General Information

Location

:

Sha Tin, New Territories

Contractor

:

SITA Sha Tin Waste Services Ltd.

Contractor Facility Office Tel : 2649 0213

Capital Cost

:

$210 million

Design Throughput

:

1,200 tonnes per day

Commissioning Date

:

October 1994

Opening Hours

:

07:30 to 23:30

Waste Delivered to

:

North East New Territories Landfill

Major Plant / Equipment

:

Yard Tractors, Highway Tractors, Trailers, Containers, Road Sweeper, Bucket Loader, Bobcat Loader, Tennant Scrubber

Other Facilities

:

Computerized Weighbridge System, Exhaust Ventilation System with Odour Removal Units, Waste Water Treatment Plant, Vehicle Wash System

 

 