Hoarding
at West Rail Site Formation Works in Yuen Long
The
project involved site formation works carried out at Yuen
Long for KCRC West Rail Construction.
Environmental Concern
Dust
and mud arising from site formation or transportation of construction
materials were the major concern affecting the users of Pat
Heung Road and Kam Tin Road.
 |
 |
 |
| No
hoarding was erected at the site boundary and the public
road was very dusty |
Vehicle
was not washed to remove dusty materials before leaving
the construction site |
Vehicle
washing facilities not provided at a vehicle exit point
and dusty deposits were brought to public road. |
Measures
Adopted
Hoarding
- Hoarding along Pat Heung Road and Kam Tin Road was erected.
Treatment
- In addition, vehicle-washing facilities were provided at
every discernible or designated vehicle exit points.
 |
 |
 |
| Hoarding
erected along site boundary |
The
vehicle exit of the construction site was cleaned |
Vehicle
washing facilities provided and in use at a vehicle exit
point |
Observations
& Achievements
Through
installation of the vehicle washing facilities and erection
of handing, the dust level along Pat Heung Road and Kam Tin
Road were greatly reduced.
|