Environmental Impact Assessment Ordinance
Bullet List of EIA Reports Approved by the Director prior to the commencement of the Ordinance
Bullet List of EIA Reports Received By the Director Bullet EIA Reports Exhibited for Public Inspection Bullet EIA Reports Approved under the Ordinance

List of EIA Reports Received By the Director
To Search by District or Application Number. disclaimers
copyright

BulletYuen Long District

Application No. Environmental Impact Assessment Report Applicant Status
EIA-302/2023 San Tin / Lok Ma Chau Development Node Civil Engineering and Development Department
- Applicant was informed on 30 Jan 2024 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 2 Feb 2024 to 2 Mar 2024.
EIA-301/2023 Northern Link MTR Corporation Limited
- Applicant was informed on 24 November 2023 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 13 Dec 2023 to 11 Jan 2024.

- Approved with conditions on 9 Feb 2024.
EIA-300/2023 Widening of Yuen Long Highway (Section between Lam Tei and Tong Yan San Tsuen) Highways Department
- Applicant was informed on 20 November 2023 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 30 Nov 2023 to 29 Dec 2023.

- Approved without conditions on 25 Jan 2024.
EIA-281/2022 Hung Shui Kiu Effluent Polishing Plant Drainage Services Department

- Applicant was informed on 1 Jun 2022 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 15 Jun 2022 to 14 Jul 2022.

Approved with conditions on 19 Oct 2022.

EIA-278/2022 Yuen Long South Effluent Polishing Plant Drainage Services Department

- Applicant was informed on 25 Mar 2022 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 6 Apr 2022 to 5 May 2022.

Approved with conditions on 25 Jul 2022.

EIA-274/2021 Mai Po Nature Reserve Infrastructure Upgrade Project World Wide Fund For Nature Hong Kong

- Applicant was informed on 2 Nov 2021 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 19 Nov 2021 to 18 Dec 2021.

Approved with conditions on 16 Feb 2022.

EIA-269/2021 Yuen Long Barrage Scheme Drainage Services Department

- Applicant was informed on 16 Mar 2021 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 29 Mar 2021 to 27 Apr 2021.

Approved without conditions on 24 May 2021.

EIA-268/2020 Drainage Improvement Works Near Four Villages in Yuen Long - Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che Drainage Services Department

- Applicant was informed on 21 Jan 2021 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 22 Feb 2021 to 23 Mar 2021.

Approved with conditions on 3 June 2021.

EIA-262/2020 Improvement of Yuen Long Town Nullah (Town Centre Section) Drainage Services Department

- Applicant was informed on 7 Apr 2020 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 22 Apr 2020 to 21 May 2020.

Approved with conditions on 31 July 2020.

EIA-261/2019 Upgrading of Remaining Sections of Kam Tin Road and Lam Kam Road Highways Department

- Applicant was informed on 31 Jan 2020 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 14 Feb 2020 to 14 Mar 2020.

Approved with conditions on 27 May 2020.

EIA-259/2018 Yuen Long Effluent Polishing Plant Drainage Services Department

- Applicant was informed on 19 Feb 2019 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 28 Feb 2019 to 29 Mar 2019.

Approved with conditions on 25 Apr 2019.

EIA-255/2018 Proposed Interim Sewage Treatment Plant and Effluent Reuse Facility at Wo Shang Wai, Yuen Long Profit Point Enterprises Limited

- Applicant was informed on 6 July 2018 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 20 Jul 2018 to 18 Aug 2018.

Approved without conditions on 3 Sep 2018.

EIA-254/2017 Housing Sites in Yuen Long South Civil Engineering and Development Department

- Applicant was informed on 27 Jul 2017 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 8 Aug 2017 to 6 Sep 2017.

Approved with conditions on 30 Nov 2017.

EIA-248/2016 Hung Shui Kiu New Development Area Civil Engineering and Development Department
EIA-242/2016 Proposed Low-rise and Low-density Residential Development at Various Lots and their Adjoining Government Land in D.D. 104, East of Kam Pok Road, Mai Po, Yuen Long. N.T. Glory Queen Limited
EIA-241/2016 Elevated Pedestrian Corridor in Yuen Long Town Connecting with Long Ping Station Highways Department
EIA-237/2016 Additional Gas-fired Generation Units Project Castle Peak Power Company Limited
EIA-232/2015 Operation of the Existing Tai Lam Explosives Magazine at Tai Shu Ha, Yuen Long for Liantang / Heung Yuen Wai Boundary Control Point Project Dragages Hong Kong Ltd.
EIA-231/2015 Operation of the Existing Tai Lam Explosives Magazine at Tai Shu Ha, Yuen Long for Liantang / Heung Yuen Wai Boundary Control Point Project Dragages Hong Kong Ltd.
- Application was withdrawn by applicant on 4 Aug 2015.

EIA-227/2015 Comprehensive Development and Wetland Protection near Yau Mei San Tsuen Asia King Development Limited
EIA-220/2014 Proposed Residential Cum Passive Recreation Development within "Recreation" Zone and "Residential (Group C)" Zone at Various Lots in DD 104, Yuen Long, N.T. Capital Chance Ltd
EIA-212/2013 Development of Lok Ma Chau Loop Civil Engineering and Development Department
EIA-205/2012 Construction of Cycle Tracks and the associated Supporting Facilities at Nam Sang Wai, Yuen Long New Territories North and West Development Office, Civil Engineering and Development Department
- Application was withdrawn by applicant on 1 Apr 2016.

EIA-204/2012 Construction of Cycle Tracks and the associated Supporting Facilities at Nam Sang Wai, Yuen Long New Territories North and West Development Office, Civil Engineering and Development Department
- Application was withdrawn by applicant on 21 Nov 2012.

EIA-169/2009 Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link MTR Corporation Limited
- Applicant was informed on 15 July 2009 of the suitability of the report for public inspection.
EIA-164/2009 Upgrading of Remaining Sections of Kam Tin Road and Lam Kam Road Highways Department
- Applicant was informed on 28 Apr 2009 of the suitability of the report for public inspection.
EIA-163/2008 Hang Hau Tsuen Channel at Lau Fau Shan New Territories North and West Development Office, Civil Engineering and Development Department
- Applicant was informed on 3 Feb 2009 of the suitability of the report for public inspection.
EIA-161/2008 Construction of a Secondary Boundary Fence and new sections of Primary Boundary Fence and Boundary Patrol Road Secretary for Security
- Applicant was informed on 23 Jan 2009 of the suitability of the report for public inspection.
EIA-160/2008 Improvement to Pok Oi Interchange Highways Department

- Applicant was informed on 13 Jan 2009 of the suitability of the report for public inspection.

EIA-159/2008 Construction of Cycle Tracks and the associated Supporting Facilities from Sha Po Tsuen to Shek Sheung River Civil Engineering and Development Department
- Applicant was informed on 2 Jan 2009 of the suitability of the report for public inspection.
EIA-149/2008 Proposed Development at Fung Lok Wai, Yuen Long at Lot 1457 R.P. in D.D.123 Mutual Luck Investment Limited

- Applicant was informed on 14 July 2008 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 8 Aug 2008 to 6 Sep 2008.

- Approved with conditions on 27 Nov 2009.

EIA-144/2008 Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Profit Point Enterprises Limited

- Applicant was informed on 26 Mar 2008 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 14 Apr 2008 to 13 May 2008.

- Approved with conditions on 31 Jul 2008.

EIA-136/2007 Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Profit Point Enterprises Limited

- Application was withdrawn by applicant on 8 Aug 2007.

EIA-132/2007 Proposed Development at Fung Lok Wai, Yuen Long at Lot 1457 R.P. in D.D.123 Mutual Luck Investment Limited

- Application was withdrawn by applicant on 30 May 2007.

EIA-122/2006 Yuen Long, Kam Tin, Ngau Tam Mei & Tin Shui Wai Drainage Improvement Stage 1, Phase 2B - Kam Tin Secondary Drainage Channel KT13 Drainage Services Department
- Applicant was informed on 2 Aug 2006 of the suitability of the report for public inspection.
 
- Report was exhibited for public to comment from 22 Aug 2006 to 20 Sep 2006.
 
- Approved without conditions on 24 Oct 2006.
EIA-117/2005 Yuen Long, Kam Tin, Ngau Tam Mei & Tin Shui Wai Drainage Improvement Stage 1, Phase 2B - Kam Tin Secondary Drainage Channel KT13 Drainage Services Department

- Application was withdrawn by applicant on 6 Feb 2006.
 
EIA-094/2004 Yuen Long and Kam Tin Sewerage and Sewage Disposal Stage 2 Drainage Services Department
- Applicant was informed on 17 Mar 2004 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 23 Apr 2004 to 22 May 2004.

- Approved without conditions on 17 Jun 2004.
EIA-093/2004 Improvements to San Tin Interchange Highways Department
- Applicant was informed on 1 Mar 2004 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 8 Mar 2004 to 7 Apr 2004.

- Approved without conditions on 3 May 2004.
EIA-086/2002 Upgrading and expansion of San Wai Sewage Treatement Works and expansion of Ha Tsuen Pumping Station Drainage Services Department
- Applicant was informed on 23 Dec 2002 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 25 Feb 2003 to 26 Mar 2003.

- Approved without conditions on 12 May 2003.
EIA-082/2002 Shenzhen Western Corridor Highways Department
- Applicant was informed on 9 Sep 2002 of the suitability of the report for public inspection.

- Report was exhibited for public to comment from 11 Sep 2002 to 10 Oct 2002.

- Approved with conditions on 4 Nov 2002.
EIA-078/2002 Deep Bay Link Highways Department
- Applicant was informed on 10 Jul 2002 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 23 Jul 2002 to 21 Aug 2002.

- Approved with conditions on 13 Sep 2002.
EIA-074/2002 Yuen Long and Kam Tin Sewerage and Sewage Disposal Stage 1 Packages 1A-1T and 1B-1T - Kam Tin Trunk Sewerage Phase I and II Drainage Services Department - Applicant was informed on 7 May 2002 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 11 Jun 2002 to 10 Jul 2002.

- Approved with conditions on 26 Aug 2002.
EIA-071/2001 Sheung Shui to Lok Ma Chau Spur Line Kowloon-Canton Railway Corporation - Applicant was informed on 2 Jan 2002 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 7 Jan 2002 to 5 Feb 2002.

- Approved with conditions on 11 Mar 2002.
EIA-067/2001 Widening of Yuen Long Highway between Lam Tei and Shap Pat Heung Interchange Highways Department - Applicant was informed on 14 Dec 2001 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 3 Jan 2002 to 1 Feb 2002.

- Approved with conditions on 22 May 2002.
EIA-044/2000 Sheung Shui to Lok Ma Chau Spur Line - Environmental Impact Assessment Kowloon-Canton Railway Corporation - Applicant was informed on 7 June 2000 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 12 June 2000 to 11 July 2000.

- The ACE EIA sub-committee and ACE were consulted on 27 June, 6 July, 11 July and 17 July 2000.

- Applicant was informed on 16 October 2000 that the report was rejected. (reasons)
EIA-037/2000 Sheung Shui to Lok Ma Chau Spur Line - Environmental Impact Assessment Kowloon-Canton Railway Corporation - Application was withdrawn by applicant on 23 Mar 2000.
EIA-033/1999 Route 10 North Lantau to Yuen Long Highway Investigation and Preliminary Design (Southern Section) Highways Department - Applicant was informed on 23 Nov 1999 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 30 Nov 1999 to 29 Dec 1999.

- Approved with conditions on 02 Feb 2000.
EIA-031/1999 Light Rail Transit (LRT) Extension in Tin Shui Wai Reserve Zone and Grade Separation of the LRT with Pui To Road and Tsing Lung Road in Tuen Mun Kowloon-Canton Railway Corporation - Applicant was informed on 18 Nov 1999 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 26 Nov 1999 to 25 Dec 1999.

- Approved with conditions on 06 Jan 2000.
EIA-030/1999 Tin Shui Wai Phase 4 Rail Extension Kowloon-Canton Railway Corporation - Applicant was informed on 18 Nov 1999 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 26 Nov 1999 to 25 Dec 1999.

- Approved with conditions on 06 Jan 2000.
EIA-026/1999 Essential Public Infrastructure Works Yuen Long, Tin Shui Wai, Tuen Mun Centre and the Eastern Access Road Kowloon-Canton Railway Corporation - Applicant was informed on 30 Sep 1999 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 02 Oct 1999 to 31 Oct 1999.

- Approved with conditions on 28 Dec 1999.
EIA-017/1999 Essential Public Infrastructure Works Associated with West Rail Stations in Yuen Long, Tin Shui Wai and Tuen Mun Centre Kowloon-Canton Railway Corporation - Applicant was informed on 22 June 1999 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 25 Jun 1999 to 24 Jul 1999.

- Approved with conditions on 20 Aug 1999.
EIA-014/1999 Main Drainage Channels and Poldered Village Protection Schemes for San Tin, NWNT EIA Study N.T. North Development Office, Territory Development Department - Applicant was informed on 04 June 1999 of the suitability of the report for public inspection.

- Report was exhibited for the public to comment from 14 Jun 1999 to 13 Jul 1999.

- Approved with conditions on 14 Sep 1999.
EIA-004/1998 Yuen Long Bypass Floodway - Feasibility Study Territory Development Department - Applicant was informed on 31 July 1998 of the suitability of the report for public Inspection.

- Report was exhibited for the public to comment from 14 Aug 1998 to 12 Sep 1998.

- Approved without condition on 10 Oct 1998.