13. ENvironmental Monitoring
and Audit Requirements
13.5 Waste
Management Implication
13.7 Terrestrial
and Marine Ecology
List of Appendices
Appendix 13.1 Implementation Schedule of Recommended
Mitigation Measures
13.1.1.2 The purpose of the EM&A programme is to ascertain and verify the assumptions implicit to, and accuracy of, EIA study predictions. The EM&A programme includes the scope of the EM&A requirements for the Project to ensure compliance with the EIA study recommendations and assess the effectiveness of the recommended mitigation measures. The following sections summarise the recommended EM&A requirements with the Implementation Schedule of Recommended Mitigation Measures presented in Appendix 13.1.
Construction Phase
13.2.1.1
EM&A
for potential dust impact should be conducted during construction
phase so as to check compliance with the legislative
requirements. Details of the monitoring
and audit programme are contained in a stand-alone EM&A Manual.
13.2.1.2
Regular
site audits for potential air quality impact are recommended to be conducted
during the entire construction phase of the Project so as to ensure the
implementation of the mitigation measures proposed in this EIA Report and the
suppression measures stipulated in Air Pollution Control (Construction Dust)
Regulation, the use of approved or exempted non-road mobile machinery
stipulated in Air Pollution Control (Non-road Mobile Machinery) (Emission)
Regulation, and the use of appropriate fuel stipulated in Air Pollution Control
(Fuel Restriction) Regulation.
Operational Phase
13.2.1.3
No adverse
impact would be anticipated during the operational phase of the Project. No EM&A
requirement would be required during the operation of the Project.
Construction Phase
13.3.1.1
Noise
monitoring is recommended as part of the EM&A programme for the
construction phase of the Project to check compliance with the construction
noise criteria.
13.3.1.2
The
implementation of the recommended mitigation
measures for construction activities should also be audited as part of the
EM&A programme, with reference to the latest implementation schedule in the
Construction Noise Management Plan (CNMP) to be submitted and agreed with the
Director of Environmental Protection (DEP).
Operational Phase
13.3.1.3
No adverse traffic noise impact
is anticipated on existing NSRs and no committed and planned NSRs have been
identified within the 300m assessment area at the time of EIA study. EM&A
requirements are not considered necessary.
13.3.1.4
As no planned fixed
noise sources would be proposed under the Project, no EM&A requirement is
therefore deemed necessary.
Construction Phase
13.4.1.1
With the
implementation of good site practices, recommended mitigation measures and
enhancement measures to control construction site runoff, no adverse water quality
impact for land-based works is anticipated during the construction phase.
Nevertheless, regular water quality impact monitoring for land-based works is
required to ensure compliance with criteria as stipulated in EIAO-TM.
13.4.1.2
The
potential water quality impact from the proposed marine works can be
effectively controlled through the implementation of recommended mitigation
measures (i.e., deployment of silt curtain). Nevertheless, regular water quality impact monitoring for
marine works is required to ensure compliance with criteria as stipulated in
EIAO-TM.
13.4.1.3
Regular
environmental site inspections at least once per week shall be carried out
during construction phase to ensure that the recommended best management practices,
mitigation measures and enhancement measures as recommended in this EIA Report
and the EM&A Manual are properly implemented by the Contractor.
Operational Phase
13.4.1.4
The minor
additional surface runoff will be collected and screened by road drainage
system before diverting into the stormwater drains. No water quality monitoring specifically for the
operational phase of the Project is therefore required.
Construction Phase
13.5.1.1
During the
construction period, it is the Contractor’s responsibility to ensure that all the waste produced
during the construction of the Project are handled, stored and disposed of in
accordance with good waste management practices, relevant legislation and waste
management guidelines.
13.5.1.2
The
Project Manager / Project Manager’s Representative and Independent Environmental
Checker shall enforce the trip ticket system in accordance with paragraphs 25
and 21 of DEVB TC(W) No. 6/2010 respectively.
13.5.1.3
Waste
materials generated during construction activities, such as construction and
demolition (C&D) materials, are recommended to be audited at regular
intervals to ensure that proper storage, transportation and disposal practices are
implemented. This measure ensures the
proper disposal of waste. The Contractor
would be responsible for the implementation of any mitigation measures to minimise waste or mitigate problems arisen from waste
materials.
13.5.1.4
A Waste
Management Plan (WMP), as part of the Environmental Management Plan should be prepared in accordance with ETWB TC(W) No. 19/2005 and submitted to
the Project Manager for approval. The
recommended mitigation measures should form the basis of the WMP. The monitoring and auditing requirements
stated in ETWB TC(W) No.19/2005 should be followed with
regard to the management of C&D materials.
Operational Phase
13.5.1.5
It is
expected that limited quantities of waste would be generated from the operation of the
Project and adverse environmental impacts would not be anticipated with the
implementation of good waste management practices. Waste monitoring and audit
programme for the operational phase of the Project is not required.
Construction Phase
13.6.1.1
Based on the site appraisal, three
potentially contaminated sites (i.e. Public Carpark and Adjacent Vegetated Land
(Site STW1), Dockyard (Site HUD1) and Sai Tso Wan Concrete Batching Plant (Site
HUD2)) were identified with potential land contamination concerns to the
Project. However, it is considered not feasible to carry out the site
investigation (SI) works under the EIA Study within the these
potentially contaminated sites. Moreover, there is an existing Vacant Land (Site LT2)
which was inaccessible at the time of site walkover. Based on the tentative construction
programme, land clearance / resumption for the Project will not commence until
2026, there could be changes in the operation or land use within the three potentially
contaminated sites and the inaccessible site which may cause further
contamination issues. Further site
appraisal should be carried out within the Proposed Clearance Limit and
off-site facilities / works areas at a later stage of the Project to confirm /
update the land uses / activities and to identify the presence of on-site and
off-site potential contamination sources. In addition, should there be any
expansion of the Proposed Clearance Limit, further site appraisal would also be
required to be carried out within the expanded area. Contamination Assessment Plan(s) (CAP(s))
presenting the findings of the further site appraisal, the latest site
conditions of the concerned sites and updated sampling strategy and testing
protocol, should be submitted to EPD for approval.
13.6.1.2
The further site
appraisal and submission of CAP(s) should be carried out prior to the
commencement of the SI works. The SI
works should be carried out according to EPD’s approved CAP(s). Following the completion of SI works and
receipt of laboratory test results, Contamination Assessment Report(s) (CAR(s))
should be prepared to present the findings of the SI works and to discuss the
presence, nature and extent of contamination.
If contamination is identified, Remediation Action Plan(s) (RAP(s)) which provides
details of the remedial actions for the identified contaminated soil and / or
groundwater should be endorsed by EPD. The
remedial actions
should be formulated with consideration given to the Source-Pathway-Receptor Paradigm by
adopting the appropriate control method(s) (i.e. source control method, pathway
control method and/or receptor control method). To minimise
the cost of remediation work, if remediation is required and where appropriate,
“pathway control” approach, e.g. by proper capping the source of contamination
by soil or concrete slabs or by the use of membranes
or solidification, would be considered to prevent migration of contaminants.
13.6.1.3
Remediation
action, if necessary, will be carried out according to EPD endorsed RAP(s) and
Remediation Report(s) (RR(s)) will be submitted after completion of the
remediation action. The RR(s) should be
endorsed by EPD prior to the commencement of construction works at the
respective identified contaminated areas (if any). The submission of CAP(s),
associated SI works and any necessary remediation
should be carried out prior to the commencement of construction works. The EM&A requirements should be carried out in the form of
monthly site inspection to ensure the recommended
mitigation measures are properly implemented.
Operational Phase
13.6.1.4
No land contamination issue
under operational phase is expected.
Construction Phase
13.7.1.1
Site
clearance associated with construction works would potentially lead to the direct and indirect impacts on habitats and species of conservation
importance.
Regular site audits and monitoring should be undertaken to implement
good site practices and mitigation measures specified in S.8.11, as well
as in other chapters in relation to noise, air quality, waste management and
water quality control so
as to alleviate the
impact of construction disturbance on the ecology in the area.
Preservation,
Transplantation and/or Compensatory Planting of Flora Species of Conservation
Importance
13.7.1.2
As described in S.8.11.3.7 –
S.8.11.3.9, a
pre-construction detailed vegetation survey should be conducted by qualified
plant ecologist(s) prior to the commencement of site clearance and construction
works in order to identify the presence of any individuals of flora species of
conservation importance within the at-grade works area, including but not
limited to Small Persimmon, Pitcher Plant, Pale Purple Eulophia,
and any other flora species of conservation importance recorded in the
literature review and the ecological survey.
The curriculum vitae of the qualified plant ecologist(s) and survey
methodologies should be submitted to AFCD for review and approval beforehand.
During the pre-construction detailed vegetation survey, each identified individuals should be tagged and mapped, with photographs
and information including their height, diameter at breast height, spread,
condition, form, amenity value, survival of transplantation and proposed
treatment etc. Prior to the commencement
of transplantation, a Plant Preservation and Transplantation Proposal should be
prepared and submitted to AFCD for approval.
The proposal shall include the findings of the pre-construction detailed
vegetation survey, the proposed methodologies of plant preservation,
transplantation and compensation, identification of suitable receptor site,
implementation programme, post-transplantation monitoring and maintenance
programme including monitoring frequency, monitoring parameters, and
recommended remedial measures. Mitigation approach in the order of in-situ preservation,
transplantation, and compensation would be followed. In the case where
some directly affected individuals of Small Persimmon were deemed infeasible
for preservation or transplantation, legitimate justifications shall be
provided. Compensation
planting of the species could be considered and implemented. The compensation ratio of affected
individuals should be in the ratio of 1:1, unless agreed otherwise with
AFCD. The recommended compensation
planting quantity, planting location, planting methodologies as well as
provision of a post-planting monitoring programme should be included in the
Plant Preservation and Transplantation Proposal. A planting proposal shall be prepared for
agreement with AFCD containing information on the recommended planting
quantity, planting location, planting methodologies as well as provision of a
post-planting monitoring programme.
Site Audit and
Monitoring for Works Around Affected Watercourses and
Waterbodies
13.7.1.3
Romer’s Tree Frog and Caridina serrata were recorded in the
downstream sections of watercourses W2 and W3.
These habitats
are sensitive to water quality deterioration from construction works planned in
the upper tributaries. To mitigate these potential impacts, temporary stream
diversions will be implemented to protect downstream fauna by maintaining water
flow and preventing construction materials from entering the watercourses. For
the marine works component, which includes dredging, marine DCM, and
reclamation, silt curtains will be deployed around the periphery of the works
area prior to commencement. This measure is designed to minimise the release of
suspended solids from the seabed into the surrounding marine environment,
thereby protecting marine water quality.
13.7.1.4
Regular site audits should be carried out to ensure best management of
construction site run-off and discharge and mitigation measures proposed for
reducing construction site run-off and discharge are being implemented with
stringent adherence to relevant guidelines stipulated in the ProPECC PN 2/23 Construction Site Drainage (EPD, 2023) and
ETWB TC(W) No. 5/2005 Protection of Natural Streams/Rivers from Adverse Impacts
Arising from Construction Works (ETWB, 2005), which should include those listed
in S.5.8.1, S.8.11.3.18 and S. 8.11.3.19.
Translocation of
Romer’s Tree Frog or Other Identified Aquatic/Water-dependent Species of
Conservation Importance
13.7.1.5
A pre-construction survey should be carried out by qualified ecologist(s) in the at-grade works area where direct impact
would be anticipated in order to identify the presence
of any individuals of Romer’s Tree Frog or any other aquatic/water-dependent
species of conservation importance (inc. amphibians and freshwater fauna). Greater caution should be paid to affected
watercourses (i.e. W1, W2 and W3) and its adjacent riparian shrubland /
grassland habitats. The scope and
methodology of the pre-construction survey, and the curriculum vitae of the
qualified ecologist(s) should be submitted and agreed with AFCD prior to
commencement of survey works. In
instances where individuals are identified in the works area and translocation
is required, the methodology and findings of the pre-construction survey, along
with a translocation and post-translocation monitoring plan presenting the
number of individuals to be translocated, the translocation methodology, the
identified translocation site, the implementation schedule, as well as
post-translocation monitoring methodology and programme should be defined and
presented in a Translocation Proposal, which shall be submitted to AFCD for
comments and approval prior to translocation works. Individuals should be translocated to nearby
habitats of similar habitat conditions, adequate barriers such as hoarding and
fencing should be set up around the works area following translocation to
prevent individuals from entering the works area. The potential translocation recipient site
should be located well outside the areas where direct and indirect impacts from
the construction works of the project (i.e. W5 and W6), as well as those of
other planned/committed projects nearby, are not expected.
Translocation of
Affected Coral Colonies
13.7.1.6
A pre-construction detailed coral survey shall be conducted in the
marine works area prior to the commencement of marine works by qualified coral
ecologist(s) with SCUBA diving qualification and experience, the curriculum
vitae of whom shall be submitted to AFCD along with the scope and methodology
of the detailed coral survey for review and agreement prior to commencement of
the survey. The survey should confirm
specifically the number, the species and the location of coral colonies to be
directly affected by the construction of the pile-supported VIPS, the
reclamation and associated dredging works.
Identified coral colonies should be numbered, sized, photographed,
mapped and tagged in the survey. An
assessment of the suitability of translocation for each identified coral colony
should be presented in the coral translocation plan, along with the proposed
recipient site, translocation methodology and programme, monitoring methodology
and programme for the translocation coral colonies. The potential translocation recipient site
should possess a coral colony composition similar to
that of the existing site and should be located well outside areas where direct
and indirect impacts from the marine works of the Project, as well as of other
planned/committed projects nearby, are not expected. The findings of the detailed coral survey and
the proposed treatment for the identified coral colonies should be reported in
the Coral Translocation Proposal and submitted to AFCD for approval prior to
commencement of the translocation works.
Enhancement
Opportunities on Seawall and Marine Structures
13.7.1.7
As recommended in S.8.11.4, several strategies
could be integrated into the design of future coastal structures, such as
seawalls on the reclaimed land for TYLL anchorages and towers, as well as
surfaces and supporting structures on the pile-supported VIPS. Following the
confirmation of the final layout and design of these structures, a
detailed Eco-shoreline Design Proposal shall be prepared and
submitted to AFCD for agreement and approval. This proposal must include a
comprehensive Ecological Monitoring Plan to establish a practical and
feasible program for assessing the effectiveness of the design. The plan will
detail the proposed monitoring methodologies, such as the use of standard
marine ecological survey techniques, and define the performance parameters to
be tracked. These parameters may include species diversity and abundance,
recruitment rates of benthic organisms, and the health of key habitat-forming
species, all of which will be proposed for AFCD's approval. The monitoring
shall commence following the establishment of the eco-shoreline and the
proposed monitoring period and frequency shall be agreed upon with AFCD. A key component of the plan will be an
adaptive management framework, which requires establishing clear performance
criteria (i.e., action and limit levels). If monitoring reveals that these
criteria are not being met, an investigation into the causes will be required,
followed by the submission of a remedial action proposal to AFCD for approval.
All monitoring and assessment work shall be conducted by qualified marine
biologists with a minimum of five years of experience in marine organism
identification and ecological restoration.
Operational Phase
13.7.1.8
No
significant ecological impact is anticipated during the operational phase of the Project, as
such no ecological monitoring and auditing during operational phase is
required.
Construction Phase
13.8.1.1
With
the implementation of water quality mitigation measures during
construction and operational phases, no adverse impact on fisheries is
anticipated, thus fisheries-specific monitoring is considered not necessary. Water quality monitoring should be undertaken
in monitoring stations between the project area and fisheries sensitive
receivers such as Ma Wan Fish Culture Zone to avoid any deterioration of water
quality due to the construction works.
Operational Phase
13.8.1.2
No adverse
impact on fisheries is anticipated during the operational phase, thus fisheries-specific
monitoring is considered not necessary.
13.9.1.1
The EIA
has recommended landscape and visual mitigation measures to be undertaken
during construction and operational phases of the Project. The design, implementation and maintenance of
landscape and visual mitigation measures should be checked to ensure that they
are fully realized and that potential conflicts between the proposed landscape
measures and any other project works and operation
requirements are resolved at the earliest possible date
and without compromise to the intention of the mitigation.
13.9.1.2
All
mitigation measures proposed in the EIA and implemented by the Contractor
should be audited by Registered Landscape Architect (RLA), as a member of the
Environmental Team, on a regular basis to ensure compliance with the intended
aims of the measures. The mitigation measures proposed should be embodied into the detailed engineering design and landscape
design drawings and contract document. Site inspection should be undertaken
monthly throughout the construction period. In particular, the extent of the
agreed works areas should be regularly checked during the construction phase.
The landscape auditor should audit the proposed mitigation measures in the EIA
to ensure that they are fully implemented during construction and the 12-month
establishment period during operational phase.
Construction Phase
13.9.1.3
Both the
temporary and permanent works would cause direct impact on the landscape
resources during construction phase, mainly the vegetation identified within
both natural and man-made slopes (i.e. LR1.1 - Hillside Vegetation of Ma Wan
and Tsing Yi, LR1.2 - Vegetation on Engineered Slope at Northwest Tsing Yi
Interchange, LR2.1 - Hillside Vegetation at North Lantau and LR2.2 - Vegetation
on Engineered Slope along North Lantau Highway), natural shoreline of the south
of Ma Wan (i.e. LR1.3 – Sandy Beach along the coastal area of Ma Wan and LR1.4
– Natural Rocky Shore along the coastal area of Ma Wan and Tsing Yi) and north
of Lantau Island (i.e. LR 2.3 – Natural Rocky Shore facing of Kap Shui Mun),
developed area of Tsing Yi (i.e. LR1.6) and watercourses at North Lantau (i.e.
LR2.7). Mitigation measures such as tree
preservation and transplantation, provision of decorative screen hoarding,
reinstatement of affected landscape area shall be checked to ensure that they
are incorporated in the detailed design.
Implementation of the applicable recommended mitigation measures shall be monitored through the site audit programme during
the construction phase.
Operational Phase
13.9.1.4
To
mitigate the landscape and visual impacts caused by the proposed works during
operational phase, mitigation measures listed in Appendix 13.1 shall be implemented as appropriate.
Specific EM&A during operational phase of the Project is not
required as long as the proposed mitigation measures
in the EIA and as depicted in the Landscape Mitigation Plan are fully
implemented.
Construction Phase
13.10.1.1
For built
heritage, no EM&A would be required.
13.10.1.2
For
terrestrial archaeology, no EM&A would be required. As a precautionary measure and pursuant to
the Antiquities and Monuments Ordinance (Cap. 53), the project proponent is
required to inform AMO immediately in case of discovery of antiquities or
supposed antiquities in the course of works, so that appropriate mitigation
measures, if needed, can be timely formulated and implemented in agreement with
and to the satisfaction of AMO.
13.10.1.3
For marine
archaeology, no EM&A would be required.
As a precautionary measure and pursuant to the Antiquities and Monuments
Ordinance (Cap. 53), the project proponent is required to inform AMO
immediately in case of discovery of antiquities or supposed antiquities in the
course of construction of the works, so that appropriate mitigation measures,
if needed, can be timely formulated and implemented in agreement with and to
the satisfaction of AMO.
Operational Phase
13.10.1.4
No impact
on terrestrial archaeology, built heritage, and marine archaeology would be anticipated
during the operational phase of the Project. Hence, mitigation measures as well as impact
monitoring and audit are not required.
Construction Phase
13.11.1.1
For the
potential risks associated with the 2 PHIs, good safety practices are
recommended to further manage and minimise the
potential risks during the construction phase of the Project. Regular audits during the construction phase are
recommended.
13.11.1.2
Blasting
activities regarding on-site transport and use of explosives should be
supervised and audited by competent site staff to ensure strict compliance with the blasting permit conditions.
Operational Phase
13.11.1.3
The risk
imposed by the Project is considered negligible during operational phase and
thus monitoring and audit are not required.