15.               Conclusion

15.1            Conclusion of EIA Study

15.1.1.1   This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the Project, based on the engineering design information available during the course of EIA study.

15.1.1.2   The assessment has been conducted, in accordance with EIAO-TM, covering the following environmental issues:

·       Air Quality Impact;

·       Noise Impact;

·       Water Quality Impact;

·       Waste Management Implications;

·       Land Contamination;

·       Ecological Impact (Terrestrial and Marine);

·       Fisheries Impact;

·       Landscape and Visual Impact;

·       Cultural Heritage; and

·       Hazard to Life.

15.1.1.3   The findings of this EIA study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project. During the EIA process, environmental control measures have been identified and incorporated into the planning and design of the Project, to achieve compliance with environmental legislation and standards during both the construction and operational phases.  The Implementation Schedule listing the recommended mitigation measures is presented in Appendix 13.1.

15.1.1.4   The various sections of this EIA Report have presented the measures to minimise the potential environmental impacts associated with the Project throughout the construction and operational phases.  The key measures to minimise the environmental impacts are summarized in Section 14.

15.1.1.5   With the implementation of the mitigation measures, the Project would be environmentally acceptable with no unacceptable residual impacts on the environmentally sensitive receivers and resources.  Table 15.1 below summarises the key environmental outcomes and benefits that have accrued from the environmental considerations and analysis during the EIA process and the implementation of environmental control measures of the Project.  Appendix 15.1 presents the summary of key assessment assumptions, limitation of assessment methodologies and related prior agreements with the Director of Environmental Protection, while Appendix 15.2 presents the summary of environmental impacts.

15.1.1.6   An Environmental Monitoring and Audit (EM&A) programme has been developed to ascertain and verify the assumptions implicit to, and accuracy of, EIA study predictions.  EM&A requirements have been recommended, where necessary, to check on project compliance of environmental legislation and standards.  These are presented in a separate stand-alone EM&A Manual.


 

Table 15.1     Summary of Key Environmental Outcomes and Benefits

Environmental Issue

Description

Environmental / Social Benefits of the Project

The existing major roads such as Tuen Mun Road and Lantau Link would experience traffic congestion during peak hours.  The Project would ameliorate the traffic conditions on these major roads and reduce the potential air quality and noise impacts to the neighbouring sensitive receivers.

Environmentally Friendly Design and Options

The Recommended Alignment for the Project has been optimised to provide the following environmentally friendly outcomes and benefits:

·    Minimisation of extensive retaining structures on existing geotechnical features at Tsing Yi;

·    Avoidance of reclamation at North Lantau Shoreline;

·    Minimisation of reclamation and dredging extents for the reclamation in Ma Wan and Tsing Yi;

·    Minimisation of overall slope cutting extent;

·    Avoidance of direct impact to ecological sensitive area;

·    Minimisation of habitat loss; and

·    Incorporation of eco-shoreline features on newly established coastal structures and shorelines

Air Quality Impact

Construction Phase:

·    Potential air quality impact from the construction works of the Project would mainly be related to construction dust from site formation, site clearance, excavation, reclamation, tunnelling, foundation works, handling and stockpiling of dusty materials, wind erosion of exposed area and operation of barging points, as well as air pollutant emissions from construction vehicles and construction vessels.  Potential air quality impact would also be expected from operation of a potential temporary concrete batching plant. Construction activities of the concurrent projects within 500m assessment area would also pose cumulative air quality impact.  With the implementation of mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation together with the recommended control measures including frequent watering on active works areas, exposed areas and unpaved haul roads and other site management measures such as good site practices, covering and proper storage of dredged materials, use of electric vehicles and EM&A programme, as well as proper implementation of dust suppression measures according to BPM 3/2 (2025) at the temporary CBP, no adverse air quality impact on ASRs in the vicinity of the work sites would be anticipated during the construction stage.

 

·    Potential odour impact from dredged materials would be minimised with the implementation of mitigation measures, such as covering of dredged materials and transporting the materials away from the Project site within 24 hours.

 

Operational Phase:

·     Cumulative air quality impacts were assessed by considering the Project-induced emissions, all relevant emission sources in the immediate vicinity of the Project site and within the 500 m assessment area, such as vehicular emission from open roads, tunnel portals and concerned facilities with vehicular emissions (Minibus Terminus, Transport Department Vehicle Examination Complex, Bus Depot, and Major Heavy Good Vehicle and Coach Parking), industrial emissions and marine emissions, as well as background contributions.  The quantitative modelling prediction results concluded that the cumulative NO2, RSP and FSP concentrations at all existing and planned ASRs would comply with the prevailing AQOs.  Also, no existing or planned ASRs would be located within the predicted AQOs exceedance zones, according to the contour plots. Thus, no adverse air quality impact on the existing and planned ASRs would be anticipated.

Noise Impact

Construction Phase:

·     Potential construction noise would be generated from the use of PME during construction phase of the Project.  A review has been conducted on the construction methodology, and it is considered that with the implementation of good site practices and mitigation measures, such as adoption of quieter construction method, quieter plant, silencer, movable noise barrier, noise enclosure / barrier, site hoarding with higher density and height, etc., adverse construction noise impact during construction phase is not anticipated.

·     The Project Proponent will further review the cumulative noise impact caused by the Project in the subsequent Construction Noise Management Plan (CNMP) submission at later construction phase to ensure that there is no adverse construction noise impact.

 

Operational Phase:

·     The predicted road traffic noise levels indicated that all existing NSRs would comply with relevant road traffic noise standards under unmitigated scenario.  No committed or planned NSRs with detailed programme are identified during preparing the EIA study, such that no adverse road traffic noise input during operational phase is anticipated.

·     No fixed noise sources would be proposed under the Project.  Therefore, no fixed noise source impact would arise from the Project.

Water Quality Impact

Construction Phase:

·     Sediment plume resulting from dredging is confined to the immediate dredging area, with simulation results showing no expected exceedances at any of the WSRs, even without mitigation efforts like silt curtains.  However, reclamation filling activities may cause temporary and short-duration exceedances of suspended sediments, particularly at WM4 during wet seasons, which can be prevented with the implementation of silt curtains to ensure compliance with WQO.  Moreover, potential water quality impacts from land-based construction activities such as wastewater, site run-off, sewage from workforce and accidental chemical spills can be mitigated through recommended practices and regular site inspections, hence minimising environmental impacts and safeguarding water quality during the construction phase.

 

Operational Phase:

·     The potential hydrodynamic impacts of the proposed reclamation were assessed using computational modelling.  Impact on the local hydrodynamic regime induced by the Project was found to be insignificant, as negligible differences in water level, salinity, flow velocities, flow rates, and fields were observed when comparing the scenarios before and after construction.  Therefore, the impact on hydrodynamic properties and hydrology induced by the Project is deemed insignificant.

Waste Management Implications

Construction Phase:

·     Inert and non-inert C&D materials, chemical wastes, general refuse, floating refuse and sediments would be generated during construction activities.  Provided that these wastes are handled, transported and disposed of according to the recommended good site practices and measures, no adverse environmental impacts (including potential hazard, air and odour emissions, noise and wastewater discharges) would be anticipated during the construction phase.

 

Operational Phase:

·     Minor floating refuse and chemical waste would be generated due to operational phase.  With the implementation of management control practices, no adverse environmental impact would be anticipated.

Land Contamination

·    With the implementation of the recommended follow up works for the Project, any soil / groundwater contamination would be identified and properly remediated prior to the construction works, therefore no insurmountable land contamination impacts to the Project are anticipated.

Ecology

·    During the early development of the Project, exhaustive effort was made to make sure the alignment and design of the TYLL would avoid direct encroachment onto any recognised sites of conservation importance and ecologically sensitive sites.  Furthermore, several adjustments and engineering options were made to avoid and further minimise the significance of direct and indirect ecological impacts arising from the Project.  The resulting impact significance on habitats, species of conservation importance and other assessed ecological elements would range between low and low to moderate if unmitigated.  Mitigation measures were recommended to avoid, minimise and compensate for any identified ecological impacts rated with an impact severity of low to moderate and above.  Some recommendations of precautionary measures and enhancement opportunities were also provided to further alleviate any potential ecological impacts and promote the ecological value of the Project.  With full implementation of the recommended mitigation measures, no unacceptable adverse residual impacts are expected to arise from the Project.

·    Regular inspection and monitoring of the implementation of mitigation measures would be required as part of the ecological monitoring programme.  Procedures and requirements for the implementation of measures for impacts on species of conservation importance were described in Section 8.13 of this EIA report.

 

Fisheries

·     The proposed reclamation works for the Project would result in permanent loss of about 19.8 ha and temporary loss of about 62 ha of fishing ground and fisheries habitat.  Since the loss only constitute a minor proportion of the marine waters in Hong Kong available for fishing, impacts to capture fisheries due to loss of fishing ground and disruption of fisheries operation are expected to be minor.  No direct impact to Ma Wan FCZ is anticipated since the works area will keep a distance from the FCZ.

·     Potential impacts of elevated levels of underwater sound are also not expected to be unacceptable.

·     The Project would not significantly alter the local hydrodynamics regime and hence the change in hydrodynamics is considered to be insignificant.

·     Indirect impacts to fisheries resources and fisheries sensitive receivers due to changes in water quality associated with construction and operation activities may occur.  However, through the adoption of non-dredged reclamation such as DCM as far as practicable (except in localised areas with thin marine deposits where dredging is recommended), alongside the provision of adequate water quality mitigation measures such as installation of silt curtain and good site practices, and implementation of water quality monitoring during construction phase, it is expected that the residual impacts associated with change of water quality are insignificant and hence no fisheries-specific monitoring is necessary.

Landscape and Visual

·     Under this Project, the existing landscape resources, including vegetation, natural rocky and sandy shoreline and waterbody would be affected in various magnitudes subject to the proposed works.  Approximately 28,010 existing trees are identified within the works area.  Of these, approximately 25,630 nos. would be retained hence not be affected by the proposed works.  Approximately 2,380 nos. of trees, including approximately 130 undesirable species (i.e. Leucaena leucocephala) would be directly affected by the proposed works and would be either removed or transplanted as far as practicable.  To mitigate the landscape impact caused by the proposed works, tree compensation strategy requirement of 1:1 in terms of number would be further explored and recommended in accordance with DEVB TC(W) No. 4/2020 – Tree Preservation.

·     For visual impact, it was considered that the proposed works would have similar structural design, massing, height and development nature to the existing infrastructure. With the implementation of mitigation measures, the residual visual impact for the identified key public viewers would be ranging from moderate to negligible during the operational phase.

·     The landscape impact resulted during construction and operational phases as well as visual impact resulted during operational phase are minimised to Slight to Negligible with the implementation of the appropriate mitigation measures including aesthetic design of aboveground structures, tree compensation, reinstatement of affected landscaping area and greenery provision on man-made slopes.

Cultural Heritage

·     No direct or indirect impact is anticipated on the built heritage identified.

·     No impact on terrestrial and marine archaeologies are anticipated during the construction and operational phases.   As a precautionary measure and pursuant to the Antiquities and Monuments Ordinance (Cap. 53), the project proponent is required to inform AMO immediately in case of discovery of antiquities or supposed antiquities in the course of works, so that appropriate mitigation measures, if needed, can be timely formulated and implemented in agreement with and to the satisfaction of AMO.

Hazard to Life

Terminals’ Operation (Chevron Terminal and STYI)

·     For both terminals, the individual risks and societal risks results taking into account the population induced by the Project were found to be in compliance with the risk criteria stipulated in Annex 4 of the EIAO-TM, and risk mitigation measures are therefore not required.

 

Explosives

·     The risk related to on-site transport and use of explosives including tunnel blasting and surface blasting have been assessed.  The individual risk and societal risk associated with the on-site transport/ use of explosives comply with the risk guidelines in Annex 4 of the EIAO-TM.