14. SUMMARY
OF ENVIRONMENTAL OUTCOMES
14.2 Environmental Benefits of the Project
14.3 Incorporation of Environmentally Friendly Options
14.4 Environmental Design Recommended
14.5 Key Environmental Problems Avoided and Environmentally Sensitive
Areas Protected
14.6 Environmental Protection Measures Recommended
14.7 Estimation of Population Protected
List of Tables
Table 14.1 Summary
of Key Environmental Problems Avoided and Sensitive Areas Protected
Table 14.2 Key
Recommended Mitigation Measures and any Associated Benefits
· Minimisation of extensive retaining structures on existing geotechnical features at Tsing Yi;
· Avoidance of reclamation at North Lantau shoreline;
· Minimisation of reclamation and dredging extents for the reclamation in Ma Wan and Tsing Yi;
· Minimisation of slope cutting;
· Avoidance of direct impact to ecological sensitive area;
· Minimisation of habitat loss; and
· Incorporation of eco-shoreline features on newly established coastal structures and shorelines.
Avoidance of Reclamation at North Lantau
Shoreline
Minimisation of Reclamation and Dredging Extents for the Reclamation in Ma Wan and Tsing Yi
Minimisation of Slope Cutting
· Adoption of environmentally friendly construction method;
· Implementation of trip-ticket system;
· Implementation of environmental monitoring and audit system; and
· Incorporation of eco-shoreline features on newly established coastal structures and shorelines
Adoption of Environmentally Friendly Construction Method
Implementation of Trip-Ticket System
Implementation
of Environmental Monitoring and Auditing System
Incorporation of Eco-shoreline Features on Newly Established Coastal Structures and Shorelines
Table 14.1 Summary of Key Environmental Problems Avoided and Sensitive Areas Protected
|
Design
Approach |
Environmental Problems Avoided and
Sensitive Areas Protected |
|
Optimised the alignment |
·
The current alignment avoided direct impact
on residential development at Ma Wan and indirect impact on Ma Wan Egrety, as
well as direct or indirect impacts on Tung Lung Chau Lighthouse which is a
declared monument. |
|
Adoption of environmentally friendly construction methods |
·
Adoption of off-site precast structures /
modular integrated construction method to minimise the impacts on air
quality, noise, water quality and waste during construction. |
|
Minimisation of extensive retaining structures on existing geotechnical
features at Tsing Yi |
·
The refined alignment design reduced slope
works and land resumption at Tsing Yi; ·
No. of affected air and noise sensitive
receivers have been reduced; and ·
The landscape and visual impacts at the
Tsing Yi Connection has been minimised. |
|
Avoidance of reclamation at North Lantau Shoreline |
·
The avoidance of reclamation at North
Lantau would benefit the preservation of the intertidal zone and ecosystem
along the shoreline, including six species of conservation importance at the
intertidal zone. |
|
Minimisation of reclamation and dredging extents for the reclamation in
Ma Wan and Tsing Yi; |
·
The total amount for dredged sediments has
been reduced, hence reducing the associated water quality impacts during
construction phase ·
The extent of channel narrowing at both MWF
and KSMF has been reduced, hence reducing the change in hydrodynamic regime
under operation phase. ·
The total reclamation area has been reduced
by about 17 %. |
|
Minimisation of slope cutting |
·
Minimised disruption to the landscape
resources and characters ·
Minimised potential impacts to the natural
habitats and associated ecology ·
Minimised the amount excavation spoil and
construction waste generation |
|
Avoidance of direct impact to ecological sensitive area |
·
The current alignment avoided potential
direct and indirect impacts on recognised sites of conservation importance
and other ecologically sensitive areas, such as the Ma Wan Egretry and Night
Roost located on the Project's northern side |
|
Minimisation of Habitat Loss |
·
To minimise the extent of habitat loss and
its impact on the ecology in this area, the proportion and extent of slope
works and at-grade roads were minimised and strategically positioned along
existing developed area. ·
Some road sections in North Lantau have
opted for tunnel or viaduct form to minimise the footprint of at-grade works
and to avoid ecological impact, i.e. the viaduct section at Yi Chuen and
tunnel connecting HKIW-NEL Link, which avoid impact on concerned watercourse. |
|
Avoidance of illegal dumping |
·
The recommended preventive measures would
avoid / minimise the chance of illegal dumping. |
|
Implementation
of Environmental Monitoring and Auditing System |
·
Ensure all the recommended measures are
properly in place and their effectiveness. |
Table 14.2 Key Recommended Mitigation Measures and any Associated Benefits
|
Environmental Aspect |
Key Recommended Mitigation Measures |
Associated Benefits |
|
Air
Quality Impact |
Construction Phase: ·
Implementation of control measures as
required in the Air Pollution Control (Construction Dust) Regulation to
minimise construction air quality impact. ·
The approved non-road mobile machinery
(NRMMs) under NRMM Regulation (excluding exempted NRMMs) would be used
on-site and NRMMs supplied with mains electricity instead of diesel-powered
should be adopted as far as possible to minimise the potential emission from
NRMMs. ·
Barging points provided with Tipping hall
enclosed by 3-side screen with top and water spraying and flexible dust
curtains to minimise dust dispersions. ·
Controlled loading of dredged materials and
covering of dredged materials to avoid potential odour emission ·
Any odorous materials shall be transported
away from the Project site within 24 hours to
minimise odour impact. Operational Phase: ·
No mitigation measures would be required. |
· Protect Air Sensitive Receivers (ASRs) by reducing
air pollutants generation and emissions. · Ensure compliance with the requirements in Annex 4
of the EIAO-TM at the ASRs |
|
Noise
Impact |
Construction Phase: ·
Implementation of quality and quieter
powered mechanical equipment (PME), temporary / movable noise barriers and
enclosure to screen off noise from relatively statie PMEs, quieter
construction methods, acoustic tunnel door or enclosure at the tunnel portal
as well as good site practices during construction phase of the Project to miminise construction noise impact. ·
For village houses / temporary structure
with residential use at North Lantau which are close to the construction
sites, it is recommended to install site hoarding with higher surface density
and height to provide extra noise attenuation to protect these NSRs. ·
Submission of Construction Noise Management
Plan (CNMP) before tendering. Operational
Phase: ·
Implementation of Low Noise Road Surfacing
(Refer to Figure 4.5 for locations and
extents) to alleviate road
traffic noise impact on surrounding NSRs. |
· Protect Noise Sensitive Receivers (NSRs) by
reducing construction and road traffic noise impacts. · Ensure compliance with the respective road traffic
noise requirements at neighbouring NSRs. |
|
Water
Quality Impact |
Construction Phase: ·
ProPECC PN 2/24 - Construction
Site Drainage should be followed to minimise construction run-off. ·
Deployment of silt curtain throughout the
reclamation works area to minimise dispersion of suspended solid/sediment
during construction/dredging. ·
ETWB TC (W) No. 5/2005 - Protection of
Natural Streams / Rivers from Adverse Impacts Arising from Construction Works
should be adopted to minimise the water quality impacts on any natural
streams or surface water systems. Operational Phase: ·
The design of site drainage and disposal of
various site effluents should follow the relevant guidelines and practices as
given in the ProPECC PN 1/23 to minimise water quality impact. ·
Best Management Practices for storm water
discharge are recommended to reduce the stormwater pollution arising from the
Project. |
·
Protect the neighbouring
Water Sensitive Recivers (WSRs) during construction and operational phases. |
|
Waste
Management Implications |
·
Implementation of good site practices and
waste reduction measures (e.g. reuse of C&D materials before off-site
disposal or develop a materials recovery and recycling programme during
construction and operation) to minimise waste
generation. ·
A Construction and Demolition Material
Management Plan should be prepared in accordance with Section 4.1.3
“Construction and Demolition Materials” of the Project Administration
Handbook for Civil Engineering Works (PAH). ·
Preparation of a Waste Management Plan, as
part of the Environmental Management Plan thus minimising waste generation
and ensuring proper disposal and treatment of waste materials. ·
Implement a trip-ticket system for each
works contract in accordance with DEVB TC(W) No. 6/2010 to ensure that the
disposal of C&D materials is properly documented and verified. ·
Handling of chemical waste in accordance
with the Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes, and disposal of chemical waste at licensed chemical waste recycling /
treatment facilities so that chemical waste can be properly handling. ·
General refuse should be stored in enclosed
bins or compaction units separately from C&D materials to minimise
hygiene issues. ·
An enclosed and covered area is preferred
to reduce the occurrence of wind-blown light materials. ·
The recyclable component of general refuse,
such as aluminium cans, paper and cleansed plastic containers shall be
separated from other wastes for ease of handling. ·
Provision and collection of recycling bins
for different types of recyclable waste shall be set up by the
Contractor. The Contractor shall also
be responsible for arranging recycling companies to collect these materials. ·
Conduct regular inspection, monitoring,
collection and disposal of floating refuse by the Contractor ·
The Contractor shall carry out an education
programme for workers in avoiding, reducing, reusing and recycling of
materials generation. Posters and
leaflets advising on the use of the bins shall also be provided in the sites
as reminders. ·
The Contractor is encouraged to deliver
waste materials to EcoPark and Y·PARK for reuse and recycling, especially for
yard wastes during slope works and tunnel works at North Lantau thus reducing
disposal volume to landfill. ·
On-site reuse of Category L sediment
generated (e.g. as backfilling materials) to minimise marine dumping of
sediment. ·
For off-site disposal of sediments, follow
the basic requirements and procedures specified under paragraph 4.2.1 of
Chapter 4 of the PAH. ·
For the purpose of site allocation and
application of marine dumping permit and if considered necessary by EPD,
separate Sediment Sampling and Testing Plan(s) (SSTP) shall be submitted to
EPD for agreement under Dumping at Sea Ordinance (DASO). ·
Additional GI works, based on the SSTP,
shall be carried out in order to confirm the disposal arrangements of the
excavated/dredged sediment and submitted to EPD for agreement under DASO. Sediment
Quality Report(s) (SQR), reporting the chemical and biological screening
results and the estimated quantities of sediment under different disposal
options, shall then be submitted to EPD for agreement under DASO. ·
Stockpiling of contaminated sediments
should be avoided. If temporary
stockpiling of contaminated sediments is necessary, the excavated / dredged
sediment should be covered by tarpaulin and the area should be placed within
earth bunds or sandbags to prevent leachate from entering the ground, nearby
drains and surrounding water bodies. The stockpiling areas should be completely paved or covered by linings
in order to avoid contamination to underlying soil or groundwater. ·
In order to minimise the potential odour /
dust emissions during excavation / dredging and transportation of the
sediment, the excavated / dredged sediments shall be wetted for the whole
processing and shall be properly covered when placed on trucks or barges. Loading of the excavated / dredged sediment
to the barge shall be controlled to avoid splashing and overflowing of the
sediment slurry to the surrounding water. ·
To avoid illegal dumping, all dumping
vessels have to be approved in a marine dumping permit issued under DASO. ·
In case Type 3
– Special Treatment / Disposal sediment were identified in the additional
sampling works, the Project Proponent shall be responsible for identifying
and agreeing with the Director of Environmental Protection the most
appropriate treatment and/or disposal arrangement for the Type 3 sediment as
required in the PAH. A possible disposal arrangement for Type 3
sediment is by geosynthetic containment. |
· Minimise waste generation. · Ensure proper handling of chemical waste. · Ensure the C&D materials are disposed of and
delivered to designated sites. · Ensure proper waste management, treatment and
reuse of excavated / dredged sediment. |
|
Land Contamination |
·
Subject to the finding of Contamination Assessment Plan(s) / further
site appraisal and Contamination Assessment Report (CAR), if contamination is
identified, the remediation measures for remediation works as stated in
Remediation Action Plan(s)
should be implemented to ensure soil / groundwater contamination, if any,
would be identified and properly remediated prior
to construction works. |
·
Land contamination issues could be resolved
before commencement of construction works. |
|
Ecology |
Permanent and Temporary Loss of
Terrestrial and Marine Habitats ·
Localising at-grade works to habitats with
lower ecological value (e.g. developed area, plantation), and opting for
tunnel and viaduct sections to reduce permanent loss of natural habitats. ·
Optimising the land required for temporary
works to necessary minimum to minimise temporary loss of natural habitats. ·
Work avoidance at the upper tributary and
box culvert installation at the section coinciding with at-grade road section
to minimise the extent of permanent loss and to retain waterflow at
watercourse W2. ·
Reduce the length and elevation level /
profile of tunnel to avoid and minimise the extent of loss of watercourse W3. ·
Where no actual construction works are
required, vegetation clearance along watercourses would be avoided, adoption
of work exclusion zone and elevated temporary works planform atop
watercourses should be implemented to avoid and minimise impact on watercourse. ·
Opting for pile-supported VIPs at North
Lantau to minimise overall reclamation extent as reclamation at Yi Chuen is
avoided. Species
of Conservation Importance with Low Mobility and Restricted Niche ·
Conduct detailed pre-construction survey to
identify individuals to be affected by works and carry out in-situ
preservation, transplantation / translocation or compensation planting where
appropriate to avoid and minimise direct impact on plant, coral and amphibian
species of conservation importance. Habitat
Fragmentation, Wildlife Movement and Injuries or Mortalities due to Roadkill
and Collision ·
Implementation of construction phasing and
habitat reinstatement following completion of temporary works to minimise the
impact of habitat fragmentation and wildlife movement impediment. ·
Incorporation of fencing, u-shaped
channels, hedge planting of dense vegetation to prevent access to and guide
wildlife away from the at-grade road structures and lead them towards the
passageways under the viaduct sections to minimise the likelihood of wildlife
injuries and mortalities due to roadkill and collision. Disturbance
and Water Quality-related Impacts ·
Implementation of precautionary measures
and good site practice to minimise construction disturbance on adjacent
habitats, species of conservation importance and associated flora and fauna. ·
Temporary stream diversion to retain
waterflow and avoid run-off of construction materials into watercourses in
accordance with guidelines specified in ETWB TC(W) No. 5/2005 Protection
of Natural Streams/Rivers from Adverse Impacts Arising from Construction
Works. ·
Implementation of water quality specific
mitigation measures recommended in the water quality impact assessment and
best management practices as stipulated in ProPECC PN 2/23 Construction
Site Drainage and ETWB TC(W) No. 5/2005 Protection of Natural
Streams/Rivers from Adverse Impacts Arising from Construction Works to
reduce the impact of water quality deterioration due to run-off, discharge
and reclamation on waterbodies and aquatic-associated species. ·
Deployment of silt curtains during
reclamation and other marine works to minimise the indirect impact of
sedimentation and runoff on marine ecology. Diversion
and Modification of Affected Watercourses ·
North-branching upper tributary of W2 would
be preserved at its headwater, while the section intercepting with the
at-grade road section would be replaced a box culvert in order to retain
water flow in the watercourse. ·
Watercourse W1 and section of W3 would be
diverted and replaced by modified watercourse of similar nature, with
incorporation of natural elements in the design. Guidelines specified in ETWB TC(W) No.
5/2005 should be followed. Stream
diversion proposal for the W1, W2 and W3 would be submitted to AFCD for
comment prior to the commencement of works. Enhancement
Opportunities on Seawall and Marine Structures ·
The use of natural building materials such
as granite boulders or irregular shaped dolosse as building blocks for riprap
and sloping seawalls is recommended. The rough textures and gaps between the
stacked building blocks would provide suitable conditions for benthos
settlement and provide sheltering habitats for marine wildlife. ·
Incorporation of elements that diversify
microhabitats and enhance the quality of settlement substrates such as the
eco-tiles or 3D-printed terracotta settlement plates with features like
indents, pits, pools, crevices, meanders and cracks should also be considered
on vertical seawalls or surfaces to encourage recruitment and settlement of
corals and other benthos. ·
Incorporating a wavy design instead of a
straight shoreline for the coastal structures could enhance structural
diversity and create varying light penetration gradients in microhabitats
which warrants further exploration if feasible. ·
Where practical, recycling of dismantled
concrete-based or steel-based building materials e.g. roadblocks, culverts,
steel rebars as artificial reef structures could also be considered in
suitable areas away from the main navigation channel. ·
Following the confirmation of the final
layout and design of created coastal structures, a proposal on eco-shoreline
design shall be prepared and submitted to AFCD for agreement and approval. |
·
Minimise the direct and indirect impacts to
the habitat and species of conservation importance during construction phase
and operational phases. ·
Minimising physical disturbance to the
surrounding habitats. ·
Reduce temporary / permanent losses of
natural habitats ·
Avoid / minimise impact on concerned
watercourses · Enhancing
the quality of newly created habitats through diversifying micro-habitats and
creating suitable settlement and sheltering habitats for wildlife |
|
Fisheries |
·
Non-dredged reclamation methods, including
DCM and jet grouting for ground treatment, will be adopted whenever
practicable to reduce the release of suspended solids and contaminants into
water bodies. ·
Implementation of water quality mitigation
measures during the construction phase, which shall cover marine-based site
investigation works, marine-based foundation works, above-water construction
works, site run-off from general site operation, and accidental spillage of
chemicals and sewage from workforce that minimising fisheries impact. |
·
Minimise the direct and
indirect finishers impact during construction and operational phases. |
|
Landscape and Visual |
Construction
Phase: ·
Trees without impact from the proposed
works should be retained and any existing trees unavoidably affected by the
works should be transplanted as far as possible in accordance with DEVB TC(W)
No. 4/2020 - Tree Preservation. ·
Erection of decorative screen hoarding with
advance planting or hoarding compatible with the surrounding setting to
alleviate the landscape impact to surrounding public viewers. ·
Construction facilities and activities on
work sites and areas should be carefully managed and controlled, including
height and disposition / arrangement to minimise any potential adverse
landscape impacts. ·
Reinstatement of the temporarily affected
landscaped area within assessment area in like-for-like basis to restore the
existing natural environment as far as possible. Operational
Phase: ·
Aesthetically pleasing design as regard to
the form, material and finishes should be incorporated into bridges,
ancillary buildings and other associated engineering facilities so as to
blend in the structures with the adjacent landscape and visual context. ·
Buffer screen planting, including shrubs,
to provide screening for the proposed structures if space is available. ·
As far as practicable, compensatory tree
planting requirement of 1:1 in terms of number in accordance with DEVB TC(W)
No. 4/2020 for compensation of felled trees subject to the availability of
space and agreement made with relevant departmental parties. ·
Landscape treatments on slope or retaining
structure in accordance with GEO Publication No. 1/2011 – Technical
Guidelines on Landscape Treatment for Slopes shall be adopted subject to
the availability of space and agreement with relevant departmental parties to
maximise the greenery provision and alleviate the visual impact due to the
loss of vegetation. |
· Minimise landscape and visual impacts during
construction and operational phases. |
|
Impact on Cultural Heritage |
·
No direct or indirect
impact is anticipated on the built heritage identified. No mitigation
measures would be required. · No impact on terrestrial and marine archaeology
are anticipated during the construction and operational phases. As a precautionary measure and
pursuant to the Antiquities and Monuments Ordinance (Cap. 53), the project proponent is required to inform AMO
immediately in case of discovery of antiquities or supposed antiquities in
the course of works, so that appropriate mitigation measures, if needed, can
be timely formulated and implemented in agreement with and to the
satisfaction of AMO. |
· Verify the presence of any archaeological remains
and identify measures if necessary prior to construction |
|
Hazard
to Life |
Construction Phase: ·
Implement the following “Good Practices” to
limit the number of causalities and/or fatalities during construction phase
of the project due to risk associated with Potentially Hazardous Installations
(PHIs): - Establishment
of emergency response / evacuation plans; - Safety
/ emergency response training and drills for all personnel; and - Maintain
the number of construction workers on-site to a minimum. ·
Implement the following recommendations to
prevent risks due to flying objects, rollover of lifting vehicles and falling
of heavy construction material during lifting activities during construction
phase of the project: - Shielding
provision such as mesh fencing to be installed along the slip road between
the proposed works areas and the terminal; and - Risk
assessment should be undertaken and method statement with lifting plan should
be formulated by the Contractor prior commencement of lifting works. ·
Implement the following recommendations to
minimise potential risks due to on-site transport of explosives: - Emergency
plan should be developed to address uncontrolled fire during transport. Case
of fire near an explosive carrying vehicle in jammed traffic should be
included in the plan. Activation of fuel and battery isolation switches on
vehicle when fire breaks out should also be included in the emergency plan to
reduce likelihood of prolonged fire leading to explosion; - Working
guideline should be developed to define procedure for explosives transport
during adverse weather such as thunderstorm; - Detonators
should be transported separately from other Class 1 explosives. Separation of
vehicles should also be maintained through the trip; - Develop
procedure to ensure the availability of parking space on site for the
explosives carrying vehicle. Delivery should not be commenced if parking
space on site is not secured; - Hot
work should be suspended during passage of the diesel vehicle truck and bulk
emulsion truck in the tunnels; - Speed
limit for the diesel vehicle truck and bulk emulsion truck in the tunnels
should be imposed. The truck may be escorted while underground to ensure
route is clear from hazards and obstructions; - Fire
screen should be used between cabin and the load on the vehicle; - Lining
should be provided within the transportation box on the vehicle; - Ensure
packaging of detonators remains intact until handed over at blasting site; - Ensure
that cartridged emulsion packages are not damaged before every trip; and - Use
experienced driver with good safety record. ·
Implement the following recommendations for
the safe use of explosives: - Blast
charge weight should be within the maximum MIC as specified for the given
blast face; - Temporary
mitigation measures such as blast doors or heavy duty blast curtains should
be installed at the portals at suitable locations underground to prevent
flyrock and control the air overpressure; - Secure
refuge areas to workers within the construction sites should be identified
for their temporary shelter during blasting; - A Chief
Shotfirer and a Blasting Engineer shall be employed in addition to the normal
blasting personnel to ensure that the works are safe and coordinated between
blasting areas; - Shotfirer
to be provided with a lightning detector, and appropriate control measures
should be in place; - A
boulder survey should be undertaken based on the likely PPV values that would
result from the blasting process.
Those boulders subject to the vibration higher than the allowable
limit should be strengthened, removed, or constructed with boulder fence,
prior to the commencement of blasting; - Establishment
of no-blast zones for areas of high sensitivity/risk; - The
surface blasting benches will be covered with blasting cages, blast mats and
blasting screens to limit flyrock potential; - All
hiking paths/ footpaths located within the 200m assessment area will be
temporarily closed during blasting/ explosives delivery from the barging
point to the blasting sites; - Drill
bits larger than 64mm should not be brought to the sites to avoid drilling a
larger blasthole by accident; and - The
Contractor will place warning signs at the concerned area (i.e. Yi Chuen) to
let the residents know the blasting schedule of the surface blasting site S01
so that they have to be evacuated or stay indoor away from windows. Before
the commencement of blasting, the contractor will also strike a gong to alert
the residents and notify the residents in person to ensure all potentially
affected personnel are fully aware of the surface blasting. |
·
Limit the number of
causalities and /or fatalities during construction phase due to risk
associated with the two PHIs at Tsing Yi. ·
Protect nearby sensitive
receivers from adverse impacts due to transportation, and use of explosive
for blasting. |
|
General |
· Implement a comprehensive Environmental Monitoring
System throughout the entire construction period. · Employ an Environmental Team (ET) and Independent
Environmental Checker (IEC) |
· Ensure compliance with all statutory requirements
and those recommendations in the EIA report |