Conditions of Approval to Apply Directly for an Environmental Permit

  1. The Applicant shall submit, prior to application for Environmental Permit, a tree preservation plan in line with the joint Works Bureau Technical Circular 24/94 and Planning, Environment and Lands Bureau Technical Circular 3/94;

  2. The Applicant shall submit, prior to application for Environmental Permit, a set of elevation plans of the proposed sewage pumping station with details of the colour scheme, facade treatment and landscape proposal for the Director's agreement;

  3. The Applicant shall submit, prior to application for Environmental Permit, detailed noise calculations to the Director demonstrating that the operation noise level from all major mechanical equipments (e.g. pumps, fans, automatic racking screen, etc.) in the proposed pumping station and the cumulative noise level from the proposed and the adjacent existing/planned pumping stations can be adequate mitigated to compile with the EIAO-TM criteria; and

  4. The Applicant shall implement all environmental mitigation measures identified in the Project Profile and/or proposed to the Director as required under conditions 1 to 3 above.