Environmental Permit No. EP-01/075/2003/A

環境許可證編號EP-01/075/2003/A

                                                                    

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Section 10,12 & 13

環境影響評估條例

(499)

10,12 &13

 

FURTHER ENVIRONMENTAL PERMIT TO CONSTRUCT A DESIGNATED PROJECT

建造指定工程項目而發出環境許可證

 

PART A (MAIN PERMIT)

A部      (許可證主要部分)

 

            Pursuant to Sections 10 and 12 of the Environmental Impact Assessment Ordinance (the Ordinance), the Director of Environmental Protection (the Director) granted the Further Environmental Permit (FEP-01/075/2003) to Sun Fook Kong (Civil) Limited (the "Permit Holder") on 6 February 2003. Persuant to Section 13 of the Ordinance, the Director amends the Further Environmental Permit (FEP-01/075/2003) based on the Application No. VEP-93/2003. The amendments, described below, are incorporated into this Environmental Permit (EP-01/075/2003/A). This Environmental Permit as amended is for the construction of the designated project described in Part B of this Permit subject to the conditions described in or attached in Part C of this Permit.

 

根據環境影響評估條例(條例)1012條的規定,環境保護署署長(署長)200326環境許可證(環境許可證編號FEP-01/075/2003)批予新福港(土木)有限公司(許可證持有人)根據條例第13的規定署長因應更改環境許可證的申請編號 VEP-93/2003 修訂新的環境許可證編號 FEP-01/075/2003。 以下修訂已包含在本環境許證 (EP-01/075/2003A) 內。 本經修訂的環境許可證可作為建造本許可證B部所說明的指定工程項目﹐但須遵守C部所指明或附載的條件。

 

The issue of this Environmental Permit is based on the documents, approvals or permissions described below:

本環境許可證的發出,乃依據下表所列的文件、批准或許可作為根據:

Application No.

申請書編號

VEP-093/2003

Document in the Register

登記冊上文件

 

 

 

 

Yuen Long Bypass Floodway Feasibility Study

Final EIA Study Report, Executive Summary and Final Environmental Monitoring & Audit Manual (Register No. AEIAR003/1998) [hereinafter referred to as "the EIA Report"]

元朗排水繞道可行性研究 - 最後環評研究報告、行政摘要及最後環境監察及審核手冊(登記冊編號:AEIAR003/1998) [下稱"環評報告"]

 

Yuen Long Bypass Floodway Feasibility Study

Reassessment of Ecological Mitigation Measures

Final Report [Hereinafter referred to as "the Ecological Reassessment Report"]

元朗排水繞道可行性研究 - 重新評估生態緩解措施最後報告[下稱"生態重估報告"]

 

The Director’s letter of approval of the EIA Report dated 17 October 1998, ref ( ) in EP2/N6/I/08 Annex(11).

環境保護署署長於19981017日發出批准環評報告的信件。檔案編號: ( ) in EP2/N6/I/08 Annex(11)

 

Environmental Permit Issued – Permit No.: EP-075/2000 issued on 16 August 2000.

 

簽發的環境許可證許可證編號:EP-075/2000; 2000816日簽發

 

Further Environmental Permit Issued – Permit No.: FEP-01/075/2000 issued on 6 August 2000.

 

簽發的環境許可證許可證編號: FEP-01/075/2003; 200326日簽發

 

Application for Variation of Environmental Permit on 22 April 2003 (Application No. No. VEP-93/2003)

2003422日申請之更改環境許可證

申請編號 VEP-93/2003

 

 

Application No.

申請書編號

Date of Application

申請日期

List of Amendments Incorporated into this Environmental Permit

已包含在本環境許可證內修訂項目

Date of Amendment

修訂日期

VEP-093/2003

22 April 2003

2003422

Vary Condition 3.6 in Part C of FEP-01/075/2003 and add Figure 5 to FEP-01/075/2003.

 

更改環境許可證編號FEP-01/075/2003 C部條件第3.6及加上圖5

19 May 2003

 2003519

 

 

 

 

 

 

                                                                                                                                  

                          Date                                                  (Elvis W.K. AU)

                         日期                                  Assistant Director of Environmental Protection

                                                                                     (Environmental Assessment and Noise)

                                                                                    for Director of Environmental Protection

                                                                                                   環境保護署署長

                                                                               助理署長(環境評估及噪音)區偉光代行

 

PART B  ( DESCRIPTIONS OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

            Hereunder is the description of the designated project mentioned in Part A of this environmental permit:

下列為本環境許可證A部所提及的指定工程項目的說明: 

       

Title of Designated Project

指定工程項目的名稱

Yuen Long Bypass Floodway

[This designated project is hereinafter referred to as "the Project".]

元朗排水繞道[這指定工程項目下稱工程項目]

Nature of Designated Project

指定工程項目的性質

 

Waterways and Drainage Works

水道及排水工程

Location of Designated Project

指定工程項目的地點        

Yuen Long

(The location and alignment of the designated project are shown in Figure 1.1 to Figure1.7 of this permit.)

(指定工程項目的地點及路線,見載於本許可證的圖1.1-1.7)

Scale and Scope of Designated Project

指定工程項目的規模和範圍

A drainage channel of width less than 100m. The scope of the project includes construction of

i)  A main drainage channel from Yuen Long Main Nullah to Kam Tin Channel. The channel will have concrete lined bed with grasscrete sides;

ii)An ancillary road system;

iii)   Associated pumping facilities; and

iv) Landscaping works.

Full description of the scale and scope of the Project are given in section 3.4 of the EIA Report (Register No. AEIAR003/1998) and section 5 of the Ecological Reassessment Report submitted with the environmental permit application.

排水道的度少於100米。工程項目的範圍包括進行下列建造工程:

i)元朗大明渠至錦田排水道的一條主要排水道。排水道底部中間將砌襯混凝土,底部兩旁則鋪砌草面物料

ii)  一個附屬道路系統

iii)相連的泵水設施

iv)景觀美化工程。

工程項目規模與範圍的詳細說明,見載於環評報告第3.4(登記冊編號:AEIAR003/1998)和隨環境許可證EP-075/2000 提交的生態重估報告第5節。

 

 

 


 

PART C (PERMIT CONDITIONS)

 

1.      General Conditions

 

1.1           The Permit Holder shall ensure full compliance with all conditions of this environmental permit (the Permit). Any non-compliance may constitute a contravention of the Environmental Impact Assessment Ordinance (the Ordinance) and may become the subject of appropriate action to be taken under the Ordinance.

       

1.2     This Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation the Noise Control Ordinance (Cap.400), Air Pollution Control Ordinance (Cap.311), Water Pollution Control Ordinance (Cap.358), Dumping at Sea Ordinance (Cap.466), the Waste Disposal Ordinance (Cap.354). This Permit does not of itself constitute any ground of defense against any proceedings instituted under any legislation.

       

1.3       The Permit Holder shall make copies of this Permit together with all document referred to in Part A of this Permit readily available at all times for inspection by the Director or his authorized officers at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.

 

1.4      The Permit Holder shall give a copy of this permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understand all conditions and all requirements incorporated by the Permit. The site(s) refers to the site(s) of the construction of the Project and should mean the same hereinafter.

 

1.5      The Permit Holder shall display conspicuously a copy of this permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended permit, is displayed at such locations.  If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

 

1.6      The Permit Holder shall construct the Project as described in Part B of this Permit.

 

1.7           The Permit Holder shall ensure that the Project is constructed in accordance with the information and recommended mitigation measures contained in the EIA Report (EIAO Register No. AEIAR 003/1998) and the Ecological Reassessment Report referred to in Part A of this Permit. Where recommendations in the EIA Report and the Ecological Assessment Report are not expressly referred in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or amended in this Permit.

 

1.8           All deposited submissions, as required under this Permit, shall be rectified in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise specified by the Director.

 

1.9           All submissions to the Director, as required under this permit, shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong).

 

 

1.10        The Permit Holder shall notify the Director the commencement date of construction of the Project at least 1 week prior to the commencement of construction of the Project. The Permit Holder shall notify the Director immediately if there is any change of the commencement date of the construction.

 

1.11        This Permit shall not remove the responsibility of any person to comply with the conditions set out in Part C of the Environmental Permit No. EP-075/2000 or where applicable any subsequent environmental permit amended by the Director under the EIA Ordinance.

 

 

2.              Submissions or Measures before Commencement of Construction

 

2.1           Before the commencement of construction of the Project, an Independent Environmental Checker (IEC) with at least 7 years experience in environmental monitoring and auditing (EM&A) or environmental management shall be employed. The IEC shall audit the overall EM&A programme including the implementation of environmental mitigation measures, submissions relating to EM&A, and any other submissions required under this Permit. In addition, the IEC shall be responsible for verifying and certifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit.    

       

2.2      An Environmental Team (ET) shall be established before the commencement of construction of the Project. The ET shall be supervised by a team leader who has at least 7 years experience in EM&A or environmental management. The ET leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual.

 

2.3       Before the commencement of construction works, 3 sets of 1 in 1000 scale layout drawings, with an Explanatory Statement showing the works boundaries, drainage channel, ancillary road alignments and any other facilities assessed in the EIA Report/Ecological Reassessment Report shall be deposited to the Director.  The layout drawings shall indicate the locations of environmental mitigation measures recommended in the EIA Report (Register No AEIAR 003/1998) and the Ecological Reassessment Report referred to in this Permit.  The layout drawings and the Explanatory Statement so provided shall be verified and certified by the IEC as being in conformity to the information and recommendations contained in the EIA Report (Register No AEIAR 003/1998) and the Ecological Reassessment Report referred to in this Permit. The Project shall be constructed in accordance with the information and recommendations contained in the EIA Report (Register No AEIAR 003/1998) and the Ecological Reassessment Report.

 

2.4           3 sets of 1 to 1000 scale Landscape Master Plan (the Plan) shall be submitted to the Director for approval, no later than 3 months after the commencement of construction of the Project. The Plan shall show the detailed landscape proposals during the construction and operation stages of the Project, and an implementation programme of the landscape works. The Plan shall include a management and maintenance schedule indicating how the landscape features will be managed and maintained. The Plan shall be verified and certified by the IEC, as being in conformity to the information and recommendations contained in the EIA Report (Register No AEIAR 003/1998). The Permit Holder shall provide additional copies of the Plan to the Director upon request from the Director. All measures recommended in the approved Plan shall be fully implemented in accordance with the details and time schedule set out in the Plan.

 

 

2.5           At least 4 weeks prior to the commencement of construction works, 3 sets of 1 to 500 scale Ecological Mitigation Plan (EMP) shall be submitted to the Director for approval. The EMP shall contain the detailed ecological mitigation proposals including, but not limited to the following measures to be adopted of the Project:-

 

a)   the grasscrete design of the channel sides and base;

b)   the design of reedbeds and water clean-up area for Ponds 9, 11 and 11B; (location shown in Figure 2)

c) the pond re-profiling design of Ponds 12, 14 and 15; and (location shown in Figure 3)

b)  an implementation programme of the ecological mitigation measures recommended in the EIA Report (Register No AEIAR 003/1998) and the Ecological Reassessment Report.

 

  The EMP shall be verified and certified by the IEC, as being in conformity to the information and recommendations contained in the EIA Report (Register No AEIAR 003/1998). Additional copies of the EMP shall be provided upon request from the Director. All measures recommended in the approved EMP shall be fully implemented in accordance with the details and time schedule set out in the Plan. 

       

2.6      Three sets of an environmental method statement for the dredging, stockpiling and transportation of sediment; and the stockpiling and transportation of construction waste and excavated material from within the works boundaries shall be deposited with the Director before the commencement of construction of works. The submission to the Director shall be verified and certified by the IEC, as being in conformity to the information and recommendations contained in the EIA Report (Register No AEIAR 003/1998) and the Ecological Reassessment Report. All mitigation measures arising from the approved environmental method statement shall be fully implemented in accordance with the details and time schedule set out in the method statement.

 

2.7      Three sets of 1 to 1000 scale layout drawings for the following shall be verified and certified by the IEC as being in conformity to the information and recommendations contained in the EIA Report and the Ecological Reassessment Report referred to in this Permit and deposited with the Director before the commencement of the construction of the relevant works ofthe Project:

       

a)      permanent drainage channels showing the incorporation of sediment traps/pits to enhance deposition; and

            

          b)   perimeter channels, and earth bunds at the site boundaries to intercept storm runoff from off-site.

            

2.8      3 sets of environmental method statement incorporating noise reducing measures recommended in sections 8.1.40 of the EIA Report (Register No. AEIAR 003/1998) and Section 3.7.6 of the EM&A Manual shall be submitted to the Director. The environmental method statement shall be verified and certified by the IEC and deposited with the Director at least 2 weeks before the commencement of construction works of the Project. The noise reducing measures shall be fully implemented.

       

   

3.           Measures during the Construction Period

 

3.1       All design and construction measures described in the submissions approved or deposited under section 2 above shall be properly implemented.

 

3.2           The sides and base of the channel bank between chainage CH 1+340 and 3+545 shall be lined with grasscrete design detailed in the EMP to be approved under condition 2.5 above.

 

3.3           Ponds 9, 11 and 11B (location shown in Figure 2 of this Permit) shall be designed and constructed as a water clean-up area, which shall be included in the EMP to be approved under condition 2.5 above.

 

3.4           Ponds 12, 14 and 15 (location shown in Figure 3) shall be re-profiled in accordance with the proposals in the EMP to be approved under condition 2.5 above.

 

3.5           The channel banks shall be planted with tree species selected from the list set out in Table 5.15 of the EIA Report (Register No. AEIAR 003/1998).

 

3.6           To protect the egretry adjacent to the fung shui knoll (location shown in Figure 3 and 4 of this Permit), no piling works shall be carried out for the Project area north of Route 3 shown on Figure 1.6 and 1.7, between March and July for the entire construction period except the bore piling works to be carried out during May to July 2003 at the location as shown in Figure 5.

       

 

4.           Environmental Monitoring and Audit Requirements

 

4.1           The EM&A programme shall be implemented in accordance with the procedures and requirements set out in the EM&A Manual. Any changes to the programme shall be certified by the ET Leader and verified by the IEC as conforming to the requirements set out in the EM&A Manual and shall be approved by the Director.

 

4.2           Samples and measurements for noise, air quality, water quality and ecological monitoring shall be taken in accordance with the requirements of the EM&A Manual of the EIA Report:

       

          a) conducting baseline air, noise and water quality and ecological monitoring at the specified locations and frequencies;

       

          b) conducting impact monitoring on air quality, noise quality, water quality and ecological at the specified locations and frequencies;

       

          c) in cases where specified criteria in the EM&A Manual are exceeded, carrying out remedial actions in accordance with the Event/Action Plan, as set out in the EM&A Manual; and

       

          d) logging and keeping records of the details of a) to c) above, within 3 working days of the collection of data or completion of remedial action, for the purposes of preparing and submitting the Environmental Monitoring and Audit Reports and Independent Environmental Checker’s Report, and to make available the information for inspection on site.

 

4.3           All environmental monitoring and audit data submitted under this Permit shall be true, valid and correct.

 

4.4           Four copies and one soft copy of the Baseline Monitoring Report verified by the Independent Environmental Checker shall be submitted to the Director 4 weeks before the commencement of any construction works that would affect the monitoring results. Additional copies of the Baseline Monitoring Report may be required by the Director.

 

 

 

4.5           Four copies and one soft copy of monthly EM&A Report verified by the Independent Environmental Checker shall be submitted to the Director within 10 working days after the end of the reporting month. Additional copies of the monthly EM&A Report may be required by the Director.

 

4.6           The submitted reports as required in condition 4.4 and 4.5 shall be rectified in accordance with the comments made by the Director within one month of receipt of the Director's comments, or otherwise specified by the Director.

 

 

5.  Electronic Reporting of EM&A Information

 

5.1   To facilitate public inspection of the Baseline Monitoring Report and monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later) unless otherwise agreed by the Director and submitted at the same time as the hard copies as described in Conditions 4.4 and 4.5 above.  For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document.  Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made.  All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director.  The content of the electronic copies of these Reports must be the same as the hard copies.

 

 

Notes:

 

1.   This Permit consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project) and PART C (Permit Conditions). Any person relying on this Permit should obtain independent legal advice on the legal implications under the Ordinance, and that the following notes are for general information only.

 

2.   The Permit Holder may apply under Section 13 of the Ordinance to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original Permit displayed on the construction sites, by the amended Permit.

    

3.   A person who assumes the responsibility for the whole or a part of the designated project may, before he assumes responsibility for the designated project, apply under Section 12 of the Ordinance to the Director for a further environmental permit.

    

4.   Under Section 14 of the Ordinance, the Director with the consent of the Secretary for Environment, Transport and Works, may suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit shall be removed from display at the construction sites.

    

5.   If this permit is cancelled or surrendered during the construction of the Project, another environmental permit must be obtained under the Ordinance before the Project could be continued. It is an offence under Section 26(1) of the Ordinance to construct or operate a designated project listed in Part I of Schedule 2 of the Ordinance without a valid environmental permit.

    

6.  Any person who constructs the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable:-

 

(i)                  on a first conviction on indictment to a fine of $ 2 million and to imprisonment for 6 months;

 

(ii)                on a second or subsequent conviction on indictment to a fine of $ 5 million and to imprisonment for 2 years;

 

(iii)               on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

 

(iv)              on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

 

(v)                in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $ 10,000 for each day on which he is satisfied the offence continued.

 

7.    The Permit Holder may appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of receipt of this Permit.

 

 

 


 


圖 1.1 | 圖 1.2 | 圖 1.3 | 圖 1.4 | 圖 1.5 | 圖 1.6 | 圖 1.7 | 圖 2 | 圖 3 | 圖 4 | 圖 5


[ ] / [ ]