TABLE OF CONTENTS
List of Tables
Table
15.1 Summary of Key Environmental Outcomes and
Benefits
List of Appendices
Appendix 15.1 Key Assessment Assumptions, Limitations
of Assessment Methodologies and Prior Agreements with the Director
Appendix 15.2 Summary of Environmental Impacts
· Air Quality Impact;
· Noise Impact;
· Water Quality Impact;
· Waste Management Implications;
· Land Contamination;
· Ecological Impact (Terrestrial and Marine);
· Fisheries Impact;
· Landscape and Visual Impact;
· Cultural Heritage; and
· Hazard to Life.
Table 15.1 Summary of Key Environmental Outcomes and Benefits
|
Environmental Issue |
Description |
|
Environmental / Social Benefits of the Project |
The
existing major roads such as Tuen Mun Road and Lantau Link would experience
traffic congestion during peak hours.
The Project would ameliorate the traffic conditions on these major
roads and reduce the potential air quality and noise impacts to the
neighbouring sensitive receivers. |
|
Environmentally Friendly Design and Options |
The Recommended Alignment for the Project
has been optimised to provide the following environmentally friendly outcomes
and benefits: · Minimisation
of extensive retaining structures on existing geotechnical features at Tsing
Yi; · Avoidance of
reclamation at North Lantau Shoreline; · Minimisation
of reclamation and dredging extents for the reclamation in Ma Wan and Tsing
Yi; · Minimisation
of overall slope cutting extent; · Avoidance of direct
impact to ecological sensitive area; · Minimisation
of habitat loss; and · Incorporation
of eco-shoreline features on newly established coastal structures and
shorelines |
|
Air Quality Impact |
Construction Phase: · Potential air
quality impact from the construction works of the Project would mainly be
related to construction dust from site formation, site clearance, excavation,
reclamation, tunnelling, foundation works, handling and stockpiling of dusty
materials, wind erosion of exposed area and operation of barging points, as
well as air pollutant emissions from construction vehicles and construction
vessels. Potential air quality impact
would also be expected from operation of a potential temporary concrete
batching plant. Construction activities of the concurrent projects within
500m assessment area would also pose cumulative air quality impact. With the implementation of mitigation
measures specified in the Air Pollution Control (Construction Dust)
Regulation together with the recommended control measures including frequent
watering on active works areas, exposed areas and unpaved haul roads and
other site management measures such as good site practices, covering and proper
storage of dredged materials, use of electric vehicles and EM&A
programme, as well as proper implementation of dust suppression measures
according to BPM 3/2 (2025) at the temporary CBP, no adverse air quality
impact on ASRs in the vicinity of the work sites would be anticipated during
the construction stage. ·
Potential odour impact from dredged
materials would be minimised with the implementation of mitigation measures,
such as covering of dredged materials and transporting the materials away
from the Project site within 24 hours. Operational Phase: ·
Cumulative air quality
impacts were assessed by considering the Project-induced emissions, all
relevant emission sources in the immediate vicinity of the Project site and
within the 500 m assessment area, such as vehicular emission from open roads,
tunnel portals and concerned facilities with vehicular emissions (Minibus
Terminus, Transport Department Vehicle Examination Complex, Bus Depot, and
Major Heavy Good Vehicle and Coach Parking), industrial emissions and marine
emissions, as well as background contributions. The quantitative modelling prediction
results concluded that the cumulative NO2, RSP and FSP
concentrations at all existing and planned ASRs would comply with the
prevailing AQOs. Also, no existing or
planned ASRs would be located within the predicted AQOs exceedance zones,
according to the contour plots. Thus, no adverse air quality impact on the
existing and planned ASRs would be anticipated. |
|
Noise
Impact |
Construction Phase: ·
Potential construction noise would be
generated from the use of PME during construction phase of the Project. A review has been conducted on the
construction methodology, and it is considered that with the implementation
of good site practices and mitigation measures, such as adoption of quieter
construction method, quieter plant, silencer, movable noise barrier, noise
enclosure / barrier, site hoarding with higher density and height, etc.,
adverse construction noise impact during construction phase is not
anticipated. ·
The Project Proponent will further review
the cumulative noise impact caused by the Project in the subsequent Construction Noise Management Plan (CNMP) submission at later construction phase to
ensure that there is no adverse construction noise impact. Operational Phase: ·
The predicted road traffic noise levels
indicated that all existing NSRs would comply with relevant road traffic
noise standards under unmitigated scenario.
No committed or planned NSRs with detailed programme are identified
during preparing the EIA study, such that no adverse road traffic noise input
during operational phase is anticipated. ·
No fixed noise sources would be proposed
under the Project. Therefore, no fixed
noise source impact would arise from the Project. |
|
Water
Quality Impact |
Construction Phase: ·
Sediment plume resulting from dredging is
confined to the immediate dredging area, with simulation results showing no
expected exceedances at any of the WSRs, even without mitigation efforts like
silt curtains. However, reclamation
filling activities may cause temporary and short-duration exceedances of
suspended sediments, particularly at WM4 during wet seasons, which can be
prevented with the implementation of silt curtains to ensure compliance with
WQO. Moreover, potential water quality
impacts from land-based construction activities such as wastewater, site
run-off, sewage from workforce and accidental chemical spills can be
mitigated through recommended practices and regular site inspections, hence
minimising environmental impacts and safeguarding water quality during the
construction phase. Operational Phase: ·
The potential hydrodynamic impacts of the
proposed reclamation were assessed using computational modelling. Impact on the local hydrodynamic regime
induced by the Project was found to be insignificant, as negligible
differences in water level, salinity, flow velocities, flow rates, and fields
were observed when comparing the scenarios before and after
construction. Therefore, the impact on
hydrodynamic properties and hydrology induced by the Project is deemed
insignificant. |
|
Waste
Management Implications |
Construction Phase: ·
Inert and non-inert C&D materials,
chemical wastes, general refuse, floating refuse and sediments would be
generated during construction activities.
Provided that these wastes are handled, transported and disposed of
according to the recommended good site practices and measures, no adverse
environmental impacts (including potential hazard, air and odour emissions,
noise and wastewater discharges) would be anticipated during the construction
phase. Operational Phase: · Minor
floating refuse and chemical waste would be generated due to operational
phase. With the implementation of management control practices,
no adverse environmental impact would be anticipated. |
|
Land
Contamination |
·
With the implementation of the recommended follow up works for the
Project, any soil / groundwater contamination would be identified and
properly remediated prior to the construction works, therefore no
insurmountable land contamination impacts to the Project are anticipated. |
|
Ecology |
·
During the early development of the
Project, exhaustive effort was made to make sure the alignment and design of
the TYLL would avoid direct encroachment onto any recognised sites of
conservation importance and ecologically sensitive sites. Furthermore, several adjustments and
engineering options were made to avoid and further minimise the significance
of direct and indirect ecological impacts arising from the Project. The resulting impact significance on
habitats, species of conservation importance and other assessed ecological
elements would range between low and low to moderate if unmitigated. Mitigation measures were recommended to
avoid, minimise and compensate for any identified ecological impacts rated
with an impact severity of low to moderate and above. Some recommendations of precautionary
measures and enhancement opportunities were also provided to further
alleviate any potential ecological impacts and promote the ecological value
of the Project. With full
implementation of the recommended mitigation measures, no unacceptable
adverse residual impacts are expected to arise from the Project. ·
Regular inspection and monitoring of the
implementation of mitigation measures would be required as part of the
ecological monitoring programme.
Procedures and requirements for the implementation of measures for impacts
on species of conservation importance were described in Section 8.13 of this
EIA report. |
|
Fisheries |
· The proposed
reclamation works for the Project would result in permanent loss of about
19.8 ha and temporary loss of about 62 ha of fishing ground and fisheries
habitat. Since the loss only
constitute a minor proportion of the marine waters in Hong Kong available for
fishing, impacts to capture fisheries due to loss of fishing ground and
disruption of fisheries operation are expected to be minor. No direct impact to Ma Wan FCZ is
anticipated since the works area will keep a distance from the FCZ. · Potential
impacts of elevated levels of underwater sound are also not expected to be
unacceptable. · The Project
would not significantly alter the local hydrodynamics regime and hence the
change in hydrodynamics is considered to be insignificant. · Indirect
impacts to fisheries resources and fisheries sensitive receivers due to
changes in water quality associated with construction and operation
activities may occur. However, through
the adoption of non-dredged reclamation such as DCM as far as practicable
(except in localised areas with thin marine deposits where dredging is
recommended), alongside the provision of adequate water quality mitigation
measures such as installation of silt curtain and good site practices, and
implementation of water quality monitoring during construction phase, it is
expected that the residual impacts associated with change of water quality
are insignificant and hence no fisheries-specific monitoring is necessary. |
|
Landscape
and Visual |
·
Under this Project, the existing landscape
resources, including vegetation, natural rocky and sandy shoreline and
waterbody would be affected in various magnitudes subject to the proposed
works. Approximately 28,010 existing
trees are identified within the works
area. Of these, approximately
25,630 nos. would be retained hence not be affected by the proposed works. Approximately
2,380 nos.
of trees, including approximately 130 undesirable species (i.e. Leucaena
leucocephala) would be directly affected
by the proposed works and would be either removed or transplanted as far as practicable. To mitigate the landscape impact caused by
the proposed works, tree compensation strategy requirement of 1:1 in terms of
number would be further explored and recommended in accordance with DEVB
TC(W) No. 4/2020 – Tree Preservation. ·
For visual impact, it was considered that
the proposed works would have similar structural design, massing, height and
development nature to the existing infrastructure. With the implementation of
mitigation measures, the residual visual impact for the identified key public
viewers would be ranging from moderate to negligible during the operational
phase. ·
The landscape impact resulted during
construction and operational phases as well as visual impact resulted during
operational phase are minimised to Slight to Negligible with the
implementation of the appropriate mitigation measures including aesthetic design
of aboveground structures, tree compensation, reinstatement of affected
landscaping area and greenery provision on man-made slopes. |
|
Cultural
Heritage |
·
No direct or indirect
impact is anticipated on the built heritage identified. ·
No impact on terrestrial
and marine archaeologies are anticipated during the construction and
operational phases. As a
precautionary measure and pursuant to the Antiquities and Monuments Ordinance
(Cap. 53), the project proponent is required to inform AMO immediately in
case of discovery of antiquities or supposed antiquities in the course of
works, so that appropriate mitigation measures, if needed, can be timely
formulated and implemented in agreement with and to the satisfaction of AMO. |
|
Hazard
to Life |
Terminals’ Operation (Chevron
Terminal and STYI) ·
For both terminals, the individual risks
and societal risks results taking into account the population induced by the
Project were found to be in compliance with the risk criteria stipulated in
Annex 4 of the EIAO-TM, and risk mitigation measures are therefore not
required. Explosives ·
The risk related to on-site transport and
use of explosives including tunnel blasting and surface blasting have been
assessed. The individual risk and
societal risk associated with the on-site transport/ use of explosives comply
with the risk guidelines in Annex 4 of the EIAO-TM. |