment are proposed to be zoned as “V” zone. As the existing NSR TYH in Tsung Yuen Ha and NSR CY3 in Chuk Yuen have been selected, no additional planned assessment point has been added for these two “V” zones.  However an additional assessment point i.e. KTW6 has been added to represent a planned NSR in the proposed “V” zone at Kan Tau Wai.

Descriptions of selected representative NSRs are tabulated in Table 4.6.  The representative NSRs are shown in the Figures 4.2 to 4.12.  Photos of existing noise sensitive receivers are shown in Figures 4.13 to 4.17.

 



4.3.1.3         Background Noise Climate

Noise surveys were carried out from November 2009 to April 2010 to investigate the background noise condition of the surrounding environment and the Project Area.  Figures 4.2 to 4.12 show the baseline noise measurement locations.

Five noise measurements were carried out in the Project Area.  The noise measurements were undertaken using Type 1 sound level meters, namely Rion NL-18 and Rion NL-31.  During each measurement, the sound level meter was checked using an acoustic calibrator generating a sound pressure level of 94dB(A) at 1kHz immediately before and after the noise measurement.  The measurements were accepted as valid only if the calibration levels before and after the noise measurement were agreed to within 1.0dB(A).  Moreover, the sound level meters and acoustic calibrators are calibrated in accredited laboratories yearly to ensure reliable performance.  The measurement results are shown in Table 4.7.

Table 4.7       Measured Noise Levels

Location ID

Location Description

Time Period

Start Time

Measured Noise Level in Leq(30min), dB(A)

Corrected Facade Noise Level, dB(A)

A

Tsung Yuen Ha

Daytime (0700 – 1900)

07:15

49

52

 

 

Evening Time (1900 – 2300)

19:00

46

49

 

 

Night-time (2300 – 0700)

06:15

42

45

B

Ng Chau Road

Daytime (0700 – 1900)

15:30

53

56

 

 

Evening Time (1900 – 2300)

19:20

49

52

 

 

Night-time (2300 – 0700)

05:45

43

46

C

Wo Keng Shan

Daytime (0700 – 1900)

09:15

51

54

 

 

Evening Time (1900 – 2300)

20:15

44

47

 

 

Night-time (2300 – 0700)

23:15

42

45

D

Loi Tung

Daytime (0700 – 1900)

16:10

46

49

 

 

Evening Time (1900 – 2300)

19:20

41

44

 

 

Night-time (2300 – 0700)

05:25

40

43

E

Po Kat Tsai

Daytime (0700 – 1900)

10:40

43

46

 

 

Evening Time (1900 – 2300)

20:15

33

36

 

 

Night-time (2300 – 0700)

23:30

33

36

4.4               Construction Phase Impact

4.4.1           Construction Airborne Noise

4.4.1.1         Identification of Emission Source

The major construction activity involved in the Project is the site formation for the construction of a BCP building, construction of a dual two-lane trunk road with connecting the BCP with Fanling Highway adjacent to Wo Hop Shek by tunnelling and open-cut methods. 

4.4.1.2         Assessment Methodology

Assessment approach to the noise impact is in line with the Guidance Note titled “Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance” (GN 9/2004).

In addition, the assessment of construction noise impact is based on standard acoustic principles, and the guidelines given in GW-TM issued under the NCO where appropriate.  Where no sound power level (SWL) can be found in the relevant TM, reference has been made to BS 5228 Part I or noise emission levels measured for PME used in previous projects in Hong Kong.  The general approach is summarized below:

i.      Assume a typical construction schedule/ programme;

ii.     Assume a typical project-specific equipment inventory for each work stage together with the number;

iii.   Obtain from GW-TM, the Sound Power Level (SWL) for each PME assumed in the equipment inventory;

iv.    Select representative NSRs for the construction noise impact assessment;

v.     Calculate the unmitigated Predicted Noise Level (PNL) and correct it for facade reflection to obtain the Corrected Noise Level (CNL) at any NSRs;

vi.    If necessary, re-select typical project-specific silenced equipment and calculate the mitigated noise impact;

vii.  Compare the mitigated CNL with the noise standards to determine acceptability and the need for further mitigation.

The calculation methodology is estimated with the following standard formula (1):

 

SPL = SWL – DC + FC                       (1)

where

Sound Pressure Levels, SPL in dB(A)

Sound Power Levels, SWL in dB(A)

Distance Attenuation, DC in dB(A) = 20∙log(D)+8 (where D is the distance between NSRs and noise source in meters)

Façade Correction, FC in dB(A) = 3dB(A)

4.4.1.3         Evaluation of Impacts

The type and quantity of Powered Mechanical Equipment (PME) likely to be used for the construction of the BCP and associated road works are described below and their Sound Power Levels (SWLs) are shown in Appendix 4.1. 

Table 4.8 to Table 4.13 and Appendix 4.2 indicates that the noise impact of unmitigated construction activities of proposed road works would cause exceedance of the relevant daytime construction noise criteria.  Mitigation measures are therefore required for these NSRs in order to alleviate the noise impacts generated during the construction phase.

Table 4.8:      Unmitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A)

NSR ID

Land Use

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Mitigation measure required

TYH

Residential

69-80

75

Yes

Yes

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

Table 4.9     Unmitigated Construction Airborne Noise Impact from Lin Ma Hang to Wo Keng Shan, Leq (30mins) dB(A)

NSR ID

Land Use

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Mitigation measure required

V1

Residential

56-87

75

Yes

Yes

V2

Residential

55-88

75

Yes

Yes

CY3

Residential

55-76

75

Yes

Yes

KL1

Residential

50-79

75

Yes

Yes

TKL1

Residential

49-85

75

Yes

Yes

TKL2

Residential

48-85

75

Yes

Yes

KTW1

Residential

56-80

75

Yes

Yes

KTW2

Residential

53-83

75

Yes

Yes

KTW3

Residential

57-83

75

Yes

Yes

KTW4

Residential

55-89

75

Yes

Yes

KTW5

Residential

58-83

75

Yes

Yes

NYH1

Residential

64-84

75

Yes

Yes

NYH2

Residential

65-79

75

Yes

Yes

PY2

Residential

67-91

75

Yes

Yes

PY3

Residential

59-82

75

Yes

Yes

PY4

Residential

59-89

75

Yes

Yes

PY5

Residential

58-81

75

Yes

Yes

PY6

Residential

57-82

75

Yes

Yes

PY7

Residential

57-76

75

Yes

Yes

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

Table 4.10     Unmitigated Construction Airborne Noise Impact at  Wo Keng Shan, Leq (30mins) dB(A)

NSR ID

 

Land Use

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Mitigation measure required

WKS1

Residential

66-81

75

Yes

Yes

WKS2

Residential

64-77

75

Yes

Yes

WKS3

Residential

62-72

75

No

No

WKS4

Residential

68-84

75

Yes

Yes

WKS5

Residential

64-89

75

Yes

Yes

WKS6

Residential

60-89

75

Yes

Yes

WKS7

Residential

60-85

75

Yes

Yes

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

Table 4.11     Unmitigated Construction Airborne Noise Impact near Sha Tau Kok Road, Leq (30mins) dB(A)

NSR ID

Land Use

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Mitigation measure required

ST1

Residential

69-82

75

Yes

Yes

ST2

Residential

68-85

75

Yes

Yes

ST3

Residential

61-79

75

Yes

Yes

ST5

Residential

64-84

75

Yes

Yes

ST6

Residential

59-80

75

Yes

Yes

LT1

Residential

58-85

75

Yes

Yes

LT2

Residential

55-79

75

Yes

Yes

LT3

Residential

59-83

75

Yes

Yes

LT4

Residential

76-78

75

Yes

Yes

TTW1

Residential

60-74

75

No

No

TTW2

Residential

63-85

75

Yes

Yes

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

Table 4.12     Unmitigated Construction Airborne Noise Impact near Po Kat Tsai, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Mitigation measure required

PKT1

Residential

63-72

75

No

No

PKT2

Residential

78-86

75

  Yes

Yes

PKT3

Residential

77-84

75

Yes

Yes

Table 4.13     Unmitigated Construction Airborne Noise Impact near Fanling, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Mitigation measure required

TH1

Residential

56-87

75

Yes

Yes

TH2

Residential

57-81

75

Yes

Yes

TH4

Residential

54-84

75

Yes

Yes

TH5

Residential

55-79

75

Yes

Yes

TH6

Residential

53-73

75

No

No

WKS1

Residential

55-72

75

No

No

KT1

Residential

59-82

75

Yes

Yes

KT2

Residential

64-86

75

Yes

Yes

KT3

Residential

62-91

75

Yes

Yes

NWP1

Residential

62-91

75

Yes

Yes

KLHSW

Residential

61-82

75

Yes

Yes

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

4.4.1.4         Mitigation Measures

Mitigation measures for each construction site are detailed below, and the following forms of mitigation measures are recommended and should be incorporated into the Contract Specifications:

¡      good site practice to limit noise emissions at source;

¡      selection of quieter plant;

¡      use of movable noise barrier;

¡      use of noise enclosure/ acoustic shed; and

¡      use of noise insulating fabric.

While it is recognised that the Contractor may develop a different package of mitigation measures to meet the required noise standards, the following suite of practical and implementable measures demonstrate an approach that would be feasible to reduce noise to acceptable levels.

Good Site Practice

Good site practice and noise management can significantly reduce the impact of construction site activities on nearby NSRs.  The following package of measures should be followed during each phase of construction:

¡      only well-maintained plant to be operated on-site and plant should be serviced regularly during the construction works;

¡      machines and plant that may be in intermittent use to be shut down between work periods or should be throttled down to a minimum;

¡      plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;

¡      mobile plant should be sited as far away from NSRs as possible; and

¡      material stockpiles and other structures to be effectively utilised, where practicable, to screen noise from on-site construction activities.

Selecting Quieter Plant

The Contractor may be able to obtain particular models of plant that are quieter than the standards given in the GW-TM.  This is one of the most effective measures and is increasingly practicable because of the availability of quiet equipment.

Quiet plant is defined as QPME whose actual SWL is less than the value specified in GW-TM for the same piece of equipment.  Examples of SWLs for specific silenced PME taken from a British Standard, namely Noise Control on Construction and Open Sites, BS 5228: Part 1: 2009 and are presented in Table 4.14.  It should be noted that various types of silenced equipment can be found in Hong Kong. 

Table 4.14     Quieter PME Recommended for Adoption during Construction Phase

PME

Power rating/size, weight

Reference

SWL, dB(A)

Handheld breaker

35kg

BS D2-10

110

Hydraulic breaker,

Excavator mounted

52kW

BS D8-12

106

Concrete lorry mixer

5m3

BS D6-35

100

Concrete pump

100kW

BS D6-36

106

Mobile crane

62kW

BS D7-114

101

Vibratory Poker, handheld

0.75kW each poker

BS D6-40

102

Bulldozer

239kW

BS D3-27

109

Excavator

45kW

BS D3-35

106

Dump truck

50t

BS D9-39

103

Vibratory roller

9kW

BS D3-115

102

Asphalt paver

90kW

BS D8-24

101

Road Roller

51kW

BS D8-30

101

Lorry

310kW

BS D3-59

105

Whilst quieter PME are listed, the Contractor may be able to obtain particular models of plant that are quieter than the PMEs given in GW-TM.

Use of Movable Noise Barriers

Movable noise barriers can be very effective in screening noise from particular items of plant when constructing the Project.  Noise barriers located along the active works area close to the noise generating component of a PME could produce at least 10 dB(A) screening for stationary plant and 5 dB(A) for mobile plant provided the direct line of sight between the PME and the NSRs is blocked.  A schematic configuration of a single movable noise barrier for PME is shown in Figure 4.18.

Use of Noise Enclosure/ Acoustic Shed

The use of noise enclosure or acoustic shed is to cover stationary PME such as air compressor and concrete pump.  With the adoption of the noise enclosure, the PME could be completely screened, and noise reduction of 15 dB(A) can be achieved according to the EIAO Guidance Note No.9/2004.  A schematic configuration of full noise enclosure for PME is shown in Figure 4.19.

Use of Noise Insulating Fabric

Noise insulating fabric can also be adopted for certain PME (e.g. drill rig, pilling auger etc).  The Fabric should be lapped such that there are no openings or gaps on the joints.  According to the approved Tsim Sha Tsui Station Northern Subway EIA Report (AEIAR-127/2008), a noise reduction of 10 dB(A) can be achieved for the PME lapped with the noise insulating fabric.

The noise screening benefit for each item of plant considered in this assessment is listed in Table 4.15.

Table 4.15     Noise Mitigation Measures for Certain PME during Construction Phase

PME

Mitigation Measures Proposed

Noise Reduction, dB(A)

Concrete pump

Noise enclosure

15

Air compressor

Noise enclosure

15

Grout pump

Noise enclosure

15

Handheld breaker

Movable noise barrier

10

Piling, large diameter bored, grab and chisel

Noise insulating fabric

10

Piling, large diameter bored, reverse circulation drill

Noise insulating fabric

10

Piling, large diameter bored, oscillator

Noise insulating fabric

10

Piling, diaphragm wall, bentonite filtering plant

Noise insulating fabric

10

Drill rig, rotary type

Noise insulating fabric

10

Air compressor

Movable noise barrier

10

Water pump

Movable noise barrier

10

Generator

Movable noise barrier

10

Poker, Vibratory, hand-held

Movable noise barrier

10

Excavator

Movable noise barrier

5

Mobile crane

Movable noise barrier

5

Prestress Jack

Movable noise barrier

5

Lorry with crane/grab

Movable noise barrier

5

Lorry

Movable noise barrier

5

Compactor, vibratory

Movable noise barrier

5

Bulldozer

Movable noise barrier

5

Asphalt paver

Movable noise barrier

5

Road Roller

Movable noise barrier

5

Dump Truck

Movable noise barrier

5

Concrete pump, lorry mounted

Movable noise barrier

5

These noise barriers should be free of gaps and made of materials having a surface mass density in excess of 7 kg/m2.  To improve the effectiveness of noise reduction, non-flammable absorptive lining can be adhered on the inner surface of the noise barriers.  The barrier can be in the form of vertical or bend top barrier with an effective height to block the line of sight to NSRs.  Given most of the NSRs are low storeys (i.e. 1-2 storey), the movable noise barriers is effective to screen the noise from the construction plant.

The effect of the use of quiet plant and using movable barriers has been investigated for the practicable construction activities and the results are presented in Table 4.16 to Table 4.21 and the detailed calculation was shown in Appendix 4.4.

Table 4.16:    Mitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Residual Impact

TYH

Residential

64-70

75

No

No

Table 4.17     Mitigated Construction Airborne Noise Impact from Lin Ma Hang to Wo Keng Shan, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Residual Impact

V1

Residential

51-72

75

No

No

V2

Residential

51-74

75

No

No

CY3

Residential

50-67

75

No

No

KL1

Residential

45-65

75

No

No

TKL1

Residential

44-71

75

No

No

TKL2

Residential

44-71

75

No

No

KTW1

Residential

43-67

75

No

No

KTW2

Residential

40-69

75

No

No

KTW3

Residential

44-69

75

No

No

KTW4

Residential

42-72

75

No

No

KTW5

Residential

45-69

75

No

No

NYH1

Residential

53-70

75

No

No

NYH2

Residential

56-66

75

No

No

PY2

Residential

56-75

75

No

No

PY3

Residential

47-68

75

No

No

PY4

Residential

48-72

75

No

No

PY5

Residential

47-68

75

No

No

PY6

Residential

46-69

75

No

No

PY7

Residential

45-63

75

No

No

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

Table 4.18     Mitigated Construction Airborne Noise Impact at Wo Keng Shan, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Residual Impact

WKS1

Residential

62-70

75

No

No

WKS2

Residential

60-69

75

No

No

WKS3

Residential

57-64

75

No

No

WKS4

Residential

55-71

75

No

No

WKS5

Residential

60-72

75

No

No

WKS6

Residential

57-75

75

No

No

WKS7

Residential

57-72

75

No

No

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

Table 4.19     Mitigated Construction Airborne Noise Impact near Sha Tau Kok Road, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Residual Impact

ST1

Residential

59-69

75

No

No

ST2

Residential

58-72

75

No

No

ST3

Residential

51-67

75

No

No

ST5

Residential

52-72

75

No

No

ST6

Residential

49-67

75

No

No

LT1

Residential

48-71

75

No

No

LT2

Residential

45-69

75

No

No

LT3

Residential

50-71

75

No

No

LT4

Residential

64-70

75

No

No

TTW1

Residential

50-61

75

No

No

TTW2

Residential

53-74

75

No

No

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

Table 4.20     Mitigated Construction Airborne Noise Impact near Po Kat Tsai, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Residual Impact

PKT1

Residential

54-59

75

No

No

PKT2

Residential

68-73

75

No

No

PKT3

Residential

67-71

75

No

No

Table 4.21     Mitigated Construction Airborne Noise Impact near Fanling, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Exceedance of noise criteria dB(A)

Residual Impact

TH1

Residential

43-73

75

No

No

TH2

Residential

44-67

75

No

No

TH4

Residential

42-70

75

No

No

TH5

Residential

42-65

75

No

No

TH6

Residential

41-60

75

No

No

WKS1

Residential

42-58

75

No

No

KT1

Residential

46-67

75

No

No

KT2

Residential

52-71

75

No

No

KT3

Residential

50-75

75

No

No

NWP1

Residential

50-75

75

No

No

KLHSW

Residential

49-68

75

No

No

Note:        Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria

With the incorporation of quiet plant and the use of movable noise barriers (to reduce noise level at source), the results indicated that the mitigated noise impact associated with the construction of the Project would comply with the daytime construction noise criterion at all the NSRs.  Residual construction noise impact is not anticipated.

The mitigation measures recommended above can be altered, the Contractor may be allowed to use acoustic blankets on PMEs or re-schedule noisy works, while it is the responsibility of the Contractor to comply with the construction noise criteria which should be stated in the contractual agreement.  It is further recommended that the Contractor should follow the “Recommended Pollution Control Clauses for Construction Contracts” to minimise the construction noise impact.

4.4.1.5         Cumulative Construction Airborne Noise Impact

According to the tentative construction programme, it is likely that there will be an overlap of this Project with some other potentially concurrent projects.  These projects are described in Section 2.10. 

For projects “Regulation of Shenzhen River Stage IV” and “Construction of a Secondary Boundary Fence and new sections of Primary Boundary Fence and Boundary Patrol Road”, the cumulative impact results in the EIA Report of the Regulation of Shenzhen River Stage IV has been referenced. Below is the summary of the cumulative noise impact at the NSRs.

Table 4.22:    Cumulative Mitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Max. Overall Noise Level, dB(A)

Noise Criteria, dB(A)

Exceedance of noise criteria, dB(A)

Residual Impact

This Project

*Concurrent Projects

TYH

Residential

64-70

54 - 71

74

75

No

No

Note:        (*) reference to the predicted results of the closest NSR in the EIA Report of the Regulation of Shenzhen River Stage IV with appropriate distance correction

Table 4.23   Cumulative Mitigated Construction Airborne Noise Impact at Lin Ma Hang to Frontier Closed Area Boundary, Leq (30mins) dB(A)

NSR ID

Usage

Predicted Noise Level dB(A)

Max. Overall Noise Level, dB(A)

Noise Criteria, dB(A)

Exceedance of noise criteria, dB(A)

Residual Impact?

This Project

*Concurrent Projects

KL1

Residential

45-65

53 - 63

67

75

No

No

TKL1

Residential

44-71

57 - 67

72

75

No

No

TKL2

Residential

44-71

53 - 63

72

75

No

No

Note:        (*) reference to the predicted results of the closest NSR in the EIA Report of the Regulation of Shenzhen River Stage IV with appropriate distance correction

For the project “Resite of Chuk Yuen Village”, as the construction of the BCP Project will be commenced after the resite of the Chuk Yuen Village, no cumulative impact is anticipated.

For project “North East New Territories (NENT) Landfill Extension”, the project boundary and works areas are out of the 300m from this Project’s boundary and therefore not applicable for concurrent noise impact assessment. 

According to the project proponent, the implementation programme of Stage 2 of the Tolo/Fanling Highway widening project is currently under review.  It is understood that there will be overlap between this project and the LT/HYW Project. However the project programme has not been confirmed at the time of preparation of this Report, cumulative impact of this project has not been taken into account.

As mentioned in Section 2.10.9, the project “Provision of Cremators at Wo Hop Shek Crematorium” is located outside 500m from the site boundary of the BCP Project, the project will not be considered as a concurrent project.

For project “Cycle Tracks Connecting North West New Territories with North East New Territories – Sheung Shui to Ma On Shan section”, the section of the Cycle Track which intersects the LT/HYW BCP Project’ study area (Fanling section) is due to be completed by mid 2012. No cumulative impacts are anticipated and hence the project will not be considered as a concurrent project.

For the project “Drainage Improvements in Northern New Territories – Package C (Remaining Works)”, the site area is located outside 300m from the site boundary of the BCP Project and hence the project will not be considered as a concurrent project.

4.4.1.6         Evaluation of Residual Impact

With the implementation of the above-mentioned mitigation measures, the construction noise levels at all the representative NSRs are predicted to comply with the noise standards stipulated in the EIAO-TM.  No residual construction noise impact is anticipated.  Nevertheless, the Contractor is recommended to implement the good site practice as mentioned in Section 4.4.1.4 and carry out the environmental monitoring and audit (EM&A) to be discussed in Section 4.6.

4.4.2           Construction Ground-borne Noise

4.4.2.1         Identification of Emission Source

Potential ground-borne noise impact during the construction phase could be caused by drill and blast activities and mechanical excavation for tunnelling works, and the use of PMEs such as the hydraulic breakers, hand-held breakers and drill rigs for other construction activities.

4.4.2.2         Assessment Methodology

Drill & Blast and Mechanical Excavation methods would be used to excavate rock along the alignment.  The interaction between the operation of equipment and the rock will induce ground-borne noise.  The prediction methodology for assessing the ground-borne noise impact from construction equipment is detailed as follows:

The method used to predict construction ground-borne noise from the use of PME construction equipment is shown below.

LA = Lv,rms +  C dist + C damping + BCF + BVR + CTN + C cum

LA

A-weighted Ground-borne noise level at NSR, ref: 20 µ-Pascal

C dist

Distance attenuation

C damping

Soil damping loss across the geological media

Lv,rms

Vibration velocity (in RMS) of a PME at a reference distance

BCF

Vibration coupling loss factor between the soil and the foundation, relative level

BVR

Building vibration reduction or amplification within a structure from the foundation to the occupied areas, relative level

CTN

Conversion from floor and wall vibration to noise, 10-8 m/s or 10-6 in/s to 20 µ-Pascal

C cum

Cumulative noise impact from concurrent projects

Reference Vibration Sources

The vibratory velocities for typical construction equipment with reference to the approved Kowloon Southern Link EIA (Register No.: AEIAR-083/2005) are listed in Table 4.24 to Table 4.25.

Table 4.24:    Reference Vibration Level based on Measurements

Construction Equipments

Construction Site

Vibration (RMS) at Reference Distance of 5.5m from source

Drilling Rig

Salisbury Road Overrun Tunnel

0.536 mm/s

Hydraulic Breaker

TST site

0.298 mm/s

Handheld Breaker

New World Centre site

0.279 mm/s

Source: Appendix 7-1 of Kowloon Southern Link EIA Report

Table 4.25:    Source Vibration Velocity of Octave Band Frequency for Hydraulic Breaker

Octave Band Frequency (Hz)

16

31.5

63

125

250

500

Source Vibration Velocity, mm/s

0.0589

0.0682

0.0620

0.0503

0.0623

0.1209

Source: Appendix 7-1 of Kowloon Southern Link EIA Report

Soil Damping Loss

Vibration wave propagation in ground will decay with distance due to damping loss within the soil.  The reduction in vibration amplitude can be estimated based on the Transportation Noise Reference Book[1].

The rate of decay will depend on vibration frequency, the soil loss factor (η), the wave speed c of the soil and the distance R between sources to the NSR.  The wave propagation properties of typical soil are shown in the Table 4.26.

Table 4.26:    Wave Propagation Properties of Soil

Ground Type

Longitudinal Wave Speed c, ms-1

Loss Factor, η

Density, g/cm3

Soil

1500

0.5

1.7

Rock

3500

0.01

2.65

For this noise impact assessment, no damping attenuation (i.e. 0 dB(A)) will be applied to propagation in rock.

Building Coupling Loss (BCL)

Interaction between the building foundation and the soil will cause some reduction in the vibration level. The correction factors shown in Table 4.27 are based on Saurenman (1982).  For conservative assessment, the lower limit adjustment factors (highlighted in Bold) have been used in the study.

Table 4.27:    Adjustment Factor for Building Coupling Loss (BCF)

Building Type

Limit

Building Coupling Loss (dB)

 

 

16

31.5

63

125

250

500

Large Masonry Building on Pile

Lower

-6

-7

-11

-13

-14

-12

Upper

-8

-10

-13

-15

-16

-14

Large Masonry Building on Spread Footings

Lower

-12

-14

-14

-13

-11

-10

Upper

-14

-16

-16

-15

-13

-12

1 to 2 Storey Residential

Lower

-4

-5

-5

-4

-3

-1

Upper

-6

-7

-7

-6

-5

-3

Building Foundation on Rock Layer

 

0

0

0

0

0

0

Building Vibration Response (BVR)

Building Vibration Response (BVR) consists of two factors, namely Building Structure Attenuation (BSA) and Building Structure Resonance (BSR).  Vibration generally reduces in level as it propagates through a building. On the other hand, amplification occurs due to building element resonance.  The following correction factors (Table 4.28) based on Saurenman (1982)[2] are proposed for the Project.

Table 4.28:    Adjustment Factor for Building Structure Attenuation (BSA)

Floor level above Grade

Floor Attenuation Factor (dB)

16

31.5

63

125

250

500

1

2

2

3

3

3

4

2

2

2

2

3

3

4

3

2

2

2

2

3

3

4 to 5

1

1

2

2

3

3

6 to 7

1

1

1

2

3

3

8 to 9

1

1

1

1

2

3

10 and above

1

1

1

1

2

3

Since ground-borne vibration level will be the highest on the lower level of a building, a conservative building structure attenuation factor of 2dB per octave band (Table 4.29) is proposed for the Project.

Table 4.29:    Building Structure Attenuation (BSA)

Octave Band Centre Frequency (Hz)

16

31.5

63

125

250

500

Floor Attenuation Factor (dB)

2

2

2

2

2

2

Ground vibration level will increase within the building due to building element resonance. The amount of amplification will depend on building construction method.  For typical concrete based building construction, a 6 dB increase per octave band (Table 4.30) has been adopted for the Project in accordance with the FTA Handbook[3] recommendation.

Table 4.30:    Building Structure Resonance (BSR)

Octave Band Centre Frequency (Hz)

16

31.5

63

125

250

500

Floor and Wall Resonance (dB)

6

6

6

6

6

6

Conversion from Vibration to Noise (CTN)

The level of radiated noise inside a room will depend on the average vibration of the room surfaces, the radiation efficiency of the surfaces and the amount of absorption inside the room.

Based on the conservation of power principle, the reverberant sound field inside the room can be approximated by the following equation:

 

Reverberant Sound Pressure Level

LA (dBA) = Lv (VdB ref 1 m in/s) + CTN             Equation 4.41

CTN = Krad + A-weighting Correction               Equation 4.42

 

where

Krad

Adjustment to account for conversion from vibration to sound pressure level including accounting for the amount of acoustical absorption inside the room

For typical residential bedroom with nominal acoustical absorption treatment, the following factors (Table 4.31) are proposed for the Project:

Table 4.31:    Room Correction Factors

Octave Band Centre Frequency (Hz)

16

31.5

63

125

250

500

Krad (dB)

0

0

0

0

0

0

A weighting

-56.7

-39.4

-26.2

-16.1

-8.6

-3.2

CTN (for vibration)

-56.7

-39.4

-26.2

-16.1

-8.6

-3.2

For Lv vibration level reference to 1 m in/s

Multiple Vibration Sources C multi

The ground-borne noise levels from the construction plant will be summed logarithmically in accordance with standard acoustic principles to obtain the total ground-borne noise level.

Cumulative Ground-borne Noise Impact C cum

Potential concurrent projects leading to cumulative impacts would be considered in the ground-borne noise prediction.

4.4.2.3         Evaluation of Construction Ground-borne Noise Impacts

Detailed assessments have been conducted for three construction equipment (hydraulic breaker, hand-held breaker and drilling rig), for tunnelling works including drill & blast and mechanical excavation along the tunnel, the results are summarised in Table 4.32.  The detailed assessment results were shown in Appendix 4.5. 

Table 4.32     Unmitigated Construction Ground-borne Noise

NSR ID

Usage

Predicted Noise Level dB(A)

Noise Criteria dB(A)

Mitigation measure required

LPT

Residential

34

65

No

STS

Residential

34

65

No

Based on the assessment result as shown in Table 4.32, the predicted ground-borne noise levels from the tunnelling work will not exceed the daytime ground-borne noise criteria and hence no mitigation measures are required.

4.5               Operation Phase Impact

4.5.1           Road Traffic Noise

4.5.1.1         Identification of Emission Source

During the operational phase, operation of the LT/HYW BCP connecting road may pose traffic noise impact on the nearby NSRs.  The road carriageways involved within the assessment area, including the proposed BCP connecting road, the modified Lin Ma Hang Road, existing roads and roads of other committed projects have been selected for assessment.  Appendix 4.6 shows the roads selected for the Road Traffic Noise Impact Assessment (RTNIA).  The classification of “New Road” and “Existing Road” are also shown in Appendix 4.6.

4.5.1.2         Assessment Methodology

Road traffic noise levels at the representative assessment points will be calculated based on the peak hour traffic flow within a 15 years period upon commencement of operation of the Project i.e., the assessment year.  Traffic noise will be predicted using the model “roadNoise”, which has been used before in other similar EIA studies. The model has fully incorporated the procedures and methodology documented in “Calculation of Road Traffic Noise (CRTN)” (1988) published by the U.K. Department of Transport. 

In accordance with the requirements specified in Section 3.4.4.2(vi)(a) of the EIA Study Brief, a number of specified scenarios have been studied as part of the road traffic noise impact assessment.  These scenarios are summarized below:

 

           Scenario (1) includes a comparison of the “with and without Project” situations at the design year to identify the significance of road traffic noise at the representative NSRs.  Predicted traffic noise impact would be considered to be significant if the traffic noise levels in the presence of the Project is greater than that without the Project at the design year (i.e. 2018) by 1.0 dB(A) or more;

           Scenario (2) involves an assessment of the unmitigated road traffic noise levels at the representative NSRs at the assessment year.  If exceedances of the relevant road traffic noise criteria are predicted, direct noise mitigation measures listed under Section 6.1 in Annex 13 of EIAO-TM will be considered;

           Scenario (3) involves an assessment of the effectiveness and adequacy of the recommended direct noise mitigation measures. It is envisaged that the direct noise mitigation measures proposed may involve erection of noise barriers and/or enclosure on the BCP connecting road.  Aesthetic design and greening measures will be considered for the noise barriers to ensure that visual intrusion is minimised to acceptable levels.  Sections of barriers proposed to protect existing NSRs will be differentiated clearly from those proposed for the protection of planned NSRs; 

           Under Scenario (4), upon exhaust of all practicable direct noise mitigation measures, in case noise exceedances are still predicted at existing NSRs (e.g. dwellings and classrooms), the eligibility of the affected NSRs for provision of indirect technical remedies in form of noise insulation and air-conditioning will be evaluated based on the three specific criteria set out in Section 3.4.4.2 (vi)(a3) of the EIA Study Brief.  For noise exceedances predicted at planned NSRs, extent of additional noise mitigation measures required to be incorporated into the design of the planned NSRs will be defined (e.g. in terms of setback distances required at a certain view angle).

If the NSRs are affected by noise from other existing roads, direct mitigation measures are required to reduce the noise from the proposed roads to a level that it

           is not higher than the standard; and

           has no significant contribution to the overall noise from other existing roads

If the noise criteria will still be exceeded at the existing NSRs after the implementation of direct mitigation measures, provision of acoustic insulation in form of windows and provision of air-conditioning for ventilation should be considered under the ExCo directive “Equitable Redress for Persons Exposed to Increased Noise Resulting from the use of New Roads”. Eligibility for indirect technical remedies should be tested against the following three criteria:

           The predicted overall noise level, L10(1 hour), from the “New Road”, together with other traffic noise in the vicinity must be above 70 dB(A) for domestic premises, 65 dB(A) for educational institutions and 55 dB(A) for home for the aged.

           The predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level.

           The contribution to the increase in the predicted overall noise level from the “New Road” must be at least 1.0 dB(A).

The road scheme within the Study Area and the surrounding road network have been set up to define the road width, surface type, traffic condition and if applicable, the height and locations of any roadside barriers.  Parapet walls with height of 0.8m above road surface along both sides of the viaduct sections of the proposed link road have been applied.  In accordance with RD/GN/032, the extent of low-noise surfacing will cover the link roads and slip roads, but not the local road sections i.e. the roundabouts at Sha Tau Kok Road and Ping Yeung, Lin Ma Hang Road, Tai Wo Service Roads etc.  This has been applied in the unmitigated scenario.

4.5.1.3         Evaluation of impacts

Scenario (1)

The comparison between with and without the Project at Year 2018 (AM) due to operation of the Proposed Connecting Road and existing roads network nearby are summarised in Table 4.33 to Table 4.36.  Detailed breakdown of road traffic noise is shown in Appendix 4.7.

Table 4.33      Comparison between With and Without Project in Year 2018 from Lin Ma Hang to North Tunnel (Existing Receivers)

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

Difference, dB(A)

(2) – (1)

Without Project (1)

With Project (2)

TYH

70

52

62

10.5 - 10.6

V1

70

64

69

5.5 – 5.8

V2

70

58

64 - 65

6.7 – 7.4

KL1

70

60

63 - 64

3.6 – 3.7

TKL1

70

62

66

3.3 – 3.4

TKL2

70

65

69

3.9 – 4.0

KTW1

70

52

63 - 64

10.6 – 11.5

KTW2

70

32

59

27.2

KTW3

70

46

65 - 66

18.4 – 20.0

KTW4

70

40

58

18.0

KTW5

70

46

64 - 66

18.5 – 19.9

NYH1

70

42

65 - 66

22.4 – 23.5

NYH2

70

34

64 - 65

30.3 – 30.8

PY1

70

0

69 - 70

69.2 – 69.5

PY2

70

37

69

31.5 – 32.2

PY3

70

37

65 - 66

28.4 – 28.9

PY4

70

38

67

29.1

PY5

70

0

65

65.0

PY6

70

34

66

31.9

PY7

70

21 - 24

64 - 65

40.6 – 42.9

WKS1

70

52

71

18.7

WKS2

70

54

66

11.7 – 12.1

WKS3

70

52

64

11.5 – 11.7

WKS4

70

66

71

4.8

WKS5

70

66

68

2.1

WKS6

70

62

68

5.3

WKS7

70

67

70

2.7

Notes:      Bold figure denotes the noise exceedance which is over the relevant EIAO-TM noise criteria.

Table 4.34      Comparison between With and Without Project in Year 2018 from Lin Ma Hang to North Tunnel (Planned Receivers)

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

Difference, dB(A)

(2) – (1)

Without Project (1)

With Project (2)

CY3

70

(*)

61 - 62

(*)

KTW6

70

64

66 - 67

2.1 – 2.2

WKS8

70

50

68

17.9 – 18.4

Notes:      (*)CY3 exists in the "with project" scenario only.

 

 

Table 4.35      Comparison between With and Without Project in Year 2018 near Sha Tau Kok Road Section (Existing Receivers)        

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

Difference, dB(A)

(2) – (1)

Without Project (1)

With Project (2)

ST1

70

47-53

63-64

12.8 – 15.7

ST2

70

57

67-68

9.7 – 11.2

ST3

70

60

68

8.1 – 8.2

ST5

70

64

72

8.6 – 8.7

ST6

70

62

71

8.1 – 8.3

TTW1

70

67

67

-0.5

TTW2

70

64

68

3.6

LT1

70

60

74

14.3

LT2

70

62

70

8.3

LT3

70

68

73

5.1 – 5.2

LT4

70

51

70

18.9 – 19.0

Notes:      Bold figure denotes the noise exceedance which is over the relevant EIAO-TM noise criteria.

Table 4.36     Comparison between With and Without Project in Year 2018 near Fanling Highway (Existing Receivers)

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

Difference, dB(A)

(2) – (1)

Without Project (1)

With Project (2)

TH1

70

70

75

4.8

TH2

70

70

72

2.1 – 2.2

TH4

70

70

70.5

0.5 - 0.6

TH5

70

73

73

-0.1

TH6

70

73

73

-0.2

WHS1

70

77

77

0.0

KT1

70

70

71

1.3

KT2

70

64-65

67

2.5 - 2.7

KT3

70

64

68

3.8

NWP1

70

71

73 - 75

2.6 - 4.1

NWP2

70

70

70 - 71

0.5 – 0.6

KLHSW

70

65-66

65 - 66

0.0

Notes:      Bold figure denotes the noise exceedance which is over the relevant EIAO-TM noise criteria.

It can be seen from the above tables that the predicted differences between with and without the Project are equal to or greater than 1.0dB(A) at a lot of the representative NSRs (as highlighted in grey) which are considered as significant impact from the proposed connecting roads. 

Scenario (2)

The roads proposed under the Project are scheduled to open in 2018.  According to the projection of the traffic impact assessment, the year with maximum traffic flow within a 15-year period upon commencement of operation of the Project is determined to be 2033.  Therefore, the traffic data for year 2033 has been adopted for the assessment.  The potential unmitigated road traffic noise impacts on the NSRs for the Project at Year 2033 (AM) due to operation of the Proposed Connecting Road and existing roads network nearby are summarised in Table 4.37 to Table 4.40 below.  Detailed breakdown of road traffic noise is shown in Appendix 4.8.

Table 4.37      Unmitigated Road Traffic Noise Impact in Year 2033 near Lin Ma Hang to Wo Keng Shan (Existing Uses)

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

Significant Contribution from New Roads*

No. of Floors exceeded the Noise Criteria

Assumed No. of Dwellings per floor

No. of Dwellings Affected

TYH

70

62

Yes

N/A

N/A

N/A

V1

70

70

Yes

N/A

N/A

N/A

V2

70

65

Yes

N/A

N/A

N/A

CY3

70

61 – 62

Yes

N/A

N/A

N/A

KL1

70

64

Yes

N/A

N/A

N/A

TKL1

70

66

No

N/A

N/A

N/A

TKL2

70

69

No

N/A

N/A

N/A

KTW1

70

64 - 65

Yes

N/A

N/A

N/A

KTW2

70

60

Yes

N/A

N/A

N/A

KTW3

70

67 – 68

Yes

N/A

N/A

N/A

KTW4

70

59

Yes

N/A

N/A

N/A

KTW5

70

66 – 67

Yes

N/A

N/A

N/A

NYH1

70

66 – 67

Yes

N/A

N/A

N/A

NYH2

70

66

Yes

N/A

N/A

N/A

PY1

70

73 – 74

Yes

2

1

2

PY2

70

73

Yes

2

1

2

PY3

70

68 - 69

Yes

N/A

N/A

N/A

PY4

70

71

Yes

1

1

1

PY5

70

67

Yes

N/A

N/A

N/A

PY6

70

68

Yes

N/A

N/A

N/A

PY7

70

66 - 67

Yes

N/A

N/A

N/A

WKS1

70

72

Yes

1

1

1

WKS2

70

67 - 68

Yes

N/A

N/A

N/A

WKS3

70

65 - 66

Yes

N/A

N/A

N/A

WKS4

70

71

Yes

1

1

1

WKS5

70

69

Yes

N/A

N/A

N/A

WKS6

70

69

Yes

N/A

N/A

N/A

WKS7

70

71

Yes

1

1

1

Notes:      (*) Significant Contribution from New Roads denotes the noise level from new roads to the overall noise level is equal to or higher than 1.0dB(A)

Table 4.38      Unmitigated Road Traffic Noise Impact in Year 2033 near Lin Ma Hang to Wo Keng Shan (Planned Uses)

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

Significant Contribution from New Roads*

No. of Floors exceeded the Noise Criteria

KTW6

70

67 - 68

No

N/A

WKS8

70

69 - 70

Yes

N/A

Notes:      (*) Significant Contribution from New Roads denotes the noise level from new roads to the overall noise level is equal to or higher than 1.0dB(A)

Table 4.39     Unmitigated Road Traffic Noise Impact in Year 2033 near Sha Tau Kok Road Section (Existing Uses)

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

Significant Contribution from New Roads*

No. of Floors exceeded the Noise Criteria

Assumed No. of Dwellings per floor

No. of Dwellings Affected

ST1

70

65 – 68

Yes

N/A

N/A

N/A

ST2

70

69 – 70

Yes

N/A

N/A

N/A

ST3

70

70

Yes

N/A

N/A

N/A

ST5

70

74

Yes

2

1

2

ST6

70

72

Yes

2

1

2

TTW1

70

68

Yes

N/A

N/A

N/A

TTW2

70

70

Yes

N/A

N/A

N/A

LT1

70

75 - 76

Yes

2

1

2

LT2

70

72

Yes

3

1

3

LT3

70

75

Yes

2

1

2

LT4

70

72

Yes

3

1

3

 Notes:     Bold figure denotes the noise exceedance which is over the relevant EIAO-TM noise criteria and the contribution from new roads to the overall noise level is equal to or higher than 1.0dB(A).

(*) Significant Contribution from New Roads denotes the noise level from new roads to the overall noise level is equal to or higher than 1.0dB(A)

Table 4.40     Unmitigated Road Traffic Noise Impact in Year 2033 near Fanling Highway (Existing Uses)

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

Significant Contribution from New Roads*

No. of Floors exceeded the Noise Criteria

Assumed No. of Dwellings per floor

No. of Dwellings Affected

TH1

70

76

Yes

1

1

1

TH2

70

73

Yes

2

1

2

TH4

70

71

Yes

2

1

2

TH5

70

73

No

N/A

N/A

N/A

TH6

70

74

No

N/A

N/A

N/A

WHS1

70

78

No

N/A

N/A

N/A

KT1

70

72

Yes

1

1

1

KT2

70

68

Yes

N/A

N/A

N/A

KT3

70

69

Yes

N/A

N/A

N/A

NWP1

70

74 - 76

Yes

2

1

2

NWP2

70

71 - 72

No

N/A

N/A

N/A

KLHSW

70

66 - 67

Yes

N/A

N/A

N/A

Notes:      Bold figure denotes the noise exceedance which is over the relevant EIAO-TM noise criteria and the contribution from new roads to the overall noise level is equal to or higher than 1.0dB(A).

(*) Significant Contribution from New Roads denotes the noise level from new roads to the overall noise level is equal to or higher than 1.0dB(A).

Table 4.41 summarises the exceedance of road traffic noise criteria with significant contribution from “new roads” for existing uses, including the number of affected dwellings. No exceedance of road traffic noise criteria for planned uses is predicted.

Table 4.41     Summary of Exceedance of Road Traffic Noise Criteria

NSR ID

Noise Criteria L10(1 hr) dB(A)

Predicted Noise Level L10 (1hr) dB(A)

No. of Floors exceeded the Noise Criteria

Assumed No. of Dwellings per floor

No. of Houses Represented

No. of Dwellings Affected

Lin Ma Hang to Wo Keng Shan

PY1

70

73 – 74

2

1

1

2

PY2

70

73

2

1

2

4

PY4

70

71

1

1

2

2

WKS1

70

72

1

1

2

2

WKS4

70

71

1

1

2

2

WKS7

70

71

1

1

2

2

Loi Tung

 

 

 

 

 

ST5

70

74

2

1

1

2

ST6

70

72

2

1

2

4

LT1

70

75 - 76

2

1

3

6

LT2

70

72

3

1

2

6

LT3

70

75

2

1

3

6

LT4

70

72

3

1

1

3

Fanling

TH1

70

76

1

1

3

3

TH2

70

73

2

1

2

4

TH4

70

71

2

1

3

6

KT1

70

72

1

1

1

1

NWP1

70

74 - 76

2

1

9

18

Total no. of Dwellings Affected

73

 

4.5.1.4         Evaluation of Mitigation Measures

Exceedance of noise criteria were found in various sensitive receivers for both existing and planned uses, direct mitigation measures should be proposed.  According to the Section 6.1, Annex 13 of EIAO-TM, direct mitigation measures as listed below should be considered and evaluated:

           Open-textured road surfacing; and

           Noise barrier/ enclosure

The mitigation measures above are at-source mitigation measures and were further elaborated in the following paragraphs.

Noise mitigation measures starting from direct ones were evaluated.  When all practicable at-source mitigation measures have been exhausted, at-receiver mitigation measures would be considered in terms of modification of layout plan and setback requirement for the planned NSRs, and consideration of provision of noise insulation for the existing NSRs where justified and eligible.

Use of low noise road surfacing (LNRS)

The use of noise absorptive paving materials on project roads can theoretically reduce the traffic noise impact.  As per the values specified in CRTN, the use of pervious macadam on road surface can reduce the basic noise level by 3.5 dB(A), as compared to that of 1.0dB(A) for common impervious paving. 

In accordance with RD/GN/032, the extent of low-noise surfacing has been considered in the unmitigated scenario and will cover the link roads and slip roads, but not the local road sections i.e. the roundabouts at Sha Tau Kok Road and Ping Yeung, Lin Ma Hang Road, Tai Wo Service Roads etc.

Noise barrier/enclosure

In view of practicability, the erection of noise barrier/ semi-enclosure along the new road sections are considered as effective mitigation measures in tackling the road traffic noise impact to sensitive receivers.

4.5.1.5         Mitigated Noise Impact

Existing Uses

As discussed above, direct mitigation measures in form of noise barrier/ enclosure should be considered in order to comply with the noise criteria.  The locations of noise barriers proposed for the existing noise sensitive uses are tabulated in Table 4.42 below and shown in Figures 4.20.1 to 4.20.4. Typical cross-sections of the proposed noise barriers are shown in Figure 4.20.5.

Table 4.42     Proposed Location of Noise Barrier for Existing Uses

Location

Chainage

Type of Noise Mitigation Measures

*Height

Length, m

Figure

Ping Yeung

9040 – 9085 (Main Road – North Bound)

Vertical Barrier

0.8m

85

4.20.1

Nga Yiu Ha

166 (Access Road to Ping Yeung ) – 450 (Slip Road – North Bound)

Vertical Barrier

2.5m

152

4.20.1

Wo Keng Shan

8585 – 8500 (Main Road – North Bound)

Vertical Barrier

2m

85

4.20.2

 

8500 – 8355 (Main Road – North Bound)

Vertical Barrier

2m above parapet

145

4.20.2

 

8180 – 8290 (Main Road – South Bound)

Vertical Barrier

1m above parapet

110

4.20.2

Loi Tung

6488 – 6855 (Main Road – South Bound)

Vertical Barrier

1.5m

367

4.20.3

 

6800 – 6855 (Main Road – South Bound)

Vertical Barrier

0.8m

55

4.20.3

 

360 (Sha Tau Kok Rd – West Bound)  – 380 (Slip Road – South Bound)

Vertical Barrier

2m

108

4.20.3

 

195 (Wo Keng Shan Rd) – 400 (Sha Tau Kok Rd – East Bound)

Vertical Barrier

1.5m

182

4.20.3

 

40 (Sha Tau Kok Rd ) – 400 (Slip Road – North Bound)

Vertical Barrier

5m

120

4.20.3

Tong Hang

1640 – 1713 (Main Road  – South Bound)

Vertical Barrier

3m

73

4.20.4

 

1589 – 1621 (Main Road  – South Bound)

Vertical Barrier

3m

32

4.20.4

 

0 – 100 (Link Road 4)

Vertical Barrier

4m above parapet

100

4.20.4

 

285 – 330 (Access to Main Road South Bound)

Vertical Barrier

5m

45

4.20.4

Wo Hop Shek

185 – 430 (Fanling Highway South Bound connecting Link Road 2)

Vertical Barrier

3m

245

4.20.4

Nam Wan Po

543 – 662 (Link Road 1)

Vertical Barrier

2.5m above parapet

119

4.20.4

 

662 - 700 (Link Road 1)

Vertical Barrier

1m

38

4.20.4

 

815 – 856 (Link Road 4)

Vertical Barrier

1m above parapet

41

4.20.4

 

276 – 336 (Tai Wo Service Road West)

Vertical Barrier

3m above parapet

60

4.20.4

 

274 – 175 (Tai Wo Service Road West)

Vertical Barrier

3m above parapet

99

4.20.4

Notes:      (*) The parapet wall is 0.8m high above road surface

With the erection of noise barriers, the predicted noise levels are shown in Table 4.43.  The detailed breakdowns for road traffic noise are shown in Appendix 4.9.

Table 4.43:    Mitigated Road Traffic Noise Levels of Existing Uses

NSR ID

Noise Criteria L10(1 hr) dB(A)

Mitigated Noise Level L10 (1hr) dB(A)

Lin Ma Hang to Wo Keng Shan

 

PY1

70

68 – 69

PY2

70

67 – 70

PY4

70

68

WKS1

70

68

WKS4

70

70

WKS7

70

70

Loi Tung

 

ST5

70

68 – 70

ST6

70

67 – 68

LT1

70

68 – 69

LT2

70

70

LT3

70

69 – 70

LT4

70

68 – 70

Fanling

 

 

TH1

70

65

TH2

70

69 - 70

TH4

70

70

KT1

70

68

NWP1

70

68 - 70

Notes:      (*) Significant Contribution from New Roads denotes the noise level from new roads to the overall noise level is equal to or higher than 1.0dB(A).

Based on the tables above, although some of the NSRs i.e. WHS1, TH5, TH6 and NWP2 would exceed the relevant noise criteria, the noise contribution from new roads is smaller than 1.0 dB(A).  Therefore, no further mitigation measure is considered.

Planned Uses

It is noted that the construction of New Territories Exempted House is permitted in V zone within the assessment area.  However, as no exceedance of road traffic noise criteria is predicted for such planned uses, no further mitigation measures is required.

4.5.2           Fixed Plant Noise

4.5.2.1         Identification of Emission Source

Potential noise impacts from operation of planned fixed plant including any noisy facilities inside the BCP and ventilation shafts of the tunnel sections of the connecting road on the nearby NSRs have been assessed quantitatively.  In accordance with Annex 5 of the EIAO-TM, the noise criteria for fixed plant noise assessment shall be either

           5 dB(A) below the appropriate Acceptable Noise Levels (ANL) shown in Table 2 of the Technical Memorandum for the Assessment of Noise from Places Other than Domestic Premises, Public Places or Construction Sites, or

           the prevailing background noise levels (for quiet areas with level 5 dB(A) below the ANL). 

For the potential noise impact from the operation of the BCP other than the inside fixed plant sources, discussion is given in Section 4.5.2.5.

Given that the Project will be developed in a quiet rural environment except the area near Fanling Highway, background noise measurements were carried out for comparison with the ANL in establishing the noise criteria (see Section 4.3.1.3).  The noise criteria of the fixed plant noise at different locations of the Project are summarised in Table 4.44 below.

Table 4.44     Noise Criteria of Fixed Plant Noise

Location Description

Representative NSR ID.

ASR

Time Period

ANL – 5, dB(A)

Corrected Facade Noise Level, dB(A)*

Fixed Plant Noise Criteria, dB(A)

Tsung Yuen Ha

TYH, V1, V2, CY3

A

Daytime

55

52

52

 

 

 

Evening Time

55

49

49

 

 

 

Night-time

45

45

45

Ng Chau Road

WKS6, WKS7

A

Daytime

55

56

55

 

 

 

Evening Time

55

52

52

 

 

 

Night-time

45

46

45

Wo Keng Shan

ST1, ST2, ST3 and TTW2

A

Daytime

55

54

54

 

 

Evening Time

55

47

47

 

 

 

Night-time

45

45

45

Loi Tung

LT4

A

Daytime

55

49

49

 

 

 

Evening Time

55

44

44

 

 

 

Night-time

45

43

43

Po Kat Tsai

PKT1, PKT2 and PKT3

A

Daytime

55

46

46

 

 

Evening Time

55

36

36

 

 

 

Night-time

45

36

36

Fanling Highway

TH1, TH4

C

Daytime

65

N/A

65

 

 

 

Evening Time

65

N/A

65

 

 

 

Night-time

55

N/A

55

Notes:      (*) A facade correction of 3dB(A) has been included in the measurement results.

4.5.2.2         Assessment Methodology

In the absence of any detailed information and noise specification for the proposed fixed plant, the maximum permissible noise emission levels at the shaft/ exhaust openings have been determined for future detailed design of the fixed plant.

For the assessment of noise from the fixed plant, the maximum permissible sound power levels (Max SWLs) of the identified fixed noise sources were determined by adopting standard acoustics principles.  The following formula was used for calculating the Max SWLs of the fixed plant:

 

SPL = Max SWL – DC + FC

where

SPL:            Sound Pressure Level in dB(A)

Max SWL:   Maximum Permissible Sound Power Level in dB(A)

DC:              Distance Attenuation in dB(A) = 20 log D + 8 [where D is the distance in m]

FC:               Façade Correction in dB(A) = +3 dB(A)

If the noise sources do not fall within the view angle of the representative NSR under assessment or are completely blocked by the residential blocks/ buildings, it is assumed that these noise sources are insignificant to that NSR and would be excluded from calculation.  While the sources fall within the view angle of the NSR but with no direct line of sight to the opening, a 10 dB(A) attenuation would be applied.

If exceedance to the noise criteria is found for one NSR, the initial SWL of the dominant sources to that NSR would be gradually lowered until the corrected SPL at that NSR meets the acceptable level.  The process would be repeated for other representative NSRs with exceedance of the noise criteria until all corrected SPLs at the representative NSRs meet the noise criteria.  The maximum allowable SWLs of the proposed fixed plants have been predicted by this approach.

4.5.2.3         Evaluation of Impacts

Noise from fixed plant for the Project would mainly be associated with BCP buildings, tunnel ventilation shaft, administration building and mid-ventilation building.  According to the preliminary design information, major fixed plant noise is attributed to the following sources as summarised in Table 4.45 below and shown in Figures 4.21.1 to 4.21.7: -

¡      BCP Buildings;

¡      Ventilation Shafts in Tunnel Portals;

¡      Mid-ventilation Building at Po Kat Tsai; and

¡      Administration Building at Loi Tung.

Table 4.45:    Summary of Fixed Plant Noise Sources

Fixed Plant Location

Fixed Noise Source

Number of Fixed Plant

Opening ID

Figure

BCP

Sewage Treatment Plant (G/F)

7

STP-A to G

4.21.1 (1)

 

Fixed X-Ray Inspection Station and Offices (G/F)

4

FXO-A to D

4.21.1 (1)

 

Fixed X-Ray Inspection Station (G/F)

4

FXI-A to D

4.21.1 (1)

 

Passenger Terminal Building (G/F)

4

PTB-A to D

4.21.1 (1)

 

Passenger Terminal Building (1/F - 4/F)

4

PTB-A to D

4.21.1 (2)

 

Fire Station (G/F)

4

FS-A to D

4.21.1 (1)

 

Police Station (G/F)

4

HKP-A to D

4.21.1 (1)

North Tunnel North Portal

Ventilation Building (G/F)

2

VB1-A-B

4.21.2

North Tunnel South Portal & Administration Building at Loi Tung

Ventilation Building (G/F)

2

VB2-A-B

4.21.3

Administration Building (G/F)

3

AB-A-C

4.21.4

South Tunnel North Portal

Ventilation Building (G/F)

2

VB3-A-B

4.21.5

South Tunnel South Portal

Ventilation Building (G/F)

2

VB4-A-B

4.21.7

Po Kat Tsai

Mid-Ventilation Building (G/F)

1

MVB-A

4.21.6

Based on the methodology mentioned above, the maximum allowable SWLs of the proposed fixed plants during daytime and night-time are predicted as summarized in Table 4.46 below.  Calculations of fixed plant noise assessment are shown in Appendix 4.10.

Table 4.46:    Maximum SWLs of the Fixed Plant

Fixed Plant Location

Fixed Noise Source

Opening ID

*Maximum SWL, dB(A)

Daytime

Evening Time

Night-time

BCP

Sewage Treatment Plant (G/F)

STP-A to G

94

91

87

 

Fixed X-Ray Inspection Station and Offices (G/F)

FXO-A to D

94

91

87

 

Fixed X-Ray Inspection Station (G/F)

FXI-A to D

88

85

81

 

Passenger Terminal Building (G/F)

PTB-A to D

90

87

83

 

Passenger Terminal Building (1/F - 4/F)

PTB-A to D

90

87

83

 

Fire Station (G/F)

FS-A to D

88

85

81

 

Police Station (G/F)

HKP-A to D

88

85

81

North Tunnel North Portal

Ventilation Building

VB1-A

102

99

92

VB1-B

107

104

97

North Tunnel South Portal & Administration Building at Loi Tung

Ventilation Building

VB2-A

107

100

98

VB2-B

107

100

98

Administration Building

AB-A

95

88

86

AB-B

95

88

86

AB-C

94

87

85

South Tunnel North Portal

Ventilation Building

VB3-A

107

102

101

VB3-B

107

102

101

South Tunnel South Portal

Ventilation Building

VB4-A

115

115

105

VB4-B

110

110

100

Po Kat Tsai

Mid-Ventilation Building

MVB-A

98

88

88

Notes: (*) Maximum SWL at each opening

4.5.2.4         Mitigation of Adverse Environmental Impact

With the fixed plant properly designed to meet the maximum SWL listed in Table 4.46, there would not be any residual impacts predicted.  However, it is still recommended that the following noise reduction measures shall be considered as far as practicable during construction:

¡      Choose quieter plant such as those which have been effectively silenced.

¡      Include noise levels specification when ordering new plant (including chillier and E/M equipment).

¡      Locate fixed plant/louver away from any NSRs as far as practicable.

¡      Locate fixed plant in walled plant rooms or in specially designed enclosures.

¡      Locate noisy machines in a basement or a completely separate building.

¡      Install direct noise mitigation measures including silencers, acoustic louvers and acoustic enclosure where necessary.

¡      Develop and implement a regularly scheduled plant maintenance programme so that equipment is properly operated and serviced in order to maintain a controlled level of noise.  

4.5.2.5         Potential Noise Impact from the Operation of the BCP

Other than the fixed plant sources inside BCP, potential noise impact may be generated from the daily operation of the BCP.  The main activities that would be involved in the daily operation include vehicles moving in and out of the BCP with relatively low speed and vehicles lining up inside the BCP for inspection i.e. vehicles in idling.  Public address system would be installed inside the BCP but the usage of the system shall be limited as the BCP would be operated mainly by sign gantry.  The closest noise sensitive receiver to the BCP i.e. the Tsung Yuen Ha Village is located at a distance of about 75m.  Given the nature of the operation within the BCP and the buffer distance to the nearest NSR, it is anticipated that the potential noise impact from the operation within the BCP shall be minimal.

4.6               Environmental Monitoring and Audit

4.6.1           Construction Phase

With the recommended mitigation measures, no residual noise impacts are predicted at all representative NSRs during the construction phase,, However, environmental monitoring and audit (EM&A) is recommended to ensure the mitigation measures and good site practice have been implemented properly, and to minimize the potential noise impact during the construction phase.  Details are given in the EM&A Manual.

4.6.2           Operational Phase

Prior to the operation phase of the Project, a commissioning test should be conducted for all major fixed noise sources to ensure compliance of the operational airborne noise levels with the EIAO-TM noise criteria. 

Road traffic noise levels should be monitored at representative NSRs, which are in the vicinity of the recommended direct noise mitigation measures, during the first year after road opening.

Details of the EM&A programme are provided in the stand-alone EM&A Manual

4.7               Conclusion

4.7.1           Construction Phase

The noise impact associated with unmitigated construction activities for the proposed BCP and the connecting road would cause exceedance of the daytime construction noise criterion at the nearby NSRs during the normal working hours.  Therefore, good site practices and mitigation measures including the use of quiet plants, erection of movable noise barriers and noise insulating fabric have been proposed to alleviate the noise impact.   With the good site practices and mitigation measures in place, no residual impacts are predicted at all the NSRs.

4.7.2           Operational Phase

The assessment has predicted that the traffic noise impact arising from the proposed connecting roads of the Project and the contribution from existing road network in Year 2033 will exceed the noise criteria at the existing NSRs with around 76 dwellings affected by the Project roads.  With the implementation of mitigation measures recommended, the noise criteria will be met at all representative NSRs with traffic noise impact dominated by the Project roads.

With the specification of maximum allowable sound power levels for the proposed fixed plants at ventilation shafts, mid-ventilation building, BCP buildings and Administration Buildings, full compliance of Noise Control Ordinance will be achieved. 

 



[1] Nelson, P.M., Transportation Noise Reference Book. 1987.

[2] Saurenman, H., Nelson, J., Wilson, G. 1982, Handbook of Urban Rail Noise and Vibration Control, US Department of Transportation Urban Mass Transportation Administration (Table 8-7).

[3] Transit noise and vibration impact assessment, US Federal Transit Administration (FTA), 2006