space space   space
space

Sha Tin Transfer Station

Image of Sha Tin Transfer Station

General Information

Location

:

Sha Tin, New Territories

Contractor

:

Swire SITA Waste Services Ltd.

Contractor Facility Office Tel : 2649 0213

Capital Cost

:

$200 million

Design Throughput

:

1,200 tonnes per day

Commissioning Date

:

October 1994

Opening Hours

:

07:00 to 23:00

Waste Delivered to

:

North East New Territories Landfill.

Major Plant / Equipment

:

Yard Tractors, Highway Tractors, Trailers, Containers, Road Sweeper, Bucket Loader, Bobcat Loader, Tennant Scrubber

Other Facilities

:

Computerized Weighbridge System, Exhaust Ventilation System with Odour Removal Units, Waste Water Treatment Plant, Vehicle Wash System

 

 

Back to topBack

 

 
2005 copyright logo| Important notices

Last Revision Date : 12 September 2007