| Environmental
Impact Assessment Report on Shenzhen River Regulation Project
Stage III
(ACE
Paper 19A/2000)
For discussion
Background
This
paper supplements ACE-EIA Paper 6/2000 and ACE Paper 19/2000
regarding the Shenzhen River Regulation Project Stage III.
The key findings and recommendations of the Environmental
Impact Assessment (EIA) study for Shenzhen River Regulation
Project Stage III (the Project) were presented to and discussed
by the ACE EIA Subcommittee at its meeting on 8.5.2000. Whilst
the Subcommittee endorsed most of the findings and recommendations
on various environmental mitigation measures subject to certain
conditions on post-project monitoring and preservation of
the Lo Wu Railway Bridge, the project proponent was requested
to re-examine the recommended disposal option with a view
to reducing the amount of material to be filled in Nam Hang
by exploring other suitable local disposal sites for the consideration
of ACE. This paper describes the background of the disposal
problem, the alternatives considered, the justifications for
disposing the excavated material in Nam Hang and the scope
for reducing the amount of soil filling in Nam Hang.
Need
for Disposal
2.The
Project involves improvement works to the stretch of Shenzhen
River of about 4km between Lo Wu and its confluence with Ping
Yuen River. Excavation is necessary for enlarging the river
channel to achieve the design flood conveying capacity. Measures
to reduce and reuse the excavated material have been considered
in the EIA study and suitable excavated material will be used
for forming the embankment on both sides of the river channel
as far as possible. Apart from this, about 1.6Mm3 of excavated
material will become surplus and has to be disposed of, out
of which 0.2Mm3 is contaminated. The EIA report recommended
that the 0.2Mm3 of contaminated material will be disposed
of at East Sha Chau; about 0.5Mm3 of uncontaminated material
will be disposed of on site in Nam Hang Middle Valley (see
Annex 1 for location of the valley) adjacent to Shenzhen River;
and the remaining 0.9Mm3 will be
disposed of in NeiLingDing Marine Dumping Ground in the Mainland.
Alternatives
Considered
3.Six
disposal schemes have been identified and assessed varying
from total marine disposal by barges to the Pearl River delta
to total terrestrial disposal within or immediately adjacent
to the site. Neither of the extremes is desirable from the
environmental, economic and construction programme point of
view and the preferred option must be able to satisfy the
following conditions:
- Environmentally
acceptable;
- Minimum
construction time to achieve early protection against loss
of human life and damage to property due to flooding; and
- Minimum
financial commitment (i.e. minimum construction cost)
4.The
recommended option of disposing one third on land and two
thirds to sea has proved to be environmentally acceptable,
is a realistic compromise amongst all factors and offers much
needed flexibility to the construction process.
Justifications
for the Use of Nam Hang Middle Valley
Problems
on Access
5.The
site for Shenzhen River Regulation Project Stage III is located
at the boundary area between the Shenzhen Special Economic
Zone and the Hong Kong Special Administrative Region. It is
surrounded by the urban city of Shenzhen in the north and
by a series of hillside and the Sandy Ridge Cemetery of Hong
Kong in the south. The only land access from Hong Kong is
via the Man Kam To boundary control point and land access
from Shenzhen is through the busy commercial area of the Lo
Wu district. Transportation of the excavated material off
site by land will cause an unacceptable impact on the already
congested cross boundary traffic in Man Kam To and the busy
traffic in Lo Wu. The relevant boundary control authorities
of the Hong Kong side (i.e. the Police, Immigration and Customs)
have strongly objected to the proposal of exporting the excavated
material through Man Kam To as frequent passage of lorries
through the boundary control area will cause unacceptable
boundary control and security problems. Marine transportation
is therefore the only feasible solution for off site disposal.
Unfortunately, the existing river within the Stage III site
does not offer suitable marine access and the improved river
will only possess limited capacity for marine transportation
because of the constraints imposed by the small headroom of
the bridges at Lo Wu, which would only allow one way passage
of small barges.
Effect
of total export of material via marine access
6.Due
to the constraints at Lo Wu, total export of the excavated
material via marine access, if adopted to replace the EIA
recommended option as mentioned in paragraph 2 above, would
cause the construction time to increase by about 17 months.
This is unacceptable from the flood control point of view
as the much needed early flood relief to people of both sides
cannot be achieved. Previous flooding incidents and the recent
flooding on 14.4.2000 due to heavy rainstorm caused extensive
damage to properties and interruption to the cross boundary
traffic and living of people of both sides. Water discharge
from the Shenzhen Reservoir would also aggravate the flooding
in the river and its catchments upstream of Lo Wu. Delay in
completion of the Stage III works would not be acceptable
by the general public. Both the LegCo and District Board have
urged the government to start the Project early to resolve
the flooding problem. Besides, the cost of total export via
marine access would be high due to long haulage.
Environmental
Acceptability
7.In
order to overcome the programme constraint, the feasibility
of on-site disposal in the three valleys on the Hong Kong
side lying between Lo Wu and Man Kam To was explored (see
Annex 1 for location of the valleys). The EIA study showed
that the in-filling of either of the two larger outer valleys
would entail significant loss of good wetland including freshwater
marsh and fishponds, together with significant woodland habitats
and some derelict ephemerally wetted agricultural lands. The
Nam Hang Middle Valley was considered to be an environmentally
acceptable option but with less filling capacity.
8.The
proposed Nam Hang Middle Valley in-filling will cause the
lost of the river meander, a part fishpond remnant (after
construction of the river embankment), an area of very low
lying freshwater marsh (adjacent to the river) and a small
area of ephemerally wetted derelict agricultural land surrounded
by variously vegetated slopes. The woodland, vegetated slopes
and grassland surrounding the derelict agricultural land in
the valley floor are subjected to frequent fire as the area
is surrounded by an active and expanding cemetery site. Most
of the slopes have been benched and pre-excavated for burials.
During the EIA study, a major fire over the Chung Yeung festival
period razed all trees and vegetation on the slopes in question
south of the security fence. The ecological value and potential
of the middle valley is thus the least of the three valleys.
This together with the increasing likelihood of further fires
as the cemetery expands have led to its selection for disposal
of surplus excavated material. The Nam Hang middle valley
proposal does not entail any loss of significant wetland or
woodland habitat.
9.The
ecological value of the whole area has been carefully appraised.
Significant fishponds, marsh and mature woodlands have been
identified in the two outermost valleys. The eastern valley
will be preserved. The commercial bloodworm ponds and their
observed feeding value for avifauna have been upheld. The
fishponds in the western valley will be taken over and reprofiled
for ecological enhancement, producing a well-balanced valley
area with all types of ecologically valuable habitats buffered
on all sides. The enhancement will make it particularly suitable
for roosting and foraging of avifauna.
10.Other
environmental impacts caused by the soil filling in Nam Hang
Middle Valley include water quality, air quality, visual and
landscape, noise, and development constraints. These were
assessed in the EIA study. With the necessary mitigation measures
in place, there would not be any unacceptable environmental
impact and there is no net ecological loss. Hence the proposed
disposal scheme is environmentally acceptable. The in-filled
valley would be planted with 4.8 ha of trees to enhance the
ecological value and to improve landscape. The woodland will
be carefully designed to prevent fire damage and to increase
biodiversity by careful selection of species. The established
woodland would also provide an effective ecological linkage
between the preserved eastern valley and the enhanced western
valley.
Considerations
in spoil disposal
11.The
use of Nam Hang Middle Valley for disposal of surplus excavated
material is in line with the practice of spoil disposal in
Hong Kong in which marine dumping should be undertaken if
there are no other better and practical land based environmentally
acceptable options. This is also in line with the approach
adopted in the EIA Study for Stage II of the Shenzhen River
Regulation Project, in which spoil was disposed of at Lok
Ma Chau (land based disposal) prior to disposal in NeiLingDing
(marine based disposal).
Scope
for Reducing the Amount of Soil Filling in Nam Hang Middle
Valley
12.The
beneficial use of the excavated materials has been considered.
Suitable excavated material will be used for forming the embankment
on both sides of the channel as far as possible. Surplus material
that is unsuitable for engineering purpose would need to be
disposed of in marine dumping ground. Other surplus material
contains a high proportion of silt/clay and can only be used
as public fill for reclamation and the nearest public filling
area is in Tuen Mun. However, land transportation of the excavated
material to Tuen Mun will cause an unacceptable impact on
the already congested Man Kam To boundary traffic as mentioned
above. For marine transportation, the constraint at Lo Wu
will cause a major problem on the construction programme similar
to the total export option. In fact, any proposal for the
beneficial use of the excavated material in both Hong Kong
and Shenzhen will be seriously restrained by the access problems
similar to the total export of material via marine access.
13.The
scope for reducing the scale of soil filling in the Nam Hang
Middle Valley is rather limited mainly due to the access problem
and the associated environmental impacts caused. The habitat
affected is situated mainly on the valley floor and the extent
of habitat loss is not proportional to the scale of soil filling.
Any reduction in soil filling would have an impact on the
construction programme while a substantial reduction would
cause an unacceptable delay to the completion of the Project.
According to the programme, however, the tentative works completion
date of September 2004 is quite near the end of the wet season
of year 2004. The completion can possibly be extended to the
onset of the following wet season. With this flexibility,
it is possible to export part of the material and to reduce
the filling quantity in the Nam Hang Middle Valley by about
100,000 m3. The material can be disposed of in the public
filling area in Hong Kong such as Tuen Mun via marine transportation.
14.This
modified disposal scheme is essentially the same as the recommended
disposal option in the EIA report but with reduced amount
of soil filling in the Nam Hang Middle Valley. It has similar
environmental impact but with the completion of the channel
work delayed to before the onset of the next wet season (see
Annex 2 for comparison of completion time for various disposal
options). It should however be stressed that there are many
uncertainties in commencing the Project on time and the construction
of a project of such scale and nature would be highly susceptible
to delay. Any slippage would render the works completion to
go beyond the onset of the wet season, which would be highly
undesirable from the flood control point of view. The construction
cost would also be higher due to longer haulage.
Conclusion
15.The
Shenzhen River Regulation Project Stage III is a unique project
located in the boundary area with very limited marine access
for transportation of excavated materials. In order to resolve
the construction difficulties and the programme constraints,
the use of Nam Hang Middle Valley for the disposal of surplus
excavated materials is essential. With the EIA study recommended
mitigation measures and the restoration plan fully implemented,
the impact of the disposal in the Nam Hang Middle Valley can
be mitigated to within an acceptable level. Although it is
feasible to reduce the amount of soil filling in the Nam Hang
Middle Valley from 0.5Mm3 to 0.4Mm3, it will not result in
any significant improvement to the environmental performance
of the scheme nor any benefits to the cost and programme.
Endorsement
Sought
16.Members
are requested to endorse the option for the disposal of surplus
excavated materials arising from the Project as recommended
in the EIA report.
Attachment
Annex
1 - Location plan of Nam Hang Valley
Annex
2 - Comparison of completion time for various disposal options
Drainage
Services Department
May 2000
|