Environmental Impact Assessment Ordinance (Cap. 499), Section 5 (7)
Environmental Impact Assessment Study Brief No. ESB-110/2003
Project Title : |
Hong Kong ¡V Zhuhai ¡V Macao Bridge |
Hong Kong Section and North Lantau |
|
Highway Connection |
|
(hereinafter known as the "Project") |
Name of Applicant : |
Highways Department, the Government of the Hong Kong Special Administrative Region |
| (hereinafter known as the "Applicant") |
1. BACKGROUND
1.1 An application (No. ESB-110/2003) for an Environmental Impact Assessment (EIA) study brief under section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by the Applicant on 8 October 2003 with a project profile (No. PP-201/2003) (the Project Profile).
1.2 The scope of the Project is to provide the ¡§Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB) Hong Kong Section (HKS) and North Lantau Highway Connection (NLHC)¡¨ (the Project), a dual-3 lane highway from the boundary of the Hong Kong Special Administrative Region (HKSAR) to the North Lantau Highway, as shown in Appendix A and described below :
(i) A highway of about 5km in length between the HKSAR boundary and the landing point at Northwest Lantau, named as HZMB HKS, which is tentatively planned to be constructed as trestle bridge structures. At the western end of this section of highway, it will be connected to the HZMB Zhujiang Section (ZS) at the Mainland/HKSAR boundary.
(ii) Another highway of about 5km in length, with link roads, between the landing point and the North Lantau Highway, named as NLHC, which is tentatively planned to be constructed as either in (a) bored tunnel from the landing point to the east tunnel portal near the Airport Channel (for Alignment 1 as shown in Appendix A) or (b) trestle bridge structures crossing the Airport Channel and as elevated road and bridge structure on the Airport Island or along the Airport Channel (for Alignment 2 as shown in Appendix A).
(iii) The connection to the North Lantau Highway at the Airport Island is only an initial proposal. In the longer term and depending on the future traffic growth, the highway will be extended across the waters east of the Airport Island and then connect to North Lantau Highway near Tai Ho.
(iv) There will be refinement of the highway alignment within the tentative study envelope as shown in Appendix A.
1.3 Pursuant to section 5(7)(a) of the EIAO, the Director of Environmental Protection (the Director) issues this EIA study brief to the Applicant to carry out an EIA study.
1.4 The purpose of this EIA study is to provide information on the nature and extent of environmental impacts arising from the construction and operation of the Project and related activities that take place concurrently. This information will contribute to decisions by the Director on :
(i)the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project and the associated activities of the Project;
(ii)the conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and
(iii)the acceptability of residual impacts after the proposed mitigation measures are implemented.
2. OBJECTIVES OF THE EIA STUDY
2.1 The objectives of the EIA study are as follows :
(i)to describe the Project and associated works together with the requirements for carrying out the Project;
(ii) to identify and describe elements of community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including natural and man-made environment and the associated environmental constraints;
(iii) to provide information on the consideration of alternatives to avoid and minimize the potential environmental impacts to the ecological sensitivity areas in Lantau Island and other sensitive uses; to compare the environmental benefits and dis-benefits of each of the different options; to provide reasons for selecting the preferred option(s) and to describe the part of environmental factors played in the selection;
(iv)to identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potential affected uses;
(v) to identify and quantify any potential landscape and visual impacts and to propose measures to mitigate these impacts;
(vi) to identify and quantify any potential losses or damage to flora, fauna and natural habitats and to propose measures to mitigate these impacts;
(vii)to identify any negative impacts on site of cultural heritage and to propose measures to mitigate these impacts;
(viii) to propose the provision of mitigation measures so as to minimize pollution, environmental disturbance and nuisance during construction and operation of the Project;
(ix) to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;
(x)to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to the sensitive receivers and potential affected uses;
(xi)to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels;
(xii)to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification; and
(xiii)to design and specify environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.
3. DETAILED REQUIREMENTS OF THE EIA STUDY
3.1 The Purpose
The purpose of this study brief is to scope the key issues of the EIA study. The Applicant has to demonstrate in the EIA report that the criteria in the relevant sections of the Technical Memorandum on the Environmental Impact Assessment Process of the Environmental Impact Assessment Ordinance (hereinafter referred to as ¡§the TM¡¨) are fully complied with.
3.2 The Scope
The scope of this EIA study shall cover the Project mentioned in sub-section 1.2 above. Information on the potential impacts on the environment within the HKSAR boundary arising from any associated works of the Project outside the HKSAR boundary, and in combination with those impacts arising from the Project, shall also be provided to facilitate the Director¡¦s consideration on the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project. The EIA study shall address the likely key issues described below, together with any other key issues identified during the course of the EIA study :
(i) the potential water quality impact caused by dredging, piling, fill extraction, filling and any other marine works activities during construction, in particular the potential release of toxic contaminants, and as a result of changes to the flow regime, flushing capacity, and water quality in Hong Kong waters during operation of the Project;
(ii) the potential impact on the hydrodynamic effects and water quality in the Airport Channel and Tung Chung Bay arising from the construction of the bridge piers and any reclamation for highway interchanges across the channel between the Airport Island and Lantau Island; as well as the potential water quality impact on Tai Ho Bay and Tai Ho streams arising from the construction of the Project;
(iii) the potential water quality impact caused by the disposal of the storm-water runoff from the highway during the operation of the Project;
(iv) the potential impact to the ecological sensitive areas, including the following and any other sensitive areas that may be identified during the course of the EIA study:
(a) the vicinities along the marine portion of the Project which are frequented by the Chinese White Dolphins;
(b) the Sites of Special Scientific Interest (SSSI) at San Tau Beach and Tai Ho on Lantau;
(c) the nursery and breeding grounds for horseshoe crabs along the northwestern Lantau coastline;
(d) the proposed Lantau North (Extension) Country Park;
(e) Sha Chau and Lung Kwu Chau Marine Park;
(f) Scenic Hill on Airport Island which might support a remnant population of the Romer¡¦s Tree Frog;
(g) Mai Po and Inner Deep Bay Ramsar Site;
(h) the potential marine parks at southwestern Lantau.
(v) the potential aquatic and terrestrial ecological impacts arising from the construction and operation of the Project, including loss of habitats and disturbance to wildlife;
(vi) the potential impacts on the local erosion and sedimentation patterns in northwestern Lantau and Deep Bay, including the mudflats in San Tau and in Deep Bay, during the construction and operation of the Project;
(vii) the potential fisheries impacts on capture and culture fisheries during the construction and operation of the Project, including the potential loss of fishing grounds, spawning and nursery grounds of fish and shrimp, impacts on oyster farming in Deep Bay;
(viii) the potential noise and air pollution impacts to sensitive receivers during the construction and operation of the Project;
(ix) the potential landscape and visual impacts caused by highway structures on existing and planned sensitive receivers, in particular, on residents of Tung Chung, visitors on the Airport Island, Tung Chung Cable Car passengers and villagers in the vicinity of the Project such as Sham Shek Tsuen, San Shek Wan, Sha Lo Wan Tsuen, Tin Sam, San Tau and Tai Ho Valley, during the construction and operation of the Project;
(x) the potential impacts on sites of cultural heritage likely to be affected by the construction works of the Project, in particular on archaeological sites at San Shek Wan, Sha Lo Wan, Sha Lo Wan (West), San Tau, Ha Law Wan and Tai Ho;
(xi) the potentialimpacts of various types of wastes to be generated from the construction and operation of the Project, in particular the excavated materials from constructing the bridge on land, the dredged sediment when constructing the bridge structures in marine waters and, any other construction waste and chemical waste to be generated from the construction and operation of the Project; and
(xii) the potential cumulative environmental impacts of the Project, through interaction or in combination with other existing, committed and planned developments in the vicinity of the Project, and that those impacts may have a bearing on the environmental acceptability of the Project. Consideration shall be given to account for the impacts from likely concurrent projects such as the Phases III & IV of the North Lantau Development, the Tung Chung ¡V Ngong Ping Cable Car, the New Contaminated Mud Disposal Facility at Airport East, the Tonggu Channel of Shenzhen Port, the 132 kV overhead pole & underground cables from Tung Chung Town Substation to Cheung Sha Substation, the future Road P1 at North Lantau, the future development on the Airport Island, the proposed submarine gas pipeline system from Tuen Mun to Tung Chung and associated offtake and pigging station at Chek Lap Kok (as detailed in Project Profile No. PP-199/2003) and the Zhujiang Section of the Hong Kong ¡V Zhuhai ¡V Macao Bridge, in particular the consequential effect in Hong Kong waters due to the overall changes to flow regime and flushing capacity at Pearl River Estuary.
3.3 Consideration of Alternative Alignment Options and Construction Methods
3.3.1 The Need of the Project
The Applicant shall study and review the need of the Project as outlined in sub-section 1.2 above, and provide information/proof to justify the need. The Applicant shall explain clearly the purpose and objectives of the Project and describe the scenarios with and without the Project.
3.3.2 Consideration of Different Alignment Options and Built-forms
In addition to the proposed alignment options mentioned in sub-section 1.2 above, the Applicant shall consider other feasible alignment options for the Project, taking on board the relevant findings of those options already addressed in the previous studies. Alternative built-form (such as tunnel) and design of the highway shall also be reviewed and investigated. A comparison of the environmental benefits and dis-benefits of possible alignment options and alternative built-forms and design shall be made with a view to recommending the preferred option to avoid adverse environmental impact on the Lantau Island to the maximum practicable extent. In particular, consideration shall be given to avoid or minimize the disturbance to the ecosystems close to the landing points and where the bridge connects to the North Lantau Highway, including inter-tidal zone and mudflats, along the northwestern Lantau coastline, and to maximize the setback from the aviation fuel storage at Chek Lap Kok Airport so as to minimize the potential hazard impacts to the Project.
3.3.3 Consideration of Alternative Construction Methods and Sequences of Works
Having regard to the cumulative effects of the construction period and the severity of the construction impacts to the affected sensitive receivers, the EIA study shall explore alternative construction methods (including those indicated in the Project Profile and other possible methods to be investigated during the course of the EIA study) and sequences of works for the Project, with a view to avoiding prolonged adverse environmental impacts to the maximum practicable extent. A comparison of the environmental benefits and dis-benefits of applying different construction methods and sequence of works shall be made.
3.3.4 Selection of Preferred Scenario
Taking into consideration the findings resulting from sub-sections 3.3.2 and 3.3.3 above, the Applicant shall recommend/justify the selection of the preferred scenario that will avoid or minimize adverse environmental effects arising from the Project, and adequately describe the part that environmental factors played in arriving at the final selection.
3.4 Technical Requirements
The Applicant shall conduct the EIA study to address all environmental aspects as described in sub-sections 3.1, 3.2 and 3.3 above. The EIA study shall include the following technical requirements on specific impacts.
3.4.1 Air Quality Impact
3.4.1.1 The Applicant shall follow the criteria and guidelines for evaluating and assessing air quality impact as stated in section 1 of Annex 4 and Annex 12 of the TM, respectively.
3.4.1.2 The study area for air quality impact assessment shall generally be defined by a distance of 500 metres from the boundary of the project site; with consideration be given to extend the area to include major emission sources that may have a bearing on the environmental acceptability of the Project. It will have to includeareas where the air quality may be potentially affected by the Project, in particular areas close to the road network affected by traffic generated from this Project. Such assessment shall be based on the best available information at the time of the assessment. In particular, the assessment shall take into account the impacts of major emission sources from the Black Point Power Station, Castle Peak Power Station and Chek Lap Kok Airport. The emissions from associated works of the Project shall also be included in determining the cumulative impacts. Besides, if the likely concurrent projects as mentioned in sub-section 3.2 (xii) above and any other concurrent projects are identified relevant during the course of the EIA study, its possible emissions shall also be taken into account in the air quality impact assessment.
3.4.1.3 The Applicant shall assess the construction dust impact arising from the land based works of the Project and the exhaust emission impacts from the vehicles, tunnel portals and vent shafts, if any, during operation of the Project with reference to the relevant sections of the guidelines in Appendices B-1 to B-3, or other methodology as agreed by the Director. The Applicant shall note that the ¡§Odour Impact¡¨ in sub-section 3.8 of Appendix B-1 is unlikely to be relevant to this Project unless there are major changes in the Project or circumstances during the course of this EIA study.
3.4.1.4 The air quality impact assessment shall include the following:
(i) Background and Analysis of Activities
(a)Provide background information relating to air quality issues relevant to the Project, e.g. description of the types of activities of the Project that may affect air quality during both construction and operation stages.
(b)Give an account, where appropriate, of the consideration/measures that had been taken into consideration in the planning of the Project to abate the air pollution impact. That is, the Applicant shall consider alternative construction methods/phasing programmes and alternative modes of operation to minimize the constructional and operational air quality impact respectively.
(c)Present the background air quality levels in the assessment area for the purpose of evaluating the cumulative constructional and operational air quality impacts.
(ii) Identification of Air Sensitive Receivers (ASRs) and Examination of Emission/Dispersion Characteristics
(a)Identify and describe representative existing and planned/committed ASRs that would likely be affected by all identified potential adverse environmental impacts arising from the Project, both on-site and off-site, including those earmarked on the relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans. The Applicant shall select assessment points of the identified ASRs that represent the worst impact point of these ASRs. A map clearly showing the locations and descriptions such as names of buildings, uses and heights of the selected assessment points shall be given. The separation distances of these ASRs from the nearest emission sources shall also be given.
(b)Provide an exhaustive list of air pollutant emission sources, including any nearby emission sources which are likely to have impact related to the Project based on the analysis of the constructional and operational activities in sub-section 3.4.1.4(i)(a) above. Examples of construction stage emission sources include stock piling, blasting, concrete batching, marine construction plant and vehicular movements on unpaved haul roads on site, etc. Examples of operational stage emission sources include exhaust emissions from vehicles, tunnel portals and vent shafts, etc. Confirmation regarding the validity of the assumptions adopted and the magnitude of the activities (e.g. volume of construction material handled, traffic mix and volume on a road etc.) shall be obtained from the relevant government departments/authorities and documented.
(iii) Construction Phase Air Quality Impact
(a)The Applicant shall follow the requirements stipulated under the Air Pollution Control (Construction Dust) Regulation to ensure that construction dust impacts are controlled within the relevant standards as stipulated in section 1 of Annex 4 of the TM. A monitoring and audit programme for the construction phase shall be devised to verify the effectiveness of the control measures proposed so as to ensure proper construction dust control.
(b)If the Applicant anticipates that the Project will give rise to significant construction dust impacts likely to exceed the recommended limits in the TM at the ASRs despite the incorporation of the dust control measures proposed in accordance with sub-section 3.4.1.4(iii)(a) above, a quantitative assessment should be carried out to evaluate the construction dust impact at the identified ASRs. The Applicant shall follow the methodology set out in sub-section 3.4.1.4(v) below when carrying out the quantitative assessment.
(iv) Operational Phase Air Quality Impact
(a) The Applicant shall calculate the expected air pollutant concentrations at the identified ASRs based on an assumed reasonably worst-case scenario under normal operating conditions. The evaluation shall be based on the strength of the emission sources identified in sub-section 3.4.1.4(ii)(b) above. The Applicant shall follow sub-section 3.4.1.4(v) below when carrying out the quantitative assessment.
(b) The air pollution impacts of future road traffic shall be calculated based on the highest emission strength from road vehicles within the next 15 years upon commencement of operation of the proposed road. The Applicant shall demonstrate that the selected year of assessment represents the highest emission scenario given the combination of vehicular emission factors and traffic flow for the selected year. The Applicant shall also take into account the different fuel standards between Hong Kong and the Mainland as well as in Macao, and assess the resultant implications on road traffic air pollution impacts to Hong Kong. The Fleet Average Emission Factors used in the assessment shall be agreed with the Director. All the traffic flow data and assumptions that used in the assessment shall be clearly and properly documented in the EIA report.
(c) If vehicular tunnels and/or full enclosures are to be proposed in the Project, it is the responsibility of the Applicant to ensure that the air quality inside these proposed structures shall comply with EPD's "Practice Note on Control of Air Pollution in Vehicle Tunnels". When assessing air quality impact due to emissions from tunnels/full enclosures, the Applicant shall ensure prior agreement with the relevant tunnel ventilation design engineer over the amount and the types/kinds of pollutants emitted from these tunnel/full enclosures; and such assumptions shall be clearly and properly documented in the EIA report.
(v) Quantitative Assessment Methodology
(a)The Applicant shall apply the general principles enunciated in the modelling guidelines in Appendices B1 to B3 while making allowance for the specific characteristic of the Project. This specific methodology must be documented in such level of details, preferably assisted with tables and diagrams, to allow the readers of the EIA report to grasp how the model has been set up to simulate the situation under study without referring to the model input files. Detailed calculations of air pollutants emission rates for input to the modelling shall be presented in the EIA report. The Applicant must ensure consistency between the text description and the model files at every stage of submissions for review. In case of doubt, prior agreement between the Applicant and the Director on the specific modelling details should be sought.
(b) The Applicant shall identify the key/representative air pollutant parameters (types of pollutants and the averaging time concentrations) to be evaluated and provide explanation for selecting such parameters for assessing the impact from the Project.
(c) The Applicant shall calculate the overall cumulative air quality impact at the ASRs identified under sub-section 3.4.1.4 (ii) above and compare these results against the criteria set out in section 1 of Annex 4 in the TM. The predicted air quality impacts (both unmitigated and mitigated) shall be presented in the form of summary table(s) and pollution contours, to be evaluated against the relevant air quality standards and on any effect they may have on the land use implications. Plans of a suitable scale should be used to present pollution contours to allow buffer distance requirements to be determined properly.
(d) If there is any direct technical noise remedy recommended in the study, its air quality implication shall be assessed. For instance, if barriers that may affect dispersion of air pollutants are proposed, then the implications of such remedies on air quality impact shall be assessed. If tunnel or noise enclosures are proposed, then portal emissions of the tunnel/enclosed road sections and air quality inside the tunnel/enclosed road sections shall also be addressed. The Applicant shall highlight clearly the locations and types of agreed noise mitigating measures (where applicable), be they barriers, tunnel/road enclosure and their portals, and affected ASRs, on the contour maps for easy reference.
(vi) Mitigation Measures for Non-compliance
The Applicant shall propose remedies and mitigating measures where the predicted air quality impact exceeds the criteria set in section 1 of Annex 4 in the TM. These measures and other associated constraints on future land use planning shall be agreed with the relevant government departments/authorities and be clearly documented in the EIA report. The Applicant shall demonstrate quantitatively that the resultant impacts after incorporation of the proposed mitigating measures will comply with the criteria stipulated in section 1 of Annex 4 in the TM.
(vii) Submission of Model Files
All input and output file(s) of the model run(s) shall be submitted to the Director in electronic format.
3.4.2 Noise Impact
3.4.2.1The Applicant shall follow the criteria and guidelines for evaluating and assessing both the construction and operational noise impacts arising from the Project as stated in Annexes 5 and 13 of the TM, respectively.
3.4.2.2The noise impact assessment shall include the following :
(i) Determination of Assessment Area
The study area for the noise impact assessment shall generally include all areas within 300m from the Project shown in Annex A of the Project Profile (No. PP-201/2003). Subject to the agreement of the Director, the assessment area could be reduced accordingly if the first layer of noise sensitive receivers (NSRs), closer than 300m from the outer project limit, provides acoustic shielding to those receivers at further distance behind. Similarly, subject to the agreement of the Director, the assessment area shall be expanded to include NSRs at distance >300m which would be affected by the construction and operation of the Project.
(ii) Provision of Background Information and Existing Noise Levels
(a) The Applicant shall provide all background information relevant to the Project, including relevant previous or current studies. Unless required for determining the planning standards, such as those for planning of fixed noise sources, no existing noise levels are required except as set out below.
(b) For ground-borne noise impact, the background information and existing noise levels shall be measured and described in a way sufficient for identification and prediction of noise impacts, and for formulation of noise criteria. Where necessary, baseline noise surveys shall be carried out to determine the existing noise conditions inside NSRs likely to be affected during the construction and operation of the Project. The type and duration of baseline surveys shall be such that there will be adequate information taking account of natural variation to define the existing conditions. Where appropriate, results from relevant past studies should be used.
(iii) Identification of Noise Sensitive Receivers
(a) The Applicant shall refer to Annex 13 of the TM when identifying the NSRs. The NSRs shall include all existing NSRs and all planned/committed noise sensitive developments and uses earmarked on the relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans. Photographs of all existing NSRs shall be appended to the EIA report.
(b)The Applicant shall select assessment points to represent all identified NSRs for carrying out quantitative noise assessment described below. The assessment points shall be agreed with the Director prior to the quantitative noise assessment. A map showing the location and description such as name of building, use, and floors of each and every selected assessment point shall be given. For planned noise sensitive land uses without committed site layouts, the Applicant should use the relevant planning parameters to work out representative site layouts for operational noise assessment purpose.
(iv) Provision of an Emission Inventory of the Noise Sources
The Applicant shall provide an inventory of noise sources including representative construction equipment for construction noise assessment such as for tunnelling and other construction works, and traffic flow/fixed plant equipment, as appropriate, for operational noise assessment. Confirmation on the validity of the inventory shall be obtained from the relevant government departments/authorities and documented.
(v) Construction Noise Assessment
(a) The assessment shall cover the cumulative noise impacts due to the construction works of the Project and other likely concurrent projects as mentioned in sub-section 3.2 (xii) above and any other relevant concurrent projects identified during the course of the EIA study.
(b) The Applicant shall carry out assessment of noise impact from construction (excluding percussive piling) of the Project during day time, i.e. 7 a.m. to 7 p.m., on weekdays other than general holidays in accordance with the methodology stipulated in paragraphs 5.3. and 5.4 of Annex 13 of the TM. The criteria in Table 1B of Annex 5 of the TM shall be adopted in the assessment.
(b) To minimize the construction noise impact, alternative construction methods to replace percussive piling shall be proposed as far as practicable. In case blasting works will be involved, it should be carried out, as far as practicable, outside the sensitive hours of 7 p.m. to 7 a.m. on Monday to Saturday and any time on a general holiday, including Sunday. For blasting that must be carried out during the above-mentioned sensitive hours, the noise impact in associated with the removal of debris and rocks should be fully assessed and adequate mitigation measures should be recommended to reduce the noise impact as appropriate.
(c) If tunnelling works will be involved, noise impact (including air-borne noise and structure-borne noise) associated with the operation of powered mechanical equipment, in particular, tunnel boring machine or equivalent, shall be assessed. If tunnel boring machine is used and it is likely that ground-borne noise will affect NSRs, the assessment criteria and methodology/model for ground-borne noise shall be agreed with the Director (with reference to sub-section 4.4.2(c) of the TM) prior to obtaining the empirical parameters required in the ground-borne noise model.
(d) If the unmitigated construction noise levels are found exceeding the relevant criteria, the Applicant shall propose practicable direct mitigation measures (including movable barriers, enclosures, quieter alternative methods, re-scheduling and restricting hours of operation of noisy task) to minimize the impact. If the mitigated noise levels still exceed the relevant criteria, the duration of the noise exceedance shall be given.
(e) The Applicant shall formulate a reasonable construction programme as far as practicable such that no work will be required in the restricted hours as defined under the Noise Control Ordinance (NCO). In case the Applicant needs to evaluate whether construction works in restricted hours as defined under the NCO are feasible or not in the context of programming construction works, reference should be made to the relevant technical memoranda issued under the NCO. Regardless of the results of the construction noise impact assessment for restricted hours, the Noise Control Authority will process the Construction Noise Permit (CNP) application, if necessary, based on the NCO, the relevant technical memoranda issued under the NCO, and the contemporary conditions/situations. This aspect should be explicitly stated in the noise chapter and the conclusions and recommendations chapter in the EIA report.
(vi) Operational Noise Assessment
(a) Road Traffic Noise
(a1) Calculation of Noise Levels
The Applicant shall analyse the scope of the proposed road alignment(s) to identify appropriate new and existing road sections for the purpose of traffic noise impact assessment. When an existing road section undergoes major modification which will directly result in 25% increase in lanes or substantial changes in alignment or characters (e.g. change to a high speed road) of the existing road, it shall be regarded as a new road for the purpose of this noise impact assessment. Figures showing extents of new roads and existing roads shall be provided in the EIA report.
The Applicant shall calculate the expected road traffic noise using methods described in the U.K. Department of Transport's ¡§Calculation of Road Traffic Noise¡¨ (1988). Calculations of future road traffic noise shall be based on the peak hour traffic flow in respect of the maximum traffic projection within a 15 years period upon commencement of operation of the proposed roadwork. The Applicant shall calculate traffic noise levels in respect of each road section and the overall noise levels from combined road sections (both new and existing) at NSRs. The EIA shall contain sample calculations and input parameters for 10 assessment points as requested by the Director. The Applicant shall prepare and provide drawings (i.e. road-plots of the traffic noise model) of appropriate scale to show the road segments, topographic barriers, and assessment points of sensitive receivers input into the traffic noise model.
The Applicant shall provide input data sets of traffic noise prediction model adopted in the EIA study as requested by the Director for the following scenarios:
(1)unmitigated scenario at assessment year;
(2)mitigated scenario at assessment year; and
(3)prevailing scenario for indirect technical remedies eligibility assessment;
The data shall be in electronic text file (ASCII format) containing road segments, barriers and noise sensitive receivers information. The data structure of the above file shall be agreed with the Director. CD-ROM(s) containing the above data shall be attached in the EIA report.
(a2)Presentation of Noise Levels
The Consultants shall present the existing and future noise levels in L10 (1 hour) at the NSRs on tables and plans of suitable scale.
A quantitative assessment at the NSRs for the proposed road alignments shall be carried out and compared against the criteria set out in Table 1A of Annex 5 of the TM. The potential noise impact of the Project shall be quantified by estimating the total number of dwellings, classrooms and other noise sensitive elements that will be exposed to noise levels exceeding the criteria set in Table 1A of Annex 5 in the Technical Memorandum.
(a3)Proposals for Noise Mitigation Measures
After rounding of the predicted noise levels according to the U.K. Department of Transport's ¡§Calculation of Road Traffic Noise¡¨ (1988), the Applicant shall propose direct technical remedies in all situations where the predicted traffic noise level exceeds the criteria set in Table 1A of Annex 5 in the TM by 1 dB(A) or more. Specific reasons for not adopting certain direct technical remedies in the design to reduce the traffic noise to a level meeting the criteria in the TM or to maximize the protection for the NSRs as far as possible should be clearly quantified and laid down. The total number of dwellings, classrooms and other noise sensitive element that will be benefited by the provision of direct technical remedies should be provided. In order to clearly present the extents/locations of the recommended noise mitigation measures, plans prepared from 1:1,000 or 1:2,000 survey maps showing the mitigation measures (e.g. enclosures/barriers, low noise road surfacing, etc.) shall be included in the EIA report.
The total number of dwellings, classrooms and other noise sensitive elements that will still be exposed to noise above the criteria with the implementation of all recommended direct technical remedies shall be quantified. The Applicant shall provide in the EIA report the information of the recommended noise mitigation measures (such as barrier types, nominal dimensions at different cross-sections, extents/locations, lengths, mPD levels of barriers) in electronic format as agreed by the Director.
In case where a number of the NSRs cannot all be protected by the recommended direct technical remedies, the Applicant shall identify and estimate the total number of existing dwellings, classrooms and other noise sensitive elements which may qualify for indirect technical remedies under the Executive Council directive ¡§Equitable Redress for Persons Exposed to Increased Noise Resulting from the Use of New Roads¡¨, the associated costs and any implications for such implementation. For the purpose of determining the eligibility of the affected premises for indirect technical remedies, reference shall be made to the following set of three criteria:
(1) the predicted overall noise level from the new road together with other traffic noise in the vicinity must be above a specified noise level (e.g. 70 dB(A) for domestic premises and 65 dB(A) for education institutions, all in L10(1hr));
(2) the predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level, i.e. the total traffic noise level existing before the works to construct the road were commenced; and
(3) the contribution to the increase in the predicted overall noise level from the new road must be at least 1.0dB(A).
(b) Fixed Noise Sources
If the Project will cause any fixed noise sources, such as the ventilation systems of the control centre and/or road tunnel, if any, the following assessment shall be followed.
(b1) Assessment of Fixed Source Noise Levels
The Applicant shall calculate the expected noise using standard acoustics principles. Calculations for the expected noise shall be based on assumed plant inventories and utilization schedule for the worst case scenario. The Applicant shall calculate the noise levels taking into account correction of tonality, impulsiveness and intermittency in accordance with the Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites.
(b2) Presentation of Noise Levels
The Applicant shall present the existing and future noise levels in Leq (30 min) at the NSRs at various representative floor levels (in m P.D.) on tables and plans of suitable scale.
A quantitative assessment at the NSRs for the proposed fixed noise source(s) shall be carried out and compared against the criteria set out in Table 1A of Annex 5 of the TM.
(b3) Proposals for Noise Mitigation Measures
The Applicant shall propose direct technical remedies within the project limits in all situations where the predicted noise level exceeds the criteria set out in Table 1A of Annex 5 of the TM to protect the affected NSRs.
(vii)Assessment of Side Effects and Constraints
The Applicant shall identify, assess and propose means to minimize any side effects and to resolve any potential constraints due to the inclusion of any recommended direct technical remedies.
(viii)Evaluation of Constraints on Planned Noise Sensitive Developments/Landuses
For planned noise sensitive uses which will still be affected even with all practicable direct technical remedies in place, the Applicant shall propose, evaluate and confirm the practicality of additional measures within the planned noise sensitive uses and shall make recommendations on how these noise sensitive uses will be designed for the information of relevant parties.
The Applicant shall take into account agreed environmental requirements / constraints identified by the study to assess the development potential of concerned sites which shall be made known to the relevant parties.
3.4.3 Water Quality Impact
3.4.3.1 The Applicant shall follow the criteria and guidelines for evaluating and assessing water pollution as stated in Annexes 6 and 14 of the TM respectively.
3.4.3.2 The study area for this water quality impact assessment shall cover the Deep Bay, North Western, North Western Supplementary, Western Buffer, Victoria Harbour, Southern, and Second Southern Supplementary Water Control Zones (as shown in Appendix C) as designated under the Water Pollution Control Ordinance (WPCO). This study area could be extended to include other areas such as stream courses and the associated water system if they are found also being impacted during the course of the EIA study and have a bearing on the environmental acceptability of the Project. The EIA study shall assess the water quality impacts due to the Project together with the Zhujiang section of the Hong Kong ¡V Zhuhai ¡V Macao Bridge.
3.4.3.3 The Applicant shall identify and analyse all physical, chemical and biological disruptions of marine, fresh water or ground water system(s), catchment area(s), stormwater pipeline and coastal water arising from the construction and operation of the Project.
3.4.3.4 The Applicant shall predict, quantify and assess any water quality impacts arising from the Project on the water system(s) and the sensitive receivers by appropriate mathematical modelling and/or other techniques proposed by the Applicant and agreed with the Director. The water quality models shall at least cover the Hong Kong waters, the Pearl River Estuary and Lema (Dangan) Channel to incorporate all major influences on hydrodynamic and water quality to Hong Kong waters. The mathematical modelling requirements are set out in Appendix D to this study brief. Possible impacts due to dredging, fill extraction, filling, mud/sediment transportation and disposal activities shall include but not be limited to changes in hydrology, flow regime, sediment erosion and deposition pattern, water and sediment quality, downstream salinity profile and effects on the flora and fauna due to such changes in the study area. The prediction shall include possible different construction stages or sequences, and different operational stages. Affected sensitive receivers shall be identified by the assessment tool with indications of degree of severity.
3.4.3.5 The Applicant shall take into account and include likely different construction and operational stages or sequences, including maintenance dredging (if any) of the Project in the assessment. The assessment shall have regard to the frequency, duration, volume and flow rate of the discharges and its pollutant and sediment loading. Reference shall be made to available information in previous studies including, but not limited to, those listed in Appendix D to this study brief. Essentially the assessment shall address the following:
(i) Collection and review of background information on the existing and planned water system(s) and their respective catchments and sensitive receivers which might be affected by the Project during construction and operation. Consideration shall also be taken for any sensitive receivers in the Mainland waters being likely affected by the construction and operation of the Project in HKSAR waters;
(ii) Characterization of water and sediment quality of the water system(s) and respective catchments and sensitive receivers which might be affected by the Project during construction and operation based on existing information or appropriate site survey and tests;
(iii) Identification and analysis of all existing and planned future activities and beneficial uses related to the water system(s) and identification of all water sensitive receivers, including those highlighted in sub-section 3.2 above. The Applicant shall refer to, inter alia, those developments and uses earmarked on the relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans;
(iv) Identification of pertinent water and sediment quality objectives and establishment of other appropriate water and sediment quality criteria or standards for the water system(s) and all the sensitive receivers in sub-section 3.4.3.5(i) above and particularly those ecologically sensitive receivers (such as Chinese White Dolphins) for the assessments in sub-sections 3.4.5 and 3.4.6;
(v) Review of the construction sequences and methods, and operation of the Project to identify any alteration of existing water courses, natural streams/ponds, shoreline or bathymetry, flow regimes, ground water levels and catchment types or areas;
(vi) Identification and quantification of all existing and likely future water and sediment pollution sources and loading. An emission inventory on the quantities and characteristics of all existing and likely future water pollution sources in the study area shall also be provided. Field investigation and laboratory tests shall be conducted as appropriate to fill in any major information gaps;
(vii) Prediction and quantification of impacts on the water system(s) and respective catchments and sensitive receivers that likely be affected by the alternations and changes identified in sub-section 3.4.3.5(v) above and the pollution sources identified in sub-section 3.4.3.5(vi) above. Both the local and regional effects on erosion, sedimentation pattern, sediment dispersion, flow regime and water quality due to any dredging of marine sediment and backfilling activities, interim and ultimate alteration of shoreline and bathmetry as a result of any marine works for the Project shall be assessed through undertaking a mathematical modelling. The location, nature, extent and rate of such works for the Project shall be clearly identified and evaluated. The assessment shall also take into account the additional pollution loading and oxygen demand exerted by sediment disturbed and any fill materials;
(viii) Identification and quantification of all dredging, fill extraction, filling, mud/sediment transportation and disposal activities and requirements. Potential fill source and dumping ground to be involved shall also be identified and cumulative environmental impacts during its operation be evaluated. Field investigation, sampling and chemical and biological laboratory tests to characterize the sediment/mud concerned shall be conducted as appropriate. The potential release of contaminants during dredging and any other marine works shall be addressed using the chemical testing results derived from sediment samples collected on site and relevant historic data. Appropriate laboratory tests such as elutriate tests and sediment pore water (interstitial water) analyses shall be performed on the sediment samples to simulate and quantify the degree of mobilization of various contaminants such as metals, ammonia, trace organic contaminants (including PCBs, PAHs, TBT and chlorinated pesticides) into the water column during dredging. The ranges of parameters to be analyzed; the number, location, depth of sediment, type and methods of sampling; sample preservation; and chemical and biological laboratory test methods to be used shall be subject to the approval of the Director. The Applicant shall also assess the pattern of the sediment deposition and the potential increase in turbidity and suspended solid levels in the water column and at the sensitive receivers due to the disturbance of sediments during dredging.
(ix) Assessment of the cumulative impacts due to other related concurrent and planned projects, activities or pollution sources along the identified water system(s) and sensitive receivers that may have a bearing on the environmental acceptability of the Project through mathematical modelling. This shall include the potential cumulative construction and operational water quality impact arising from, inter alia, the associated works of the Project, the activities and planned projects highlighted in sub-section 3.2 (xii) above;
(x) The water quality impact assessment shall include an assessment of the inter-relation between tidal hydraulics, the bridge configuration and the flushing capacity with a view to mitigating the pollution problems experienced in Hong Kong waters as a result of any reduced flushing caused by the entire bridge (including both Hong Kong section and Zhujiang section) and other associated structures. The water quality impact assessment shall also consider the disposal of the storm-water runoff from the highway during the operation of the Project;
(xi) The Applicant shall devise mitigation measures to avoid or minimize the impacts identified above. The residual impacts on the water system(s) and the sensitive receivers with regard to the relevant water and sediment quality objectives, criteria, standards or guidelines shall be assessed and quantified using appropriate mathematical models set out in Appendix D to this study brief.
(xii) With reference to the assessment findings in sub-section 3.4.3.4 above, review relevant existing emergency response plan(s) and if necessary, propose modification(s) to the existing emergency response plan(s), or derive additional emergency response plan(s) as appropriate to deal with chemical spillage due to vehicle accidents during the operational stage of the Project. The plan(s) shall aim to contain and/or remove the accidental spillage so as to prevent and/or minimize exposure to contaminants by environmentally sensitive receivers/areas such as Chinese White Dolphins and SSSI/marine park.
3.4.4 Waste Management Implications
3.4.4.1 The Applicant shall follow the criteria and guidelines for evaluating and assessing waste management implications as stated in Annexes 7 and 15 of the TM respectively.
3.4.4.2The assessment of waste management implications shall cover the following:
&nbs