Loading

Problems & Solutions

West New Territories (WENT) Landfill

Image of West New Territories (WENT) Landfill
click on the magnifier to view the location map

Background

Location : Nim Wan, Tuen Mun
Area   : 110 ha
Max. height of filling : 170 mPD
Max. depth of waste : 120 m
Capacity : 61 Mm³
Current waste intake : about 7,300 tonnes per day (2014)
Waste types : Municipal waste
    Construction waste
Operation hours : 08:00 to 20:00 (daily throughout the year)
Aftercare period : 30 years after completion of operation

Contractual Arrangement

Contract type : Design, construction, operation, restoration and aftercare to be carried out by the Contractor to the specified performance criteria
Client : Environmental Protection Department
Contractor : SITA Waste Services Ltd.
Contractor Facility Office Tel : 2472 3455
Commencement of construction : May 1993
Commencement of operation : November 1993

Financial Details

Capital cost : $2,000 million
Operation cost : $303 million/year

Capital cost is in money-of-the-day prices.
Operation cost is in 2014/15 financial year.

 

 

Back to topBack

User review date: 
Thursday, 24 December, 2015