Background

Location : Nim Wan, Tuen Mun
Area -land : 67 ha
  -marine : 43 ha
  -Total : 110 ha
Max. height of filling : 170 mPD
Max. depth of waste : 120 m
Capacity : 61 Mm³
Current waste intake : about 6,400 tonnes per day (2012)
Waste types : Municipal waste
    Construction waste
Operation hours : 08:00 to 20:00 (daily throughout the year)
Operation life : up to about 2018/19
Aftercare period : 30 years after completion of operation

Contractual Arrangement

Contract type : Design, construction, operation, restoration and aftercare to be carried out by the Contractor to the specified performance criteria
Client : Environmental Protection Department
Contractor : SITA Waste Services Ltd.
Contractor Facility Office Tel : 2472 3455
Commencement of construction : May 1993
Commencement of operation : November 1993

Financial Details

Capital cost : $2,000 million
Operation cost : $223 million/year

Capital cost is in money-of-the-day prices.
Operation cost is in 2012/13 financial year.

 

 