The minutes were confirmed without amendments.
Agenda Item 2 : Matters Arising
Para. 25 : Strategic Assessment and Site
Selection Study for Contaminated Mud Disposal 2. Members
noted that the Council discussed the issue at the meeting
held on 23 July 2001 and it had no objection to the proponent's
undertaking the EIA study for the recommended site and disposal
method for contaminated mud when the existing East Sha Chau
mud pit was filled up. However, the Council urged the Administration
to expedite the study and implementation of a long-term facility
for dredged mud.
Para. 46 : Updated EM&A Manual for
Dredging at West Po Toi Marine Borrow Area
3. Members noted that a copy of the
updated EM&A Manual (as at 9 July 2001) was circulated
to them on 11 July 2001.
Para. 48 : Bi-weekly updated on dredging
and EM&A at West Po Toi 4. Members noted that
a summary of sand dredging progress and EM&A for the period
11 to 19 July 2001 was circulated to them on 24 July 2001
by e-mail.
Agenda Item 3, 4 & 5 : Central
Reclamation Phase III (CRIII) / Wan Chai Development Phase
II (WDII) / Central - Wan Chai Bypass and Island Eastern Corridor
Link (CWB & IECL)
(ACE-EIA Paper 7/2001, 8/2001 & 9/2001)
5. The Chairman welcomed CE(HK)1/TDD
et. al. to the meeting. CE(HK)1/TDD introduced the
background of the three projects. TD/Maunsell and PM(CRIII)/Atkins
presented the projects in details. TD/Maunsell highlighted
that the timeframes for the three projects were as follows:
CRIII August 2002 - March 2007
WDII March 2004 - February 2010C
WB & IECL March 2004 - February 2012
6. The Chairman asked whether it was possible to extend
the CWB tunnel beyond the Cross Harbour Tunnel so as to reduce
the environmental impacts of the elevated IECL. TD/Maunsell
replied that the consultants had assessed the feasibility
of the total tunnel option during the Trunk Road options Study
in end 1999 and found the proposal undesirable and that it
would involve an unacceptable high level of risks in constructing
a deep tunnel underneath the existing Cross Harbour Tunnel.
Furthermore, the Trunk Road would need to connect to the existing
island Eastern Corridor, which was an elevated structure.
TD/Maunsell pointed out that if the IECL was built
in tunnel, then a substantial length of the existing Island
Eastern Corridor would require reconstruction. The extent
could be up to North Point Ferry Pier.
7. A Member enquired about the length
of the tunnel and what ventilation facilities would be provided.
TD/Maunsell said that the tunnel would be 2.3 kilometers
long (compared to the existing Cross Harbour Tunnel which
has a length of 1.7 kilometers) and three ventilation buildings
would be constructed at the beginning, the middle and at the
end of the tunnel to provide ventilation.
Cumulative impacts of reclamation on water
quality of the Harbour
8. A Member noted that although the
change in mean discharges across Victoria Harbour due to the
reclamation of CRIII and WDII would be less than 0.5% each,
the cumulative changes from other reclamation projects of
the same timeframe would amount to almost 5%. She asked how
the Administration would address the cumulative impact concerned.
In response, TD/Maunsell said that CRIII and WDII reclamations
were not massive reclamations but only to smoothen the existing
shoreline to enhance water flow in the Harbour. The two reclamations
would contribute insignificant changes in the mean discharges
across the Harbour. In reply to the Chairman's follow up question,
TD/Maunsell assured the meeting that with the predicted
impacts, the water quality of the Harbour would still comply
with the Water Quality Objectives (WQO).
9. Atg.AD(EA)/EPD supplemented that
the 5% impact was cumulated from a number of proposed reclamation
projects within the Harbour including the South East Kowloon
Development Study. The impact of CRIII and WDII on the water
quality of the Habour was insignificant as these reclamation
projects would smooth out the shoreline after implementation
and would not increase additional pollutants into the Harbour.
In the meantime, the Harbour Assessment Treatment Scheme (HATS)
when implemented would be expected to bring improvement to
the water quality in the Harbour.
10. A Member asked whether the improvement
in the water quality of the Harbour brought about by HATS
could compensate for the 5% change in flow discharge. In response,
Atg.AD(EA)/EPD said that the HATS project would collect
wastewater from the catchments around the Victoria Harbour
for treatment before discharge and so it was anticipated that
the improvement would more than compensate for the change
in flow discharge.
11. The Chairman asked how the project
proponents would prevent fish kills which occurred during
the West Kowloon Reclamation. TD/Maunsell said that
the CRIII and WDII situations were totally different from
that of the West Kowloon Reclamation in which embayment was
formed. However, with due regard to past experience, they
would tighten the standards and implement measures such as
channeling storm water outfall to the outside of the embayment
until the permanent culvert extension had been constructed.
They would also adopt more vigorous water quality-monitoring
programme to prevent fish kills. The measures would be incorporated
into relevant works contracts.
12. A Member asked whether the hemispherical
shoreline at the west of the Hong Kong Convention & Exhibition
Center (HKCEC) would form an embayment and whether it would
have any impact on water quality. TD/Maunsell explained
that it was not an embayment but a causeway of piled deck
arrangement to allow vessels to come in for exhibition purpose.
The water quality modeling had taken into account the design
of the shoreline and the results indicated compliance with
WQO.
Dredging and disposal of contaminated
mud
13. On the Chairman's question, TD/Maunsell
said that under the WDII project, about 990,000 m3 of mud
would be dredged and about 60% of which (approximately 600,000
m3) was estimated to be contaminated and would be disposed
at designated mud pit. PM(CRIII)/Atkins said that under
the CRIII project, about 580,000 m3 of mud would be dredged
and about 60% of which (approximately 370,000m3) would be
disposed by means of confined marine disposal.
14. The Chairman asked whether it was
possible to maximize the re-use of the dredged mud and minimize
the amount to be disposed in mud pit. In reply, PM(CRIII)/Atkins
said that they had conducted soil tests in 1995 during site
investigation and found that the mud concerned was unsuitable
for purposes like reclamation because of its soft, clay-type
nature.
15. In response to the Chairman's follow up
question, PM(CRIII)/Atkins said that the soil tests
were conducted according to the requirements set out in the
Works Bureau Technical Circular 22/1992. Since this Circular
was later superseded by 3/2000 with new parameters in the
test, they were at present re-conducting the soil tests using
the new parameters. The Chairman pointed out that the volume
of contaminated mud which required disposal/treatment should
preferably be quantified in the EIA report but deemed the
assessment adequate because of the recent change in the contaminated
mud classification scheme.
16. A Member enquired about the volume
of Class H contaminated materials arising from the three projects
which would require special treatment/disposal and based on
international experience how effective were the geosynthetic
containers in isolating the contaminated mud. TD/Maunsell
said that based on a preliminary study, about 2,000 m3 Class
H contaminated mud would arise from the projects but the exact
volume was subject to further detailed study. As regards the
geosynthetic containers, they had been used in similar applications
in the United States. To ensure effectiveness, the project
proponent would carry out trial tests in the context of local
requirements.
17. The Chairman asked whether there
were any fallback options should the trial tests fail. TD/Maunsell
said that they were confident in adjusting the design of the
containers as well as the operational procedures so that they
could adopt the method in Hong Kong.
18. In reply to the Chairman's question, SM(WDII)/Maunsell
said that the size of the containers would depend on the type
of handling method and the environment in which they were
used. Therefore the trial tests would ascertain detailed handling
mechanism to ensure efficiency and safety of the new method.
CE(HK)1/TDD supplemented that the project proponent
would carry out the trial test as soon as TDD had obtained
funding approval from the Finance Committee.
19. A Member asked whether the test
results would be subject to EPD's scrutiny. Atg.AD(EA)/EPD
said that if the Subcommittee so wished, that could be
imposed as a condition for endorsing the EIA report for its
approval and for it to be incorporated a s a condition under
the relevant Environmental Permit, if necessary. CE(HK)1/TDD
said that they had no objection to submitting the test results
to EPD for scrutiny and submitting a report to the Council.
20. In response to a Member's suggestion,
TD/Maunsell said that swimming was not within the beneficial
use of the Harbour. Nonetheless, he would consider his advice
to erect signs at strategic locations around the works area
to warn people not to swim in the Harbour during construction
stage.
Construction waste and project coordination
21. A Member pointed out that Hong
Kong was running out of space for disposal of construction
and demolition (C&D) waste and asked whether the proponents
had any commitment to make use of C&D materials for reclamation
purpose. In addition, he asked how the two project proponents
(TDD and HyD) would interface and co-ordinate so as to ensure
the efficient management of the projects. He raised the question
because poor project management would not only affect the
projects but also create the impression of lack of communication
and co-ordination between government departments.
22. On the first question, CE(HK)1/TDD
said that they would maximize the use of C&D materials
for the two reclamation projects. and Atg.AD(EA)/EPD
supplemented that the Civil Engineering Department and the
Environment and Food Bureau had examined their public fill
management plan.
23. On the second question, CE(HK)1/TDD
said that TDD would be responsible for CRIII and WDII reclamations,
the entrusted tunnel box works related to CWB and IECL, and
advance railway protection works for the proposed North Hong
Kong Island Line (NIL). When the CWB tunnel box works were
finished, the required work sites would be handed over to
Hy D for the subsequent tunnel installation and ancillary
works for CWB and IECL. Atg.CE(MW2-2)/HyD said that
the two Departments would not work on the same area at the
same time.
24. A Member enquired about the timeframe
for the construction of NIL and Shatin to Central Link (SCL)
and which party would be responsible for addressing the cumulative
impacts arising from the railway project. CE(HK)1/TDD said
that according to his understanding, the MTRC had submitted
proposals for SCL which were now being considered by the Administration.
The EIA study for CRIII had taken into account the impacts
of the construction of the NIL protection work. If there turned
out to be considerable deviations between this assessment
and the future EIA for NIL, the company concerned should address
the issue. Atg.AD(EA)/EPD supplemented that the advantage
of carrying out protection works for NIL was to reduce the
need to open up the newly reclaimed area for the construction
of the NIL. Should there be major changes in the proposal
submitted by the company concerned, the proponent must address
such changes under the NIL EIA. Any Environmental Permit issued
by the Director of Environmental Protection could also be
varied with the inclusion of the necessary mitigation measures
to address changes.
Visual impact
25. A Member asked whether there were
guidelines for building design in the reclamation area. TD/Maunsell
said that they had undertaken an urban design study to derive
a set of design guidelines including those on building density
and height. Apart from the reclamation area, they had also
looked at the land-use planning of the north shore of the
Hong Kong Island. The Planning Department had considered the
design guidelines which would become conditions for the Outline
Zoning Plan (OZP). Their intention was to allow more flexibility
for future developers and architects to create more attractive
designs to serve as landmarks on the waterfront area.
26. In reply to a Member's question, CE(HK)1/TDD
said that according to the authorized OZP for Central Reclamation
Phase III, the proposed government complex would be situated
in the Tamar reclamation area.
27. On a Member's question about building
height restrictions, TD/Maunsell said that they had
undergone lengthy discussions with the Planning Department
and the Architectural Services Department about height limits.
He believed that the current proposal had imposed optimum
height restrictions on buildings in the reclamation area.
28. In response to the Chairman's enquiry,
CE(HK)1/TDD said that the OZP for Central Reclamation
Phase III and the Planning Department would submit the draft
OZP for WDII to the Town Planning Board in August 2001.
29. The Chairman said that if Members
so wished, they could raise their concern over the visual
impact of the three projects at a Council meeting so as to
draw the attention of the Director of Planning who was represented
at Council meetings.
30. A Member asked what access would
be available for the public to go to the waterfront area when
elevated structures like the IECL were blocking the way. TD/Maunsell
explained that the intention was to provide as many pedestrian
accesses as possible from the hinterland to the waterfront
promenade. At the eastern end, a wide landscaped deck would
join the Victoria Park to the waterfront promenade. To the
west of Victoria Park, a footbridge would be built to provide
access to the promenade. Furthermore, a wide pedestrian connection
would link the Causeway Bay hinterland via the World Trade
Center to the promenade. Near Wan Chai, there would be a pedestrian
walkway to the promenade through the reprovisioned Hung Hing
Road. Finally, a wide pedestrian deck would provide access
to the ferry pier and waterfront promenade. It was also their
intention to provide subways for access to the proposed public
square east of the HKCEC Extension from the proposed NIL Exhibition
Station.
31. In reply to a Member's follow up question,
TD/Maunsell said that the proposed Noon Day Gun would
be re-located to the tip of the breakwater in the proposed
Kellett Island Marina.
32. In response to a Member's question, TD/Maunsell
said that taxi stands, coach loading/unloading areas and parking
spaces would be provided at various proposed developments
near the accesses to the waterfront promenade. The existing
public transport terminus in Wanchai would be expanded to
meet expected increase in demand.
33. On a Member's follow up question, TD/Maunsell
said that they had carried out traffic impact assessment and
the results had been considered by the Transport Department
and the Police. The conclusion was that the proposed works
would not cause traffic problems in the areas concerned.
34. A Member asked whether the project
proponents had any intention to build more piers to provide
service for ferries and leisure boats. TD/Maunsell
said that after consultation with the Transport Bureau, one
single pier with two berths would be built at the east of
the HKCEC Extension to provide licensed ferry services. As
for leisure boats/harbour cruises, the proposed features of
the waterfront promenade would allow loading/unloading of
passengers along the seawall.
EM&A
35. In reply to the Chairman's question, CE(HK)1/TDD
said that they would employ an independent environment checker
to audit the monitoring results of the projects. They would
also put the EM&A data onto the internet for public information.
36. To summarise the discussion, the Chairman
said that the Subcommittee was pleased to note that the projects
had gone through public consultations and the comments had
been incorporated into the EIA studies. The Subcommittee also
found it encouraging that a considerable section of CWB would
be constructed in the form of a tunnel to minimize environmental
impacts. The Subcommittee noted that proper water quality
assessment had been conducted and the results complied with
WQO. As regards construction waste and contaminated mud disposal,
Members were assured that the reclamations would maximize
the use of C&D materials and trials would be carried out
to ascertain the effectiveness and safety of geosynthetic
containers. On project management, it was noted that entrustments
of works had been agreed between TDD and Hy D. In terms of
visual impact, the proponents had consulted the Planning Department
on urban design plan and guidelines and would impose them
as conditions in the relevant OZP. Finally on EM&A, the
proponents would employ independent environment checker to
audit the monitoring results and the data would be uploaded
onto the internet for public information.
37. The Subcommittee agreed to recommend
the endorsement of the three EIA reports with the following
conditions:
38. The Chairman said that two items
were scheduled for discussion at the meeting tentatively scheduled
for 6 August. They were Implementation of the Drainage Improvement
Works for Ping Yuen River and EIA Report on Modifications
to MTRC Tsim Sha Tsui Station. The Secretary explained
that the statutory deadline for the Council to comment on
the EIA report of the latter project would expire by 14 September
before the September Council meeting. If Members would wish
to discuss the report at a Subcommittee meeting, it would
be preferable for them to do so before Members would leave
for the study visit to Europe on 6 August
39. A Member proposed and other Members
agreed that it was not necessary to consider the EIA report
on the MTRC project at a Subcommittee meeting. They considered
the EIA report acceptable and would recommend it to the Council
for endorsement without conditions.
40. As regards the item on Ping Yuen River,
as there was no statutory time limit for the Council to submit
comments, the Subcommittee decided to postpone the
item to the September meeting scheduled for 3 September 2001.
Monthly Update on Applications under the
EIA Ordinance
41. Members noted the monthly updates
as at 25 July 2001.
Noise Review Report at Lee On Station
42. The Chairman referred to the noise
review report and said that the Council endorsed in December
1999 the EIA report on KCRC-Tai Wai to Ma On Shan Extension
with a condition that the proponent should provide information
on ways to minimize noise impacts. In compliance with the
endorsement condition, the project proponent had provided
a copy of the Noise Review Document at Lee On Station for
Members' reference.
Tentative Items for Next Meeting
43. Members noted that two items were scheduled
for discussion at the meeting on 3 September, namely Comprehensive
Feasibility Study for the Revised Scheme of South East Kowloon
Development and Proposed Citybus Headquarters and Bus Maintenance
Depot in Chai Wan. Atg.AD(EA)/EPD pointed out that
Members had not selected the Citybus project for discussion.
However, EPD had received quite substantive comments from
the public at the consultation stage of the project profile.
The Department therefore recommended that the Subcommittee
should consider the report. Members agreed.
Resignation
44. A Member informed the meeting that
he had resigned from his post in the Friends of the Earth
(FoE) and thus another representative from FoE would attend
ACE and EIA Subcommittee meetings starting from September
onwards. The Chairman thanked that Member for his contributions
to the Subcommittee.
Agenda Item 7 : Date of Next Meeting
45. The next meeting was scheduled for 3 September
2001 at 4:00pm.
EIA Subcommittee Secretariat
August 2001