Redressing Noise by Engineering Measures
The Executive Council endorsed in November 2000 the policy to address the noise impacts from existing roads. The policy has two strands: to retrofit barriers on existing roads and to re-surface local roads with low-noise material.
Retrofitting Barriers
31 road sections with noise exceeding 70 dB(A) have been identified as technically feasible for retrofitting noise barriers and are included in the public works programme. The criteria for retrofitting include requirements that the barrier does not obstruct emergency access or fire-fighting; that it does not reduce road safety or impede pedestrian and vehicular movements; that it does not cause severe disruption to commercial or social activities; and that there be adequate space for the barrier or enclosure. Retrofitting noise barriers on two sections of Fanling Highway were completed in 2006. Retrofit projects along 6 road sections have been upgraded to Cat A and construction works are in progress/being arranged. Follow-up action for noise barriers along other road sections are in progress (see below table). Upon the completion of these projects, 28 000 flats will have noise levels lowered by one to over 20 decibels and the majority of the beneficiaries along the roads will have noise lowered to below the 70 dB(A) limit.
Resurfacing Local Roads
Low-noise road surfacing materials can reduce noise by up to 3 dB(A) and 72 local road sections have been deemed suitable for the surfaces. In addition, in view of the improvement of the durability of the low noise road surface materials, 26 more local roads beyond the original engineering criteria have also been included in the trial programme. It is expected that the whole resurfacing programme will benefit about 60,000 flats upon resurfacing of all the candidate roads.
|
List of 36 Retrofit Projects included in the Public Works Programme
(as at 31.12.2007)
| Ref No. |
Road Section |
PWP Category |
|
1
|
Fanling Highway (near Choi Yuen Estate) (1)
|
Cat A
|
|
2
|
Fanling Highway (near Fanling Centre) (1)
|
Cat A
|
|
3
|
Cheung Pei Shan Road (2)
|
Cat A
|
|
4
|
Yuen Shin Road (near Kwong Fuk Estate)
|
Cat A
|
|
5
|
Tseung Kwan O Road (near Hing Tin Estate) (2)
|
Cat A
|
|
6
|
Tseung Kwan O Road (near Tsui Ping (South) Estate) (2)
|
Cat A
|
|
7
|
Tsing Tsuen Bridge (Tsuen Wan and Tsing Yi)
|
Cat A
|
|
8
|
Kwun Tong Bypass
|
Cat A
|
|
9
|
Tuen Mun Road (Tsuen Wan)
|
Cat B
|
|
10
|
Tuen Mun Road (Yau Kom Tau)
|
Cat B
|
|
11
|
Tuen Mun Road (Sham Tseng)
|
Cat B
|
|
12
|
Tuen Mun Road (Agnlers' Beach)
|
Cat B
|
|
13
|
Tuen Mun Road (Tsing Lung Tau)
|
Cat B
|
|
14
|
Tuen Mun Road (Castle Peak Bay)
|
Cat B
|
|
15
|
Tuen Mun Road (Sam Shing Hui)
|
Cat B
|
|
16
|
Fanling Highway (Po Shek Wu Road to East Rail Fanling Station
|
Cat B
|
|
17
|
Fanling Highway (East Rail Fanling Station to Wo Hing Road)
|
Cat B
|
|
18
|
Sha Tin Road
|
Cat B
|
|
19
|
Tai Po Road (Sha Tin Section)
|
Cat B
|
|
20
|
Yuen Wo Road
|
Cat B
|
|
21
|
Tai Po Tai Wo Road
|
Cat B
|
|
22
|
Ma Wang Road
|
Cat B
|
|
23
|
Chai Wan Road
|
Cat D
|
|
24
|
Tuen Mun Road (Town Centre)
|
Cat B
|
|
25
|
Tuen Mun Road (Fu Tei)
|
Cat B
|
|
26
|
Po Lam Road North
|
Cat B
|
|
27
|
Po Ning Road
|
Cat B
|
|
28
|
Tai Po Road (Sham Shui Po)
|
Cat B
|
|
29
|
Hoi On Road
|
Cat B
|
|
30
|
New Clear Water Bay Road
|
Cat B
|
|
31
|
Ma On Shan Road (3)
|
Cat B
|
Notes:
(1) Works completed in February 2006
(2) Under construction
(3) Works under review (low noise surfacing material adopted as an alternative noise mitigation measure)
|
|