MTR Corporation Limited
|
Tung Chung Line Extension
Monthly EM&A Report No. 25
[for June 2025] |
2.......... Environmental Monitoring and Audit
3.......... implementation status on the environmental protection requirements
List of Tables
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Major Construction Activities in the Reporting Period
Table 2.2 Summary of 1-Hour TSP Monitoring Results in the Reporting Period
Table 2.3 Summary of Construction Noise Monitoring Results in the Reporting Period
Table 3.1 Summary of EP Submissions Status
List of Appendices
Appendix A
Monthly EM&A Report for June 2025 – Contract 1201 Tung Chung West Station
and Tunnels
Table 1.1 Summary of Awarded Works Contracts
|
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental Team |
|
1201 |
Tung Chung West Station and Tunnels |
June 2023 |
Bouygues – Dragages (1201) JV |
AECOM Asia Co. Ltd. |
|
1202 |
Tung Chung East Station and Associated Enabling Works for Track Diversions |
July 2023 |
Paul Y. – CRCC (TUE1202) JV |
Acuity Sustainability Consulting Limited |
Table 2.1 Summary of Major Construction Activities in the Reporting Period
|
Works Contract |
Site |
Construction Activities |
|
1201 |
Tung Chung West (TCW) Area |
TCW · Site set up · H-pile loading test · Drilling · TBM Maintenance Plug · TBM Parking Plug · ELS · Station structure · Pumping test |
|
Tung Chung Crescent (TCC) and Tung Chung Ancillary Building (TCA) Areas |
TCC · Grouting works · Site Roof Cover · Noise Enclosure · U/T Cut & Cover Tunnel Top Slab and Wall TCA · Slurry Treatment Plant in operation · Shaft Excavation & Backfilling · Superstructure Tunnel between TCA and TCW · TBM U/T Tunnelling |
|
|
Barging Facility Area |
· Site setup · Material storage |
|
|
1202 |
Tung Chung East (TCE) Area
|
TCE Station · Substructure works for ancillary building, extended area at station · Superstructure works for main station, ancillary building and extended area at station · Temporary works of tower crane operation · Construction of underground utilities Integrated Entrance (IE) and Temporary Works Area in Area 113 · Truss assembly and installation · Superstructure works · ABWF works East and West Sides of TCE Station · Drainage works · Noise barrier installation Car Park · ABWF works Trackside Works · Construction works for OHL installation · Construction works for cable installation |
Table 2.2 Summary of 1-Hour TSP Monitoring Results in the Reporting Period
|
Monitoring Station ID |
Location |
TSP Concentration (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Exceedance due to the Project Construction (Yes/No) |
|
Works Contract 1201 |
|||||
|
DM-2 |
Sheraton Hong Kong Tung Chung Hotel Shopping Mall |
18.0 – 118.5 |
326 |
500 |
No |
|
DM-3 |
Shops at Tung Chung Crescent |
15.6 – 79.1 |
327 |
500 |
No |
|
DM-4 |
Yat Tung Shopping Centre |
17.7 – 142.3 |
312 |
500 |
No |
|
DM-5b(2) |
Ma Wan Chung Village |
15.6 – 83.0 |
333 |
500 |
No |
|
Works Contract 1202 |
|||||
|
DM-1b(3) |
G/F of Ying Yuet House |
82.8 – 169.6 |
327 |
500 |
No |
|
DM-1a |
TCNTE East - Planned Commercial Development (COM-1/Area 57) |
N/A(4) |
342 |
500 |
No |
Note:
(1) Impact monitoring to be carried out during the construction period of corresponding activity
(2) Alternative monitoring location to DM-5 Ma Wan Chung Village in the approved EM&A Manual
(3) Alternative monitoring location to DM-1 Rosita Yuen Kindergarten in the approved EM&A Manual
(4) Impact monitoring to be carried out upon the commence of operation and during the construction period of the corresponding activity
Table 2.3 Summary of Construction Noise Monitoring Results in the Reporting Period
|
Monitoring Station ID |
Location |
Noise Level (Leq,30mins, dB(A)) |
Limit Level (Leq,30mins, dB(A)) |
Exceedance due to the Project Construction (Yes/No) |
|
Works Contract 1201 |
||||
|
NM2 |
Block 9 of Tung Chung Crescent |
Below Baseline Level – 59.7 |
75 |
No |
|
NM3a(2) |
2/F rooftop of Yat Tung Shopping Centre |
70.8 – 72.5 |
75 |
No |
|
Works Contract 1202 |
||||
|
NM1 |
Ying Tung Estate |
Below Baseline Level – 60.8 |
75 |
No |
|
NM4 |
Tung Chung Area 113 |
N/A(1) |
75 |
No |
|
NM6 |
Tung Chung Area 100 |
N/A(1) |
75 |
No |
Note:
(1) Impact monitoring to be carried out upon the intake of the population and during the construction period of the corresponding activity
(2) Alternative monitoring location to NM3 Yat Tung Estate in approved EM&A Manual
Table 2.4 Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month
|
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
|
1201 |
0 |
0 |
0 |
|
1202 |
0 |
0 |
0 |
Table 3.1 Summary of EP Submissions Status
|
EP Condition (EP-614/2022) |
Submission |
Submission date |
|
Condition 1.12 |
Notification of Commencement Date of Construction |
9 Mar 2023 9 May 2023 (updated) |
|
Condition 1.14 |
Notification of Commencement Date of Operation |
No later than 1 month prior to the commencement of operation |
|
Condition 2.9 |
Notification of Setup of Community Liaison Group |
21 Mar 2023 |
|
Condition 2.10 |
Construction Works Phasing Schedule |
14 Apr 2023 (deposited) |
|
Condition 2.11 |
EP Submission Schedule |
14 Apr 2023 (deposited) |
|
Condition 2.12 |
Management Organization |
28 Apr 2023 18 Sep 2023 (updated) 22 Jan 2024 (updated) 27 Feb 2025 (updated) |
|
Condition 2.13 |
Construction Noise Management Plan (CNMP) · Works Contract No. 1201
· Works Contract No. 1202 |
10 Mar 2023 31 May 2023 (approved) 25 Sep 2023 (approved) 30 Oct 2023 (approved) 8 Nov 2024 (approved) 10 Mar 2023 27 Jun 2023 (approved) 12 Sep 2023 (approved) 1 Nov 2023 (approved) 19 Mar 2025 (approved) |
|
Condition 2.14 |
Rail Noise Mitigation Plan (RNMP) |
13 Jan 2023 25 Aug 2023 (approved) |
|
Condition 2.15 |
Plan on Noise Enclosure at Tung Chung Crescent |
13 Apr 2023 29 Aug 2023 (approved) 1 Nov 2024 (approved) |
|
Condition 2.16 |
Compensatory Tree Planting Implementation Plan |
To be submitted at least 2 months before the commencement of the compensatory tree planting |
|
Condition 2.17 |
Landscape and Visual Mitigation Plan (LVMP) |
12 Apr 2023 13 Dec 2024 (deposited) 16 Apr 2025 (deposited) |
|
Condition 2.18 |
Contingency and Response Plan |
14 Nov 2024 17 Feb 2025 (approved) |
|
Condition 2.19 |
Wastewater Management Plan (WWMP) |
9 Mar 2023 29 May 2023 (approved) 13 Sep 2023 (approved) |
|
Condition 2.20 |
Waste Management Plan (WMP) |
16 Feb 2023 30 Mar 2023 (deposited) |
|
Condition 2.23 |
Further Archaeological Testing Report |
28 Sep 2022 22 May 2023 (deposited) |
|
Condition 2.25 |
Fixed Plant Noise Audit Report |
To be submitted at least 1 month before commencement of operation of the Project |
|
Condition 3.3 |
Baseline Monitoring Report |
28 Apr 2023 17 May 2023 |
|
Condition 3.4 |
Monthly EM&A Report No.1 to 24
Monthly EM&A Report No.25 |
Reported in previous Monthly EM&A Reports This submission |
|
Condition 4.2 |
Dedicated Internet Website |
10 Jul 2023 15 Mar 2024 (updated) |
Monthly EM&A Report
for
Contract 1201
Tung Chung West Station and Tunnels
(June 2025)
Monthly EM&A Report
for
Contract 1202
Tung Chung East Station and Associated Enabling Works for Track Diversions
(June 2025)