EIA Study Brief No.
ESB-102/2002
May 2002
Environmental Impact Assessment
Ordinance (Cap. 499), Section 5 (7)
Environmental Impact
Assessment Study Brief No. ESB-102/2002
Name of Applicant:
Architectural Services Department
(hereinafter known as
the "Applicant")
1. BACKGROUND
1.1 An
application (No. ESB-102/2002) for an Environmental Impact Assessment (EIA)
study brief under section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by the captioned Applicant on 25th March 2002 with
a Project Profile (No. PP-166/2002).
1.2 The Applicant proposes to construct a new crematorium of 6 cremators with total capacity of 1,260 kg per hour to replace the existing 6 cremators (hereinafter referred as the Project). The location of the Project is shown in Figure No. 1 in the Project Profile. The Project also includes the provision of a full range of ancillary facilities required for the operation of a crematorium, including:
(a) air pollution control systems to control the emission
of the cremators
(b) four service halls
(c) four joss paper burners
(d) emergency generator room
(e) underground fuel tanks
(f) mortuary
(g) office accommodation
(h) store rooms and dangerous goods store
(i) public toilets
(j) parking spaces for coaches and private cars
(k) refuse storage chambers
(l) garden of remembrance
1.3
Pursuant to section 5(7)(a) of the EIAO,
the Director of Environmental Protection (the Director) issues this EIA study
brief to the Applicant to carry out an EIA study for the Project.
1.4 The purpose of this EIA study is to provide information on the nature and extent of environmental impacts arising from the construction and operation of the proposed project and related activities taking place concurrently. This information will contribute to decisions by the Director on:
(i) the overall
acceptability of any adverse environmental consequences that are likely to
arise as a result of the proposed project;
(ii) the conditions and
requirements for the detailed design, construction and operation of the proposed project to mitigate
against adverse environmental consequences wherever practicable; and
(iii) acceptability of residual
impacts after proposed mitigation measures are implemented.
2. OBJECTIVES
OF THE EIA STUDY
2.1 The
objectives of the EIA study are as follows:
(i) to describe the
proposed project together with the requirements for carrying out the proposed
project;
(ii)
to identify and describe elements of
community and environment likely to be affected by the proposed project and/or
likely to cause adverse impacts to the proposed project, including natural and
man-made environment and the associated environmental constraints;
(iii)
to describe the considerations given in
selecting the proposed site, layout, design (including technology to be adopted
for the new cremators), and construction method; to provide reasons for
selecting the preferred option and to describe the part environmental factors
played in the selection process;
(iv)
to identify and quantify emission sources
and determine the significance of impacts on sensitive receivers and
potentially affected uses;
(v)
to identify and quantify waste management
requirements and propose measures to mitigate or prevent impacts, and measures
to be adopted to avoid introducing land contamination at the new cremators・
site;
(vi)
to identify and quantify any potential
visual impacts and to propose measures to mitigate impacts;
(vii)
to identify the negative impacts and
propose the provision mitigation measures so as to minimize pollution,
environmental disturbance and nuisance during construction and operation of the
project;
(viii)
to identify, predict and evaluate the
residual (i.e. after practicable mitigation) environmental impacts and the
cumulative effects expected to arise during the construction and operation
phases of the proposed project in relation to the sensitive receivers and
potential affected uses;
(ix)
to identify, assess and specify methods,
measures and standards, to be included in the detailed design, construction and
operation of the proposed project which are necessary to mitigate these
environmental impacts and cumulative effects and reduce them to acceptable
levels;
(x)
to identify constraints associated with
the mitigation measures recommended in the EIA study; and
(xi)
to design and specify an environmental
monitoring program, and if required, other environmental monitoring and audit
requirements, to ensure the implementation and the effectiveness of the
recommended environmental protection and pollution control measures.
3. DETAILED
REQUIREMENTS OF THE EIA STUDY
3.1 The purpose
of this study brief is to scope the key issues of the EIA study. The Applicant has to demonstrate in the
EIA report that the criteria in the relevant sections of the Technical
Memorandum on the Environmental Impact Assessment Process of the Environmental
Impact Assessment Ordinance (hereinafter referred to as the TM) are fully
complied with.
3.2 The Scope
3.2.1 The
scope of this EIA study shall cover the project proposed in the Project Profile
and shall include the works and facilities mentioned in section 1.2 above. Figure 1 of this Study Brief shows the
location of the new and existing crematoriums. The EIA study shall address the likely key issues described
below, together with any key issues identified during the course of the study
and the
cumulative environmental impacts of the Project, through interaction or in
combination with other existing, committed and planned developments in the
vicinity of the Project:
(i) the
consideration given in selecting the proposed site, layout, design (including
technology to be adopted for the new cremators), and construction method for
the Project;
(ii) the
air quality impacts arising from the construction and operation of the Project;
(iii) the measures to be adopted to avoid introducing land
contamination at the new cremators・ site, as well as the waste management for
the construction and operation of the Project;
(iv) the
visual impacts from the construction and operation of the Project;
(v)
the safety requirements related to
storage of fuel;
(vi)
the construction and
operational noise impacts of the Project;
and,
(vii) handling of any
effluent discharge from the air pollution control/scrubbing systems for the new
crematorium during operation stage;.
3.2.2 The
Applicant shall also assess all the environmental impacts during the
transitional stage of the Project before the existing cremators cease
operation, scenarios to include test runs of the new cremators concurrently
with the existing cremators remain operative in full service.
3.3.3 Regarding
the potential cumulative impacts, other projects under planning to be
considered to include, but not necessarily limited to, the construction stage
impacts due to the proposed Diamond Hill No. 2 Fresh Water Service Reservoir
and any potential developments on the cleared land along Po Kong Village Road
near the Project・s site.
3.3 Decommissioning
of the Existing Diamond Hill Crematorium
3.3.1 Section 4.2 of the Project Profile stated that the existing Diamond
Hill Crematorium will be decommissioned when the proposed new crematorium is in
operation. However, section 1.2 of
the Project Profile on the project scope only listed out those work items
related to the new cremators but did not mention the decommissioning of the
existing cremators. The Applicant shall state clearly whether or not the
decommissioning of the existing cremators is covered under the EIA Study.
3.3.2 If the Applicant confirms that environmental impacts of
the decommissioning and demolition of the existing cremators is covered in the
EIA Study, the Applicant shall also address in the EIA the issues stated in
Appendix A to this Study Brief related to the decommissioning element.
3.3.3 If
the Applicant confirms that
environmental impacts of the decommissioning and demolition of the existing
cremators is not covered in the EIA Study, the Applicant shall provide information on the future plan on the existing
cremators, including any plan on the assessment of the environmental impacts of
the decommissioning project.
3.4 Description
of Siting, Layout, Design and Construction Methods Considered
3.4.1 The existing operation of the
Diamond Hill Crematorium which is located in the urban area surrounded by many
residential developments is of concern to the public. There have been environmental complaints against the smoke
and odour emissions from the cremators.
In addition, several schools located close to the Crematorium are
currently under construction.
3.4.2 Given the general public・s
concerns on the existing location of the Crematorium, while the Project Profile
stated that the Project would provide cremators of advance technology, the
Applicant shall state the justifications for continually using the proposed site
for the reprovisioning proposal.
3.4.3 The Applicant shall also describe
the consideration given to other possible layout(s) within the proposed site,
available technology options for the new cremators, and alternative
construction method to minimise excessive nuisances during the construction
stage of the Project. In
particular, such considerations should cover the potential environmental
impacts to nearby existing and planned sensitive receivers when different
layout, technology or construction method are used. The Applicant shall state the justifications for the
selecting the proposed layout, technology and construction method.
Technical Requirements
3.5 The
Applicant shall conduct the EIA study to address all environmental aspects of
the works and activities as described in the scope as set out above.
3.6 The EIA
study shall include the following technical requirements on specific impacts.
3.6.1 Air Quality Impact
3.6.1.1 The Applicant shall follow the criteria and guidelines
for evaluating and assessing air quality impact as stated in section 1 of Annex
4 and Annex 12 of the TM respectively.
3.6.1.2 The
assessment area for air quality impact shall be defined by a distance of 500 m
from the boundary of the project site, yet it may be extended depending on the
circumstances and the scale of the project.
3.6.1.3 The
Applicant shall assess the air pollutant concentrations making reference to the
relevant sections of the air modelling guideline in Appendices B-1 to B-4 to
this EIA Study Brief, or other methodology as agreed by the Director. The Applicant shall make reference to
the Guidelines with respect to construction dust impacts, cumulative
construction dust impact and stack emissions evaluation. In consideration of construction dust
impact, the Applicant shall make reference to the Fugitive Dust Model (FDM) in
Appendixes B-1 and B-3; in consideration of cumulative construction dust
impact, the Applicant shall make reference to the FDM in Appendixes B-1, B-2
and B-3; in consideration of stack emissions evaluation, the Applicant shall
make reference to the Industrial Source Complex Dispersion Model (ISCST3) in
Appendixes B-1 and B-4.
3.6.1.4 The
air quality assessment shall cover the construction and operation of the
Project, and include the following:
Background
and analysis of activities
(i) Provide
background information relating to air quality issues relevant to the project,
e.g. description of the types of activities during construction stage of the project
such as site clearance, excavation, material handling and wind erosion that
will likely give rise to dust emissions and those activities during operation
stage of the project such as operation of the cremators that will give off
gaseous emissions.
(ii) Give
an account, where appropriate, of the consideration/measures that had been
taken into consideration in the planning of the project to abate the air
pollution impact. That is, the Applicant should state the considerations given
to the use of various potential construction methods/phasing programmes and
cremator technologies and modes of operation to minimise the constructional and
operational air quality impact respectively. For example, consideration should be given to the use of
gaseous fuel to reduce emissions during cremation.
(iii)
Present the background air quality levels
in the assessment area for the purpose of evaluating the cumulative
constructional and operational air quality impacts. Also compare and present the anticipated improvements over
the existing level in terms of air emission data.
Identification
of ASRs and examination of emission/dispersion characteristics
(iv)
Identify and describe representative
existing and planned/committed air sensitive receivers (ASRs) that would likely
be affected by the project, including those earmarked on the relevant Outline
Zoning Plans, Development Permission Area Plans, Outline Development Plans and
Layout Plans. The Applicant shall select the assessment points of the
identified ASRs such that they represent the worst impact point of these ASRs.
A map showing the location and a description including the name of the
buildings, their uses and height of the selected assessment points shall be
given. The separation distances of these ASRs from the nearest emission sources
should also be given. Please also
note that the proposed Diamond Hill No. 2 Fresh Water Service Reservoir has
been planned for construction in the near future and would be about 150 meters
from the proposed new crematorium.
(v)
Provide an exhaustive list of air
pollutant emission sources, including any nearby emission sources which are
likely to have impact on the project based on the analysis of the
constructional and operational activities of the project in (i) above. Examples of constructional stage
emission sources include stock piling, concrete batching, etc. Examples of
operational stage emission sources include cremators, any nearby industrial
source, etc. Confirmation of the validity of the assumptions and the magnitude
of the activities (e.g. volume of construction materials handled etc.) shall be
obtained from the relevant government department/authorities and documented.
Constructional
air quality impact
(vi) The
Applicant shall follow the requirements of the Air Pollution Control (Construction
Dust) Regulation in dust control to ensure construction dust impacts are
controlled within the relevant standards as stipulated in section 1 of Annex 4
of the TM. An audit and monitoring program during constructional stage shall be
initiated to verify the effectiveness of the control measures and to ensure
that the construction dust levels be brought under control.
(vii)
If the Applicant anticipates a
significant construction dust impact that will likely cause exceedance of the
recommended limits in the TM at the ASRs despite incorporation of the dust
control measures stated in (vi) above, a quantitative assessment should be
carried out to evaluate the construction dust impact at the identified ASRs
based on the emission strength of the emission sources identified in (v) above.
The Applicant shall follow (x) to (xiii) below when carrying out the
quantitative assessment.
Operational
air quality impact
(viii)
In addition to preparing a list of emission
sources required in (v) above, the Applicant shall state the target emission
levels for the cremators, and compare them with the standards specified in the
latest set of Guidance Note on the Best Practicable Means for Crematoria issued
by the Air Management Group of EPD, and other relevant overseas standards. The target emission levels, including
but not limited to that for dioxin, should be agreed with the Director prior to
the carrying out of the quantitative assessment on operational air quality
impact.
(ix)
The Applicant shall calculate the
expected air pollutant concentrations at the identified ASRs. Calculations for
the expected impact shall be based on an assumed reasonably worst case scenario
under normal operating conditions and during the testing stage of the new
cremators. Special attention shall
be placed on the testing stage of the new cremators when there is potential for
both the existing and new cremators being operated and emitting air pollutants
concurrently. The evaluation shall
be based on the strength of the emission sources identified in (v) and (viii)
above. The Applicant shall follow (x) to (xiii) below when carrying out the
quantitative assessment.
Quantitative
Assessment Methodology
(x)
The Applicant shall apply the general
principles, where applicable, enunciated in the modeling guidelines in
Appendices B1 to B-4 while making allowance for the specific characteristic of
the Project. This specific methodology must be documented in such level of
details (preferably with tables and diagrams) to allow the readers of the
assessment report to grasp how the model is set up to simulate the situation at
hand without referring to the model input files. Details of the calculation of
the emission rates of air pollutants and a map showing the emission sources and
the identified ASRs for input to the modeling shall be presented in the report.
The Applicant must ensure consistency between the text description and the
model files at every stage of submission. In case of doubt, prior agreement
between the Applicant and the Director on the specific modelling details should
be sought.
(xi)
The Applicant shall identify the
key/representative air pollutant parameters (types of pollutants and the
averaging time concentration) to be evaluated and provide explanation for
choosing these parameters for the assessment of the impact of the project. Among the identified parameters,
emissions such as toxic air pollutants (including but not limited to dioxins)
and odour (if any) shall be included.
(xii)
The Applicant shall calculate the
cumulative air quality impact at the identified ASRs and compare these results
against the criteria set out in section 1 of Annex 4 in the TM. The predicted
air quality impacts (both unmitigated and mitigated) shall be presented in the
form of summary table and pollution contours, for comparison with relevant air
quality standards and examination of the land use implications of these
impacts. Plans of suitable scale should be used for presentation of pollution
contour for determining buffer distances required. In order to get a full picture of air emissions in
particular dioxins from the proposed Project, an inventory figure (in g
I-TEQ/year) should be estimated and presented.
Mitigating measures for non-compliance
(xiii)
The Applicant shall propose remedies and
mitigating measures where the predicted air quality impact exceeds the criteria
set in section 1 of Annex 4 in the TM. These measures and any constraints on
future land use planning shall be agreed with the relevant government
departments/authorities and documented. The Applicant shall demonstrate
quantitatively that the resultant impacts after incorporation of the proposed
mitigating measures will comply with the criteria stipulated in section 1 of Annex
4 in the TM.
Submission of model files
(xiv)
All input and output file(s) of the model
run(s) shall be submitted to the Director in electronic format.
3.6.2 Land Contamination Impact
& Waste Management
Land Contamination Prevention
3.6.2.1To prevent contamination
problems from arising in future, the Applicant shall:
(i) identify
the possible sources of contamination, including but not limited to dioxin, in
their operations; and
(ii) formulate
appropriate operational practices, waste management strategies and
precautionary measures for prevention of contamination problems.
Waste
Management Implications
3.6.2.2 The Applicant shall follow the criteria and
guidelines for evaluating and assessing waste management implications as stated
in Annexes 7 and 15 of the TM, respectively.
3.6.2.3 The assessment of waste management implications
shall cover the following:
(i)
Analysis of Activities and Waste
Generation
(a) The
Applicant shall identify the quantity, quality and timing of the waste arising
as a result of the construction and operation activities, based on the sequence
and duration of these activities.
(ii)
Proposal for Waste Management
(a) Prior
to considering the disposal options for various types of wastes, opportunities
for reducing waste generation and on-site or off-site re-use shall be fully
evaluated. Measures which can be
taken in the planning and design stages e.g. by modifying the design approach
and in the construction stage for maximising waste reduction shall be
separately considered.
(b) Having
taken into account all the opportunities for reducing waste generation and
maximising reuse, the types and quantities of the wastes required to be
disposed of as a consequence shall be estimated and the disposal options for
each type of waste described in detail.
The disposal method recommended for each type of wastes shall take into
account of the result of the assessment in section (c) below.
(c) The
impact caused by handling (including labeling, packaging & storage),
collection, and disposal of wastes shall be addressed in detail and appropriate
mitigation measures proposed. This
assessment shall cover the following areas:
(i) potential
hazard;
(ii)
air & odour emission;
(iii) noise;
(iv) wastewater
discharge;
(v) public
transport.
3.6.3 Visual Impact
3.6.3.1 The Applicant shall follow the
criteria and guidelines for evaluating and assessing visual impact as stated in
section 1 of Annex 10 and in Annex 18 of the TM, respectively. The assessment shall also cover all
items classified as Designated Projects under Schedule 2 of the EIAO. Both
construction and operational impacts shall be assessed. In particular, the transition stage
where both the existing and new crematoriums co-exist shall be covered.
3.6.3.2 The assessment area for the visual
impact assessment shall be defined by the visual envelope of the project.
3.6.3.3 The Applicant shall review relevant
outline development plans, outline zoning plans, layout plans, other published
land use plans, planning briefs, studies and guidelines on landscape framework,
urban design concept, designated view corridors, open space network and
landscape links that may affect the appreciation of the project. The aim is to gain an insight to the
future outlook of the area affected so as to assess whether the project can fit
into surrounding setting. Any
conflict with published land use plan(s) should be highlighted and appropriate
follow-up action should be recommended.
3.6.3.4 The Applicant shall assess the
visual impacts of the proposed development. In particular, the cumulative visual impacts of the existing
and proposed crematorium shall be assessed and taken into account in the
formulation of mitigation measures and the assessment of residual impacts. As
some nearby sensitive receivers have direct line of sight to the site,
mitigation measures such as proper landscape screening shall be provided. The visual impact assessment shall
include the following:
(i) identification
and plotting of visual envelope of the project within the assessment area;
(ii) identification
of the key groups of sensitive receivers within the visual envelope and their
views at both ground level and elevated vantage points;
(iii) description
of the visual compatibility of the project with the surrounding, and the
planned setting and its obstruction and interference with the key views of the
adjacent areas; and
(iv) the
severity of visual impacts in terms of nature, distance and number of sensitive
receivers. The visual impacts of
the project with and without mitigation measures shall also be included so as
to demonstrate the effectiveness of the proposed mitigation measures.
3.6.3.5 Alternative layout, design and
construction method that would avoid or reduce the identified visual impacts
shall be evaluated for comparison before adopting other mitigation or
compensatory measures to alleviate the impacts. The mitigation measures proposed shall not only be concerned
with damage reduction but should also include consideration of potential
enhancement of existing visual quality.
The Applicant shall recommend mitigation measures to minimise the
adverse effects identified above, including provision of a landscape design.
3.6.3.6 The mitigation measures shall
include provision of screen planting, revegatation of disturbed land,
compensatory planting, provisioning of amenity areas, design of structures,
provision of finishes to structures, colour scheme and texture of material used
and any measures to mitigate the impacts on existing land use. Parties shall be identified for the on
going management and maintenance of the proposed mitigation works to ensure
their effectiveness throughout the operation phase of the project. A practical programme and funding
proposal for the implementation of the recommended measures shall be provided.
3.6.3.7 Annotated illustration materials
such as coloured perspective drawings, plans and section/elevation diagrams,
photographs taken at vantage points, and computer-generated photomontage shall
be adopted to fully illustrate the visual impacts of the project to the
satisfaction of the Director. The
Applicant shall record the technical details in preparing the illustration that
may need to be submitted for verification of accuracy of the illustrations.
3.6.4 Hazard to Life
The
Applicant shall state the fuel for cremation process of the Project. If fuel gas is used, the Applicant
shall confirm that it is provided by direct fuel gas pipeline and there will be
no on-site storage of the fuel gas.
For other non-fuel gas dangerous goods (DG) defined in the Dangerous
Goods Ordinance (Cap. 295) but not covered by the Gas Safety Ordinance (Cap.
51), the Applicant shall confirm that the storage quantity would be similar to
that in the existing crematorium or petrol filling stations and that the
storage will comply with FSD・s safety requirements.
3.6.5 Noise Impact
3.6.5.1 The Applicant shall follow the
criteria and guidelines for evaluating and assessing noise impact as stated in
Annexes 5 and 13 of the TM respectively.
3.6.5.2 The noise impact assessment shall
include the followings:
(i)
Determination
of Assessment Area
The
noise impact assessment shall include all areas within 300m from the project boundary.
Subject to the agreement of the Director, the assessment area could be reduced
accordingly if the first layer of noise sensitive receivers, closer than 300m
from the project boundary, provides acoustic shielding to those receivers
located further away.
(ii)
Provision
of Background Information
The
Applicant shall provide all background information relevant to the project
including relevant previous and current studies. Unless involved in the
planning standards, no existing noise levels are particularly required.
(iii)
Identification
of Noise Sensitive Receivers
(a) The
Applicant shall refer to Annex 13 of the TM when identifying the noise
sensitive receivers (NSRs). The NSRs shall include all existing ones and all
planned or committed noise sensitive developments and uses earmarked on the
relevant Outline Zoning Plans, Outline Development Plans and Layout Plans.
(b) The
Applicant shall select assessment points to represent all identified NSRs for
carrying out quantitative noise assessment described below. The assessment
points shall be agreed with the Director prior to the quantitative noise
assessment. A map showing the location and description including name of
building, use, and floors of each and every selected assessment point shall be
given.
(iv)
Provision
of an Emission Inventory of the Noise Sources
The
Applicant shall provide an inventory of noise sources including construction
equipment for construction and demolition noise assessment and fixed plant
equipment for operational noise assessment. Confirmation of the validity of the
inventory shall be obtained from the relevant government
departments/authorities.
(v)
Construction
/ Demolishing Noise Assessment
(a) The
Applicant shall carry out assessment of noise impact from construction
(excluding percussive piling) of the project during day time, i.e. 7 a.m. to 7
p.m., on weekdays other than general holidays in accordance with the
methodology stipulated in paragraphs 5.3. and 5.4 of Annex 13 of the TM. The
criteria in Table 1B of Annex 5 of the TM shall be adopted in the assessment.
(b)
To minimize
the construction noise impact, alternative construction methods to replace
percussive piling shall be proposed as far as practicable.
(c)
If the
unmitigated construction noise levels are found to exceed the relevant criteria,
the Applicant shall propose practicable direct mitigation measures (including
movable barriers, enclosures, quieter alternative methods, re-scheduling and
restricting hours of operation of noisy task(s) to minimize the impact. If the mitigated noise levels still
exceed the relevant criteria, the duration of the noise exceedance shall be
given.
(d) In case the Applicant would like to evaluate whether construction works in restricted hours as defined under the Noise Control