|
Guidelines
for Soakaway System
THE
SOAKAWAY SYSTEM
v) The
Soakaway Pit/Trench
Purpose
: Percolation of wastewater to surrounding subsoil.
Design
Considerations:
(a) Soakaway
pit should be sufficiently large to avoid flooding and overflow.
The minimum capacity of the pit should accommodate all the
wastewater produced during one washing or in one day, whichever
figure is the greater.
(b) Permeability
of Soil. If the percolation rate is too high, the wastewater
might drain into the nearby watercourses before any effective
treatment. If it is too low, the pit/trenches might soon clog
up and wastewater would overflow. A site percolation test
should be conducted to determine the soil permeability. Table
2 illustrates the maximum allowable loadings of soakaway pits
and trenches. The common simplified procedures of percolation
test for determining the absorption capacity of soil are given
below:
- Excavate
a hole 300mm square to the proposed depth of the pit and
trench.
- Fill
the hole with approximately 150mm of water and allow it
to seep away completely; no need to measure the time.
- Refill
the hole with water to a depth of 150mm and observe the
time, in minutes, for water to seep completely away.
Table
2 Soakaway Area Requirements at Different Soil Percolation
Rates
| Time
for water to fall 150mm in test pit (minutes) |
Required
trench bottom area (m2) per 1,000L/day of wastewater |
Required
pit percolation area (m2) per 1,000L/day of
wastewater |
| 6
or less |
31 |
23 |
| 12 |
38 |
29 |
| 30 |
51 |
38 |
| 60 |
72 |
53 |
| 180 |
152 |
111 |
Note
1.
This table is only applicable to small inland duck farms or
those poultry or pig farms intending to carry out dry muck-out
of livestock waste.
2. A septic
tank is required for pig farms.
(c) Sufficient
Soakaway Area. A reasonable percolation rate which is neither
too high nor too low is about 60 minutes for water to fall
150mm. With such a percolation rate, a pig farm using 15L/pig/day
of washwater and removing 80% of solids during dry muck-out
requires a minimum soakaway trench area of 0.9m2 for every
pig (ie. 0.75m of trench if it is 1.2m wide). Table 3 illustrates
how this requirement can be affected by different operational
practices. For a chicken farm using 0.4L/chicken/week of washwater
and achieving 97% removal of solids, a minimum of about 0.4m2
of trench is required for every 100 chickens (ie. 0.33m of
trench if it is 1.2m wide). Table 4 illustrates how this requirement
can be affected by different operational practices. Similarly,
a duck farm generating 1,000L/day of wastewater requires 72m2
of trench (ie. 60m of trench if it is 1.2m wide). Table 2
illustrates how this requirement can be affected by different
soil percolation rates.
Table
3 Soakaway Trench Area Requirement for Pig Farms with Different
Operational Practices
| Percentage
removal of solids during dry muck-out |
70% |
80% |
90% |
| Minimum
soakaway trench area requirement (m2/pig) |
1.1 |
0.9 |
0.7 |
Note
The
above is based on
1. a
soil percolation time (rate) of 60 minutes for water to fall
150mm (N.B. The trench area requirement may be reduced if
the percolation rate is increased, pro rata to the requirements
shown in Table 2; on the other hand, the trench area would
need to be increased if the percolation rate is slower.);
2. a
septic tank is provided; and
3. a washwater
usage rate of 15L/pig/day. (N.B. the trench area requirement
can be reduced slightly by reducing the amount of washwater
used.)
Table
4 Soakaway Trench Area Requirement for Chicken Farms with
Different Operational Practices
| Quantity
of washwater used per wash (L/chicken) |
Wash
interval (day) |
Minimum
soakaway trench area (m2/100 chicken) for different percentage
removal of solids during dry muck-out |
| 95% |
97% |
99% |
| 0.4 |
3 |
0.70 |
0.46 |
0.22 |
| 7 |
0.64 |
0.40 |
0.16 |
| 28 |
0.61 |
0.37 |
0.13 |
Note
The above is based on a soil percolation time (rate) of 60
minutes for water to fall 150mm. (N.B. the trench area requirement
may be reduced if the percolation rate is increased, pro rata
to the requirements shown in Table 2; on the other hand, the
trench area requirement would need to be increased if the
percolation rate is slower.)
(d) A
soakaway pit or trench should be located sufficiently far
away from building foundations, watercourses and wells, in
order to safeguard public health and maintain the structural
integrity of nearby buildings. A safe distance is generally
30m from watercourses and wells, and 3m from structures.
Maintenance
Requirement : Periodic removal of any sludge accumulated.

|