TABLE OF CONTENTS
Sign Page
1 Introduction.. 1
1.1 Project Background. 1
1.2
Location and Scope of the Project 1
1.3
Purpose of this Manual 2
1.4
Project Organisation. 3
1.5
Structure of the Manual 5
2 Air
Quality.. 7
2.1
Introduction. 7
2.2
Monitoring Parameters. 7
2.3
Monitoring Equipment 8
2.4
Laboratory Measurement / Analysis (For TSP Measurement only) 12
2.5
Monitoring Locations. 12
2.6
Baseline Monitoring (for TSP only) 14
2.7
Impact Monitoring (for TSP, RSP and FSP) 15
2.8
Event and Action Plan. 15
2.9
Mitigation Measures. 20
2.10
Audit Requirements. 20
3 Noise.. 21
3.1
Introduction. 21
3.2
General Monitoring Requirement and Equipment 21
3.3
Monitoring Parameters. 22
3.4
Monitoring Locations. 22
3.5
Baseline Monitoring. 23
3.6
Impact Monitoring. 23
3.7
Event and Action Plan. 23
3.8
Mitigation Measures. 25
3.9
Audit Requirements. 25
4 Water
Quality.. 26
4.1
Introduction. 26
4.2
Water Quality Parameters. 26
4.3
Sampling Procedures and Monitoring Equipment 26
4.4
Laboratory Measurement / Analysis. 28
4.5
Water Quality Monitoring Stations. 28
4.6
Details of Water Quality Monitoring. 30
4.7
Construction Site Audits. 33
5 Waste
Management implications. 35
5.1
Introduction. 35
5.2
Mitigation Measures. 35
5.3
Audit Requirement 36
6 MarinE
Ecology.. 37
6.1
Introduction. 37
6.2
Mitigation Measures. 37
6.3
Monitoring Requirements. 37
6.4
Audit Requirements. 37
7 Fisheries. 38
7.1
Introduction. 38
7.2
Mitigation Measures. 38
7.3
Monitoring and Audit Measures. 39
8 Landscape
and Visual.. 40
8.1
Introduction. 40
8.2
Mitigation Measures. 40
8.3
Audit Requirements. 40
9 Cultural
Heritage.. 41
9.1
Introduction. 41
9.2
Mitigation Measures. 41
10 Site Inspection
/ Audit.. 43
10.1
Site Inspection Requirements. 43
10.2
Compliance with Legal and Contractual Requirements. 44
10.3
Environmental Complaints. 44
11 Reporting.. 47
11.1
Introduction. 47
11.2
Electronic Reporting of EM&A Information. 47
11.3
Baseline Monitoring Report 47
11.4
Monthly EM&A Reports. 48
11.5
Quarterly EM&A Summary Reports. 53
11.6
Final EM&A Review Report for Construction Phase. 54
11.7
Data Keeping. 55
11.8
Interim Notifications of Environmental Quality Limit Exceedances. 56
List of
tables
Table 2.1
Recommended Performance Metrics and Target Values for On-site Checking
of PM Monitoring Equipment 10
Table 2.2 Proposed Construction
Air Quality Monitoring Stations. 13
Table 2.3 Summary of
Construction Air Quality Impact Monitoring Programme 15
Table 2.4 Action and Limit
Levels for Construction Air Quality Impact 16
Table 2.5 Event and Action Plan
for Construction Air Quality Impact (TSP monitoring) 17
Table 2.6
Event and Action Plan for Construction Air Quality Impact (RSP and FSP
monitoring) 19
Table 3.1 Proposed Noise
Monitoring stations during Construction Phase of the Project 22
Table 3.2 Action and Limit
Levels for Construction Noise. 23
Table 3.3 Event and Action Plan
for Construction Noise. 24
Table 4.1 Proposed Marine Water
Quality Stations for Baseline and Impact Monitoring. 29
Table 4.2 Action and Limit
Levels for Water Quality. 31
Table 4.3 Event and Action Plan
for Water Quality Monitoring. 32
LIST OF FIGURES
|
Figure 1.1
|
Project Boundary and Layout Plan
|
|
Figure 2.1
|
Locations of Representative Air
Sensitive Receivers
|
|
Figure 2.2
|
Locations of Construction Dust
Monitoring Stations
|
|
Figure 3.1
|
Locations of Construction Noise
Monitoring Stations
|
|
Figure 4.1
|
Locations of Water Quality
Monitoring Stations
|
LIST OF APPENDICES
1
Introduction
1.1
Project
Background
1.1.1 The Government of the Hong Kong Special Administrative Region (the
Government) is taking forward the Invigorating Island South (IIS) initiative
announced in the 2020 Policy Address to develop the Southern District into a
place full of vibrancy, vigour, and velocity for people to work, live, explore
new ideas and have fun. One of the key projects under the IIS initiative
is to explore the feasibility of expanding the Aberdeen Typhoon Shelter (ATS)
and enhancing the vessel berthing area.
1.1.2 In the 2021 Policy Address, the Government announced to commence an investigation and design study in 2022 for the expansion of the ATS to create additional vessel berthing area. To this end, the
Civil Engineering and Development Department (CEDD) engaged AECOM as the
Consultant in April 2022 to undertake the Assignment "CE 80/2021 –
Expansion of Aberdeen Typhoon Shelter – Investigation, Design and
Construction" (hereinafter referred to as “the Project”). The Project aims
to address the strong regional demand for sheltered vessel space in Hong Kong
Island South. Beyond providing essential berthing, the expansion of the
ATS also aims to foster tourism, leisure, and recreation opportunities in the
Southern District and explore the possibilities for future marina development.
1.1.3 The Government announced in the 2024 Policy Address to conduct detailed
design for the expansion of Aberdeen Typhoon Shelter, including the integration
of public landing facilities with the proposed breakwater at Tai Shue Wan to
create synergies.
1.2
Location
and Scope of the Project
1.2.1
The
Project site is located at Aberdeen Channel. It is sandwiched by Ap Lei
Pai and Ap Lei Chau in the west and Tai Shue Wan in the east. Its
northern side is bounded by the breakwaters of the existing Aberdeen South
Typhoon Shelter of about 26 hectares (ha) which were constructed in the
1960s. Its southern side is facing East Lamma Channel. The Project
boundary encompasses about 46 ha and includes expansion of ATS from its
southern part to provide extra sheltered space of about 24 ha (including
passageways) for local vessels, as indicated on the Project boundary and layout
plan in Figure 1.1.
1.2.2 The major works items for the Project includes the following:
(i)
Proposed eastern
breakwater, approximately 340 metre (m) in length, pointing to southwest with
about 50 m tip bending southward, with open space and proposed marine access in
form of public landing facilities (i.e. landing steps / ramp) and associated seabed
stabilisation works;
(ii)
Proposed western
breakwater, approximately 300 m in length, pointing to northeast with about 85
m tip bending northward, with landing facilities for maintenance purpose and
associated seabed stabilisation works;
(iii)
Proposed land access,
approximately 240 m in length, connecting the proposed eastern breakwater to Tai
Shue Wan waterfront along the rocky shoreline within the Project boundary;
(iv)
Proposed wave wall in
the form of floating breakwater of about 110 m in length in the sea area within
the ATS expansion area at a location approximately 70 m eastward of the tombolo
between Yuk Kwai Shan and Ap Lei Pai;
(v)
Modification of the
crest of existing eastern breakwater to form a new open space with pedestrian
access to Shum Wan Road; and
(vi)
Modification of the
existing western breakwaters, which includes shortening of the breakwater by
approximately 70 m with a view to straightening the navigation channel.
1.2.3 The detailed design of the proposed breakwaters, wave wall in the form
of floating breakwater, land access, modifications of the existing breakwaters,
and other design elements are subject to further refinements.
1.3
Purpose of this Manual
1.3.1 The purpose of this Environmental Monitoring and Audit (EM&A) Manual
is to guide the setups of an EM&A programme to ensure compliance with the
Environmental Impact Assessment (EIA) study recommendations, to assess the
effectiveness of the recommended mitigation measures and to identify any
further need for additional mitigation measures or remedial action. This
Manual outlines the monitoring and audit programme for the construction and
operation phases of the Project. It aims to provide systematic procedures
for monitoring, auditing and minimising environmental impacts associated with
construction works and operational activities.
1.3.2 Hong Kong environmental regulations have served as environmental
standards and guidelines in the preparation of this Manual. In addition,
the EM&A Manual has been prepared in accordance with the requirements
stipulated in Annex 21 of the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM).
1.3.3 This Manual contains the following information:
·
Responsibilities of the
Contractor, the Engineer or Engineer’s Representative (ER), Environmental Team
(ET) and Independent Environment Checker (IEC) with respect to the
environmental monitoring and audit requirements during the
course of the Project;
·
Project organisation
for the EM&A works;
·
The basis for, and
description of the broad approach underlying the EM&A programme;
·
An implementation
schedule, summarising all recommended environmental mitigation measures with reference
to the programme for their implementation including those identified at
detailed design, contract preparation, construction and operation stages of the
Project;
·
Details of the
methodologies to be adopted, including all field laboratories and analytical
procedures, and details on quality assurance and quality control programme;
·
The rationale on which
the environmental monitoring data will be evaluated and interpreted;
·
Definition of Action
and Limit levels;
·
Establishment of Event
and Action plans;
·
Requirements for
reviewing pollution sources and working procedures required in the event of
non-compliance with the environmental criteria and complaints; and
·
Requirements for
presentation of environmental monitoring and audit data and appropriate
reporting procedures.
1.3.4 For the purpose of this Manual, the ET Leader, who shall be responsible
for and in charge of the ET, shall refer to the person delegated the role of
executing the EM&A requirements.
1.4
Project
Organisation
1.4.1 The roles and responsibilities of the various parties involved in the
EM&A process and the organisational structure of the organisations
responsible for implementing the EM&A programme are outlined below.
The proposed project organisation and lines of communication with respect to
EM&A works are shown in Appendix A.
Engineer
or Engineer’s Representative (ER)
1.4.2 The ER is responsible for overseeing the construction works and for
ensuring that the works undertaken by the Contractor in accordance with the
specification and contractual requirements. The duties and
responsibilities of the ER with respect to EM&A may include:
·
Supervise the
Contractor’s activities and ensure that the requirements in the EM&A Manual
are fully complied with;
·
Inform the Contractor when
action is required to reduce impacts in accordance with the Event and Action Plans;
·
Participate in joint
site inspection undertaken by the ET; and
·
Adhere to the procedures
for carrying out complaint investigation.
The
Contractor
1.4.3 The Contractor shall report to the ER. The duties and
responsibilities of the Contractor comprise the following:
·
Work within the scope
of the contract and other tender conditions with respect to environmental requirements;
·
Operate and strictly
adhere to the guidelines and requirements in this EM&A programme and
contract specifications;
·
Provide
assistance to ET
in carrying out monitoring and auditing;
·
Participate in the site
inspections undertaken by ET as required, and undertake correction actions;
·
Provide information /
advice to ET regarding works activities which may contribute, or be continuing
to the generation of adverse environmental conditions;
·
Submit proposals on
mitigation measures in case of exceedance of Action and Limit levels in
accordance with the Event / Action Plans;
·
Implement measures to
reduce impact where Action and Limit levels are exceeded; and
·
Adhere to the
procedures for carrying out complaint investigation.
Environmental
Team (ET)
1.4.4 The ET Leader and the ET shall be employed to conduct the EM&A
programme and ensure the Contractor’s compliance with the Project’s
environmental performance requirements during construction. The ET shall
be an independent party from the Contractor and the IEC and shall be led and
managed by the ET Leader. The ET Leader shall possess at least 7 years of
experience in EM&A and/or environmental management and have relevant
professional qualifications, or have sufficient
relevant EM&A experience subject to approval of the ER and the
Environmental Protection Department (EPD).
1.4.5 The duties and responsibilities of the ET are:
·
Monitor various
environmental parameters as required in this EM&A Manual;
·
Implement the EM&A programme;
·
Analyse the
environmental monitoring and audit data and review the success of EM&A
programme to cost-effectively confirm the adequacy of mitigation measures
implemented and the validity of the EIA predictions and to identify any adverse
environmental impacts arising;
·
Carry out regular site
inspection to investigate and audit the Contractor's site practice, equipment
and work methodologies with respect to pollution control and environmental
mitigation, and effect proactive action to pre-empt problems; carry out ad hoc
site inspections if significant environmental problems are identified;
·
Report to the
Contractor of any potential non-compliance;
·
Follow up and close out
non-compliance actions;
·
Audit and prepare
monitoring and audit reports on the environmental monitoring data and site
environmental conditions;
·
Report on the environmental
monitoring and audit results to the IEC, Contractor, the ER and EPD or its
delegated representative;
·
Recommend suitable
mitigation measures to the Contractor in the case of exceedance of Action and
Limit levels in accordance with the Event and Action Plans;
·
Advice to the
Contractor on environmental improvement, awareness, enhancement matters, etc.
on site;
·
Timely submission of
the EM&A report to the Project Proponent and the EPD; and
·
Adhere to the
procedures for carrying out complaint investigation in accordance with Section
10 of this Manual.
Independent
Environmental Checker (IEC)
1.4.6 The IEC shall be an independent party from the Contractor and the ET and
possess at least 7 years’ experience in EM&A and/or environmental
management. The IEC shall report directly to the EPD on matters relating to the
EM&A programme and environmental impacts from the Project.
1.4.7 The duties and responsibilities of the IEC are:
·
Review the EM&A
works performed by the ET (at least at monthly intervals);
·
Carry out random sample
check and audit the monitoring activities and results (at least at monthly
intervals);
·
Validate and confirm
the accuracy of monitoring results, monitoring equipment, monitoring locations,
monitoring procedures and locations of sensitive receivers;
·
Report the audit
results to the ER and EPD;
·
Conduct random site inspection;
·
Review the EM&A
reports submitted by the ET;
·
Review the
effectiveness of environmental mitigation measures and project environmental performance;
·
Review the proposal on
mitigation measures submitted by the Contractor in accordance with the Event
and Action Plans;
·
Check the mitigation
measures that have been recommended in the EIA and this Manual, and ensure they
are properly implemented in a timely manner, when necessary; and
·
Adhere to the
procedures for carrying out complaint investigation.
1.4.8 Sufficient and suitably qualified professional and technical staff shall
be employed by the respective parties to ensure full compliance with their
duties and responsibilities, as required under the EM&A programme for the
duration of the Project.
1.5
Structure
of the Manual
1.5.1 Following this introductory section, the remainder of the Manual is set
out as follows:
·
Section 2 – Sets out
EM&A requirement for air quality impact;
·
Section 3 – Sets out
EM&A requirement for noise impact;
·
Section 4 – Sets out
EM&A requirement for water quality impact;
·
Section 5 – Sets out
EM&A requirement for waste management implications;
·
Section 6 – Sets out
EM&A requirement for marine ecological impact;
·
Section 7 – Sets out
EM&A requirement for fisheries impact;
·
Section 8 – Sets out
EM&A requirement for landscape and visual impact;
·
Section 9 – Sets out
EM&A requirement for cultural heritage impact;
·
Section 10 – Describes
scope and frequency of environmental site audits and sets out the general
requirements of the EM&A programme; and
·
Section 11 – Details
the EM&A reporting requirements.
2
Air Quality
2.1
Introduction
2.1.1 Potential air quality impacts arising from the construction phase of the
Project were addressed in the EIA Report. The representative ASRs within the
assessment area are presented in Figure
2.1. With implementation of the recommend control measures, no adverse
air quality impact from the Project during construction phase would be
anticipated. Dust monitoring and audit is proposed to be conducted during
construction so as to check compliance with the
legislative requirements.
2.1.2 Regular site environmental audit at least once per week is recommended
to be conducted during the entire construction phase of the Project so as to ensure the implementation of the proposed air
quality mitigation measures stipulated in Air Pollution Control
(Construction Dust) Regulation and Section 3.8 of the EIA report are
in order. Implementation schedule of mitigation measures is presented in Appendix B.
2.1.3 Potential air quality impact from operation of the Project were also
assessed and no adverse impact would be anticipated during the operation phase
of this Project.
2.1.4 As no adverse air quality impacts from operation of the Project would be
anticipated, monitoring and audit programme for the operation phase is
considered unnecessary.
2.1.5 This section presents the requirements, methodology, equipment,
monitoring locations, criteria and protocols for the monitoring and audit of
air quality impact during the construction phase of the Project.
2.2
Monitoring
Parameters
2.2.1 Air quality impact may arise from various construction activities of the
Project, including filling for the proposed breakwater, construction of the
proposed land access, as well as the modification of existing eastern and
western breakwaters, and material handling to be undertaken within the Project
boundary. Therefore, 1-hour Total Suspended Particulates (TSP)
concentrations, 1-hour and 24-hour average Respirable Suspended Particulate
(RSP) concentrations, and 24-hour average Fine Suspended Particulate (FSP)
concentration are recommended to be monitored and audited at the proposed
monitoring locations during the construction phases.
2.2.2 The criteria against which ambient air quality monitoring to be assessed
are 1-hour TSP limit of 500 µg/m3, 1-hour RSP action level of 150
µg/m3, 24-hour RSP limit of 100 µg/m3 and 24-hour FSP
limit of 50 µg/m3. The 24-hour limits for FSP and 1-hour action
level and 24-hour limit for RSP are subject to change based on the prevailing
AQOs implemented at the time of the dust monitoring works. The limit levels are
not to be exceeded at ASRs.
2.2.3 Monitoring and audit of the TSP, RSP and FSP levels shall be carried out
by the ET to ensure that any deteriorating air quality could be readily detected and timely action shall be undertaken to rectify
such situation.
2.2.4 All relevant data including temperature, pressure, weather conditions,
and other special phenomena and work progress of the concerned site, etc.,
should be recorded down in detail. A sample data sheet is shown in Appendix C1.
2.3
Monitoring
Equipment
TSP
monitoring
2.3.1 High volume sampler (HVS) in compliance with the following
specifications should be used for carrying out the 1-hour TSP monitoring:
·
0.6 – 1.7 m3
per minute (20 – 60 standard cubic feet per minute) adjustable flow range;
·
equipped with a timing
/ control device with ± 5 minutes accuracy for 24 hours operation;
·
installed with
elapsed-time meter with ± 2 minutes accuracy for 24 hours operation;
·
capable of providing a
minimum exposed area of 406 cm2;
·
flow control accuracy:
± 2.5% deviation over 24-hour sampling period;
·
equipped with a shelter
to protect the filter and sampler;
·
incorporated with an
electronic mass flow rate controller or other equivalent devices;
·
equipped with a flow
recorder for continuous monitoring;
·
provided with a peaked
roof inlet;
·
incorporated with a manometer;
·
able to hold and seal
the filter paper to the sampler housing at horizontal position;
·
easy to change the
filter; and
·
capable of operating continuously
for 24-hour period.
2.3.2 The ET is responsible for the provision, installation, operation,
maintenance and dismantling of the instrument. The ET shall strictly follow the
operation manual to ensure normal operation of the instrument. He shall
ensure that sufficient number of HVSs with appropriate
calibration kit is available for carrying out the baseline, regular impacts
monitoring and ad-hoc monitoring. The HVSs shall be equipped with an
electronic mass flow controller and be calibrated against a traceable standard
at regular intervals, in accordance with requirements stated in the
manufacturers operating manual. All the equipment, calibration kit,
filter papers, etc., shall be clearly labelled. If the ET Leader proposes
to use a direct reading dust meter to measure 1-hour TSP levels, he shall
submit sufficient information to the IEC to prove that the instrument is capable of achieving a comparable result as that of the
HVS before it may be used for the 1-hour sampling. The instrument shall
also be calibrated regularly, and the 1-hour sampling shall be determined
periodically by HVS to check the validity and accuracy of the results measured
by direct reading method,
2.3.3 Initial calibration of the air quality monitoring equipment shall be
conducted upon installation and prior to commissioning at bi-monthly
intervals. The transfer standard shall be traceable to the
internationally recognised primary standard and be calibrated annually.
The calibration data shall be properly documented for future reference by the
concerned parties such as the IEC. All the data shall be converted into
standard temperature and pressure condition.
2.3.4 The flow-rate of the sampler before and after
the sampling exercise with the filter in position shall be verified to be
constant and be recorded on the data sheet as shown in Appendix C1.
RSP
and FSP monitoring
2.3.5 RSP and FSP concentrations shall be monitored continuously by air sensor
at monitoring stations specified in Section 2.5. The air sensor to
be employed shall meet the purpose of the monitoring which is 1-hour RSP,
24-hour RSP and 24-hour FSP concentrations in the ambient air. The air sensor
shall have a resolution of at least 1 µg/m3, an accuracy of ±
10% to standard particles, equipped with a shelter to protect the sensor and
capable of operating continuously for a 7 days period.
It shall be capable of detection of PM10, while size specification
would be optional subject to the environmental management strategy of the site.
Particulates is typically measured using an optical
approach where light scattered by a particle is used to estimate the particle
mass concentration. The measurement range and detection limit of the air sensor
shall be able to measure the full range of particulates commonly found in the
ambient, e.g. 0 – 1000 µg/m3. The accuracy of a sensor, in
terms of precision and bias, shall also be evaluated during selection of air
sensor, according to the manufacturer’s specification, evaluation reports and
published literature. Whether the air sensor has calibrated upon purchase, when
and how collocation shall be performed and how to correct the measurement shall
be consulted with the sensor manufacturer and fully understood before the air
monitoring. Other factors, such as response time, durability, enclosure, ease
of use, power supply, any data display, data transmission, data access, data
handling and cost shall also be considered when selecting air sensor. Guidelines
on the use of air sensor refer to The Enhanced Air Sensor Guidebook 2022, USEPA,
or for further technical details at USEPA’s Air Sensor Toolbox website.
2.3.6 Generally, air sensors should be placed at least 1.5 m above ground and
away from any obstruction, vegetation or emission source which would interfere
with the measurement. Other factors of the monitoring location, such as
security, availability of power supply, reliable communication (cellular,
Wi-Fi, etc.), should also be considered
On-site
Calibration and Quality Control
2.3.7 To ensure accuracy of the measurement, monitoring equipment, including
the air sensors, should be calibrated regularly. The calibration should be
conducted by collocating the air sensor and a Transfer Standard (TS).
2.3.8 A Transfer Standard (TS) is another particulate matter (PM) monitor that
is at least as capable as the air sensor to be calibrated. Another sensor that
has just been calibrated may serve the purpose provided its performance is
known to be stable during the subsequent collocation period to be used as TS.
Right before each on-site calibration, the TS itself needs to be calibrated
e.g. collocating with an PM reference monitor - such as the Federal Reference
Method (FRM) or the Federal Equivalent Method (FEM) PM monitor at the
accredited laboratories or research institutes - that has been calibrated
against traceable standard. The TS/reference monitor collocation should
last at least seven days.
2.3.9 The TS with known performance characteristics will visit and collocate
with each air sensor for calibration. During collocation, the TS should be
placed near the subject sensor (<1 m if practicable) so that both devices
would be monitoring under the same environment, i.e. the same pollution sources
and weather conditions. The TS is then turned on to warm-up for 30 – 60
minutes. The collocation period starts after the warm-up and TS is then left
running with the subject sensor for at least three hours. The measurements from
the sensor to be calibrated and the TS during the collocation period will be
statistically analysed. The response of the sensor should be adjusted if its
performance during on-site calibration does not meet the evaluation criteria as
shown in Table
2.1.
Table 2.1 Recommended Performance Metrics and Target
Values for On-site Checking of PM Monitoring Equipment
|
Performance Metric
|
Target Value
|
|
Tier
1 – Linear regression of minute average measurements
|
Bias
|
Slope
|
0.75
– 1.25
|
|
Linearity
|
Coefficient
of Determination (R2)
|
>0.70
|
|
Tier
2 – Root mean squared error of minute average measurements
|
Error
|
Root
Mean Squared Error (RMSE)
|
<8
µgm-3 for RSP and <5 μgm-3 for FSP
|
2.3.10 On-site calibration of the monitoring
equipment shall be conducted by ET and agreed by IEC on the following approach:
• Prepare a TS for PM monitoring, which has been calibrated
against a PM reference monitor (i.e. the FRM or FEM PM monitor).
• The inlets of the TS and the subject sensor shall be
collocated at the same height with a horizontal separation distance of <1 m.
• Warm-up the transfer standard on-site if necessary.
• Collocated monitoring shall be conducted in a
continuous period to collect at least 180 valid minute average measurements.
The valid data rate shall be at least 80% during the collocation period.
• The collected minute average measurement results
should be statistically analysed using the two-tier approach as presented in Table 2.1.
2.3.11 During
Tier 1 checking, linear regression of the minute average measurements from the
sensors and the TS should be performed. The slope and coefficient of
determination (R2) from the linear regression should be calculated
and meet the target values in Table
2.1. If these criteria are not met due to narrow range of
PM concentration (>30 μg/m3 and >25 μg/m3
as recommended span range for RSP and FSP, respectively) during the collocation
period, the Tier 2 checking on mean squared error shall be determined and
compared against the target value in Table 2.1. If the monitoring equipment fails to meet both Tiers 1 and 2 target
values, the monitoring equipment needs to be re-calibrated or replaced.
2.3.12 The
collocated monitoring of TS and each air sensor on the field should be carried
out every month. If a sensor failed in 3 consecutive collocated monitoring, the
sensor should be checked or maintained to improve its performance, or it should
be replaced.
Construction
Dust Monitoring Plan
2.3.13 Before
commencing the air monitoring, the ET should formulate a construction dust
monitoring plan with air sensor and submit to IEC to seek their feedback and
consent. The plan should be aligned with the EM&A Manual and verified
by IEC. The plan should include but not limited to the followings:
· Details on the pollutants and environmental parameters
to be monitored;
· Describe the equipment and measurement method to be used;
· Address the criteria for placing air sensors;
· Discuss the monitoring locations selected and rationale;
· Describe the criteria for selecting air sensors and
test to determine if they are working properly;
· Determine the collocation location and establish the
calibration and/or collocation and data correction methods;
· Identify types of data that may be used in the data
analysis, including nearby reference monitor data, weather data, etc.
· List the procedures to maintain and operate air
sensors, including site visits, routine maintenance, emergency maintenance,
daily data review, periodic collocations, etc.;
· Describe the Quality Control (QC) procedures to be performed;
· Describe how the data are processed, stored and adjusted;
· Describe the ownership of the data and who is granted
access to it;
· Describe how the air monitoring data to be managed,
tracing the path of data generation in the field to the final data use and end storage;
· Describe the procedures to verify and validate data
during collection period;
· Describe the methods to produce meaningful figures and
visualisation;
· Describe how the monitoring results will be used.
2.3.14 The
ET is responsible for the provision of the monitoring equipment and should
provide sufficient number of air sensors for the field
work and TS for carrying out continuous on-site monitoring and ad-hoc
monitoring.
Wind
Data Monitoring Equipment
2.3.15 Wind
data monitoring equipment shall also be provided and set up at conspicuous
locations for logging wind speed and wind direction close to/or at the air
quality monitoring locations. The equipment installation location shall be
proposed by the ET and agreed with the ER and the IEC. For installation and
operation of wind data monitoring equipment, the following points shall be
observed.
·
The wind sensors shall
be installed on masts at an elevated level 10 m above ground so that they are
clear of obstructions or turbulence caused by the buildings;
·
The wind data shall be
captured by a data logger. The data recorded in the data logger shall be
downloaded for analysis simultaneously;
·
The wind data
monitoring equipment shall be re-calibrated at least once every
six months; and
·
Wind direction should
be divided into 16 sectors of 22.5 degrees each.
2.3.16 In
exceptional situations, the ET may propose alternative methods to obtain
representative wind data upon approval from the ER and agreement from the IEC.
2.3.17 If
the ET Leader proposes alternative dust monitoring equipment / methodology
after the approval of this Manual, agreement from the IEC and EPD should be
sought. The instrument should also be calibrated regularly following the
requirements specified by the equipment manufacturers.
2.4
Laboratory Measurement / Analysis (For TSP Measurement
only)
2.4.1 A clean laboratory with constant temperature and humidity control and
equipped with necessary measuring and conditioning instruments to handle the
dust samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory shall be the Hong Kong
Laboratory Accreditation Scheme (HOKLAS) accredited or other internationally
accredited laboratory.
2.4.2 If a site laboratory is set up or a non-HOKLAS accredited laboratory is
hired for carrying out the laboratory analysis, the laboratory equipment shall
be verified by the IEC and approved by the ER. Measurement performed by
the laboratory shall be demonstrated to the satisfaction of the ER and the IEC.
2.4.3 The IEC shall conduct regular audit of the measurement performed by the
laboratory so as to ensure the accuracy of measurement
results. The ET shall provide the ER with one copy of the Title 40 of the
Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his/her
reference.
2.4.4 Filter paper of size 8"x10" shall be labelled before
sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over
24-hour and be pre-weighed before use for the sampling.
2.4.5 After sampling, the filter paper loaded with dust shall be kept in a
clean and tightly sealed plastic bag. The filter paper shall then be
returned to the laboratory for reconditioning in the humidity-controlled
chamber followed by accurate weighing by an electronic balance with a readout
down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
2.4.6 All the collected samples shall be kept in a good condition for 6 months
before disposal.
2.5
Monitoring
Locations
2.5.1 The selected monitoring locations are the worst potentially affected air
sensitive receivers located in the vicinity of construction sites. The proposed
air quality monitoring locations during construction phase are listed in Table 2.2 below and shown in Figure 2.2.
Table 2.2 Proposed Construction Air Quality Monitoring Stations
|
Monitoring Station ID
|
ASR ID in EIA Report
|
Location
|
Approximate Horizontal
Distance from the Project Boundary (m)
|
|
AM1
|
A3a
|
Shipyards and workshops
|
208
|
|
AM2
|
A4
|
Shipyard and Temporary Industrial Area
|
75
|
|
AM3
|
A8
|
Water World Ocean Park
|
84
|
|
AM4
|
A10a
|
Fullerton Ocean Park Hotel
|
13
|
|
AM5
|
A10b
|
Fullerton Ocean Park Hotel
|
22
|
2.5.2 The status and locations of the air sensitive receivers may change after
issuing this Manual. In such case, the ET shall propose updated
monitoring locations and seek approval from ER and IEC and agreement from EPD
on the proposal.
2.5.3 When alternative monitoring locations are proposed, the following
criteria, as far as practicable, shall be followed:
·
at the site boundary or
such locations close to the major site activities which are likely to have air
quality impacts;
·
close to the air
sensitive receivers as defined in the EIAO-TM;
·
assurance of minimal disturbance
to the occupants and working under a safe condition during monitoring.
·
proper position/siting
and orientation of the monitoring equipment; and
·
take
into account the
prevailing meteorological conditions.
2.5.4 The ET shall agree with the IEC on the position of the HVS and PM
sensors for installation of the monitoring equipment. When positioning the
HVS/the PM sensors, the following points shall be noted:
·
a horizontal platform
with appropriate support to secure the HVS/the PM sensors against gusty wind
shall be provided;
·
the distance between
the HVS/the PM sensors and an obstacle, such as building, must be at least twice
the height that the obstacle protrudes above the HVS/the PM sensors.
·
A minimum of 2 m
separation from wall, parapets and penthouses is required for rooftops samplers;
·
A minimum of 2 m
separation from any supporting structure, measure horizontally is required.
·
general housekeeping,
cleaning works and other preventative maintenance activities such as checking
the operating status of individual monitoring equipment should be carried out
to ensure the proper operation of the system;
·
to ensure
representative sampling, the inlet of the HVS/the PM sensors should not be
obstructed by nearby objects;
·
any wire fence and
gate, to protect the HVS/the PM sensors, shall not cause any obstruction during
monitoring;
·
no furnace or
incinerator flue is nearby;
·
airflow around the
instrument is unrestricted;
·
permission must be
obtained to set up the HVS/the PM sensors and to
obtain access to the monitoring stations; and
·
a secured supply of
electricity is needed to operate the HVS/the PM sensors.
2.5.5 Subject to site conditions and monitoring results, the ET Leader, with
IEC and EPD endorsement, may decide whether additional monitoring locations
should be included or any monitoring locations could
be removed / relocated during the construction phase.
2.6
Baseline
Monitoring (for TSP only)
2.6.1 Baseline monitoring shall be carried out to determine the ambient 1-hour
TSP levels at the monitoring locations at least 14 consecutive days prior to
the commencement of the Project. During the baseline monitoring, there shall
not be any construction or dust generating activities in the vicinity of the
monitoring stations. 1-hour TSP sampling shall be done at least three times per
day at each monitoring station. The baseline monitoring will provide data for
the determination of the appropriate Action levels with the Limit levels set
against statutory or otherwise agreed limits. General meteorological conditions
(wind speed, direction and precipitation) and notes regarding any significant
adjacent dust producing sources should also be recorded throughout the baseline
monitoring period. A summary of baseline monitoring is presented in Table 2.3.
2.6.2 Before commencing the baseline monitoring, the ET shall inform the IEC
of the baseline monitoring programme such that the IEC can conduct on-site
audit to ensure accuracy of the baseline monitoring results.
2.6.3 In case the baseline monitoring cannot be carried out at the designated
monitoring locations during the baseline monitoring period, the ET Leader shall
carry out the monitoring at alternative locations which can effectively
represent the baseline conditions at the impact monitoring locations. The
alternative baseline monitoring location shall be approved by the ER and agreed
with IEC and approved by EPD.
2.6.4 In exceptional cases, when insufficient baseline monitoring data or
questionable results are obtained, the ET Leader shall liaise with the IEC and
EPD to agree on an appropriate set of data to be used as a baseline reference
and submit to ER for approval.
2.6.5 If the ET Leader considers that significant changes in the ambient
conditions have arisen, a repeat of the baseline monitoring may be carried out
to update the baseline levels. The monitoring should be at times when the
Contractor's activities are not generating dust, at least in the proximity of
the monitoring stations. The revised baseline levels, in turn, the air
quality criteria, shall be agreed with the IEC and EPD.
2.7
Impact
Monitoring (for TSP, RSP and FSP)
2.7.1 During construction phase of the Project, the ET shall carry out
continuous impact monitoring in terms of 1-hour TSP concentration. The sampling
frequency of at least three times in every six-days should be undertaken when
the highest dust impact occurs. In case of non-compliance with the air
criteria, more frequent monitoring, as specified in the Action Plan in the
following section, should be conducted. The additional monitoring programme
should be continued until the excessive emission or the deterioration in the
air quality is rectified. The impact monitoring programme is summarised in Table 2.3.
Table 2.3 Summary of Construction Air Quality Impact
Monitoring Programme
|
Monitoring Period
|
Duration
|
Sampling Parameter
|
Frequency
|
|
Baseline Monitoring
|
Consecutive days of at least 2 weeks before
commencement of major construction works
|
1-hour TSP
|
3 times per day
|
|
Impact Monitoring
|
Throughout the construction phase
|
1-hour TSP
|
3 times in every 6 days
|
|
Impact Monitoring
|
Throughout the construction phase
|
1-hour RSP
|
Continuous monitoring
|
|
Impact Monitoring
|
Throughout the construction phase
|
24-hour RSP
|
Continuous monitoring
|
|
Impact Monitoring
|
Throughout the construction phase
|
24-hour FSP
|
Continuous monitoring
|
2.7.2 The monthly schedule of the compliance and impact monitoring programme
should be drawn up by the ET one month prior to the commencement of the
scheduled construction period. Before commencing the impact monitoring, the ET
shall inform the IEC of the impact monitoring programme such that the IEC can
conduct on-site audit to ensure accuracy of the impact monitoring results.
2.7.3 For 1-hour average RSP concentration, 24-hour rolling average RSP
concentration and 24-hour rolling average FSP concentration, continuous
monitoring will be carried out by air sensors throughout the construction phase
of the Project.
2.8
Event
and Action Plan
2.8.1 The baseline monitoring results form the basis for determining the air
quality criteria for the impact monitoring for TSP. The ET shall compare the
impact monitoring results with air quality criteria set up for 1-hour TSP,
1-hour RSP, 24-hour RSP and 24-hour FSP. Table 2.4 shows the air quality criteria, namely Action and Limit levels to be
used. Should non-compliance of the air quality criteria occur, action in
accordance with the Action Plan in Table 2.5 (for TSP monitoring) and Table 2.6 (for RSP and FSP monitoring) shall be carried out. The action and
limit level may subject to change based on the prevailing AQOs implemented at
the time of the monitoring works.
Table 2.4 Action and Limit Levels for Construction
Air Quality Impact
|
Parameter
|
Action Level
|
Limit Level
|
|
1-hour TSP
|
BL <= 384 µgm-3, AL =
(BL * 1.3 + LL)/2
BL > 384 µgm-3, AL = LL
|
500 µg/m3
|
|
1-hour RSP
|
150 µg/m3
|
Not Applicable
|
|
24-hour RSP
(rolling average)
|
Not Applicable
|
100 µg/m3
|
|
24-hour FSP
(rolling
average)
|
Not Applicable
|
50 µg/m3
|
|
Note:
[1] BL = Baseline level, AL =
Action level, LL = Limit level
|
Table 2.5 Event and Action Plan for Construction
Air Quality Impact (TSP monitoring)
|
Event
|
Action
|
|
ET
|
IEC
|
ER
|
Contractor
|
|
Action level being exceeded by one sampling
|
1. Identify
source, investigate the causes of complaint and propose remedial measures;
2. Inform
Contractor, IEC and ER;
3. Repeat
measurement to confirm finding; and
4. Increase
monitoring frequency to daily.
|
1. Check
monitoring data submitted by ET;
2. Check
Contractor’s working method; and
3. Review
and advise the ET and ER on the effectiveness of the proposed remedial
measures.
|
1. Notify Contractor.
|
1. Identify
source(s), investigate the causes of exceedance and propose remedial measures;
2. Implement
remedial measures; and
3. Amend
working methods agreed with the ER as appropriate
|
|
Action level being exceeded by two or more
consecutive sampling
|
1. Identify
source;
2. Inform
Contractor, IEC and ER;
3. Advise
the Contractor and ER on the effectiveness of the proposed remedial measures;
4. Repeat
measurements to confirm findings;
5. Increase
monitoring frequency to daily;
6. Discuss
with IEC and Contractor on remedial actions required;
7. If
exceedance continues, arrange meeting with
Contractor, IEC and ER; and
8. If
exceedance stops, cease additional monitoring.
|
1. Check
monitoring data submitted by ET;
2. Check
Contractor’s working method;
3. Discuss
with ET, ER and Contractor on possible remedial measures;
4. Advise
the ET and ER on the effectiveness of the proposed
remedial measures; and
5. Supervise implementation of
remedial measures.
|
1. Confirm
receipt of notification of exceedance in writing;
2. Notify
Contractor;
3. Ensure
remedial measures properly implemented.
|
1. Identify
source and investigate the causes of exceedance;
2. Submit
proposals for remedial measures to the ER with a copy to ET and IEC within
three working days of notification;
3. Implement
the agreed proposals; and
4. Amend
proposal as appropriate.
|
|
Limit level being exceeded by one sampling
|
1. Identify
source, investigate the causes of exceedance and propose remedial measures;
2. Inform
Contractor, IEC, ER, and EPD;
3. Repeat
measurement to confirm findings;
4. Increase
monitoring frequency to daily; and
5. Assess
effectiveness of Contractor’s remedial actions and keep IEC,
EPD and ER informed of the results.
|
1. Check
monitoring data submitted by ET;
2. Check
Contractor’s working method;
3. Discuss
with ET and Contractor on possible remedial measures;
4. Advise
the ER on the effectiveness of the proposed remedial measures; and
5. Supervise
implementation of remedial measures.
|
1. Confirm
receipt of notification of exceedance in writing;
2. Notify
Contractor;
3. Ensure
remedial measures properly implemented.
|
1. Identify
source(s) and investigate the causes of exceedance;
2. Take
immediate action to avoid further exceedance;
3. Submit
proposals for remedial measures to ER with a copy to ET and IEC within three
working days of notification;
4. Implement
the agreed proposals; and
5. Amend proposal if appropriate.
|
|
Limit level being exceeded by two or more
consecutive sampling
|
1. Notify
IEC, ER, Contractor and EPD;
2. Identify
source;
3. Repeat
measurement to confirm findings;
4. Increase
monitoring frequency to daily;
5. Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented;
6. Arrange
meeting with IEC and ER to discuss the remedial actions to be taken;
7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results; and
8. If
exceedance stops, cease additional monitoring.
|
1. Check
monitoring data submitted by the ET;
2. Discuss
amongst ER, ET, and Contractor on the potential remedial actions;
3. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; and
4. Supervise
the implementation of remedial measures.
|
1. Confirm
receipt of notification of exceedance in writing;
2. In
consultation with the ET and IEC, agree with the Contractor on the remedial
measures to be implemented;
3. Supervise
the implementation of remedial measures; and
4. If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated.
|
1. Identify
source(s) and investigate the causes of exceedance;
2. Take
immediate action to avoid further exceedance;
3. Submit
proposals for remedial measures to the ER with a copy to the IEC and ET
within three working days of notification;
4. Implement
the agreed proposals;
5. Revise
and resubmit proposals if problem still not under
control; and
6. Stop
the relevant portion of works as determined by the
ER until the exceedance is abated.
|
Table 2.6 Event and Action Plan for Construction
Air Quality Impact (RSP and FSP monitoring)
|
Event
|
Action
|
|
ET
|
IEC
|
ER
|
Contractor
|
|
Action level being exceeded by one sample
|
1. Notify
IEC and ER;
2. Check
the monitoring data and error messages to confirm if the performance of the
monitoring equipment is normal;
3. If
exceedance is confirmed, identify source(s), investigate the causes of
exceedance and propose remedial measures;
4. Assess
effectiveness of Contractor’s remedial measures and keep IEC and ER informed
of the results until exceedance stops.
|
1. Check
monitoring data submitted by ET;
2. Check
Contractor’s working method;
3. Discuss
with ET, ER and Contractor on possible remedial measures;
4. Advise
ER and ET on the effectiveness of the proposed remedial measures;
5. Supervise
implementation of remedial measures.
|
1. Confirm
receipt of notification of exceedance in writing;
2. Notify
Contractor;
3. In
consultation with IEC and ET, agree with the Contractor on the remedial
measures to be implemented;
4. Ensure
remedial measures are properly implemented.
|
1. Identify
sources of exceedance and discuss with ER, ET and IEC on possible remedial measures;
2. Implement
remedial measures;
3. Amend
working methods if appropriate.
|
|
Action level exceedance for two or more
consecutive samples
|
1. Notify
IEC and ER;
2. Check
the monitoring data and the performance of the monitoring equipment (refer to
Section 2.3.10 and Table
2.1);
3. If
exceedance is confirmed, identify source(s), investigate the causes of
exceedance and propose remedial measures;
4. Discuss
with IEC and Contractor on possible remedial measures required;
5. Assess
effectiveness of Contractor’s remedial measures and keep IEC and ER informed
of the results until exceedance stops.
6. Notify
EPD if the exceedance is confirmed to be related to the Project.
|
1. Check
monitoring data submitted by ET;
2. Check
Contractor’s working method and verify the performance of the monitoring
equipment to be checked by ET (refer to Section 2.3.10 and Table 2.1);
3. Discuss
with ET and Contractor on possible remedial measures;
4. Advise
ER and ET on the effectiveness of the proposed remedial measures;
5.
Supervise implementation of remedial measures.
|
1. Confirm receipt of notification
of exceedance in writing;
2. Notify Contractor;
3. In consultation with IEC and ET,
agree with the Contractor on the proposal for remedial measures to be implemented;
4. Ensure the proposal for remedial
measures are properly implemented.
|
1. Identify the sources and discuss
with ER, ET and IEC on possible remedial measures;
2. Submit a proposal for remedial
measures to ER, IEC and ET within 2 working days of notification of
exceedance for agreement;
3. Implement the agreed proposal;
4. Amend proposal if appropriate.
|
|
Limit level exceedance for one 24-hr rolling
average RSP concentration record or/and one 24-hr rolling average FSP
concentration record
|
1. Notify
IEC, ER, Contractor and EPD;
2. Check
the monitoring data and the performance of the monitoring equipment (refer to
Section 2.3.10 and Table
2.1);
3. If
exceedance is confirmed, identify source(s), investigate the causes of
exceedance and propose remedial measures;
4. Discuss
with IEC, ER and Contractor on possible remedial measures required;
5. Assess
effectiveness of Contractor’s remedial measures and keep IEC and ER informed
of the results until exceedance stops.
6. Notify
EPD if the exceedance is confirmed to be related to the Project.
|
1. Check
monitoring data submitted by ET;
2. Check
Contractor’s working method; and verify the performance of the monitoring
equipment to be checked by ET (refer to Section 2.3.10 and Table 2.1);
3. Discuss
with ER, ET and Contractor on the possible remedial measures;
4. Advise
ER and ET on the effectiveness of the proposed remedial measures;
5. Review
Contractor’s remedial measures whenever necessary to assure their
effectiveness and advise ER and ET accordingly;
6. Supervise
the implementation of remedial measures
|
1. Confirm
receipt of notification of exceedance in writing;
2. Notify
Contractor;
3. In
consultation with the IEC and ET, agree with the Contractor on the proposal
for remedial measures to be implemented;
4. Ensure
the proposal for remedial measures are properly implemented;
5. If exceedance continues, identify what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated.
|
1. Identify
the sources and discuss with ER, ET and IEC on possible remedial measures;
2. Take
immediate action to avoid further exceedance;
3. Submit
a proposal for remedial measures to ER, IEC and ET within 2 working days of
notification of exceedance for agreement;
4. Implement
the agreed proposal;
5. Review
and resubmit proposals if the problem is still not under control;
6.
Stop the relevant portion of works as determined by ER until the
exceedance is abated.
|
2.9
Mitigation Measures
2.9.1 Mitigation measures for construction phase air quality impact have been
recommended in the EIA Report. All the recommended mitigation measures
are detailed in the implementation schedule presented in Appendix B. The Contractor shall
be responsible for the design and implementation of these measures.
2.10
Audit
Requirements
2.10.1 Regular
site inspection and audit at least once per week shall be conducted during the
entire construction phase of the Project to ensure the recommended mitigation
measures are properly implemented.
3
Noise
3.1
Introduction
3.1.1 The EIA has identified and assessed the potential noise impacts during
both construction and operation phase of the Project. Construction noise
mitigation measures and good site practices have been proposed to minimise the
potential construction noise levels. A noise monitoring and audit programme
should be undertaken to confirm such mitigation measures would be implemented
properly.
3.1.2 For marine traffic noise impact, the predicted marine traffic noise
level at identified NSR N1
is expected to be well below the prevailing noise level and comply with the established
noise criteria in the absence of mitigation measures and adverse noise impact
is not anticipated.
3.1.3 In this section, the requirements, methodology, equipment, monitoring
locations, criteria and protocols for the monitoring and audit of noise impacts
during construction phase of the Project are presented.
3.2
General
Monitoring Requirement and Equipment
3.2.1 As referred to in the Technical Memorandum (TM) issued under the Noise
Control Ordinance (NCO), sound level meters in compliance with the
International Electrotechnical Commission Publications 651: 1979 (Type 1) and
804:1985 (Type 1) specifications shall be used for carrying out the noise
monitoring. Immediately prior to and following each noise measurement, the
accuracy of the sound level meter shall be checked using an acoustic calibrator
and generating a known sound pressure level at a known frequency. Measurements
shall be accepted as valid only if the calibration level from before and after
the noise measurement agree to within 1.0 dB.
3.2.2 Noise measurements shall not be made in fog, rain, wind with a steady
speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall
be checked with a portable wind speed meter capable of measuring the wind speed
in m/s.
3.2.3 The ET is responsible for the provision of the monitoring equipment. He shall
ensure that sufficient noise measuring equipment and associated instrumentation
are available for carrying out the baseline monitoring, regular impact
monitoring and ad hoc monitoring. All the equipment and associated
instrumentation shall be clearly labelled. The equipment installation location
shall be proposed by the ET Leader and agreed with the IEC and EPD.
3.2.4 The noise monitoring station shall normally be at a point 1 m from the
exterior of the sensitive receivers building façade and be a position 1.2 m
above the ground. If there is a problem with access to the normal monitoring
position, an alternative position shall be chosen, and a correction to the
measurements shall be made. For reference, a correction of +3 dB(A) shall be
made to the free field measurements. The ET shall agree with the IEC on the
monitoring position and the corrections adopted. Once the positions for the
monitoring stations are chosen, the baseline monitoring and the impact
monitoring shall be carried out at the same positions.
3.3
Monitoring
Parameters
3.3.1 The construction noise levels should be measured in terms of the
30-minute A-weighted equivalent continuous sound pressure level (Leq (30-min)). Leq (30-min)
should be used as the monitoring parameter for the time
period between 0700 and 1900 hours on normal weekdays.
3.3.2 Supplementary information for data auditing and statistical results such
as L10 and L90 should also be obtained for reference. Sample noise field data
sheets are shown in Appendix C2 of
this Manual for reference. The ET Leader may modify the data record sheet for
this EM&A programme but the format of which should be agreed by the IEC.
3.4
Monitoring
Locations
3.4.1 Based on the qualitative construction noise assessment in the EIA
Report, adverse construction noise impact associated with the Project is not
anticipated with the implementation of the recommended mitigation measures and
good site practices. Figure 3.1
shows the proposed construction phase noise monitoring station. Details of the
proposed noise monitoring station is summarised in Table 3.1.
Table 3.1 Proposed Noise Monitoring stations during Construction
Phase of the Project
|
Noise Monitoring Point
|
EIA ID
|
Location
|
Monitoring Period
|
|
CM1
|
N1
|
Tower 1, Larvotto
|
Works at existing eastern breakwater during non-restricted hours
|
3.4.2 The status and locations of noise sensitive receivers (NSRs) may change
after issuing this Manual. If such cases exist, the ET shall propose updated
monitoring locations and seek approval from the IEC and agreement from EPD of
the proposal.
3.4.3 When alternative monitoring locations are proposed, the monitoring
locations shall be chosen based on the following criteria:
i.
at locations close to
the major site activities which are likely to have noise impacts;
ii. close to the NSRs; and
iii.
for monitoring
locations located in the vicinity of the sensitive receivers, care shall be
taken to cause minimal disturbance to the occupants during monitoring.
3.5
Baseline
Monitoring
3.5.1 Baseline noise monitoring shall be carried out daily at all of the proposed monitoring stations for at least 2 weeks
prior to the commissioning of the construction works. A schedule of the
baseline monitoring shall be approved by the IEC before the monitoring starts.
3.5.2 During the baseline monitoring, there shall not be any construction
activities in the vicinity of the monitoring stations.
3.5.3 In exceptional cases, when insufficient baseline monitoring data or
questionable results are obtained, the ET Leader shall liaise with EPD and in
consultation with the IEC to agree on an appropriate set of data to be used as
a baseline reference.
3.6
Impact
Monitoring
3.6.1 Construction noise monitoring should be carried out at the designated
monitoring station when there are Project-related construction activities being
undertaken within a radius of 300 m from the monitoring stations. The
monitoring frequency should depend on the scale of the construction activities.
An initial guide on the monitoring is to obtain one set of 30-minute
measurement at each station between 0700 and 1900 hours on normal weekdays
at a frequency of once a week when construction activities are underway.
3.6.2 If construction works are extended to include works during the hours of
1900 - 0700, and/or percussive piling is be carried out, applicable permits
under NCO shall be obtained by the Contractor. The monitoring requirements and
conditions stipulated in the permits have to be
followed.
3.6.3 In case of non-compliance with the construction noise criteria, more
frequent monitoring, as specified in the Action Plan in Table
3.3 shall be carried out. This additional monitoring shall be continued
until the recorded noise levels are rectified or proved to be irrelevant to the
construction activities.
3.7
Event
and Action Plan
3.7.1 The Action and Limit levels for construction noise are defined in Table 3.2. Should non-compliance of the
criteria occur, action in accordance with the Action Plan in Table 3.3 shall be carried out.
Table 3.2 Action and Limit Levels for Construction Noise
|
Time Period
|
Action Level
|
Limit Level
|
|
0700 – 1900 hours
on normal weekdays
|
When one documented complaint is received
|
75 dB(A)
|
Notes:
If works are
to be carried out during restricted hours and/or percussive piling is be
carried out, the monitoring requirements and the conditions stipulated in the
Construction Noise Permit (CNP) issued by the Noise Control Authority have to be followed.
Table 3.3 Event and Action Plan for Construction
Noise
|
Event
|
Action
|
|
ET
|
IEC
|
ER
|
Contractor
|
|
Action Level
|
1. Notify
IEC and Contractor;
2. Carry
out investigation;
3. Report
the results of investigation to the IEC, ER and Contractor;
4. Discuss
with the Contractor and formulate remedial measures; and
5. Increase
monitoring frequency to check mitigation effectiveness.
|
1. Review
the analysed results submitted by the ET;
2. Review
the proposed remedial measures by the Contractor and advise the ER accordingly; and
3. Supervise
the implementation of remedial measures.
|
1. Confirm
receipt of notification of failure in writing;
2. Notify
Contractor;
3. Require
Contractor to propose remedial measures for the analysed noise problem; and
4. Ensure
remedial measures are properly implemented.
|
1. Submit
noise mitigation proposals to IEC; and
2. Implement
noise mitigation proposals.
|
|
Limit
Level
|
1. Identify
source;
2. Inform
IEC, ER, EPD and Contractor;
3. Repeat
measurements to confirm findings;
4. Increase
monitoring frequency;
5. Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented;
6. Inform
IEC, ER and EPD the causes and actions taken for the exceedances;
7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results; and
8. If
exceedance stops, cease additional monitoring.
|
1. Discuss
amongst ER, ET, and Contractor on the potential remedial actions;
2. Review
Contractors remedial actions whenever necessary to assure their effectiveness
and advise the ER accordingly; and
3. Supervise
the implementation of remedial measures.
|
1. Confirm
receipt of notification of failure in writing;
2. Notify
Contractor;
3. Require
Contractor to propose remedial measures for the analysed noise problem;
4. Ensure
remedial measures properly implemented; and
5. If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated.
|
1. Take
immediate action to avoid further exceedance;
2. Submit
proposals for remedial actions to IEC within
3 working days of notification;
3. Implement
the agreed proposals;
4. Resubmit
proposals if problem still not under control; and
5. Stop
the relevant portion of works as determined by the ER until the exceedance is
abated.
|
3.8
Mitigation
Measures
Construction
Phase
3.8.1 To minimise the potential construction noise impact on the affected NSR,
quieter PME/quieter construction methods would be adopted where feasible
including use of quieter PME (e.g. generator), quieter construction method for
demolition works of existing breakwater (e.g. quieter saw and hydraulic
crusher), use of self-compacting concrete for concreting work to replace use of
vibratory poker and pre-cast columns and decking for construction of potential
access. Mitigation measures including adopting movable noise barriers,
temporary noise barriers are also recommended.
3.8.2 In addition to the above construction noise mitigation measures, good
site practices listed below and the noise control
requirements stated in EPD’s “Recommended Pollution Control Clauses for
Construction Contracts” should be included in the Contract Specification
for the Contractor to follow and implemented to further minimise the potential
noise impacts during the construction phase of the Project:
·
Only well-maintained plant
should be operated on-site and plant should be
serviced regularly;
·
Utilising silencers or
mufflers on construction plant;
·
Mobile plant should be
located as far away from NSRs as possible;
·
Plant that are in intermittent
use should be shut down between works periods or throttled down to a minimum;
·
Plant known to emit
noise strongly in one direction should, where possible, be orientated so that
the noise is directed away from the nearby NSRs;
·
Material stockpiles and
other structures such
as site hoarding should
be effectively utilised to screen noise from on-site construction activities;
and
·
Appropriate traffic
routes for transportation of large volume of construction
materials/spoils/excavated materials should be identified to minimise potential
noise impacts.
3.8.3 It is recommended that Construction Noise Management Plan (CNMP) should
be prepared based on the best available information and checked before the
invitation of tender and the commencement of construction works, subject to the
contract arrangement of the Project and agreement with EPD.
3.8.4 The implementation schedule of the good site practices is presented in Appendix B.
3.9
Audit
Requirements
3.9.1 Regular site environmental audit during the construction phase of the
Project should be conducted at least once per week to ensure proper
implementation of mitigation measures and good site practices as listed in Appendix B and the noise control
requirements stated in EPD’s "Recommended Pollution Control Clauses for
Construction Contracts” to further minimise the potential noise nuisance
during construction phase.
4
Water Quality
4.1
Introduction
4.1.1 As identified in the EIA Report, release of suspended sediment is
identified as the key water quality parameter caused by dredging, sand blanket
filling and deep cement mixing (DCM) installation. Marine water quality
monitoring is recommended to ensure that any unacceptable increase in suspended
solids/turbidity and decrease in dissolved oxygen due to the identified marine
construction works could be readily detected and timely action be taken to
rectify the situation.
4.2
Water
Quality Parameters
4.2.1
Dissolved
oxygen (DO), turbidity and suspended solids (SS) levels should be monitored at
designated marine water quality monitoring stations during the dredging, sand
blanket filling and DCM installation. DO and turbidity should be measured
in-situ whereas SS should be determined by laboratory.
4.2.2 Measurements shall be taken at three water depths, including 1 m below
water surface, mid-depth and 1 m above seabed, except where the water depth is
less than 6 m, in which case the mid-depth station may be omitted. If the
water depth is less than 3 m, only the mid-depth station will be monitored.
4.2.3 Enough replicates in-situ measurements and water samples
collected from each independent monitoring event are required for all
parameters to ensure a robust statistically interpretable dataset.
4.2.4 In addition to the water quality parameters as shown in Section 4.2.1,
other relevant data shall also be recorded, including monitoring
location/position, time, water depth, pH value, salinity, temperature, tidal
stages, current velocity and direction, sea conditions, weather conditions and
any special phenomena or work activities undertaken around the monitoring and
works area that may influence the monitoring results. A sample data
record sheet is shown in Appendix C3
for reference.
4.3
Sampling
Procedures and Monitoring Equipment
Dissolved
Oxygen and Temperature Measuring Equipment
4.3.1 The instrument shall be a portable and weatherproof DO measuring
instrument complete with cable and sensor, and use a
DC power source. The equipment shall be capable of measuring:
·
a DO level in the range
of 0 - 20 mg L-1 and 0 - 200% saturation; and
·
a temperature of 0 - 45
degree Celsius.
4.3.2 It shall have a membrane electrode with automatic temperature
compensation complete with a cable. Sufficient stocks of spare electrodes
and cables shall be available for replacement where necessary. For
example, YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument.
4.3.3 Shall salinity compensation not be built-in to the DO equipment, in-situ
salinity shall be measured to calibrate the DO equipment prior to each DO
measurement.
Turbidity
Measurement Instrument
4.3.4 Turbidity shall be measured in-situ by the nephelometric
method. The instrument shall be portable and weatherproof turbidity
measuring instrument using a DC power source complete with cable, sensor and
comprehensive operation manuals. It shall have a photoelectric sensor
capable of measuring turbidity between 0 - 1000 NTU (for example, Hach model
2100P or an approved similar instrument). The cable shall not be less
than 25 m in length. The meter shall be calibrated to establish the
relationship between NTU units and the levels of suspended solids.
Sampler
4.3.5 A water sampler is required. It shall comprise a transparent
Polyvinyl Chloride (PVC) cylinder, with a capacity of not less than 2 litres,
which can be effectively sealed with latex cups at both ends. The sampler
shall have a positive latching system to keep it open and prevent premature
closure until released by a messenger when the sampler is at the selected water
depth (for example, Kahlsico Water Sampler or an
approved similar instrument).
Water
Depth Detector
4.3.6 A portable, battery-operated echo sounder shall be used for the
determination of water depth at each designated monitoring station. This
unit can either be handheld or affixed to the bottom of the work boat, if the
same vessel is to be used throughout the monitoring programme.
Salinity
4.3.7 A portable salinometer capable of measuring salinity in the range of 0 -
40 parts per thousand (ppt) shall be provided for measuring salinity of the
water at each monitoring location.
pH
4.3.8 The instrument shall consist of a potentiometer, a glass electrode, a
reference electrode and a temperature-compensating device. It shall be
readable to 0.1 pH in a range of 0 to 14. Standard buffer solutions
of at least pH 7 and pH 10 shall be used for calibration of the instrument
before and after use. Details of the method shall comply with American
Public Health Association (APHA), 19th ed. 4500-HTB.
Sample
Containers and Storage
4.3.9 Water samples shall be stored in high density polythene bottles with no
preservative added, packed in ice (cooled to 4 ℃ without being frozen)
and delivered to the laboratory and analysed as soon as possible after
collection. Sufficient volume of samples shall be collected to achieve
the required detection limit.
Monitoring
Position Equipment
4.3.10 A
hand-held or boat-fixed type digital Differential Global Positioning System
(DGPS) with way point bearing indication or other equipment instrument of
similar accuracy, shall be provided and used during marine water monitoring to
ensure the monitoring vessel is at the correct location before taking
measurements.
Current
Velocity and Direction
4.3.11 No specific
equipment is recommended for measuring the current velocity and
direction. The environmental contractor shall seek approval of their
proposed equipment with the client prior to deployment.
Calibration
of In-situ Instruments
4.3.12 All in-situ
monitoring instruments shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or any other international accreditation
scheme before use and subsequently re-calibrated at three monthly intervals
throughout all stages of the water quality monitoring programme.
Responses of sensors and electrodes shall be checked with certified standard
solutions before each use. Wet bulb calibration for a DO meter shall be
carried out before measurement at each monitoring location.
4.3.13 Sufficient
stocks of spare parts shall be maintained for replacements when
necessary. Backup monitoring equipment shall also be made available so
that monitoring can proceed uninterrupted even when some equipment is under
maintenance, calibration, etc.
4.4
Laboratory
Measurement / Analysis
4.4.1 Analysis of SS level shall be carried out in a HOKLAS or other international accredited laboratory. Sufficient
water samples shall be collected at the monitoring stations for carrying out
the necessary laboratory analysis. The analysis shall commence within 24
hours after collection of the water samples. The analyses shall follow
the standard methods described in APHA Standard Methods for the Examination of
Water and Wastewater, 19th edition or other approved methods. Detailed
testing methods, pre-treatment procedures, instrument use, Quality
Assurance/Quality Control (QA/QC) details (such as blank, spike recovery,
number of duplicate samples per batch, etc.), detection limits and accuracy
shall be submitted to EPD for approval prior to the commencement of monitoring
programme. EPD may also request the laboratory to carry out analysis of
known standards provided by EPD for quality assurance. Additional
duplicate samples may be required by EPD for inter laboratory calibration.
Remaining samples after analysis shall be kept by the laboratory for 3 months
in case repeat analysis is required. If in-house or non-standard
methods are proposed, details of the method verification may also be required
to submit to EPD. In any circumstance, the sample testing shall have
comprehensive quality assurance and quality control programmes. The
laboratory shall prepare to demonstrate the programmes to EPD or his
representatives when requested.
4.5
Water
Quality Monitoring Stations
4.5.1 It is recommended to establish control and impact monitoring stations to
monitor water quality impact during construction phase. Four impact
monitoring stations in vicinity to the construction site have been selected
that may potentially be affected during the construction phase. Two
control stations have been selected such that they are located within the same
water body as the impact monitoring stations but are located outside the area
of influence of the works. Data collected from the control stations
enables a comparison of the water quality at the potentially impacted site with
the ambient water quality. The proposed water quality monitoring stations
are shown in Table 4.1. Figure 4.1 indicates the approximate
locations of the water quality monitoring stations.
Table 4.1 Proposed Marine Water Quality Stations for
Baseline and Impact Monitoring
|
Monitoring Station
|
ID in EIA Report
|
Description
|
Easting (m)
|
Northing (m)
|
|
WC1
|
-
|
Control Station - Flood Tide
|
835
792
|
809
602
|
|
WC2
|
-
|
Control Station - Ebb Tide
|
834
745
|
811
082
|
|
WM1
|
CR9
|
Coral
Communities - Tai Shue Wan
(Impact
Monitoring Station)
|
835
121
|
810
680
|
|
WM2
|
CR8
|
Coral
Communities - South of Tai Shue Wan (Impact Monitoring Station)
|
835
194
|
810
391
|
|
WM3
|
CR7
|
Coral
Communities - Sam Shui Kok
(Impact Monitoring Station)
|
835
585
|
810
175
|
|
WM4
|
-
|
South
of the Project Site
(Impact
Monitoring Station)
|
834
899
|
810
026
|
Notes:
Two control stations (WC1 and WC2) are required due to different flow
directions during flood and ebb tides.
4.5.2
The status
and locations of the above monitoring stations may change after issuing this
Manual. If such cases exist, the appointed ET Leader may propose
alternative monitoring locations taking into consideration of the latest
status, availability and/or accessibility of the various possible monitoring
locations. Any change to the monitoring stations shall be justified by
the ET Leader, agreed by the ER, verified by the IEC before seeking approval
from EPD prior to the implementation of sampling programme.
4.5.3 When alternative monitoring locations are proposed, they should be
chosen based on the following criteria:
·
at locations close to
and preferably at the boundary of the site activities as indicated in the EIA
report, which are likely to have water quality impacts;
·
close to the sensitive
receptors which are directly or likely to be affected;
·
for monitoring
locations located in the vicinity of the sensitive receptors, care should be
taken to cause minimal disturbance during monitoring; and
·
control station shall
be selected at a location to allow a comparison of the water quality at the
potentially impacted site with the ambient water quality. The control
station shall be selected such that it is located within the same body of water
as the impact monitoring station but is located outside the area of influence
of the works.
4.6
Details
of Water Quality Monitoring
Baseline
Monitoring
4.6.1 Baseline conditions of water quality should be established by the ET and
agreed with IEC and EPD. The purposes of the baseline monitoring are to
establish ambient conditions prior to the commencement of the works, to
demonstrate the suitability of the proposed control and impact monitoring
stations, and for establishment of the Action and Limit levels.
4.6.2 The baseline conditions should be established by measuring the water
quality parameters including pH, salinity, temperature, DO (in mg/L and % of
saturation), turbidity and SS at the proposed monitoring stations as shown in Figure 4.1 (also see Table 4.1), 3 days per week, at mid-flood and
mid-ebb tides, for a period of 4 weeks prior to the commencement of dredging,
sand blanket filling and DCM installation. The interval between two sets
of monitoring shall not be less than 36 hours, and the baseline monitoring
schedule shall be submitted to DEP and IEC at least one week prior to the
commencement of the baseline monitoring. The ET Leader shall seek
approval from the ER, IEC and EPD on the alternative proposal prior to its
implementation.
4.6.3 There shall not be any major construction activities in the vicinity of
the stations during the baseline monitoring. The ET shall be responsible
for undertaking the baseline monitoring and submitting the results within 10
working days from the completion of the baseline monitoring work.
4.6.4 In exceptional cases when insufficient baseline monitoring data or
questionable results are obtained, the ET Leader shall seek approval from the
ER, IEC and EPD on an appropriate set of data to be used as baseline reference.
Construction
Monitoring
4.6.5 During dredging, sand blanket filling and DCM installation, impact
monitoring shall be undertaken 3 days per week, with sampling/measurement at
the monitoring stations as shown in Figure
4.1 (also see Table 4.1). The
ET should carry out spot check to ensure that the Contractor has undertaken all
recommended control measures to prevent direct contact of pollutants with
rainwater or runoff, and measures to abate contaminants in the stormwater
runoff. Parameters to be monitored include pH, salinity, temperature, DO
(in mg/L and % of saturation), turbidity and SS. The interval between two
sets of monitoring shall not be less than 36 hours except where there are
exceedances of Action and/or Limit levels, in which case the monitoring
frequency shall be increased.
4.6.6 Requirements as stated in Section 4.5.2 shall be followed.
Any change to the EM&A requirements or programme shall be justified by the
ET Leader, agreed by the ER, verified by the IEC before seeking approval from
EPD prior to its implementation.
4.6.7 Proposed water quality monitoring schedule shall be submitted to ER, IEC
and EPD at least 1 week before the first day of the monitoring month. The
ER, IEC and EPD shall also be notified immediately for any changes in schedule.
Post-Construction
Monitoring
4.6.8 Upon completion of all construction activities, a post-construction
monitoring exercise on water quality shall be carried out for four weeks in the
same manner as the baseline monitoring. The results of the monitoring
shall be presented in the Final EM&A Summary Report.
Water
Quality Compliance
4.6.9 Construction phase water quality monitoring will be evaluated against
Action and Limit levels. The proposed Action and Limit levels for water
quality is presented in Table 4.2.
Action and Limit levels are used to determine whether operational modifications
are necessary to mitigate impacts to water quality. In
the event that the levels are exceeded, appropriate actions in Event and
Action Plan (Table 4.3) should be
undertaken and a review of works will be carried out by the Contractor.
4.6.10 Any
noticeable change to water quality will be recorded in the monitoring reports
and will be investigated and remedial actions will be undertaken to reduce
impacts. Particular attention will be paid to the Contractor's
implementation of the recommended mitigation measures as listed in Appendix B.
Table 4.2 Action and Limit Levels for Water Quality
|
Parameters
|
Action
|
Limit
|
|
DO in mg/L
(Surface, Middle &
Bottom) b
|
Surface & Middle
<5%-ile
of baseline data for surface and middle layers
Bottom
<5%-ile
of baseline data for bottom layer
|
Surface & Middle
<4 mg/L or <1%-ile of baseline data for surface and middle layers
Bottom
<2 mg/L or <1%-ile of baseline data for bottom layer
|
|
SS in mg/L
(depth-averaged a)
c
|
>95%-ile
of baseline data and >120% of upstream control station’s SS recorded on
the same day
|
>99%-ile
of baseline data and >130% of upstream control station’s SS recorded on
the same day
|
|
Turbidity in NTU
(depth-averaged a)
c
|
>95%-ile
of baseline data and >120% of upstream control station’s turbidity
recorded on the same day
|
>99%-ile of baseline data and >130% of upstream control
station’s turbidity recorded on the same day
|
Notes:
a.
“Depth-averaged” is calculated by taking the arithmetic means of reading of all
three depths.
b.
For DO, non-compliance of the water quality limits occurs when monitoring
result is lower than the limits.
c.
For SS and turbidity, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
Table 4.3 Event and Action Plan for Water Quality
Monitoring
|
Event
|
|
Action
|
|
|
ET
|
IEC
|
ER
|
Contractor
|
|
Action level being exceeded
by one sampling day
|
·
Repeat in-situ measurement on the
next day of exceedance to confirm findings;
·
Check monitoring data, equipment and
Contractor's working methods;
·
Identify source(s) of impact and record in
notification of exceedance;
·
Inform IEC, ER and Contractor.
|
·
Check monitoring data submitted by ET
and Contractor’s working methods.
|
·
Confirm receipt of notification of exceedance in writing.
|
·
Confirm receipt of notification of exceedance in writing;
·
Check plant and equipment and rectify unacceptable practice.
|
|
Action level being exceeded
by two or more consecutive sampling days
|
·
Repeat in situ measurement on the
next day of exceedance to confirm findings;
·
Check monitoring data, plant, equipment
and Contractor’s working methods;
·
Identify source(s) of impact and record in
notification of exceedance;
·
Inform IEC, ER and Contractor;
·
Discuss with IEC and Contractor on
additional mitigation measures and ensure that they are implemented.
|
·
Check monitoring data submitted by ET
and Contractor’s working methods;
·
Discuss with ET and Contractor on
additional mitigation measures and advise ER accordingly;
·
Access the effectiveness of the
implemented mitigation measures.
|
·
Confirm receipt of notification of exceedance in writing;
·
Discuss with the IEC on the proposed
additional mitigation measures and agree on the mitigation measures to be implemented;
·
Ensure additional mitigation measures are properly implemented.
|
·
Confirm receipt of notification of exceedance in writing;
·
Check plant and equipment and rectify
unacceptable practice;
·
Consider changes of working methods
·
Discuss with ET and IEC on additional
mitigation measures and proposed them to ER within 3 working days;
·
Implement the agreed mitigation measures.
|
|
Limit level being exceeded
by one sampling day
|
·
Repeat in situ measurement on the
next day of exceedance to confirm findings;
·
Check monitoring data, plant, equipment
and Contractor’s working methods;
·
Identify source(s) of impact and record in
notification of exceedance;
·
Inform IEC, ER, Contractor and EPD;
·
Discuss with IEC and Contractor on
additional mitigation measures and ensure that they are implemented.
|
·
Check monitoring data submitted by ET
and Contractor’s working methods;
·
Discuss with ET and Contractor on
additional mitigation measures and advise ER accordingly;
·
Access the effectiveness of the
implemented mitigation measures.
|
·
Confirm receipt of notification of exceedance in writing;
·
Discuss with the IEC on the proposed
additional mitigation measures and agree on the mitigation measures to be implemented;
·
Ensure additional mitigation measures are
properly implemented;
·
Request Contractor to critically review
the working methods.
|
·
Confirm receipt of notification of exceedance in writing;
·
Check plant and equipment and rectify
unacceptable practice;
·
Critically review the need to change working
methods
·
Discuss with ET and IEC on additional
mitigation measures and proposed them to ER within 3 working days;
·
Implement the agreed mitigation measures.
|
|
Limit level being exceeded
by two or more consecutive sampling days
|
·
Repeat in situ measurement on the
next two days of exceedance to confirm findings;
·
Check monitoring data, plant, equipment
and Contractor’s working methods;
·
Identify source(s) of impact and record in
notification of exceedance;
·
Inform IEC, ER, Contractor and EPD;
·
Discuss with IEC and Contractor on
additional mitigation measures and ensure that they are implemented.
|
·
Check monitoring data submitted by ET
and Contractor’s working methods;
·
Discuss with ET and Contractor on
additional mitigation measures and advise ER accordingly;
·
Access the effectiveness of the
implemented mitigation measures.
|
·
Confirm receipt of notification of exceedance in writing;
·
Discuss with the IEC on the proposed
additional mitigation measures and agree on the mitigation measures to be implemented;
·
Ensure additional mitigation measures are
properly implemented;
·
Request Contractor to critically review
the working methods.
|
·
Confirm receipt of notification of exceedance in writing;
·
Check plant and equipment and rectify
unacceptable practice;
·
Critically review the need to change working
methods
·
Discuss with ET and IEC on additional
mitigation measures and proposed them to ER within 3 working days;
·
Implement the agreed mitigation measures.
|
4.7
Construction Site Audits
4.7.1 Regular site environmental audit during the construction phase of the
Project should be conducted at least once per week to ensure that the
recommended mitigation measures are to be properly undertaken during
construction phase of the Project. It can also provide an effective
control of any malpractices and therefore achieve continual improvement of
environmental performance on site. Site audits shall include site
inspections and compliance audits.
Mitigation
Measures
4.7.2 Mitigation measures for construction phase water quality impact have
been recommended in the EIA Report. All the recommended mitigation
measures are detailed in the implementation schedule presented in Appendix B. The Contractor shall
be responsible for the design and implementation of these measures.
Site
Inspections
4.7.3 Site inspections should be carried out by the ET based on the
recommended mitigation measures for water pollution control as detailed in Appendix B. In
the event that the recommended mitigation measures are not fully or
properly implemented, deficiency shall be recorded and reported to the site
management. Suitable actions should be carried out to:
·
Investigate the
problems and the causes;
·
Issue action notes to
the Contractor which is responsible for the works;
·
Implement remedial and
corrective actions immediately;
·
Re-inspect the site
conditions upon completion of the remedial and corrective actions; and
·
Record the event and
discuss with the Contractor for preventive actions.
Compliance
Audits
4.7.4 Monitoring of the treated effluent quality from the works areas is
required during the construction phase of the Project. The monitoring
shall be carried out at the pre-determined discharge point. Compliance
audits are to be undertaken to ensure that a valid discharge licence has been
issued by EPD prior to the discharge of effluent from the Project site.
The monitoring frequency and parameters specified in the discharge licence
shall be fully considered during the monitoring. All monitoring
requirements shall be approved by EPD. The audit results reflect whether
the effluent quality is in compliance with the
discharge licence requirements. In case of non-compliance, suitable
actions shall be undertaken to:
·
Notify the site
management for the non-compliance;
·
Identify the sources of
pollution;
·
Check the
implementation status of the recommended mitigation measures;
·
Investigate the
operating conditions of the on-site treatment systems;
·
Implement corrective
and remedial actions to improve the effluent quality;
·
Increase monitoring
frequency until the effluent quality is in compliance with
the discharge licence requirements; and
·
Record the
non-compliance and propose preventive measures.
5
Waste Management implications
5.1
Introduction
5.1.1 Potential waste management implication arising from the construction and
operation phases of the Project were addressed in the EIA Report. Waste
management during construction phase will mainly be the contractor’s
responsibility to ensure that any wastes produced during the construction and
demolition works are handled, stored and disposed of in accordance with good
waste management practices and relevant regulations and other legislative
requirements. Provided that these wastes are handled, transported and disposed of
using approved methods and that the recommended good site practices and
relevant legislation are strictly followed, adverse environmental impacts would
not be expected.
5.1.2 Provided that the waste is handled, transported and disposed of using
approved methods during the operation phase of the Project, no adverse
environmental impacts would be expected with the implementation of good waste
management practices. EM&A would not be necessary during the
operation phase.
5.2
Mitigation
Measures
5.2.1 Mitigation measures for waste management recommended in the EIA Report
should form the basis of the site Waste Management Plan (WMP) to be developed
by the Contractor in the construction stage. A WMP, as a part of the
Environmental Management Plan (EMP), should be prepared in accordance with ETWB
TC (W) No.19/2005 and submitted to the Engineer for approval. The
monitoring and auditing requirement stated in ETWB TC (W) No.19/2005
should be followed with regard to the management of
C&D materials. Appendix B
provides the implementation schedule of the recommended mitigation measures
during both construction and operation phases.
5.2.2 Waste generated during the construction activities should be audited
regularly at least once per week by the ET to determine if waste is being
managed in accordance with approved procedures and the site WMP. The audit
should look at all aspects of on-site waste management practices including
waste generation, storage, recycling, transport and disposal. Apart from site
inspection, documents including licenses, permits, disposal and recycling
records should be reviewed and audited for compliance with the legislations and
contract requirements. In addition, the routine site inspections should check
the implementation of the recommended good site practices, waste reduction
measures, and other waste management mitigation measures.
5.2.3 With the appropriate handling, storage and removal of waste arisings
during the construction and operation of the Project as presented in Appendix B, the potential to cause
adverse environmental impacts would be minimised. During the site
inspections, the ET shall pay special attention to the issues relating to waste
management and check whether the Contractor has implemented the recommended good
site practices, waste reduction measures and other mitigation measures.
5.3
Audit
Requirement
5.3.1 Regular audits and site inspections should be carried out at least once
per week during construction phases by the ER, ET and Contractor to ensure that
the recommended good site practices and the recommended mitigation measures
listed in Appendix B are properly
implemented by the Contractor. The audits should concern all aspects of on-site
waste management practices including waste generation, storage, recycling,
transport and disposal. Apart from site inspection, documents including
licences, permits, disposal and recycling records should be reviewed and
audited for compliance with the legislation and contract requirements.
5.3.2 The requirements of the environmental audit programme are set out in Section
10 of this Manual. The audit programme will verify the implementation
status and evaluate the effectiveness of the mitigation measures.
6
MarinE Ecology
6.1
Introduction
6.1.1 Potential marine ecological impacts arising from the construction and
operation phases of the Project were assessed in the EIA Report. These
potential impacts included direct habitat loss, direct injury / mortality of
wildlife, and indirect construction and operation disturbances. The Project
site primarily situated in the Aberdeen Channel where habitats directly
affected included both natural habitats (i.e. rocky shoreline, subtidal soft
and hard bottom habitat) and man-made habitat (i.e artificial
seawalls) that are already subjected to high level of disturbance from existing
marine traffic. Despite 13 coral species of conservation importance
recorded and anticipated to be potentially directly impacted by the Project,
all the species are common and widespread species in Hong Kong with low
coverage (<5%) and sparsely distributed within the vicinity of the Project
site, and the directly impacted area for each proposed work element is very
small, direct impact to these coral species of conservation importance is
therefore anticipated to be Low.
6.1.2 With the implementation of appropriate mitigation measures, no
unacceptable adverse residual impacts would be anticipated. Nonetheless,
EM&A is considered necessary during construction of the Project and the
requirements are described below. No specific ecological EM&A during
operation phase is recommended.
6.2
Mitigation
Measures
6.2.1 The implementation of mitigation measures recommended in the EIA Report to
minimise potential ecological impacts are provided in Appendix B.
6.3
Monitoring
Requirements
6.3.1 Regular weekly marine water quality monitoring should be undertaken
during the construction phase to ensure that all the recommended mitigation
measures to control water quality impacts and associated marine ecological
impacts are properly implemented. Details of monitoring and audits
requirements for marine water quality are set out in Section 4 of this
Manual.
6.3.2 During operation phase, no specific ecological monitoring is required as
residual impacts on the marine ecology are negligible. However, a four-week
post-construction water quality monitoring programme will be in place upon
completion of marine works as mentioned in Section 4 of this Manual.
6.4
Audit
Requirements
6.4.1 Site audits should be undertaken on a weekly basis to check the proper
implementation and maintenance of recommended mitigation measures during
construction phase of the Project. In case of non-compliance, contractor
should be informed to strengthen the proposed mitigation measures accordingly.
6.4.2 No EM&A programme is required during the operation phase.
7
Fisheries
7.1
Introduction
7.1.1 Potential fisheries impacts arising from the
construction and operation phases of the Project were addressed in the EIA
Report. The
impact on fisheries during construction and operation phases is considered
minor. With the implementation of water quality mitigation measures
during construction and operation phases, potential impacts on fisheries will
be further minimised. No unacceptable residual fisheries impacts
during construction and operation phases of the Project will be resulted.
7.2
Mitigation
Measures
7.2.1 Mitigation measures such as deployment of double silt curtains, closed
grab and restriction of dredging rates recommended in the water quality impact
assessment for controlling water quality impact (Section 4 refers) will
also serve to protect fisheries from indirect impacts and ensure no
unacceptable impact on fisheries resources and operations.
7.2.2 Contractor must register as a chemical waste producer if chemical wastes
would be produced from the construction activities. The Waste Disposal
Ordinance (Cap. 354) and its subsidiary regulations in
particular the Waste Disposal (Chemical Waste) (General) Regulation
should be observed and complied with for control of chemical wastes.
7.2.3 Any service shop and maintenance facilities should be located on hard
standings within a bunded area, and sumps and oil interceptors should be
provided.
7.2.4 Maintenance of vehicles and equipment involving activities with
potential leakage and spillage should only be undertaken within the areas
appropriately equipped to control these discharges.
7.2.5 Good site practices should be strictly followed to avoid adverse impacts
arising from the construction activities. Recommendations for good site
practices during the construction phase include:
·
Nomination of approved
personnel, such as a site manager, to be responsible for implementation of good
site practices, arrangements for waste collection and effective disposal to an
appropriate facility;
·
Training of site
personnel in site cleanliness, concepts of waste reduction, reuse and
recycling, proper waste management and chemical waste handling procedures;
·
Provision of sufficient
waste reception/ disposal points, and regular collection of waste;
·
Adoption of appropriate
measures to minimise windblown litter and dust during transportation of waste
by either covering construction vessels or by transporting wastes in enclosed containers;
·
Provision of regular
cleaning and maintenance programme for drainage systems, sumps and oil interceptors;
·
Adoption of a recording
system for the amount of wastes generated, recycled
and disposed (including the disposal sites); and
·
Preparation of Waste
Management Plan, as part of the Environmental Management Plan.
7.3
Monitoring
and Audit Measures
7.3.1 Regular weekly marine water quality monitoring should be undertaken
during the construction phase to ensure that all the recommended mitigation
measures to control water quality impacts and associated fisheries impacts are
properly implemented. Details of monitoring and audits requirements for marine
water quality are set out in Section 4 of this Manual.
7.3.2 No unacceptable residual fisheries impacts
during construction and operation phases of the Project will be resulted.
Thus, no environmental monitoring and auditing program specific for fisheries
is required. However, a four-week post-construction water quality monitoring
programme will be in place upon completion of marine works as mentioned in Section
4 of this Manual.
8
Landscape and Visual
8.1
Introduction
8.1.1 Potential landscape and visual impacts arising from the construction and
operation phases of the Project were addressed in the EIA Report. Results
indicated that landscape and visual impact arising from construction of the
Project with the implementation of the mitigation measures is acceptable.
8.2
Mitigation
Measures
8.2.1 The implementation of mitigation measures recommended in the EIA Report
to minimise potential landscape and visual impacts are provided in Appendix B.
8.3
Audit
Requirements
8.3.1 Monitoring and audit should be undertaken during the construction phase
of the Project to ensure and check that the implementation and maintenance of
landscape and visual mitigation measures are being properly carried out.
Regular site inspections should be undertaken through the construction period.
9
Cultural Heritage
9.1
Introduction
9.1.1 There is no built heritage identified within the Project boundary and
assessment area. One other identified item with no status (existing
breakwaters) is located within the Project boundary while one other identified
item with no status (No. 198 light beacon and associated landing facilities) is
located within the 300 m assessment area. Potential impact is anticipated
from the Project to the existing western breakwater as shortening of the
existing western breakwater is proposed in the Project. Mitigation
measures for the existing western breakwater are recommended. On the other
hand, since there is no impact anticipated to No. 198 light beacon and
associated landing facilities, no mitigation measure is required.
9.2
Mitigation
Measures
Construction
Phase
Built
Heritage
9.2.1 No EM&A programme is required during the construction phase.
During construction phase, potential direct impact involving shortening is
anticipated from the Project to the existing western breakwater. It
should be preserved by record (3D scanning, photographic and video) before the
shortening and modification. Furthermore, the end of the shortened western
breakwater should be constructed to preserve a similar shape and materials of
the tetrapod in its current layout.
Archaeology
9.2.2 There will be no need for any mitigation measures during the
construction phase.
9.2.3 For precautionary measures, AMO should be informed immediately if marine
archaeological materials having certain to significant values are found during the course of construction works of the Project.
Operation
Phase
Built
Heritage
9.2.4 As no adverse impacts to any built heritage in concern during the
operation phase, no mitigation measure is required to the built heritage and
other identified item.
Archaeology
9.2.5 There will be no need for any mitigation measures during the operation
phase.
10
Site Inspection / Audit
10.1
Site
Inspection Requirements
10.1.1 Site
inspection provides a direct means to trigger and enforce specified
environmental protection and pollution control measures. These shall be undertaken
regularly and routinely to inspect construction activities in
order to ensure that appropriate environmental protection and pollution
control mitigation measures are properly implemented. The site inspection
is one of the most effective tools to enforce the environmental protection
requirements at the works area.
10.1.2 The
ET Leader shall be responsible for formulating the environmental site
inspection, the deficiency and remedial action reporting system, and for
carrying out the site inspection works. He shall submit a proposal for
site inspection and deficiency and remedial action reporting procedures to the
Contractor for agreement, and to the ER for approval. The ET’s proposal for
rectification would be made known to the IEC.
10.1.3 Regular
site inspections shall be carried out at least once per week. The areas
of inspection shall not be limited to the environmental situation, pollution
control and mitigation measures within the site; it should also review the
environmental situation outside the works area which
is likely to be affected, directly or indirectly, by the site activities.
The ET shall make reference to the following
information in conducting the inspection:
·
the EIA and EM&A recommendations
on environmental protection and pollution control mitigation measures;
·
ongoing results of the
EM&A program;
·
works progress and programme;
·
individual works
methodology proposals (which shall include proposal on associated pollution
control measures);
·
contract specifications
on environmental protection and pollution prevention control;
·
relevant environmental
protection and pollution control laws; and
·
previous site
inspection results undertaken by the ET and others.
10.1.4 The
Contractor shall keep the ET Leader updated with all relevant information on
the construction contract necessary for him to carry out the site inspections.
Inspection results and associated recommendations for improvements to the
environmental protection and pollution control works shall be submitted to the
IEC and the Contractor within 24 hours for reference and for taking immediate
remedial action. The Contractor shall follow the procedures and time-frame stipulated in the environmental site inspection,
and the deficiency and remedial action reporting system formulated by the ET
Leader, to report on any remedial measures subsequent to
the site inspections.
10.1.5 The
ET shall also carry out ad hoc site inspections if significant environmental
problems are identified. Inspections may also be required subsequent to receipt of an environmental complaint, or as
part of the investigation work, as specified in the Action Plan for
environmental monitoring and audit.
10.2
Compliance
with Legal and Contractual Requirements
10.2.1 There
are contractual environmental protection and pollution control requirements as
well as environmental protection and pollution control laws in Hong Kong with
which construction activities must comply.
10.2.2 In
order that the works are in compliance with the
contractual requirements, all works method statements submitted by the
Contractor to the ER for approval shall be sent to the ET Leader for vetting to
see whether sufficient environmental protection and pollution control measures
have been included. The implementation schedule of mitigation measures is
summarised in Appendix B.
10.2.3 The
ET Leader shall also review the progress and programme of the works to check
that relevant environmental laws have not been violated, and that any
foreseeable potential for violating laws can be prevented.
10.2.4 The
Contractor shall regularly copy relevant documents to the ET Leader so that
works checking could be carried out effectively. The document shall at
least include the updated Works Progress Reports, updated Works Programme, any
application letters for different license / permits under the environmental
protection laws, and copies of all valid licenses / permits. The site
diary shall also be available for the ET Leader's inspection upon his request.
10.2.5 After
reviewing the documentation, the ET Leader shall advise the Contractor of any
non-compliance with contractual and legislative requirements on environmental
protection and pollution control for them to take follow-up actions. If
the ET Leader's review concludes that the current status
on license / permit application and any environmental protection and pollution
control preparation works may result in potential violation of environmental
protection and pollution control requirements, he shall also advise the
Contractor accordingly.
10.2.6 Upon
receipt of the advice, the Contractor shall undertake immediate action to
remedy the situation. The ER shall follow up to ensure that appropriate
action has been taken in order to satisfy contractual
and legal requirements.
10.3
Environmental
Complaints
10.3.1 Complaints
shall be referred to the ET Leader for action. The ET Leader shall undertake
the following procedures upon receipt of any complaint:
i.
log complaint and date
of receipt onto the complaint database and inform the IEC immediately;
ii.
investigate the
complaint to determine its validity, and assess whether the source of the
problem is due to works activities;
iii.
identify mitigation
measures in consultation with the IEC if a complaint is valid and due to works;
iv.
advise the Contractor
if mitigation measures are required;
v.
review the Contractor's
response to identified mitigation measures, and the updated situation;
vi.
if the complaint is
transferred from the EPD, submit interim report to the EPD on status of the
complaint investigation and follow-up action within the time frame assigned by
the EPD;
vii.
undertake additional
monitoring and audit to verify the situation if necessary, and review that
circumstances leading to the complaint do not recur;
viii.
report investigation
results and subsequent actions to complainant (if the source of complaint is
identified through EPD, the results should be reported within the timeframe
assigned by EPD); and
ix.
record the complaint,
investigation, the subsequent actions and the results in the monthly EM&A
reports.
10.3.2 A
flow chart of the complaint response procedure is shown below.
10.3.3 During
the complaint investigation work, the Contractor and ER shall co-operate with
the ET Leader in providing all the necessary information and assistance for
completion of the investigation. If mitigation measures are identified to
be required in the investigation in consultation with the IEC, the Contractor
shall promptly carry out the mitigation works. The ER shall ensure that
the Contractor has implemented the mitigation measures.
11
Reporting
11.1
Introduction
11.1.1 Reports
can be provided in an electronic medium upon agreeing the format with the ER
and EPD. This would enable a transition from a paper / historic and reactive
approach to an electronic / real time proactive approach. All the
monitoring data (baseline and impact) shall also be submitted in electronic
format.
11.1.2 ET
Leader shall submit baseline monitoring report, monthly EM&A report,
quarterly EM&A summary report and final EM&A review report. In
accordance with Annex 21 of the EIAO-TM, a copy of the monthly, quarterly
summary and final review EM&A reports shall be made available to the
Director of Environmental Protection.
11.2
Electronic
Reporting of EM&A Information
11.2.1 To
facilitate public inspection of the baseline monitoring report and various
EM&A reports via the Environmental Impact Assessment Ordinance (EIAO)
Internet website and at the EIAO register office, electronic copies of these
reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF Adobe 11 Pro version or later),
unless otherwise agreed by EPD and shall be submitted at the same time as the
hardcopies. For the HTML version, a content page capable of providing
hyperlink to each section and sub-section of these reports shall be included at
the beginning of the document. Hyperlinks to all figures, drawings and
tables in these reports shall be provided in the main text from where the
respective references are made. All graphics in these reports shall be in
interlaced GIF format unless otherwise agreed by EPD. The content of the
electronic copies of these reports must be the same as the hard copies.
The summary of the monitoring data taken shall be included in the various
EM&A Reports to allow for public inspection via the EIAO Internet website.
11.3
Baseline
Monitoring Report
11.3.1 Baseline
Environmental Monitoring Report(s) shall be prepared within 10 working days of
completion of the baseline monitoring and then certified by the ET Leader.
Copies of the Baseline Environmental Monitoring Report shall be submitted to
the Contractor, the IEC, ER and EPD. The ET Leader shall liaise with the
relevant parties on the exact number of copies they require.
11.3.2 The
Baseline Environmental Monitoring Report shall include, but not be limited to
the following information:
i.
up to half a page
executive summary;
ii. brief project background information;
iii. drawings showing locations of the baseline
monitoring stations;
iv. an updated construction programme
with milestones of environmental protection / mitigation activities annotated;
v.
monitoring results (in
both hard and soft copies) together with the following information:
-
monitoring methodology;
-
name of laboratory and
types of equipment used and calibration details;
-
parameters monitored;
-
monitoring locations
(and depth);
-
monitoring date, time,
frequency and duration; and
-
QA/QC results and
detection limits.
vi. details on influencing factors,
including:
- major activities, if any, being
carried out on the site during the period;
- weather conditions during the
period; and
- other factors which might affect
results.
vii. determination of the Action and Limit levels
for each monitoring parameter and statistical analysis of the baseline data,
the analysis shall conclude if there is any significant difference between
control and impact stations for the parameters monitored;
viii. revisions for inclusion in the EM&A Manual; and
ix.
comments,
recommendations and conclusions.
11.4
Monthly
EM&A Reports
General
11.4.1 The
results and finding of all EM&A works required in the Manual should be
recorded in the monthly EM&A reports prepared by the ET Leader and endorsed
by the IEC. The EM&A report shall be prepared and submitted within 10
working days at the end of each reporting month, with the first report due the
month after construction commences. Each monthly EM&A report shall be
submitted to the following parties: the Contractor, the IEC, the ER and
EPD. Before submission of the first EM&A report, the ET Leader shall
liaise with the parties on the required number of copies and format of the
monthly reports in both hard copy and electronic medium.
11.4.2 The
ET Leader shall review the number and location of monitoring stations and
parameters every six months, or on as needed basis, in order
to cater for any changes in the surrounding environment and the nature
of works in progress.
First
Monthly EM&A Report
11.4.3 The
first monthly EM&A report shall include at least but not be limited to the
following:
i.
executive summary (1-2
pages):
- breaches of Action and Limit levels;
- complaint log;
- notifications of any summons and
successful prosecutions;
- reporting changes; and
- future key issues.
ii. basic project information:
- project organisation including key
personnel contact names and telephone numbers;
- construction programme with fine
tuning of construction activities showing the inter-relationship with
environmental protection/mitigation measures for the month;
- management structure, and
- works undertaken during the month.
iii. environmental status:
- advice on the status of statutory
environmental compliance, such as the status of compliance with the EP
conditions under the EIAO, submission status under the EP and implementation
status of mitigation measures;
- works undertaken during the
reporting month with illustrations (such as location of works, etc.); and
-
drawings showing
the Project area, any environmental sensitive receivers and the locations of
the monitoring and control stations (with co-ordinates of the monitoring
locations).
iv. a brief summary of EM&A requirements including:
- all monitoring parameters;
- environmental quality performance
limits (Action and Limit levels);
- Event-Action Plans;
- environmental mitigation measures as
recommended in the Final EIA report; and
- environmental requirements in
contract documents.
v.
implementation status:
- advice on the implementation status
of environmental protection and pollution control / mitigation measures, as
recommended in the Final EIA report, summarised in the updated implementation
schedule.
vi. monitoring results (in both hard and
soft copies) together with the following information:
- monitoring methodology;
- name of laboratory and types of
equipment used and calibration details;
- monitoring parameters;
- monitoring locations (and depth);
- monitoring date, time, frequency,
and duration; and
- weather conditions during the
period.
- graphical plots of the monitored
parameters in the month annotated against:
o the major activities being carried
out on site during the period;
o weather conditions that may affect
the results; and
o any other factors which might affect
the monitoring results;
- any other factors which might affect
the monitoring results; and
- QA/QC results and detection limits.
vii. report on non-compliance, complaints,
notifications of summons and successful prosecutions:
- record of all non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
levels);
- record of all complaints received
(written or verbal) for each media, including locations and nature of
complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary;
- record of all notification of
summons and successful prosecutions for breaches of current environmental
protection / pollution control legislations, including locations and nature of
the breaches, investigation, follow-up actions taken, results and summary;
- review of the reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures; and
- description of the actions taken in
the event of non-compliance and deficiency reporting and any follow-up
procedures related to earlier non-compliance.
viii. others:
- an account of the future key issues
as reviewed from the works programme and work method statements;
- advice on the solid and liquid waste
management status;
- a forecast of the works programme,
impact predictions and monitoring schedule for the next three months;
- compare and
contrast the
EM&A data with the EIA predictions and annotate with explanation for any
discrepancies; and
-
comments (for examples,
effectiveness and efficiency of the mitigation measures), recommendations (for
example, any improvement in the EM&A programme) and conclusions.
Subsequent
Monthly EM&A Reports
11.4.4 Subsequent
monthly EM&A reports shall include the following:
i.
executive summary (1 -
2 pages):
- breaches of Action and Limit levels;
- complaints log;
- notifications of any summons and successful
prosecutions;
- reporting changes; and
- future key issues.
ii. basic project information:
- project organisation including key
personnel contact names and telephone numbers;
- construction programme with fine
tuning of construction activities showing the inter-relationship with
environmental protection/mitigation measures for the month;
- management structure, and
- works undertaken during the month.
iii. environmental status:
- advice on the status of statutory
environmental compliance, such as the status of compliance with the EP
conditions under the EIAO, submission status under the EP and implementation
status of mitigation measures;
- works undertaken during the month
with illustrations including key personnel contact names and telephone numbers;
and
- drawing showing the Project area,
any environmental sensitive receivers and the locations of the monitoring and
control stations.
iv. implementation status:
- advice on the implementation status
of environmental protection and pollution control / mitigation measures, as
recommended in the Final EIA report, summarised in the updated
implementation schedule.
v.
monitoring results (in
both hard and soft copies) together with the following information:
- monitoring methodology;
- name of laboratory and types of
equipment used and calibration details;
- parameters monitored;
- monitoring locations (and depth);
- monitoring date, time, frequency,
and duration;
- weather conditions during the period;
- graphical plots of the monitored
parameters in the month annotated against;
o the major activities being carried
out on site during the period;
o weather conditions that may affect
the results; and
o any other factors which might affect
the monitoring results.
- any other factors which might affect
the monitoring results; and
- QA/QC results and detection limits.
vi. report on non-compliance,
complaints, and notifications of summons and successful prosecutions:
- record of all non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
levels);
- record of all complaints received
(written or verbal) for each media, including locations and nature of
complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary;
- record of all notification of
summons and successful prosecutions for breaches of current environmental
protection / pollution control legislations, including locations and nature of
the breaches, investigation, follow-up actions taken, results and summary;
- review of the reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures; and
- description of the actions taken in
the event of non-compliance and deficiency reporting and any follow-up
procedures related to earlier non-compliance.
vii. others:
- an account of the future key issues
as reviewed from the works programme and work method statements;
- advice on the solid and liquid waste
management status;
- a forecast of the works programme,
impact predictions and monitoring schedule for the next three months;
- compare and
contrast the
EM&A data with the EIA predictions and annotate with explanation for any
discrepancies; and
- comments (for examples,
effectiveness and efficiency of the mitigation measures), recommendations (for
example, any improvement in the EM&A programme) and conclusions.
viii. appendices
- Action and Limit levels;
- graphical plots of trends of
monitored parameters at key stations over the past four reporting periods for
representative monitoring stations annotated against the following:
o major activities being carried out
on site during the period;
o weather conditions during the
period; and
o any other factors that might affect
the monitoring results.
- monitoring schedule for the present
and next reporting period;
- cumulative statistics on complaints,
notifications of summons and successful prosecutions; and
-
outstanding issues and
deficiencies
11.5
Quarterly
EM&A Summary Reports
11.5.1 A
quarterly EM&A summary report of around five pages shall be produced by the
ET Leader and shall contain at least the following information. Apart
from these, the first quarterly summary report should also confirm that the
monitoring work is proving effective and that it is generating data with the
necessary statistical power to categorically identify or confirm the absence of
impact attributable to the works. Each quarterly EM&A report shall be
submitted to the following parties: the IEC, the ER and EPD.
i.
executive summary (1 -
2 pages);
ii. basic project information including
a synopsis of the project organisation, programme, contacts of key management,
and a synopsis of works undertaken during the quarter;
iii. a brief summary of EM&A requirements including:
- monitoring parameters;
- environmental quality performance
limits (Action and Limit levels); and
- environmental mitigation measures,
as recommended in the Final EIA report.
iv. advice on the implementation status
of environmental protection and pollution control / mitigation measures, as
recommended in the Final EIA report, summarised in the updated implementation schedule;
v.
drawings showing the Project
area, any environmental sensitive receivers and the locations of the monitoring
and control stations;
vi. graphical plots of the trends of
monitored parameters over the past four months (the last month of the previous
quarter and the present quarter) for representative monitoring stations
annotated against:
- the major activities being carried
out on site during the period;
- weather conditions during the
period; and
- any other factors which might affect
the monitoring results.
vii. advice on the solid and liquid waste management
status;
viii. a summary of non-compliance (exceedances) of the environmental quality
performance limits (Action and Limit levels);
ix. a brief review of the reasons for
and the implications of non-compliance, including a review of pollution sources
and working procedures;
x.
a summary description
of the actions taken in the event of non-compliance and any follow-up
procedures related to earlier non-compliance;
xi. a summarised record of all
complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken;
xii. a summary record of notifications of summons
and successful prosecutions for breaches of the current environmental
protection / pollution control legislations, locations and nature of the
breaches, investigation, follow-up actions taken and results;
xiii. comments (for examples, a review of the effectiveness and efficiency of
the mitigation measures and the performance of the environmental management
system, that is, of the overall EM&A programme); recommendations (for
example, any improvement in the EM&A programme) and conclusions for the
quarter; and
xiv. proponents' contacts and any hotline
telephone number for the public to make enquiries.
11.6
Final
EM&A Review Report for Construction Phase
11.6.1 The
construction phase EM&A program shall be terminated upon completion of
those construction activities that have the potential to result in a
significant environmental impact.
11.6.2 The
proposed termination should only be implemented after the proposal has been
endorsed by the IEC, the Engineer and the Project proponent followed by final
approval from the Director of Environmental Protection.
11.6.3 The
final EM&A review report for construction phase should be prepared by the
ET Leader and contain at least the following information. The final EM&A
review report shall be submitted to the following parties: the IEC, the ER and
EPD.
i.
executive summary (1 -
2 pages);
ii. basic project information including
a synopsis of the project organisation, contacts of key management, and a
synopsis of work undertaken during the course of the
Project or past twelve months;
iii. a brief summary of EM&A requirements including:
- monitoring parameters;
- environmental quality performance
limits (Action and Limit levels); and
- environmental mitigation measures,
as recommended in the Final EIA report.
iv. advice on the implementation status
of environmental protection and pollution control / mitigation measures, as
recommended in the Final EIA report, summarised in the updated implementation schedule;
v.
drawings showing the
Project area, any environmental sensitive receivers and the locations of the
monitoring and control stations;
vi. graphical plots of the trends of
monitored parameters over the course of the Project, for all monitoring
stations annotated against:
- the major activities being carried
out on site during the period;
- weather conditions during the period;
- any other factors which might affect
the monitoring results; and
- the return of ambient environmental
conditions in comparison with baseline data.
vii. compare and contrast the EM&A data with the EIA
predictions and annotate with explanation for any discrepancies;
viii. provide clear-cut decisions on the environmental acceptability of the
Project with reference to the specific impact hypothesis;
ix. advice on the solid and liquid waste
management status;
x.
a summary of
non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels);
xi. a brief review of the reasons for
and the implications of non-compliance including review of pollution sources
and working procedures;
xii. a summary description of the actions taken in
the event of non-compliance and any follow-up procedures related to earlier non-compliance;
xiii. a summary record of all complaints received (written or verbal) for each
media, liaison and consultation undertaken, actions and follow-up procedures taken;
xiv. review monitoring methodology adopted and with the benefit of hindsight,
comment on its effectiveness (including cost effectiveness);
xv. a summary record of notifications of summons
and successful prosecutions for breaches of the current environmental
protection/pollution control legislations, locations and nature of breaches,
investigation, follow-up actions taken and results;
xvi. review the practicality and effectiveness of the EIA process and
EM&A programme (for example, a review of the effectiveness and efficiency
of the mitigation measures and the performance of the environmental management
system, that is, of the overall EM&A programme), recommendations (for
example, any improvement in the EM&A programme); and
xvii. a conclusion to state the return of
ambient and / or the predicted scenario as per EIA findings.
11.7
Data
Keeping
11.7.1 No
site-based documents (such as monitoring field records, laboratory analysis
records, site inspection forms etc.) are required to be included in the
EM&A reporting documents. However, any such documents should be
properly maintained by the ET and be ready for inspection upon request.
All relevant information should be recorded in electronic format, and the
software copy must be available upon request. All document and data
should be kept for at least one year after completion of the construction
contract.
11.8
Interim
Notifications of Environmental Quality Limit Exceedances
11.8.1 With
reference to the Event and Action Plan, when the environmental quality
performance limits are exceeded, the ET Leader shall immediately notify the IEC
and EPD, as appropriate. The notification shall be followed up with advice to
IEC and EPD on the results of the investigation, proposed actions and success
of the actions taken, with any necessary follow-up proposals. A sample template
for the interim notifications is presented in Appendix D.