| Agenda
Item 1 : Confirmation of Minutes of the 66th, 67th, 68th &
69th Meetings
The minutes
were confirmed subject to amendments proposed by a Member
to draft minutes of the 66th and 67th meetings.
Agenda
Item 2 : Matters Arising
2. There
were no matters arising from the last meeting.
Informal
dialogue
3. The
Chairman said that at the Council meeting held in December
2001, the Subcommittee was tasked to re-examine whether minutes
of meetings should be kept for informal dialogues with project
proponents and to report back to the Council. The purpose
of informal dialogues was to provide an opportunity for project
proponents to highlight areas of concern and issues of contention,
identify different views and explore common grounds to resolve
conflicts before formal submission of the EIA reports.
4. Mr.
Elvis Au pointed out that such dialogues were becoming
popular in the United States because the process was likely
to lead to more constructive conclusions. Mr. C C Lay
also observed at the last EIA congress that informal dialogues
were useful in providing a forum for Members to better understand
the various stages involved in a project before narrowing
down to a preferred option.
5. The
Chairman said that the verdict of the appeal case on the
Spur Line suggested that early and open dialogues between
the project proponent and parties concerned would facilitate
the EIA process. If time permitted, the Subcommittee should
welcome opportunities for early dialogue on projects with
significant potential impact or those which would impinge
on sensitive areas. Such dialogues should be initiated by
the project proponent. He then referred to the "points for
discussion" tabled and invited Members' comments.
6. A
Member said that since informal dialogues were conducted
outside the provisions of the EIA Ordinance and project proponents
were unlikely to provide comprehensive information about the
projects, Members' views should not be taken as final and
minutes of the dialogues were therefore not necessary.
7. A
Member agreed with the Chairman that early dialogues were
warranted for projects with significant potential impact and
that they should be initiated by the project proponent. Regarding
minutes of the dialogues, he was of the opinion that a record
should be kept for the internal reference of the Subcommittee
but should not be released to the project proponent. The record
should be circulated to Members for necessary amendment.
8. A
Member suggested that as the purpose of the dialogues
were to highlight issues of concern, the format of the record
could be issue-based with a summary of the comments raised
by Members and response provided by the project proponent
without mentioning who said what.
9. A
Member asked apart from project proponents whether the
Subcommittee would consider having dialogues with stakeholders,
independent experts and non-Government organizations. She
considered that there were merits for having Subcommittee-initiated
dialogues. The criteria for accepting or rejecting informal
dialogues should be established to provide a clear guidance
to those concerned. The timing of informal dialogues was also
important lest the project proponent would make use of Members'
views during an informal dialogue to back up the project when
they consulted other bodies. There were also worries that
the project proponent might make a lot of efforts to lobby
Members during informal dialogue and neglect formal consultation
with the Subcommittee. Also, too many dialogue meetings would
increase the burden of Members who already had a heavy schedule
of meetings to consider reports submitted formally under the
EIA Ordinance.
10. A
Member pointed out that early dialogues were conducted
partly in response to the verdict of the Spur Line appeal.
Regarding dialogues with stakeholders and other bodies, as
EPD was the authority to approve or reject EIA reports, it
was more appropriate for EPD rather than the Subcommittee
to hear comments from those bodies.
11. The
Chairman emphasized that the Council's statutory role
was to advise Director of Environmental Protection its views
on EIA reports. The Subcommittee could seek expert advice
on issues on a need basis. A Member concurred with
the Chairman and recalled that the Subcommittee had sought
advice from dolphin and dragonfly experts on two occasions
in the past.
12. Taking
into account Members' comments, the Chairman concluded
that the Secretariat should keep brief notes on informal dialogues
with project proponents and should circulate the notes to
Members for amendments, if any. The notes would not be issued
to the project proponent and Members' views expressed during
the dialogue would not be reported back to the Council.
Informal
dialogue on Shenzhen Western Corridor
13. A
Member understood that the proponent of the Shenzhen Western
Corridor project might circulate a draft EIA report to Members
for the informal dialogue scheduled for the next meeting.
She did not consider it appropriate for the project proponent
to do so for after all informal dialogues were different from
formal consultation under the statutory EIA process. Another
Member shared that Member's concern.
14. The
Chairman asked the Secretariat to explain the situation
to the project proponent and request them to highlight issues
of concern rather than to send in a draft EIA report. The
Secretariat
Agenda
Item 3 : Improvement to Tung Chung Road between Lung Tseng
Tau and Cheung Sha(ACE-EIA Paper 8/2002)
15. Noting
that the project site was within the water gathering ground
managed by the Water Services Department (WSD), a Member asked
whether EPD and WSD would jointly monitor the water quality
impact of the project. In response, Mr. Au said that
WSD was a member of the Environmental Study Management Group
and EPD would liaise closely with WSD during the implementation
stage of the project.
[The proponent
team was invited into the meeting room at this juncture.]
16. The
Chairman welcomed Mr. W C Chan et. al. to the meeting.
Mr. Simon Illingworth presented the EIA to Members.
17. The
Chairman commended the efforts that the consultants had
put in the EIA report, in particular the section on ecological
assessment and the innovative design for managing site run-off.
Width
of grassed verge and footway of on-line section
18. A
Member asked whether the provision of a 2m footway and
a 1.6m grassed verge was necessary to accommodate new utilities.
In reply, Mr. Illingworth explained that the space
under the carriage way and the verge on the other side of
the road would be occupied by drainage pipes and existing
utilities respectively. Thus, the new utilities and the gas
main could only be accommodated under the 1.6m grassed verge
and the 2m footway. However, for the off-line section, most
of the new utilities could go underneath the existing carriage
way which would become obsolete upon completion of the project.
19. In
response to that Member's question on the possibility of putting
all the new utilities under the grassed verge, Mr. Illingworth
said it was impossible because the ground under the verge
was already congested with utility services like cables and
junction boxes. No other utilities should be placed on top
of the gas main for safety reason.
20. Noting
that the 132kV cables were to be put under the carriageway,
a Member queried the practicality of the proposal and
pointed out that the drainage system would be interrupted
in case of cable repairs. Mr. Illingworth agreed with
that Member and said that the China Light & Power (CLP) had
requested them to move the cables to the ground underneath
the grassed verge.
21. A
Member asked whether it was feasible to put all the utility
services into a common duct instead of spreading them underneath
the footway. In response, Mr. Illingworth said that
there would be problems with the construction of a common
duct and it might end up with more construction work. The
1.6m grassed verge was only required for the on-line section
which took up about 35% of the length of the whole improved
road. The impact would not be significant.
22. A
Member asked whether CLP was required to seek permission
to decommission the overhead cables and replace them with
underground cables. Mr. Illingworth said CLP seemed
to have discussed the proposal with EPD.
23. In
response to the Chairman's question, Mr. Illingworth
confirmed that the width of the grassed verge and the footway
of the on-line section could not be further reduced.
Drainage
pipes for collecting run-off
24. The
Chairman enquired about the likelihood of the sediments
of the road surface run-off choking the drainage pipe. In
response,
Mr.
Illingworth explained that the drainage pipe would be fitted
with gratings so that it was unlikely for large sediments
to enter the system which would operate on a self-flushing
basis.
25. A
Member queried the need for the 3.5m maintenance access
road if the drainage pipe was self-flushing. In response,
Mr. Illingworth clarified that the access would only
be required for the section between Shek Mun Kap and Lung
Tseng Tau. Although the pipe was expected to be self-flushing,
access was required in case of damage. The access road could
be used as a future cycle track and would be constructed on
top of the drainage pipe.
Effectiveness
of sedimentation tanks
26. The
Chairman relayed a Member's query about the effectiveness
of the sedimentation tanks to attain the effluent standard
of 25ppm. In response, Mr. Illingworth pointed out
that the proposed size of the tanks was already at a maximum
with acceptable construction impact. They proposed to install
a filter system in the tanks to attain the standard aimed.
The detailed design of the tanks would be circulated to government
departments at the next stage and the operation would be audited
under the EM&A programme.
27 The
Chairman enquired about measures to be included in the
EM&A programme to ensure that the standard was met. In response,
Ms. Helen Cochrane said that they proposed daily and
weekly monitoring of the relevant parameters at various points
along the alignment. In case of exceedances, the contractor
would make necessary rectifications.
28. The
Chairman was concerned that the exceedances could not
be rectified in time should the filter system require retrofitting.
In response, Mr. Illingworth said that they would consider
installing more filters along the drainage channel. Ms.
Cochrane explained that the chance of exceedances was
insignificant, as the site runoff would be discharged to different
catchments.
29. In
reply to a Member's enquiry, Mr. Illingworth said that
the drainage system would cover the bus-bays and an oil interceptor
would be installed at the roundabout upstream of the southern
discharge to preserve the Cheung Sha Beach.
Impact
from elevated structures
30. A
Member asked how the impact of the elevated structures,
in particular the bridges across the streams, could be minimized.
In response, Mr. Illingworth explained that the span
of the bridges would generally be no more than 30m so that
they could use pre-cast beams or falsework to avoid impacting
on the streams. It was not certain how the detailed designs
would be but it would probably be a mixture of pre-cast beams
over straight sections and in-situ concrete over curved sections.
For haul roads, they would use temporary bridges.
31. A
Member asked whether construction would be carried out
during dry season to minimize the risk of run-off down the
streams. In response, Mr. Illingworth clarified that
there would not be any difference in constructing the elevated
structures in wet or dry seasons as no impact on the streams
was anticipated. However, for sensitive streams where new
culverts would be built, construction work would be carried
out in dry season and non-breeding season as far as practicable.
32. A
Member asked whether the impact would be reduced if steel
structures were used for bridges. Mr. Illingworth said
that steel structures would require painting and might not
be more environmentally friendly than concrete.
Noise
impact arising from existing road
33. In
response to a Member's enquiry, Ms. Cochrane explained
that the exceedances in noise level shown in Table 5.22 of
the EIA report were arising from the existing Tung Chung Road
and not from the section of Tung Chung Road to be improved
under this project. The Highways Department would review the
situation upon commissioning of the project and, if necessary,
initiate action to include that section of the existing Tung
Chung Road into the retrofitting programme for existing roads.
Translocation
programme for species of conservation importance
34. In
reply to a Member's enquiry on the translocation programme,
Ms. Cochrane said that the detailed specifications
would be drawn up at the design phase of the EM&A. Mr.
Shuan Nicholson pointed out that the experience in translocating
the Romer's Tree Frog in the Chek Lap Kok Airport project
demonstrated that translocation was feasible.
35. A
Member enquired about the rationale for translocating
the affected species to a nearby area bearing in mind that
the species concerned already existed in that area, whether
construction work would start only after the programme was
proved successful, and whether the species would be moved
back to the project site upon completion of works. In response,
Dr. Mike Leven confirmed that the species would be
located to a nearby habitat. Unlike the Chek Lap Kok project
where the habitat was destroyed permanently, the habitat affected
in the project would be restored to a condition suitable for
the species after construction was completed. The translocation
programme would not involve an entire population but a number
of individuals only and it would not be necessary to move
the individuals back to the site.
36. A
Member asked whether it would be a better option to keep
the affected individuals in a laboratory and release them
back to the original habitats when the construction works
was finished. In response, Dr. Leven commented that
the proposal was plausible but unnecessary.
37. In
response to a Member's question, Mr. Nicholson said
that it was proposed in the EM&A Manual that the monitoring
on the translocation programme would last for twelve months
after the commissioning of the improved road.
38. A
Member asked what actions would be taken if the project
proponent failed to find the translocated species during the
monitoring period. In response, Dr. Leven said that
the detailed action plan would be prepared at the detailed
design stage. In the worst-case scenario, it would be possible
to introduce the species back to the habitats.
39. Mr.
Cary Ho confirmed that in line with the usual arrangement,
the mitigation measures would be incorporated into the conditions
of the environmental permit. EPD in collaboration with AFCD
would ensure the comprehensiveness of the proposed measures.
Compensation
planting
40. A
Member commented that whilst the 25.45 ha of compensation
planting would mitigate for the loss of visual and landscaping
value, it was not certain how it could translate into ecological
value.
41. In
response, Dr. Leven explained that the area of compensation
planting was more than double of the loss of woodland and
shrubland. That was meant to compensate for the loss of the
ecological value of the woodland and shrubland in the long
term. He then drew Members' attention to Table 8.31 of the
report which showed the details of the compensation planting
programme.
42. A
Member asked whether there were other measures for slope
enhancement apart from hydroseeding. In response, Dr. Leven
said that the Geotechnical Engineering Office had set out
in their Good Practice Manual a list of treatment for slope
enhancement. At the detailed design stage, the engineers would
advise on measures that were possible in engineering terms
and the ecologists would decide on option(s) that would maximize
the ecological value.
43. In
response to a Member's question on the implementation schedule
and the monitoring of native woodland planting, Mr. Illingworth
said that planting would be carried out in parallel with the
construction work of the road. Ms. Cochrane said that
monitoring would be carried out for 24 months after planting.
Visual
impacts
44. A
Member said that the cut slope on the southern section
of the road from Pak Kung Ngau was visually intrusive and
asked whether there were any measures to minimize the impacts.
In response, Mr. Illingworth said that the retaining
walls on both the downhill side and uphill side of the road
were meant to reduce the footprint of the project. On the
downhill side, trees and creepers would be planted in front
of the wall to hide the road in the long run. However, on
the uphill side, only limited planting could be done in planters
attached to the front face of the retaining wall since no
grassed verge was provided to minimize the footprint of the
works. As regards bridges, although no planting could be provided,
the visual impacts of those which were over stream courses
shaded by trees would be minimized. In the short term, visual
impacts were inevitable but in the long run when the plantings
mature they would be able to hide the road.
Disposal
of materials resulting from vegetation clearance
45. A
Member noticed in Table 7.3 of the report that 4,824 tonnes
of vegetation clearance would be disposed in landfill and
asked whether there were alternative methods to dispose or
reuse them. In response, Mr. Illingworth said that
there were no local facilities to compost the materials but
they would liaise with AFCD and other relevant government
departments to see if the materials could be reused in habilitation
planting. Ms. Cochrane supplemented that the materials
could be compressed before disposal in landfill to help save
landfill capacity.
46. A
Member suggested using the tree trunks as fences in country
parks. Mr. Illingworth said they had considered that
and learned that AFCD would only accept trunks of certain
sizes. They would liaise closely with the department for such
opportunities. The Chairman commented that the proposal
might form a good example for future highway projects. Mr.
Cary Ho said that logs from past highway projects had
indeed been used to make tables, chairs and fences in country
parks. However, not all materials were suitable for the purpose.
Impacts
on field cattle
47. The
Chairman informed the project proponent about the concern
of a member of the public about the impacts of the project
on feral bovids (field cattle) in the project area. In response,
Dr. Leven said that field cattle were not found near
the site and therefore not a concern for the project. In any
case, whether the cattle were an advantage to the environment
was debatable as they grazed on certain plant species.
Impacts
on country park
48. In
reply to a Member's question, Mr. Illingworth said
that the project would affect about 5 ha of country park.
A combination of compensation/mitigation measures including
compensation planting was proposed in the EIA report.
49. In
response to a Member's question, Mr. Illingworth confirmed
that they had consulted the Country and Marine Parks Board
on the project and would discuss the EIA report of the project
with the Board in the near future.
Transportation
of waste materials
50. Noting
that 15,000 truck trips would be required to transport waste
materials from the site, a Member asked whether there
was any traffic management in place to minimize emissions
from the trucks.
51. In
response, Ms. Cochrane said that compared to the whole
Tung Chung Road, emissions from the trucks concerned would
be insignificant. The truck routes would be diverted to minimize
impacts on residential areas. Mr. Illingworth supplemented
that they had carried out a traffic impact assessment for
the project. The existing road was subject to user control.
The operation of the improved road would be subject to similar
control. The maximum number of construction vehicles allowed
on the road at any one time would be recommended at a later
stage.
52. A
Member referred to Table 2.11 of the report and queried
the high percentage (34%) of road usage by heavy vehicles
for the northern section. In response, Mr. Illingworth
explained that since only residents in Lantau could obtain
a closed-road permit, the proportion of non-private vehicles
such as franchised buses and goods vehicles would be relatively
higher.
Robust
EM&A and management of contractors
53. The
Chairman stressed the importance of a robust EM&A programme
to ensure timely rectifications for unexpected problems.
54. Having
regard to past records of poor site practices on Lantau which
was of high conservation value, a Member urged the
proponent to monitor the work of the contractors rigorously.
The project proponent noted Members' concerns.
Conclusion
and recommendations
55. The
Chairman proposed and Members agreed to recommend
the EIA report to the Council for endorsement with the following
conditions:
| |
(a) |
there
should be a robust EM&A programme to improve the effectiveness
of the sedimentation tanks and appropriate measures (such
as filter system) would be incorporated, if necessary;
and |
|
(b) |
the
project proponent should liaise with AFCD and other Government
departments on the beneficial use of the materials resulting
from vegetation clearance so as to reduce the amount to
be taken to the landfills. |
Agenda
Item 4 : Fill Bank at Tseung Kwan O Area 137
(ACE-EIA Paper 7/2002)
56. Having
considered the EIA report and the ACE-EIA paper, Members
agreed that the Subcommittee would recommend the EIA report
to the Council for endorsement without conditions and that
there was no need for the project proponent to make a presentation
at the meeting.
Agenda
Item 5 : Any Other Business
Tentative
schedule for next meeting
57. The
Chairman informed Members that a meeting would be held
on 3 June 2002 at 4:00pm to discuss the final soil quality
report arising from the Kai Tak Airport North Apron Decommissioning
project. After the meeting, there would be an informal dialogue
with the project proponent to discuss the preliminary EIA
findings of the Shenzhen Western Corridor project.
58. A
Member regretted that she had another commitment on 3
June and asked if the discussion on the final soil quality
report could be rescheduled so that she could discuss the
issue of quality standards with the project proponent. In
response, Mr. Au said that the project proponent intended
to commission construction works in Areas 1A and 1B which
were outside the contamination hotspots in early July 2002.
The works concerned would be held up if the discussion were
to be postponed to the meeting in July.
59. The
Chairman pointed out that the issues on soil standards
had been dealt with when the Subcommittee and the Council
considered the EIA report. The concern of the Subcommittee
would be whether the results of the soil quality report indicated
that the decontamination works had complied with the agreed
standards
60. Mr.
Elvis Au updated Members that the EIA on Yuen Long, Kam
Tin Sewerage and Sewage Disposal Stage I was scheduled for
the meeting on 8 July 2002. Another possible item would be
the EIA report on aviation fuel pipelines.
Agenda
Item 6 : Date of Next Meeting
61. The
next meeting was scheduled for 3 June 2002.
EIA
Subcommittee Secretariat
June 2002
|