1                             Introduction

1.1                       Background

1.1.1                 In view of the growing population and general aspirations for healthy life and physical activities, the Hong Kong Government is planning for more sports grounds and indoor sports centres to make up for the general shortage in Hong Kong. Based on population projection, a shortfall of sports centres and standard sports ground in East Kowloon is anticipated. With overwhelming support from the sports communities and the local communities including district councils, the Hong Kong Government has proposed building a Multi-purpose Sports Complex at Kai Tak (hereafter called “Kai Tak Multi-Purpose Sports Complex” or “the Project”) which will provide high-quality sports facilities to help alleviate Hong Kong’s shortage of public sports facilities and will also provide new venues suitable for hosting major local and international sports events. The Project will comprise a main stadium which shall be multi-functional to optimize utilization and to deliver a spectator experience. The Project will mainly cater for a wide range of major sports events but will also provide venues for other infrequent non-sports activities such as concerts, exhibitions, carnivals, etc.

1.1.2                 A Comprehensive Planning and Engineering Review of South East Kowloon Development (SEKD) was commenced in 2004 and a Preliminary Outline Development Plan (PODP) was first prepared. In 2007, Civil Engineering and Development Department (CEDD) of HKSAR commissioned the “Kai Tak Development Engineering Study” including a Schedule 3 Environmental Impact Assessment (EIA) Study, to confirm the feasibility of the proposed development as recommended in the PODP. The Kai Tak Multi-purpose Sports Complex is one of the key components in the PODP. Besides, the statutory Kai Tak Outline Zoning Plan was formulated in 2007 with subsequent changes made in 2009. The latest Kai Tak OZP (No. S/K22/4) was approved in 2012 with the Project as a planned development.

1.1.3                 The environmental impacts of the Project have been broadly addressed in the Schedule 3 EIA report for the Kai Tak Development (KTD), which was approved under the Environmental Impact Assessment Ordinance (EIAO) on 4 March 2009. The approved EIA report for the KTD recommended that a further EIA study is required under the EIAO to address the potential environmental impacts of the Project in detail given that the Project has been identified as a designated project under Schedule 2 of the EIAO.

1.2                       The Project

1.2.1                 The Project site covers a land area of about 28.2 hectares. It is bounded by Central Kowloon Route to the south and dissected by Road D2 in the middle. It is a multi-purpose complex comprising a 50,000-seat Main Stadium, a 7,000-seat Public Sports Ground, an Indoor Sports Centre, and other ancillary/supporting facilities such as car parking spaces, hotel, office area for sports-related organizations and a commercial area. The location and details of the facilities are illustrated in Figure 1-1. More detailed description of the Project is given in Chapter 2.

1.3                       Designated Projects

1.3.1                 The Project contains the following designated project elements under Part I, Schedule 2 of the EIAO:

l   Item O.6 – An open air concert venue with a capacity to accommodate more than 10,000 persons; and

l   Item O.7 – An outdoor sporting facility with a capacity to accommodate more than 10,000 persons.

1.3.2                 A project profile (No. PP-509/2014) was submitted by the Architectural Services Department (ArchSD) to EPD for application of an EIA study brief under Section 5(1)(a) of the EIAO on 3 June 2014. An EIA Study Brief (No. ESB- 274/2014) was issued by the Environmental Protection Department (EPD) on 16 July 2014.

1.4                       Objectives of the EIA Study

1.4.1                 The objective of this Assignment was to carry out an EIA to investigate the environmental acceptability during construction and operation of the Project. Potential environmental impacts were identified and evaluated with recommendations on appropriate mitigation measures. In accordance with Clause 2.1 of the EIA Study Brief, the objectives of the EIA study were:

(i)            to describe the Project and associated works together with the requirements and environmental benefits for carrying out the Project;

(ii)          to identify and describe elements of community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including natural and man-made environment and the associated environmental constraints;

(iii)        to provide information on the consideration of alternative options of the Project including alternative siting, scale/size, extent, layout, configuration/orientation, design, transport linkage, people dispersion routes/methods after major sports/non-sports events and construction methods with a view to avoiding and minimizing potential environmental impacts to environmentally sensitive areas and sensitive uses; to compare the environmental benefits and dis-benefits of different options; to provide reasons for selecting the preferred option(s) and to describe the part environmental factors played in the selection of preferred option(s);

(iv)        to identify and quantify emission sources, including air and gaseous emission, noise emission, sewage and wastewater emission, waste generation and contaminated material generation and determine the significance of impacts on sensitive receivers and potential affected uses;

(v)          to identify and quantify any potential losses or damage to flora, fauna and natural habitats;

(vi)        to identify and systematically evaluate any potential landscape and visual impacts and to propose measures to mitigate these impacts;

(vii)      to identify any negative impacts on sites of cultural heritage and to propose measures to mitigate these impacts;

(viii)    to propose the provision of infrastructure or mitigation measures so as to minimize pollution, environmental disturbance and nuisance during construction and operation of the Project;

(ix)        to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;

(x)          to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to the sensitive receivers and potential affected uses;

(xi)        to identify, assess and specify methods, measures and standards to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels;

(xii)      to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification; and

(xiii)    to design and specify environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.

1.5                       Scope of the EIA Study

1.5.1                 This EIA report addresses all key potential environmental issues associated with the construction and operation phases of the Project as specified under Clause 3.2 of the EIA Study Brief:

(i)            potential air quality impact on sensitive receivers during construction and operation of the Project, including dust emissions during construction, odour, vehicular (including traffic generated from the Project) and other air emissions during operation;

(ii)          potential hazard to life impact during the construction and operation of the Project due to the potentially hazardous facilities, including in particular the Ma Tau Kok Gas Works and all associated facilities;

(iii)        potential noise impact on sensitive receivers during construction and operation of the Project, including noise generated by construction activities, noise arising from sports as well as non-sports events of the Project (e.g. noise from the public address system and noise from human activities, etc.), traffic noise (including traffic generated from the Project) and fixed plant noise during operation;

(iv)        potential water quality impact on relevant water system(s) including the Victoria Harbour (Phase One and Phase Two) Water Control Zone and relevant water sensitive receivers during construction and operation of the Project;

(v)          potential sewerage and sewage treatment implications arising from the Project;

(vi)        potential waste management implications arising from the construction and operation of the Project, including handling and disposal of construction and demolition materials, chemical waste, food waste and general refuse;

(vii)      potential land contamination impact arising from the Project;

(viii)    potential ecological impact, including habitat loss and fragmentation during construction and operation of the Project;

(ix)        potential landscape and visual impacts due to the construction and operation of the Project; and

(x)          potential cultural heritage impact during construction and operation of the Project; and

(xi)        potential cumulative environmental impacts of the Project, through interaction or in combination with other existing, committed and planned projects such as Central Kowloon Route, Shatin Central Link, Trunk Road T2, Roads D2 & D3, Metro Park and Station Square in KTD, etc. in the vicinity of the Project, and those impacts which may have a bearing on the environmental acceptability of the Project.

1.6                       Structure of EIA Report

1.6.1                 The EIA Report comprises the following Chapters:

l   Ch. 1      Introduction

l   Ch. 2      Project Description

l   Ch. 3      Air Quality Impact Assessment

l   Ch. 4      Hazard to Life Assessment

l   Ch. 5      Noise Impact Assessment

l   Ch. 6      Water Quality Impact Assessment

l   Ch. 7      Sewerage and Sewage Treatment Implications

l   Ch. 8      Waste Management Implications

l   Ch. 9      Land Contamination Assessment

l   Ch. 10    Terrestrial Ecological Impact Assessment

l   Ch. 11    Landscape and Visual Impact Assessment

l   Ch. 12    Cultural Heritage Impact Assessment

l   Ch. 13   Environmental Monitoring and Audit Requirements

l   Ch. 14    Implementation Schedule of Mitigation Measures

l   Ch. 15    Environmental Outcomes

l   Ch. 16   Conclusion

 

 

2                             project description

2.1                       General Description of the Project

2.1.1                 The Kai Tak Multi-purpose Sports Complex (the MPSC or the Project) is situated in the North Apron Area of the Kai Tak Development (KTD) site. The site area is about 28.2 hectares. The location of site is indicated as “Other Specified Use” annotated “Stadium” on the approved Kai Tak Outline Zoning Plan No. S/K22/4. It is surrounded by a few major transport links, including the proposed Shatin to Central Link (SCL) tunnel to the north, Central Kowloon Route (CKR) to the south and the possible provision of environmentally friendly linkage system (EFLS) to the east. Road D2 which is under construction will dissect the site into two portions. The Project site, which is in the heart of KTD, is considered as a suitable location for the development of the Multi-purpose Sports Complex.

2.1.2                 The proposed multi-purpose complex comprises a 50,000-seat Main Stadium, a 7,000-seat Public Sports Ground, an Indoor Sports Centre, and other ancillary/supporting facilities such as car parking spaces, hotel, office area for sports-related organizations and a commercial area. An application for planning permission under s16 of the Town Planning Ordinance will be submitted to the Town Planning Board for the development of a hotel of a suitable scale within the MPSC and the relaxation of the building height restriction for the Main Stadium. The master layout plans of the Project are shown in Figures 2-1a and 2-1b.

2.2                       Need of the Project

2.2.1                 The HKSAR Government’s strategic policy for developing sports in Hong Kong has three objectives: (a) to promote sports in the community, (b) to support elite sports, and (c) to make Hong Kong a centre for major international sports events. Sports facilities are provided in accordance with the above policy objectives.

2.2.2                 Hong Kong has a general shortage of public sports facilities. Based on the Hong Kong Planning Standards and Guidelines and the population projection for East Kowloon (including the Kowloon City, Kwun Tong and Wong Tai Sin Districts), there will be a shortfall of three sports centres and one standard sports ground by 2021.

2.2.3                 Hong Kong also lacks up-to-date venues for staging major international sports events. The existing ageing venues have insufficient seating capacity and lack appropriate supporting facilities and flexibility in operation.

2.2.4                 A Comprehensive Planning and Engineering Review of South East Kowloon Development was commenced in 2004. The Planning Department commissioned the Kai Tak Planning Review (KTPR) as Part I of the Comprehensive Review. Three stages of extensive public participation and engagement were carried out under KTPR from 2004 till 2006.

2.2.5                 A Preliminary Outline Development Plan (PODP) was formulated as an outcome of the KTPR. The Project was identified as an anchor of the KTD. One of the conclusions of KTPR was that “The community’s views envisage Kai Tak as a hub of sports, recreation, tourism and entertainment.” It was also considered that the events at the Stadium Complex “will be a significant catalyst to re-activate and re-energize the waterfront”.

2.2.6                 Based on the PODP, a Kai Tak Outline Zoning Plan was drafted and later approved by the Chief Executive in Council under the Town Planning Ordinance.

2.2.7                 Part II of the Comprehensive Review was an engineering feasibility study, which included an EIA study under Schedule 3 of the EIAO. The EIA report was approved by EPD on 4 March 2009. The feasibility of the PODP was confirmed and a Recommended Outline Development Plan (RODP) was formulated. The latest RODP is provided in Appendix 2B.

2.2.8                 To sum up, the development of a multi-purpose sports complex is a long-awaited project with overwhelming support from the communities including District Councils and the sports sector. It has been planned as a key component of the KTD, and the general feasibility has been established. It will provide new venues suitable for hosting major local and international sports events and help alleviate Hong Kong’s shortage of sports facilities and open space for the community. In this sense, the Project makes a direct and significant contribution to realize the Government’s policy objectives for sports development.

2.2.9                 Without this Project, the site will likely remain for a longer period as a large piece of construction site and carparks. Not only is the view unpleasant, the exposed ground is susceptible to soil erosion. The current land uses are also incompatible with the future surrounding development, not to mention that the demand for sports facility remains unmet. Upon completion of the MPSC, the landscaped area will be grown with vegetation that will help preventing soil erosion and enhancing the landscape and visual quality of the area. The design of the MPSC will be coherent with the surrounding KTD Area in the future. The operation of facilities inside the Project would create job opportunities. The Main Stadium will also serve as a landmark facility in the Project.

2.3                       Project Programme

2.3.1                 The construction works of the Project are scheduled to commence in 2017 for completion in 2020/2021. The Project is scheduled to commission in 2021.

2.4                       Concurrent Projects

2.4.1                 During the construction period of the Project, the potential concurrent construction works in the vicinity (500 m from the Project Site) are set out below.

Table 2-1        List of Concurrent Projects

No.

Project

Time Line

1

East Portion of Central Kowloon Route (CKR)

Scheduled for completion in 2021 but possible delay of at least 2 years based on the latest information

2

Reconstruction and Upgrading of Kai Tak Nullah

Scheduled for completion in April 2018

3

Kai Tak Development Stage 4 (Road D2 construction)

Scheduled for completion in 3rd quarter of 2017

4

North Apron Remaining Infrastructure

Scheduled for completion in late of 2021

5

Kai Tak Approach Channel and Kwun Tong Typhoon Shelter Improvement Works (Phase 2)

Scheduled for completion in December 2018

6

Shatin Central Link (SCL)

Scheduled for completion in 2019 based on the latest information

2.5                       Consideration of Alternative Development Options

2.5.1                 In order to fulfil the requirements for international sports events, the Main Stadium is not envisaged as a stand-alone facility. It will be accompanied by a range of supporting facilities that will create a critical mass of development for producing a dynamic and vibrant sports environment. Associated facilities comprise a public sports ground, an indoor sports centre, a warm-up track, a nursery site for maintaining palletised grass when not required for stadium events, car parking, servicing areas, circulation areas, and commercial support provision in the form of hotel, retail, etc. It was estimated that these facilities would require a site of up to 24 hectares.

2.5.2                 The Home Affairs Bureau carried out the “Study on Requirements for Major New Sports and Recreation Venues” in 2001 and the findings of the study were updated in 2005.

2.5.3                 The 2001 study identified and examined 8 candidate sites that might best accommodate such a sports complex. The assessment criteria for determining the suitability are listed below:

(a)      Land Costs: The preferred site should be located on Government land, preferably previously identified for stadium development. The potential use and value of the land for other uses (e.g. housing development) or other Government, Institution or Community (“G/IC”) facilities to meet district deficit or for long term planning should be considered.

(b)     Compatibility with Surrounding Existing and Proposed Land Uses: The preferred site should be in an area where adjacent uses have a compatible zoning, i.e. open space, other G/IC uses. The adjacent uses should complement the stadium, i.e. sports related uses.

(c)      Proximity to Candidate Use Groups: The stadium should be located in proximity to users.

(d)     Design Flexibility: There would be more flexibility in designing a brand new stadium than to upgrade or provide temporary structures at existing venues ill-suited to accommodate large-scale spectatorship.

(e)      Availability of Public Transport Facilities: Mass transit access is desirable. At minimum, good public access to the site should be achievable. The site should also have comprehensive pedestrian links to all the Public Transport Interchanges. A user-friendly pedestrian environment should also be achievable ensuring easy access and evacuation from the venue.

(f)      Traffic Capacity: There should be a comprehensive road or rail network, linking the area with other parts of the territory. Multiple road accesses should be achievable.

(g)     Natural Environment: The site should be set in a pleasant environment. It should be set within a comprehensively designed and conceived landscape framework.

(h)     Environmental Concerns: Sensitive receivers should not be located in close proximity to the site, e.g. residential uses. The surrounding land uses should also not create adverse impacts to the stadium.

(i)       Infrastructure Capacity: There should be adequate infrastructure capacity (e.g. roads, drainage, sewerage, electricity, cabling, etc.) to serve a large stadium.

(j)       Land reclamation: The land should preferably be formed and ready for construction. Land formation would take extra time if stadium is built on newly reclaimed land.

2.5.4                 The identified locations and their evaluation of suitability are summarized as follows:

(i)       Northshore Lantau: It was proposed developing northshore Lantau on reclaimed land. The land may accommodate a new stadium. However, the location is too isolated and remote. The distance may discourage people from using the stadium. From the environmental point of view, it is difficult to justify the reclamation for building a stadium if there are alternative sites. The air quality in the area would also be undesirable for international athletes.

(ii)     West Kowloon Reclamation: The West Kowloon Reclamation has been developed into a cultural district. A stadium would not be compatible with the existing development. In addition, the space there was not adequate for a stadium of international standards.

(iii)   Tseung Kwan O: The previously identified site would be amidst existing adjacent residential areas. The area was not earmarked for stadium use and has been subsequently zoned into new residential areas. Noise disturbance from the sports events would be unacceptable for the residents. The compatibility of the stadium with its environment remained a question.

(iv)   Kai Tak Development: KTD has allocated a site for stadium development. It is located at the southwest of the former airport apron and has been planned to be compatible with its surroundings. The size of the site is adequate for an international stadium. The site is easily accessible by vehicles and will be served by two future SCL stations. The unique location makes the stadium a new landmark for Hong Kong. According to international experiences, the development of an international stadium would also help regenerate the old industrial districts surrounding KTD.

(v)     Mei Foo: A four-hectare site had been allocated for a regional stadium. It is located in the metro area served by public transport. However, the size of the site and vehicular access to the site cannot support the requirement for an international stadium. The adjacent residents would also object such a development.

(vi)   Tuen Mun: A 6.35 hectare site has been designated for stadium use. There is a swimming complex and indoor gymnasium nearby. The site is served by Light Rail Transit but not Mass Transit Railway nor major roads. The site area is not sufficient for a stadium of international standards and there are existing residential areas next to the site.

(vii) Victoria Park: Victoria Park is well connected with public transport and commercial facilities. However, the current facilities in the park are highly utilized by the public and objections are anticipated for a stadium in the park. The road capacities in the future may not be enough for supporting such a stadium. Furthermore, the proximity of the Hong Kong Stadium to the location is considered undesirable for a mega sports venue.

(viii)                Pak Shek Kok: A reclamation area next to the Hong Kong Science Park had been zoned for recreation purposes, but subsequently rezoned as residential area. It could accommodate a stadium but not the associated facilities for an international venue. Access to the site could not sustain such a stadium.

2.5.5                 It is concluded that the site inside the KTD is most suitable for the stadium development. The planning of the stadium had been incorporated in the KTPR. The layout of the site has been laid down so that the Main Stadium is located by the waterfront. After considering all the key factors including environmental factors in the option selection, the proposed multi-purpose sports complex in KTD is the preferred option to avoid and minimize adverse environmental effects to the maximum practicable extent.

2.6                       Consideration of Alternative Construction Methods and Sequences of Works

Construction Activities

2.6.1                 Major works of the Project are anticipated to commence in 2017. Pre-construction works for the Project, such as, topographic survey, tree survey, utility survey and ground investigation, will commence in late 2016 for completion by 2017. Concurrent projects which are located in close proximity to the Project site have been scheduled before and after 2017 for construction as detailed in Section 2.4 above. BEAM Certification and building information management (BIM) will be adopted during the Project design and various building phases so as to enhance the quality of development for ensuring that environmental considerations are fully integrated right at the design, planning, construction and operation stages.

2.6.2                 Though precast and prefabrications are carried out outside the Project site, the contractor of the pre-casting and prefabrication activities will adopt good management practices and appropriate pollution control measures to minimize any environmental impacts arising from the casting yards and fabrication workshops.

2.6.3                 Upon taking over the site, the Project Contractor’s focus should be on boundary hoarding, site accommodation and secure storage areas, temporary utilities, such as power/water supply, setting out and clearance of debris and the temporary site traffic routes, ingress and egress from site to the nearby barging point. It will be important to survey the extent and usefulness of the former airport concrete hard standing which remains vacant. If removal of this concrete slab is deemed necessary using saw cutting, or other heavy duty concrete breaking equipment, dust suppression, watering and noise attenuation measures will be provided as necessary. A Construction Waste Management Plan will be implemented.

2.6.4                 In the North Sector, it is likely that steel H-piles will be adopted for the Public Sports Ground and Indoor Sports Centre. Vibration or hydraulic ram equipment should be adequate for initial penetration, to minimize noise emissions, but percussive equipment will be necessary to achieve a final set to satisfy the acceptance criteria of individual piles. Provisions will be made for coring through rock and boulders, and rock sockets. Piling equipment will be suitably shielded or enclosed to comply with noise emission requirements. Generally pile caps will be designed to provide an overall efficient system together with the piling layout so as to minimize excavation, and in particular excavation below ground water level, and thus minimise the operation time of power mechanical equipment. For pile caps below 2.5m deep and basement construction, however, steel sheet piling or equivalent support, i.e. excavation and lateral support (ELS) will be necessary for excavated faces, and to provide a cut-off below the relatively high ground water level. ELS system will be required for excavation deeper than 2.5m and greater than 5.0m in length and as the works may affect any roads, building structures, slopes steeper than 30° or water mains of 75mm in diameter or greater, the affected area being defined as within 45° line up from the base of the excavation to the ground surface. Removal of excavated materials by road vehicles will be strictly controlled, with washing facilities at site exit points and the covered loads will be sent to the disposal areas designated by Civil Engineering and Development Department (CEDD) and EPD. Whenever possible, the adjacent existing marine barging point will be used for off-site disposal. Working within the protection areas adjacent to the existing Kai Tak Tunnel will require special protection measures, including temporary steel casting for piling works and grouting or similar for ground improvement. Drainage and other services will be installed, as the working areas become available.

2.6.5                 In the South Sector, the foundation for Main Stadium and hotel/office blocks will likely be steel H piles. The piles will be founded on rock, at a depth of 40 to 50 metres below ground and will be constructed with appropriate means to contain noise emissions. Concrete supplies will come from off-site plants. Disposal of excavated materials will be facilitated by using existing barging point near the south boundary of the Project site.

2.6.6                 Conventional concrete structures with a long span steel roof will be proposed for the Public Sports Ground and Indoor Sports Centre. Precast concrete elements like spectator stands, stairs will be extensively used as an alternative to in situ concreting to minimize environmental impacts arising from the concrete mixing on-site. The structures are relatively conventional, and the dust and noise emissions and visual impacts from construction activities can be readily controlled within statutory limits. Early construction of the podium deck crossing Road D2 from above will facilitate working access between the North and South Sectors. The hotel-office blocks are likely to be on reinforced concrete structures, which will be constructed using conventional method. Metal temporary works and metal scaffolding with appropriate screening will be adopted to contain noise, minimize visual impact and airborne emissions.

2.6.7                 Construction of the Main Stadium will be the most visible activity of the works on-site. The Main Stadium is assembled from heavy and large steel trusses, requiring specialist lifting plants. The steel trusses are fabricated off-site and the secondary back-up structures and spectator stands would likely be reinforced concrete pre-cast off-site. Access to marine landing facilities will reduce reliance on surrounding roads. The special retractable roof system will be a particular highlight. All equipment and specialist plants will be operated strictly in accordance with statutory noise and dust limits apart from construction safety and any applications for night-works to the Authority should be made only with full justification.

2.6.8                 Activities during fitting-out will largely be inside completed building envelopes, so that the works are shielded and thus noise or lighting impacts are minimized. The exception will be building facades, utility connections and external works on hard and soft landscaping, including tree planting, greening and paving works, which are generally daytime activities. In the event that special structures are necessary to contain noise emissions from crowd flows at night-time, such works will be completed during this stage along with the fitting-out.

2.6.9                 Miscellaneous finishing works will be in progress during the day-time across the whole of the Project, but these will not be major in nature. Night-time works if necessary will be limited to areas shielded from exterior view.

Alternative Construction Sequence

2.6.10             The proposed construction sequence is based on conventional bottom up construction starting from site clearance, site formation, foundation, superstructure, Mechanical and Electrical (M&E) plants installation, utilities, finishes and external works. The tentative construction programme is shown in Appendix 2A.

2.6.11             As the Project site covers approximately 28.2 hectares, it will be practical, economical and environmentally friendly to carry out construction works in geographical zones with construction procedures following Sections 2.6.1 to 2.6.9 for each zone so as to minimise any cumulative environmental impact. The proposed zoning sequence is shown in Figure 2-2. In implementing this zoning sequence, the construction programme of Road D2 which separates the site into two sectors shall be addressed such that the overhead decks at Zones N1 and N4 are constructed to facilitate smooth construction within Project site as a whole. Furthermore, the sewerage connections, as given in Chapter 7, and construction material/waste delivery routes, as given in Chapter 8, are designed to ensure a smooth interface with the construction of Road D2.

Alternative Construction Method

2.6.12             The construction method will likely be dominated by the Project contractor(s). However, prefabricated construction method should be adopted as far as practicable to minimise material waste and impact caused by noise and dust. The prefabricated construction method will be implemented as contract requirements. Marine access is planned for delivery of prefabricated units direct to the site.

2.7                       Selection of Preferred Scenario

2.7.1                 Having regard to the findings in Sections 2.2 and 2.5, including the consideration of environmental factors, the subject site inside the KTD is considered most suitable for the development of the proposed multi-purpose sports complex.

2.7.2                 As discussed in Section 2.6, alternative construction methods and sequences of construction works have been considered to maximize the environmental benefits and avoid/minimize adverse environmental impacts arising from the Project. Details of the technical assessments for various environmental issues are provided in later chapters in this EIA report.