|
(ACE
Paper 07/2000)
For discussion
Introduction
This
paper sets out the Administration's plans for the process
and expected timetable for conducting the review of the Strategic
Sewage Disposal Scheme (SSDS) for Members' consideration.
Background
2.In
October 1999, taking account both of the rate of progress
with the tunnelling work for Stage I of the SSDS and of continuing
public questions on a number of aspects of the system, including
the adequacy of the treatment to be provided and its cost
effectiveness, the Administration decided that, before seeking
funds for further stages, an independent review should be
conducted.The review is to consider the experience with Stage
I works, the present plans for later stages, and alternative
proposals, so as to make recommendations on the future direction
of the Strategy.A background note on the SSDS is at Annex.
3.In
setting up the review, the following principles are considered
to be fundamental:
- The
process should be open and participatory.The public will
be given full access to all the background information prepared
for the review panel.All who wish to make a submission to
the review panel will be welcome to do so either in writing
or verbally during a public forum.All written submissions
received, including any submission which may be made by
the Administration, will be forwarded to the review panel
for consideration and, unless objected to by the submission
proponents, will be published; and
- The
review panel will be drawn from experts of high professional
standing in sewage treatment, tunnelling, economics and
environmental assessment, so that it can take a comprehensive
view of the current scheme and alternative proposals.
The
Review Process
4.The
following sets out how it is intended to take forward the
review in the light of the principles described in paragraph
3:
| 7
April |
Further
discussion at the LegCo Panel on Environmental Affairs. |
| 10
April |
Formal
commencement of the process.A digest of information about
present and projected sewage loads, environmental conditions,
and other information relevant to planning of sewage systems
for the main urban area will be made available to the
public. |
| 10
April - 10 June |
Period
for members of the public and the Administration to submit
written views/ proposals to the review panel. |
| April/May |
First
visit by overseas members of the review panel to join
with the local members to get to know each other, discuss
procedures, conduct site visits, make initial contacts,
and to meet ACE and LegCo EA Panel. |
| June/July |
Second
visit of overseas members. The review panel will conduct
a public forum to receive verbal submissions.A moderator,
who is not a member of the review panel or of the Administration,
will preside over the forum. |
| August
- October |
The
review panel to consider the submissions received, review
alternative options, and prepare its recommendations.
Further meetings and visits if the panel members consider
them necessary. |
| 30
October and shortly thereafter |
The
review panel to submit their recommendations to the Administration.
They will be invited to brief ACE and the LegCo EA Panel. |
| December
and January |
Public
consultation. |
Composition
of the Review Panel
5.The
review panel will comprise international and local experts
in wastewater treatment, marine biology, tunnelling and financial
analysis.Specifically, it will be made up of:
- 3
international wastewater treatment experts including 1 expert
in biological nutrient removal processes nominated by the
International Water Association and 2 who participated in
the review of the SSDS conducted in 1994/95
- 1
international tunnelling expert
- 1
local expert in marine biology nominated by The Marine Biological
Association of Hong Kong
- 1
local engineer nominated by the Hong Kong Institution of
Engineers
- 1
local expert in financial analysis
Terms
of Reference of the Review
6.The
terms of reference have been drafted to give the review panel
full scope to consider alternative proposals.The review panel
will be requested to:
- review
proposals for further developments of SSDS based on the
experience gained from Stage I;
- review
alternative options for the sewage strategy presented by
members of public or the Administration, in terms of environmental
benefits, engineering feasibility, cost-effectiveness, economic
and systems sustainability, and time required; and
- make
recommendations on the most sustainable way forward for
development of the sewage system for the main urban area.
In
carrying out the above tasks, the review panel will attend
meetings as necessary and present findings.
7.The
review panel will also be asked to advise the Administration
as soon as possible if, after assessing experience with Stage
I, there is any strong likelihood that its recommendations
may have significant impact upon the remaining Stage I works
currently in progress, to the extent that it would be necessary
to consider stopping or altering these works.
Secretariat
for the Review Panel
8.A
secretariat will be established from which the public and
interested parties can seek information, and a website will
be set up from which the digest of technical information can
be obtained.The secretariat will also serve as the focal point
to receive submissions and forward them to the review panel.
Advice
sought
9.Members
are invited to note and give their views on the planned process
for conducting the review of the SSDS.
Environment
and Foo Bureau
March 2000
Annex
An
Outline of Progress with the Strategic Sewage Disposal Scheme
The
Strategic Sewage Disposal Scheme was conceived in the 1980's
as a means of replacing the present unacceptable discharges
of sewage from the main urban area into the central harbour
after receiving preliminary treatment by:
- Collection
of all discharges from the main urban areas
- Centralized
treatment
- Discharge
of the treated effluent through an outfall in oceanic waters
south of Hong Kong
2.As
originally projected, the scheme was to consist of two treatment
plants, providing primary treatment supplemented with lime
dosing.Several means for conveying the sewage from the catchment
areas to the treatment plants and to the outfall were considered.Deep
tunnels were selected because the greater geotechnical problems
in construction were considered to be offset by reduced engineering
complexity, reduced operational risks and reduced interference
with other urban infrastructure.
3.The
scheme was divided into four stages:
- Stage
I collecting sewage from the urban areas of Kowloon, Tsuen
Wan, Tseung Kwan O and the northeastern part of Hong Kong
Island for primary treatment at Stonecutters Island Sewage
Treatment Works (SCISTW).
- Stage
II comprising an effluent transfer system to an outfall
south of Hong Kong.
- Stage
III/IV collecting sewage from the north and south-western
parts of Hong Kong for treatment at Mount Davies before
adding to the oceanic outfall.
4.Following
review in 1995, the scheme was revised:
- The
treatment system at SCISTW to be upgraded to a chemical
process using ferric chloride
- Stages
III/IV to be diverted to convey the sewage to SCISTW
- Stage
II to undergo further EIA assessment of the outfall location
and treatment level
Present
Position
5.Stage
I of SSDS comprises a treatment plant at Stonecutter's Island,
pumping and screening stations and seven deep tunnels with
a total length of 25.3 km.One tunnel, the interim outfall
tunnel, 1.7 km in length, has already been completed and is
now in operation.The SCISTW is also in operation and is currently
treating about 320,000 cubic metres of sewage daily. This
represents 25% of the total design flow from the whole SSDS
Stage I catchment. Since the SCISTW was put into operation
in May 1997, the performance of the chemical treatment process
using ferric chloride is satisfactory. Over 80% suspended
solids and 70% biochemical oxygen demand on average are removed
from the raw sewage against the respective target removal
rate of 75% and 35%.
6.To
date, 19.4 km (82%) of the six sewage collection tunnels have
been excavated. Two tunnels have been bored through and are
being lined.We expect to complete excavation of the remaining
4.2 km during this year and to commission the whole sewage
collection system in 2001.The progress of the tunnelling works
as at 19 March 2000 is as follows:
| Tunnel |
Length
of Tunnel(m) |
Excavation
completed up to end 12/1999 |
Excavation
completed in this quarter |
Total
Excavation completed to 19.3.2000 |
| Western
Tunnels |
| Tunnel
from Kwai Chung to Tsing Yi |
779 |
779
(100%) |
N/A |
779
(100 %) |
| Tunnel
from Tsing Yi to Stonecutters Island |
3580 |
2669
(75%) |
82
(2%) |
2751
(77%) |
| Eastern
Tunnels |
| Tunnel
from Tseung Kwan O to Kwun Tong |
5332 |
5332
(100%) |
N/A |
5332
(100%) |
| Tunnel
from Chai Wan to Kwun Tong |
4830 |
2662
(55%) |
745
(16%) |
3407
(71%) |
| Tunnel
from Kwun Tong to To Kwa Wan |
3572 |
2536
(71%) |
763
(21%) |
3299
(92%) |
| Tunnel
from To Kwa Wan to Stonecutters Island |
5495 |
2857
(52%) |
939
(17%) |
3796
(69%) |
The
tunneling progress as at 19 March 2000 is shown on the attached
drawing No.DSS/99/001R.
7.The
EIA study for Stage II has been completed. It has recommended
that the outfall be located in the southeast of Lamma Island,
and that the treatment process should be further upgraded.A
disinfection process should be added at the time of constructing
the Stage II tunnels and land reserved should biological nutrient
removal processes need to be added in future.
|