TABLE OF CONTENTS

2.    Project Description. 2-1

2.1      Site Location and History of the Project 2-1

2.2      Objective and Need of the Project 2-1

2.3      Consideration of “With” and “Without” Project Scenarios. 2-2

2.4      Environmental Benefits of the Project 2-3

2.5      Details of the Project 2-3

2.6      Design Changes to the Project 2-4

2.7      Consideration of Alignment Options. 2-5

2.8      Project Details. 2-15

2.9      Construction Methodologies. 2-17

2.10     Implementation Programme. 2-24

2.11     Summary of Alternative Mitigation Measures. 2-26

2.12     Concurrent Projects. 2-30

2.13     Documentation of Public Concerns. 2-33

 

List of Tables

Table 2.1      Summary of Landing Options

Table 2.2      Summary of alignment options for Tsing Yi Connection

Table 2.3      Summary of alignment options for Main Bridges cum North Lantau Interchange

Table 2.4      Comparison and Summary of Possible Construction Methods for the TYLL

Table 2.5      Summary of Key Construction Works for the Project

Table 2.6      Summary of Alternative Mitigation Measures

Table 2.7      Summary of Potential Concurrent Projects

Table 2.8      Summary of the Major Concerns and the Subsequent Actions Taken in Response

 


 

List of Figures

Figures 2.1.1 - 2.1.4          General Layout Plan

Figures 2.1.5                     Alternative Landing Point Options

Figure 2.2                          Proposed Barging Points for the Project

Figure 2.3                          Tsing Yi Option 1

Figure 2.4                          Tsing Yi Option 2

Figure 2.5                          Tsing Yi Option 3 (Recommended)

Figure 2.6                          General Arrangement of the Main Bridge – Main Bridges cum North Lantau Option 1

Figure 2.7                          General Arrangement of the Main Bridge – Main Bridges cum North Lantau Option 2 (Recommended)

Figures 2.8.1 - 2.8.13        Construction Method

Figure 2.9                          Alignment Options for the Tsing Yi Section

Figure 2.10                        Tentative Location for Temporary Concrete Batching Plant

 

 

List of Appendices

Appendix 2.1   Locations of Concurrent Projects

 


2.                   Project Description

2.1               Site Location and History of the Project

2.1.1.1      The Project is situated at North Lantau and Tsing Yi. It consists of a cable-supported bridge which spans over the Ma Wan Fairway (MWF) and Kap Shui Mun Fairway (KSMF). The areas in close vicinity of the Project site in Tsing Yi are mainly occupied by industrial uses (e.g. cement works, dockyard, oil depots, etc.), while the project area in North Lantau is zoned as green belt where North Lantau Highway is located in the vicinity with some village houses or temporary structures scattering in San Po Tsui, Yi Chuen and Tso Wan.

2.1.1.2      The 2017 and 2018 Policy Addresses indicated that a Feasibility Study on Route 11 (between Yuen Long and North Lantau) shall be commenced as soon as possible for the long-term development of Northwest New Territories (NWNT), and to enhance the road network connecting to Hong Kong International Airport (the airport) and cope with the long-term development of Lantau Island. The findings of the Traffic Impact Assessment (TIA) Study indicated that Route 11, serving as an additional route for the urban-bound vehicles from NWNT, would attract more traffic to Lantau Link, thus causing delays for access to the major developments on Lantau Island, including the airport. Hence, the TIA Study recommended that a new highway infrastructure downstream of Route 11, i.e. Tsing Yi - Lantau Link (TYLL), should be completed in tandem with Route 11.

2.1.1.3      HyD commissioned another consultancy study titled “Feasibility Review of Tsing Yi - Lantau Link – Feasibility Study” (hereinafter referred to as “TYLL FS”) under Agreement No. CE 50/2020 (HY) in March 2021 to ascertain the technical feasibility of TYLL and determine a preferred alignment, taking account of the latest planning and development parameters. 

2.1.1.4      Subsequently, HyD commissioned an Investigation, Design and Construction consultancy of the Project in May 2023, to review the findings of previous feasibility study, identify the recommended alignment, conduct impact assessments on environment, traffic, marine, land and other related aspects, and carry out site investigation, detail design and supervision on construction works for TYLL. 

2.2               Objective and Need of the Project

2.2.1           Objective of the Project

2.2.1.1      The objective of the Project is to provide a new road connecting Route 11 on Lantau Island and Tsing Sha Highway at Tsing Yi serving as an alternative route to Lantau Link for the vehicles commuting between NWNT and urban areas, thus improving the traffic condition of Lantau Link which is the vital road connection between developments / infrastructures (including the airport and Hong Kong-Zhuhai-Macao Bridge (HZMB)) on Lantau Island and the urban areas.

2.2.2           Need of the Project

2.2.2.1      To meet the traffic demands arising from developments in the NWNT (including the Hung Shui Kiu / Ha Tsuen New Development Area (NDA) and the Yuen Long South Development), a group of major roads are earmarked for future developments, which comprises Route 11 (section between Yuen Long and North Lantau), Tuen Mun Bypass, TYLL and Widening of Yuen Long Highway (section between Lam Tei and Tong Yan San Tsuen).

2.2.2.2      According to the traffic impact assessment carried out as part of the TYLL FS, the traffic capacity of the Lantau Link will not be able to cope with the additional traffic commuting between the NWNT/ Lantau and the urban areas via Route 11 and Lantau Island after the completion of Route 11.  Hence, TYLL is required to ameliorate future traffic condition on Lantau Link.

2.2.2.3      The Project serves as a major carriageway connecting North Lantau, the proposed Route 11 (section between Yuen Long and North Lantau), and Tsing Yi.  It is expected the Project will greatly improve the traffic conditions on Lantau Link which is the vital road connection between developments / infrastructures (including the airport and HZMB) on Lantau Island and the urban areas.

2.2.2.4      Furthermore, the Project can serve as an alternative route to the existing Lantau Link for vehicles commuting between Lantau Island and the urban areas. This will improve the resilience of the NWNT traffic network in the event of traffic incidents or emergencies in major roads.  By providing multiple access points and connections to major roads in NWNT, the Project and Route 11 will serve as a reliable pathway for redirecting traffic towards urban areas during such events.  Moreover, the Project and Route 11 will act as a strategic route connecting NWNT and urban areas to Lantau, thereby enhancing the overall resilience of the road network connecting to the airport and HZMB.   

2.3               Consideration of “With” and “Without” Project Scenarios

2.3.1           Consideration of “Without” Project Scenario

2.3.1.1      Without the implementation of the Project, substantial amount of traffic load from new and existing developments in NWNT heading towards Tsuen Wan, West Kowloon, Lantau Island and Hong Kong Island, etc. would have to rely on the existing Tuen Mun Road or Lantau Link. The traffic impact assessment indicates that the Tuen Mun Road and Lantau Link would not have sufficient capacity to handle the future traffic demands, resulting in traffic congestion anticipated during peak hours, consequently leading to higher vehicular emissions from decreased traffic speeds.

2.3.2           Consideration of “With” Project Scenario

2.3.2.1      Upon completion of the Project, TYLL is expected to ameliorate the forecast traffic condition on Lantau Link and major roads connecting the NWNT and the urban areas, increase route choices and strengthen the resilience of the entire road network.  Together with other road projects that are currently under implementation, TYLL is also expected to help create traffic capacity to effectively unleash the development potential of the NWNT and Lantau Island effectively.

2.3.2.2      The implementation of the Project results in a significant improvement in the traffic conditions between NWNT and urban areas, including Tsing Yi, NWNT and Lantau Island.  Additionally, it brings benefits to the overall transport system by introducing alternative route choices for commuting traffic, ameliorating the traffic condition of Lantau Link.  Through the optimisation of the Project's alignment, it achieves more than just reducing travel time for road users; it also effectively reduces energy consumption and minimises environmental impact on the neighbourhood.

2.4               Environmental Benefits of the Project

2.4.1.1      As mentioned in the above sections, the existing major roads such as Tuen Mun Road and Lantau Link would experience traffic congestion during peak hours. The Project would ameliorate the traffic conditions on these major roads and reduce the potential air quality and noise impacts to the neighbouring sensitive receivers.

2.4.1.2      Furthermore, eco-shoreline features would also be incorporated on newly established coastal structures and shorelines.  It is expected that these features will facilitate the recruitment, settlement and colonisation of marine benthos, thereby enhancing the overall quality and diversity of associated marine ecosystems in the vicinity. 

2.5               Details of the Project

2.5.1           Location and Scope of the Project

2.5.1.1      The location of the Project is shown in Figure 2.1.1. The scope of the Project comprises the following:

(a)       construction of the cable-supported bridges crossing the MWF and KSMF (hereinafter referred to as the “Main Bridges”) including:

(i)       a dual three-lane 3-span continuous and earth-anchored suspension bridge crossing the MWF between Ma Wan and Tsing Yi with a main span of about 1400m;

(ii)      a dual three-lane earth-anchored single-tower suspension bridge crossing the KSMF between North Lantau and Ma Wan with a main span of about 500m;

(b)       construction of North Lantau Interchange, consisting of slip roads, tunnel and viaducts at North Lantau to connect the cable-supported bridge crossing the KSMF to North Lantau Highway, the proposed Tsing Lung Bridge under Route 11 and the proposed Hong Kong Island West – Northeast Lantau Link (HKIW-NEL Link);

(c)       construction of Tsing Yi Connection, consisting of extension of the TYLL mainline from the proposed cable-supported bridge crossing the MWF to connect with the Tsing Sha Highway at the west of Nam Wan Tunnel and provision of slip roads and viaducts to connect with the local roads in Tsing Yi;

(d)       construction of viaduct at Ma Wan South to connect the cable-supported bridges;

(e)       modification / realignment of Tsing Sha Highway and Cheung Tsing Highway northbound; and

(f)         associated works including civil, marine, drainage, sewerage, road works, traffic aids, street lighting, traffic control and surveillance system (TCSS), toll collection facilities, bridge facilities, fire services works, electrical and mechanical (E&M) works, re-provisioning of facilities affected and utility diversion, environmental mitigation works, landscaping works, site clearance and demolition, earth works, slope works, geotechnical works, natural terrain hazard mitigation works, reclamation works, etc.

2.6               Design Changes to the Project

2.6.1           General

2.6.1.1      Subsequent to the issue of the EIA Study Brief (No. ESB-359/2023) in June 2023, the Project Proponent has been optimising the alignment and design of the Project proactively to avoid and minimise environmental impacts where practicable. The Project Proponent had sought and received confirmation that a fresh study brief is not required due to these changes in accordance with Section 6.2 of the study brief. The assessments to these changes have been included under this EIA Study and the summary of the key project design changes are summarised in the sections below.  Details of alignment are shown at Figure 2.1.1 to Figure 2.1.4.

2.6.2           Exclusion of Tsing Yi Road West Connection Viaduct (TYRWV)

2.6.2.1      Under the original planning of the Project in the feasibility study, a slip road in the form of a viaduct, i.e. TYRWV, was proposed to connect the mainline of the Project with Tsing Yi Road West. The construction of this around 1.7km long TYRWV abutting Sai Tso Wan Road will require slope works/retaining structures and temporary works, which will generate construction and demolition materials and cause impact to nearby sensitive receivers. In this design development, it was found that this TYRW could be excluded while maintaining necessary connection with minor adjustment to the interchange.

2.6.2.2      This arrangement will also increase the horizontal distance between the proposed road under the Project and the sensitive receivers along Sai Tso Wan Road.  To illustrate this point, the closest distance between the proposed roads and the existing Potentially Hazardous Installation (PHI), namely Shell Tsing Yi Installation, will increase from 20m in the Project Profile to 60m in the current scheme. This would not only reduce the risk to road users but also minimise the environmental impacts such as air quality impact in both construction stage and operation stage.

2.6.3           Reduction in Total Reclamation Area

2.6.3.1      Earlier design of the Project as shown in the Project Profile included reclamations in North Lantau, Ma Wan and Tsing Yi to accommodate the towers and anchorages of long span bridges.  Subsequently, the alignment has been refined and the bridge form has been changed, the extent of the proposed reclamation works has also been reviewed with due consideration to the engineering, environmental and marine operation aspects. As a result, the footprints of the proposed reclamations are reduced. One of the refinements include the avoidance of reclamation at North Lantau by adopting a pile-supported Vessels Impact Protection System (VIPS) at the existing shoreline at North Lantau. The VIPS provides protection to the bridge pier against vessel impact, hence eliminating the need for reclamation. As a result, the total reclamation area in the current scheme (about 19.8 hectares) is reduced by about 4.1 hectares (17%) when compared with the original scheme in the Project Profile (about 23.9 hectares).

2.6.4           Rearrangement of the slip road tunnel connecting to the proposed HKIW-NEL Link to separate tunnel tubes and confirmed layout of slip roads connecting to North Lantau Highway

2.6.4.1      The scope of the Project includes the construction of slip roads, viaducts and a road tunnel at North Lantau connecting the mainline of the Project to the proposed HKIW-NEL Link and North Lantau Highway. During the preparation of the Project Profile, the planning and design of the proposed HKIW-NEL Link and the road alignment of the Project was still at a very preliminary stage. Therefore, we could only include an indicative arrangement of such connection in the Project Profile.

2.6.4.2      Further to the preliminary design of the Project, rearrangement of the slip road tunnel as two distinct tunnel tubes (one for each traffic bound) less than 800 m in length between portals was found to be required in order to maintain sufficient vertical clearance from the mainlines of the Project and the HKIW-NEL Link. Nevertheless, the tunnel portals at both ends would stay at a similar location.

2.6.4.3      The current scheme of the road alignment design also includes two slip roads connecting to North Lantau Highway (eastbound and westbound).  In the design, the routing and elevation were adjusted to minimise the required slope cutting works.

2.6.4.4      Similar ecological profile, habitat compositions and conditions to the original scheme are observed in the concerned areas (such as shrubland of low to moderate value, developed area and plantation of low ecological value). The scope of key environmental issues such as noise impact, air quality impact, terrestrial ecological impact, etc. need to be assessed as identified in the Project Profile are still covered in the current scheme.  While the assessment area of the applicable impact assessments in the EIA study had been adjusted according to the revised boundary of the revised road and tunnel alignment, there is no additional environmental issue associated with the proposed changes presented in the current scheme.

2.7               Consideration of Alignment Options

2.7.1           General

2.7.1.1      Having thoroughly reviewed the possible alignment options of the TYLL mainline investigated in the TYLL FS, recommendations from the public, and other alternative options, the recommended alignment option (Figure 2.1.1 refers) is still considered as the most cost effective and environmentally friendly alignment option of the TYLL mainline for connecting North Lantau and Tsing Yi.  It was therefore selected based on various engineering and environmental factors and will be taken forward for design and construction of the Project.

2.7.1.2      The following sections present the key elements and construction methodologies adopted in determining the most cost effective and environmentally friendly alignment option.

2.7.2           Tunnel Options for Crossing Fairways under Previous Stages of the Project

2.7.2.1      The tunnel options crossing both the KSMF and MWF near the fairway junction area in either immersed tube tunnel or tunnel boring machine form, followed by various landing points at Tsing Yi and Lantau in different structural forms were reviewed and evaluated in the previous stages of the Project.  All tunnel options for crossing the fairways were not recommended after considering their traffic planning, engineering and constructability, environmental issues, marine aspect, programme, cost as well as impact on local community and public acceptance.

2.7.3           Landing Point Options in Tsing Yi and Lantau

2.7.3.1      Other than the current recommended alignment, three alternative landing options are considered for this section of the Project, namely Alternative Landing Option 1, Alternative Landing Option 2 and Alternative Landing Option 3 (see Figure 2.1.5).

2.7.3.2      The current recommended alignment connects North Lantau Highway and Route 11 via an interchange at Ng Kwu Leng, crosses the KSMF and MWF by long span bridges, lands at the Hongkong United Dockyards (HUD) at Tsing Yi west, and connects to Tsing Yi North coastal Road, Cheung Tsing Highway and Tsing Sha Highway via slip roads. 

2.7.3.3      Alternative Landing Option 1 connects North Lantau Highway and Route 11 via an interchange at Ng Kwu Leng, crosses the KSMF and MWF both at a skewed angle by two long span bridges, followed by slip roads and a land tunnel after landing at the south-west of Tsing Yi, and finally connects with Cheung Tsing Tunnel via Tsing Yi Road West and Tsing Sha Highway. For Alternative Landing Option 1, additional reclamation works would be required near Tang Lung Chau and Tsing Yi west.  In addition, considerable amount of slope works and tunnel works associated with the proposed slip roads in Tsing Yi west would be involved, leading to a higher volume of excavated materials and associated construction dust impacts.

2.7.3.4      Alternative Landing Option 2 connects North Lantau Highway and Route 11 via San Po Tsui, crosses the KSMF and MWF by two long span bridges, lands at Wok Tai Wan, and connects to Tsing Yi North Coastal Road, Cheung Tsing Highway and Tsing Sha Highway via slip roads.  For Alternative Landing Option 2, similarly, additional reclamation works at Tsing Yi west would be required for supporting the slip roads connecting to Tsing Yi North Coastal Road and the back span at the eastern end of the long span bridge.  Moreover, the alignment is in close proximity to Ma Wan residential areas, a theme park and the Ma Wan Tung Wan Beach.  Major visual and environmental impacts to the residents, visitors and beach users are expected.

2.7.3.5      Alternative Landing Option 3 connects North Lantau Highway and Route 11 via an interchange at Ng Kwu Leng, crosses the KSMF and MWF by long span bridges, lands at the Shell Tsing Yi Installation at Tsing Yi west, and connects to Cheung Tsing Highway and Tsing Sha Highway via slip roads.  Alternative Landing Option 3 might require the shifting of Cheung Tsing Highway towards northeast into existing slope.  Therefore, substantive slope works, including significant additional construction and demolition material, as well as environmental impact.  The landing point is located at a reduced distance to the air sensitive receivers (ASRs) in Sai Tso Wan and the two existing PHIs, namely Chevron Hong Kong Limited Tsing Yi Terminal and Shell Tsing Yi Installation.  This would result in relatively greater potential direct impacts and long-term indirect disturbances to the environmental sensitive receivers.  Besides, Alternative Landing Option 3 is located right beside Shell Tsing Yi Installation and is susceptible to higher risk to life of the road users in case of fire in oil depot.

Table 2.1     Summary of Landing Options

Alignment Option

Pros

Cons

Recommended Option (Y/N)

Engineering Factors

Recommended Alignment

·       Connection to the Tsing Yi North Coastal Road, Cheung Tsing Highway and Tsing Sha Highway.

·       Adequate separation between TYLL and Tsing Ma Bridge to prevent aerodynamic interference.

·       Smaller reclamation extent compared to Alternative Landing Options 1 and 2.

 

Y

Alternative Landing Option 1

 

·       No connection to the Tsing Yi North Coastal Road.

·       Travelling distance is about 40% longer than the Recommended Alignment and may degrade the traffic performance and affect its utilisation, which may in turn undermine its intended function to divert traffic from other existing routes such as Tuen Mun Road and the Lantau Link.

·       Additional reclamation works near Tang Lung Chau and Tsing Yi west and considerable amount of cut slopes and tunneling works associated with the proposed slip roads in Tsing Yi west would be required, hence resulting in higher capital and long-term maintenance cost.

N

Alternative Landing Option 2

 

·       Aerodynamic interference of two closely-spaced long-span bridges would cause road safety concerns on both Tsing Ma Bridge and TYLL.

·       Additional reclamation works near Tsing Yi west and realignment of MWF would be required, hence resulting in higher capital and long-term maintenance cost.

N

Alternative Landing Option 3

 

·       Inadequate space and headroom for proposed slip road connection to Cheung Tsing Highway and Tsing Sha Highway due to the presence of several layers of existing viaducts at merging / diverging points.

N

Environmental Factors

Recommended Alignment

·       Smaller reclamation extents when compared with Alternative Landing Options 1 and 2.

·       Adequate distance maintained between the project and PHIs.

 

Y

Alternative Landing Option 1

 

·       Additional reclamation works near Tang Lung Chau and Tsing Yi west and considerable amount of cut slopes and tunneling works associated with the proposed slip roads in Tsing Yi west would be required.

·       Generate large amount of construction and demolition materials.

N

Alternative Landing Option 2

 

·       Proposed alignment and its associated reclamation would be very close to the existing residential blocks of Ma Wan and Ma Wan Tung Wan beach, resulting in significant visual and environmental impacts.

N

Alternative Landing Option 3

 

·       Proposed alignment is close to the existing oil depot and there might not be adequate space for constructing hazard mitigation measures.

N

 

2.7.4           Tsing Yi Option 1 selected from previous stages of the Project

2.7.4.1      The Tsing Yi Option 1 selected from previous stages (alignment shown on Project Profile) connects with North Lantau Highway and Route 11 via an interchange at Ng Kwu Leng, crosses the KSMF and MWF, and finally connects with Tsing Sha Highway on the west of Nam Wan Tunnel after landing on Tsing Yi.  This Tsing Yi Option 1 in bridge form excelled in engineering and constructability, environmental issues, programme, cost, impact on local community, public acceptance criteria, transport planning and marine aspect.

2.7.4.2      The Tsing Yi Option 1 has been reviewed and the following design refinements and / or modifications were considered, refined or explored: -

(a)   Appropriate widening of the marginal strips or hard shoulders to ensure adequate forward traffic visibility, which would affect the road design shown in the Tsing Yi Option 1 and require shifting the Cheung Tsing Highway northbound further west;

(b)   Eliminate the Tsing Yi Road West viaduct by incorporating it into the Cheung Tsing Highway; 

(c)   Provide access for traffic from CTT westbound to TYLL westbound;

(d)   Minimise retaining wall height at Tsing Yi;

(e)   Provide similar connectivity for TYLL and Lantau Link at Tsing Yi;

(f)    Consider the local geological fault line at Ma Wan;

(g)   Reduce of cut slope extent at TYLL interface with Route 11 and North Lantau Highway; and

(h)   Provide minimum 270m separation from Tsing Ma Bridge from the aerodynamic performance viewpoint.

2.7.4.3      In view of the above, other alignment options comprising sections of tunnels, viaducts, at-grade roads and cable-supported bridge have been considered for the Project.  In consideration of the alignment options, the Project is presented in the following two sections: -

(a)   Tsing Yi Connection; and

(b)   Main Bridges cum North Lantau Interchange.

2.7.4.4      The alignment options for the two sections of the Project are discussed in the sections below.

2.7.5           Tsing Yi Connection

General

2.7.5.1      Tsing Yi Connection of the TYLL is located at the west of the Nam Wan Tunnel and the CTT.  Being west of these two tunnels provides better opportunities to merge with and diverge to the existing road network on the western side of Tsing Yi.

2.7.5.2      The alignment of TYLL is restricted by the landing points on Tsing Yi, where oil depots and shipyards are located.   Furthermore, the location of the TYLL should be on the south side of the existing Tsing Ma Bridge such that direct connectivity with the HKIW-NEL Link, CTT, and Nam Wan Tunnel can be developed.  The TYLL will connect with Tsing Sha Highway at the Tsing Yi Connection.

2.7.5.3      There are three alignment options considered for this section of the Project, namely Tsing Yi Option 1, Tsing Yi Option 2 and Tsing Yi Option 3 (Recommended) (see Figure 2.3, Figure 2.4 and Figure 2.5, respectively).  The comparison of these three options is presented in Figure 2.9.

Tsing Yi Option 1

2.7.5.4      Realignment of Tsing Sha Highway northbound lanes proposed in this option requires a high and few hundred metres long retaining wall structure at a steep slope.  Construction of the high and long retaining wall would pose construction and programme risks to the Project and therefore should be reviewed.

2.7.5.5      Tsing Yi Road West viaduct connection to TYLL Bridge (hereafter referred to as TYRW-TYLL Viaduct) into Tsing Sha Highway under the Tsing Yi Option 1 requires ground-level space for columns / foundations, which may obstruct current and future land uses adjacent to Sai Tso Wan Road.  The eastbound TYLL diverging to the TYRW-TYLL Viaduct should take into account the cable arrangement of the TYLL Main Bridge design.

2.7.5.6      There is no connection between the CTT westbound and the TYLL westbound proposed under the Tsing Yi Option 1.

2.7.5.7      The existing slip road connections at Northwest Tsing Yi Interchange and Tsing Sha Highway near Liu To Shan connecting CTT, Nam Wan Tunnel, Tsing Yi Road West, Tsing Yi North Coastal Road, Ting Kau Bridge and Tsing Ma Bridge are complicated with various merging, diverging and weaving movements.  It is noted that the existing connectivity needs to be maintained and the TYLL Main Bridge should have the same or similar connectivity to the existing road network.

2.7.5.8      The TYLL will not connect with CTT directly.  To provide a connection between TYLL and CTT, widening towards the east side is feasible but should be avoided (subject to engineering design) to avoid deep cutting of the existing slope adjacent to Cheung Tsing Highway eastbound.  There would also be insufficient weaving length for the traffic from TYLL eastbound to CTT eastbound; and the traffic from Tsing Sha Highway to Tsing Yi Road West.  Therefore, the alignment should be widened towards the west side.  This widening would increase slope works in Tsing Yi, leading to a higher volume of excavated materials and associated construction dust impacts.  It would also reduce the distance from the proposed roads to the ASR in Sai Tso Wan and the two existing PHIs, namely Chevron Hong Kong Limited Tsing Yi Terminal and Shell Tsing Yi Installation to approximately 20m. This would result in relatively greater potential direct impacts and long-term indirect disturbances to the environmental sensitive receivers.

Tsing Yi Option 2

2.7.5.9      Tsing Yi Option 2 is developed and refined from Tsing Yi Option 1. A new slip road was proposed to connect Nam Wan Tunnel and TYLL westbound lane directly, removing a two-lane width spatial requirement on the existing Tsing Sha Highway and eliminating the need for extensive slope work in Tsing Yi.  This option would increase slope works along Cheung Tsing Highway, require more land lot areas for construction of elevated roads and vehicles movement would be closer to air and noise sensitive receivers.

Tsing Yi Option 3 (Recommended)

2.7.5.10   Tsing Yi Option 3 (Recommended) is developed based on the Tsing Yi Option 1 and Tsing Yi Option 2.  Tsing Yi Option 3 (Recommended) has the same connectivity as the Tsing Yi Option 1 with less extensive slope work in Tsing Yi and accommodating the following modifications: -

(a)       TYRW-TYLL Viaduct incorporated into the Cheung Tsing Highway, this modification will reduce the total number of retaining walls and temporary working platforms, thereby minimising land impact; and

(b)       Provision of direct traffic connection from CTT westbound to TYLL westbound as an alternative route to the Lantau Link to improve traffic resilience.

Summary of Alignment Option Considered

2.7.5.11   A summary of the above options for Tsing Yi Connection is given below with the recommended option identified.

Table 2.2     Summary of alignment options for Tsing Yi Connection

Alignment Option

Pros

Cons

Recommended Option (Y/N)

Engineering Factors

Tsing Yi Option 1

·   Direct connection to Tsing Yi Road West.

·   TYRW-TYLL Viaduct requires land adjacent to Sai Tso Wan Road.

·   No direct connection between TYLL and CTT.

·   Large temporary working platforms are anticipated for the construction of bored pile wall along existing slopes.

N

Tsing Yi Option 2

·   The amount of retaining structures is less than the Tsing Yi Option 1.

·   TYRW-TYLL Viaduct requires land adjacent to Sai Tso Wan Road.

·   Appropriate widening of the marginal strips or hard shoulders to satisfy adequate forward visibility distance.

·   No direct connection between TYLL and CTT.

N

Tsing Yi Option 3 (Recommended)

·   The amount of retaining structures is fewer than the Tsing Yi Option 1 and 2.

·   The modification of existing road is less than Tsing Yi Option 2 by approximately 4.3km.

·   Direct connection of TYLL westbound and CTT westbound.

·   TYRW-TYLL Viaduct incorporated into Tsing Sha Highway.

·   Appropriate widening of the marginal strips or hard shoulders to satisfy adequate forward visibility distance.

·   Large temporary working platforms are anticipated for the construction of bored pile wall along existing slopes.

Y

Environmental Factors

Tsing Yi Option 1

 

·     Affect large number of trees (~909 nos. of trees) at existing slope.

·     Closer to the two existing PHIs (~20m) and ASRs at Sai Tso Wan.

·     Large construction area would impose greater environmental implication.

N

Tsing Yi Option 2

 

·     Affect large number of trees (~909 nos. of trees) at existing slope.

·     Closer to the two existing PHIs (~10m) and ASRs at Sai Tso Wan.

·     Large construction area would impose greater environmental implication and generate higher amount of construction waste.

N

Tsing Yi Option 3 (Recommended)

·     Omission of viaduct connection leads to smaller construction works area and minimise landscape and visual impacts.

·     Affect smaller number of trees (~461 nos. of trees) at existing slope.

·     The works area is reduced by 15 ha as compare with Tsing Yi Option 1 and 2

 

Y

 

2.7.6           Main Bridges cum North Lantau Interchange

General

2.7.6.1      The signature element of the proposed TYLL will be the approximately 3.3km long-span bridges crossing over the MWF and the KSMF from Tsing Yi Connection to North Lantau Interchange. The mainline of TYLL will then connect to Route 11 in a dual-2-lane arrangement.  Four slip roads of TYLL will also be provided as listed below: -

(a)     North Lantau Highway eastbound and TYLL eastbound;

(b)     North Lantau Highway westbound and TYLL westbound;

(c)     HKIW-NEL Link southbound and TYLL westbound; and

(d)     HKIW-NEL Link northbound and TYLL eastbound.

2.7.6.2      The TYLL will connect to Route 11, North Lantau Highway, and the proposed HKIW–NEL Link at North Lantau Interchange. There are two alignment options considered for two long-span bridges cum associated connection at North Lantau Interchange, namely Main Bridges cum North Lantau Option 1 and Main Bridges cum North Lantau Option 2 (see Figures 2.6 and 2.7) which are presented below.

Main Bridges cum North Lantau Option 1

2.7.6.3      Main Bridges cum North Lantau Option 1 is developed based on the proposed alignment in the Project Profile, and consists of an earth-anchored twin-tower suspension bridge across MWF, and a cable-stayed bridge across KSMF.  There is a portion of the viaduct structure in between the cable-supported bridges.

2.7.6.4      One land anchorage at Tsing Yi and one marine anchorage are required for the suspension bridge across MWF.  A large marine anchorage is required to support the larger resultant force from the bridge structure acting on the anchorage.

2.7.6.5      A major constraint to this bridge form for KSMF would be the Disneyland Height Restriction.  Although technically feasible, a relaxation to the restriction is required in order to proceed with this bridge form.  In addition, the Lantau backspan stay-cable may interfere with the existing helicopter flight path. The design of the cable-stayed bridge would take into consideration the challenging interfacing issues and offer helicopter pilots sufficient horizontal and vertical clearances with the bridge structural elements for the safe operation of helicopters.

2.7.6.6      A straight backspan alignment is required to facilitate the efficient design and construction of the cable-stayed bridge, hence limiting the flexibility for optimising the North Lantau Interchange alignment.  The requirements for the connection at North Lantau, constrained by the need for a tie-in with HKIW-NEL Link, also lead to a widened Lantau side span of the cable-stayed bridge to cater for the merging / diverging arrangement for the proposed slip roads (two lanes for each direction) connecting HKIW-NEL Link.  Widening of the side span by the same width is required to minimise unbalanced effects on the cable-stayed system.  The unconventional deck arrangement will complicate the design and construction of the cable-stayed bridge, and an increase in site formation and tunnelling works are also required on Lantau Island.

Main Bridges cum North Lantau Option 2 (Recommended)

2.7.6.7      Main Bridges cum North Lantau Option 2 consists of an earth-anchored twin-tower suspension bridge across MWF and an earth-anchored single-tower suspension bridge across KSMF.  There is a portion of ground-supported viaduct structure in between the suspension bridges.

2.7.6.8      One land anchorage is required for each suspension bridge.  The suspension cables for both bridges are also rigidly supported by the common marine anchorage adjacent to the south-eastern corner of the Ma Wan Island shoreline.  The shared marine anchorage is lowered to below deck level.  The size of the marine anchorage is also optimised as the horizontal forces from the two suspension bridges can be balanced and thus reduce the size of the common anchorage.  Part of the common anchorage will be embedded below ground. 

2.7.6.9      On the western side of the single-tower suspension bridge across KSMF, the prismatic cable-supported portion of the bridge deck terminates at the Lantau shoreline.  This arrangement allows the main alignment of TYLL to turn northeast towards Route 11 upon approaching Lantau Island thus minimising the extent of slope cut required for the construction of the proposed North Lantau Interchange.  The slope cutting on the North Lantau side will be reduced compared to Option 1 due to elimination of the straight side-span.

Summary of Alignment Option Considered

2.7.6.10   A summary of the above options for Main Bridges cum North Lantau Interchange is given below with the recommended option identified.

Table 2.3         Summary of alignment options for Main Bridges cum North Lantau Interchange

Alignment Option

Pros

Cons

Recommended Option (Y/N)

 

Engineering Factors

Main Bridges cum North Lantau Option 1

·       Full closure to KSMF is not required for cable-stayed bridge construction.

 

 

 

·       KSMF cable-stayed bridge does not comply with Disneyland Height Restrictions.

·       Reduces the airspace at North Lantau Interchange for helicopter flights.

·       Increased deck width of Lantau side span is required to cater for the merging/diverging length.

·       Significant increase in site formation and tunnelling works required on North Lantau Island.

N

 

Main Bridges cum North Lantau Option 2

(Recommended)

·       Complies with Disneyland Height Restrictions.

·       Curved alignment begins at Lantau Shoreline with reduced site formation works.

·       One-off short duration of full closure at KSMF is required.

Y

 

Environmental Factors

Main Bridges cum North Lantau Option 1

 

·       Require reclamation at North Lantau and larger reclamation area in Ma Wan. The total reclamation area is approximately 26.3 ha.

·       Generate large amount of marine sediment due to larger reclamation area.

·       Affect larger number of trees (2,420 nos. of trees).

N

 

Main Bridges cum North Lantau Option 2

(Recommended)

·       Reclamation at North Lantau is not required.

·       The total reclamation area is approximately 19.8ha. Reduced the overall area of reclamation by approximately 6.5 ha as compared with Main Bridges cum North Lantau Option 1.

·       Minimise slope cutting at North Lantau which in turn preserves the natural features of the area hence minimising ecological impacts and tree felling.

·       Affect smaller number of trees (1,920 nos. of trees).

 

Y

 

 

2.8               Project Details

2.8.1           Recommended Alignment for the Project

2.8.1.1      The Recommended Alignment is an integration of Tsing Yi Option 3 (Recommended) of Tsing Yi connection and Main Bridges cum North Lantau Option 2 (Recommended) as discussed in Section 2.7 above, which is highlighted in the following sections. The Recommended Alignment is shown in detail in Figure 2.1.1 to Figure 2.1.4.

2.8.1.2      The Recommended Alignment has the advantages as illustrated below:

(a)   Additional reclamation, site formation, slope cutting and tunnel works are avoided, resulting in cost saving with less generation of C&D materials, less environmental impacts and less impact to the natural terrain;

(b)   Encroachment of bridge towers into MWF is avoided, hence less impact to marine traffic;

(c)   Aerodynamic interference between the existing Lantau Link and the proposed TYLL, which results if the long span bridges are located close to each other, is avoided; and

(d)   The provision of connection to Tsing Yi North Coastal Road, and shorter travelling distance, render better traffic performance.

Tsing Yi Connection

2.8.1.3      Tsing Yi Option 3 has the advantages below:

(a)   Tsing Yi Option 1 does not allow the traffic from CTT westbound to TYLL westbound.  A slip road connecting Cheung Tsing Highway northbound and TYLL westbound is therefore proposed to facilitate the westbound traffic of CTT to have a direct access to TYLL westbound and thus better connectivity with CTT; and

(b)   With the provision of the slip road mentioned above, both bound traffic between TYLL and the existing local road, i.e. Tsing Yi Road West, can be maintained and the pair of slip roads running along Sai Tso Wan Road proposed in the Tsing Yi Option 2 is no longer required.  The enhanced Tsing Yi Connection under the Recommended Alignment will be more cost-effective land impact is also minimised.

 

Main Bridges cum North Lantau Interchange

2.8.1.4      Main Bridges cum North Lantau Option 2 has the advantages below:

(a)   On the western side of the single-tower suspension bridge, the prismatic cable-supported portion of the bridge deck will terminate at the approach to Lantau shoreline and allow the alignment of TYLL mainline to turn northeast earlier towards Route 11 and thus can greatly minimise the extent of site formation and slope cutting works for the construction of the proposed North Lantau Interchange, resulting in cost saving with less generation of C&D materials, less environmental impacts and less impact to the natural terrain;

(b)   Owing to the termination of the bridge deck of single-tower suspension bridge at the Lantau shoreline mentioned above, this will not impose constraints on the design of the proposed North Lantau Interchange and the connection with the slip roads of the interfacing projects;

(c)   The common marine anchorage for both suspension bridges near the south-eastern corner of Ma Wan Island is modified.  There will be a section of about 200 m long free of suspenders in between the two suspension bridges.  This section will be in the form of concrete viaducts, resulting in cost saving with a shorter length of the side span of the single-tower suspension bridge at the south of Ma Wan;

(d)   Taking into account the bridge form for crossing the KSMF and the modified layout of North Lantau Interchange, the alignment option with single-tower suspension bridge form will have a noticeable lower overall construction cost; 

(e)   The airspace in the vicinity of the KSMF will continue to be free in absence of a bridge tower on Lantau side and thus no interference with the existing helicopter flight path; and

(f)    Single-tower suspension bridge will only have one bridge tower located at the south of Ma Wan hence complying the Disneyland Height Restrictions.

2.8.2           Work Area(s) / Site(s) and Their Locations

2.8.2.1      The works areas / sites were identified based on their intended use during construction phase of the Project.  Works areas serve as locations for site offices and material storage during the construction period.  Works sites include on-site construction activities such as site formation, excavation and foundation works, etc. Transient and localised activities like temporary traffic management schemes, outside the works areas / sites but within the Project area are required.  These activities are not anticipated to have critical environmental impacts when good site practices and control measures (e.g. Recommended Pollution Control Clauses promulgated by EPD) are implemented.  The works areas / sites are shown in Figure 2.2 as the Project Boundary.  The works areas / sites will be reinstated and handed over upon Project completion in 2033 tentatively.

2.8.2.2      The Recommended Alignment of TYLL requires four reclamation areas with a total area of 19.8 ha, to accommodate and protect the proposed bridge towers and anchorage against ship collision impact. Tsing Yi Tower, Ma Wan South Tower, Ma Wan South Anchorage and Kap Shui Mun Tower are the proposed bridge towers / anchorage to be constructed on the reclamation areas. The reclamation areas are shown in Figure 2.1.1.

2.8.2.3      There are construction haul roads proposed at both ends of the TYLL.  The construction haul roads at North Lantau Interchange are mainly required for construction vehicles to transport construction materials and personnels to works sites when there is no direct connection to public road.  The construction haul roads at Tsing Yi Connection are required for the construction vehicles / plants to access the proposed road realignment / modification works on the existing slopes. The alignment of construction haul roads can be adjusted on-site to minimise the impacts on surrounding environment by maintaining separation distances from sensitive receivers and implementing good site control measures.  The construction haul roads shall be reinstated upon Project completion.

2.9               Construction Methodologies

2.9.1           Overview

2.9.1.1      The key construction elements of the Project include tunnel, cable supported bridges crossing MWF and KSMF, reclamation areas for the proposed bridge towers and anchorage, viaducts and at-grade roads, see Figures 2.8.1 to 2.8.13.  This section provides an overview of the construction planning for the Project, focusing on key aspects such as the anticipated methods and sequence of works for the essential construction elements.

2.9.2           Construction Methodology for Tunnel

2.9.2.1      Considering the available geological information, it is suggested that tunnel excavation for the Project will primarily take place in areas with favourable geological conditions.  The commonly deployed excavation methods, include drill-and-blast and mechanical methods such as drill-and-break, would be adopted.  The choice of tunnel construction method primarily depends on local constraints and the proximity of sensitive areas.

2.9.2.2      The primary method of construction for the tunnel is expected to be the drill-and-blast method, which involves controlled blasting to excavate medium to hard rock.  The potential environmental impacts, specifically concerning noise, dust, and visual disturbances, will be significantly decreased and limited to areas in close proximity to the portals. Considering the relatively short length of the tunnel, daily delivery of explosive from Mines Division is sufficient for the blasting works, thus no project specific magazine is considered required.

2.9.2.3      Compared to mechanical breaking methods, such as using rock breakers or excavators, the drill-and-blast method is more effective for tunnel excavation. It significantly reduces the construction period, providing both financial benefits and faster project commissioning.

2.9.2.4      In urban construction projects, the Tunnel Boring Machine (TBM) is frequently used for tunnel construction. However, it is not deployed for constructing the tunnel in this specific project. North Lantau mainly composes of igneous rocks, which poses a challenge to TBM which is more likely to be utilised for softer ground profiles. Moreover, TBM necessitate accurate navigation to ensure the tunnel is constructed in the correct direction and right angle. Consequently, challenges may arise when working on curved tunnels of shorter lengths under TYLL. Furthermore, the cost of applying TBM is higher than employing drill-and-blast method.

2.9.3           Construction Methodology for Reclamation

2.9.3.1      As stated in Chapter 4 of Project Administration Handbook (PAH) for Civil Engineering Works published by Civil Engineering and Development Department, it is Government Policy to leave the marine mud in-situ subject to site condition, any dredging required shall have full justification and all relevant implications reviewed.

2.9.3.2      In view of thick marine deposits layer and its weak soil properties in TYLL, it is technically required to dredge the whole layer of marine deposits and replace it with firm materials for controlling the settlement of the reclaimed islands and to ensure stability of the seawall structures. Taking into account the depth of the dredged trench, the extent and quantity of the dredging work will be excessive.

2.9.3.3      It is therefore considered that the fully dredged method is not applicable for the whole reclamation extent of TYLL. It would only be applicable in local areas where non-dredged methods, such as Deep Cement Mixing (DCM) and jet grouting methods, could not be carried out on site. According to the geotechnical condition, rocks (potentially of varying weathering grades), boulders / cobbles / gravels, sandy materials, dumped materials and debris are present at the seabed in these areas.  In view of these seabed features and the relatively thin layers of marine deposits in local areas, dredging of limited depths to remove thin and local marine deposits as well as various boulders / cobbles / gravels / debris may be considered as a more practical method. In case dredging is unavoidable, efforts will be made to minimise the extent of dredging.

2.9.3.4      To enhance the strength and stiffness of the thick soft marine deposits so as to control the stability of the seawalls and long-term settlement of the reclaimed areas, DCM is proposed to be deployed as the primary ground treatment works supporting the proposed bridge tower and anchorage structures.  The use of DCM for seabed treatment is considered as the most robust option with the least shortcomings when compared with other ground treatment schemes given the Project’s needs. Non-dredged reclamation with the marine deposits left in place may be adopted to avoid the need for dredging and disposal of thick marine deposits especially for the reclamation of the Tsing Yi and Ma Wan South Towers of the proposed bridge crossing MWF.

2.9.3.5      Dredging of soft marine deposits is proposed in areas where thin layer of marine deposits is found across the entire reclamation site including areas of the proposed reclamation for the towers of proposed bridges crossing MWF and KSMF and Ma Wan South anchorage, when the DCM method is ineffective.  Furthermore, there may be local areas where the soft marine deposit is underlain directly by in-situ soils (e.g. saprolite), which is relatively hard for the DCM rigs to penetrate and therefore embedment condition of the DCM clusters is not expected to be acceptable.  To ensure adequate control of residual settlement in the reclamation area and stability of the seawall structures, dredging is recommended for these thin layers of marine deposits.  For areas where thick marine deposits are present, there may be seabed features of boulders / cobbles / gravels / debris which are potential obstructions for the DCM works.  Consideration should be given to the combined ground treatment pile-supported using removal of shallow obstructions followed by DCM treatment. 

2.9.3.6      The actual construction sequences and processes of the reclamation filling shall be further developed by the contractor but the envisaged construction processes of the adopted reclamation summarised as below: -

1.     Installation of silt curtain;

2.     Dredging for seawall and four main reclamation areas simultaneously (Approx.12 numbers of dredgers);

3.     Installation of geotextile, sand blanket and primary silt curtain;

4.     Carry out DCM (approx. 50%) for main reclamation area;

5.     Backfilling of fully dredged zone;

6.     Installation of rockfill; and

7.     Reclamation filling to formation level.

2.9.3.7      Regarding to the construction method of pile-supported VIPS, the bored piles would be used for supporting the above VIPS. It aims to provide the protection of bridge structures instead of the reclamation sea wall.

2.9.4           Construction Methodology for Main Bridges

2.9.4.1      The Main Bridges of the proposed TYLL is currently designed as a combination of twin-tower suspension bridge across MWF and single-tower suspension bridge across KSMF, connecting North Lantau and Tsing Yi West.  The main components of the Main Bridges of TYLL include the foundations, towers, cable anchorages, suspension cables and bridge decks.

2.9.4.2      The towers of the Main Bridges of TYLL are typically supported by large diameter bored pile foundations.  The piled foundations are each in the form of a pile cap on top of a pile group for efficient load transfer, and they are commonly use in sea crossings if the site and ground conditions warrant load transfer to lower strata. Piled foundations offer advantages such as optimal use of construction materials, accelerating construction, reducing noise and minimising vibrations.

2.9.4.3      The Main Bridge towers will be of concrete construction using either jump form or slip form methods for the in-situ concrete pour. The choice of construction materials and methods takes into account factors such as construction time, cost, durability, and maintenance requirements.

2.9.4.4      The anchorages for the suspension cables will be located at the landing points on both sides of each bridge and, at Ma Wan South, a shared, common anchorage will be founded on reclamation.  A commonly adopted type of anchorage is the gravity type anchorage, which involves a substantial underground concrete mass structure. A significant amount of concrete would be required for constructing both the anchorages and the bridge towers.  To enable efficient and timely concrete production for the Project, it is anticipated that the contractor would establish a temporary concrete batching plant with an estimated capacity of approximately not more than 10,000 tonnes within the works area, subject to contractor’s design. A tentative, available location for a temporary concrete batching plant is shown in Figure 2.10.

2.9.4.5      To protect the bridge towers, marine bridge piers and marine anchorage in Ma Wan and Tsing Yi, reclamations in Ma Wan and Tsing Yi are unavoidable.  Holistic engineering consideration has been taken to minimise the clearance between the edge of reclamation and the foundation of bridge tower / pier / anchorage, to avoid physical collision between vessel and bridge structure. 

2.9.4.6      After the construction of towers and anchorages are completed, the construction process will proceed with the installation of suspension cables.  Subsequently, the suspenders will be installed, followed by the erection of the bridge deck.  The bridge deck will be made of steel and will be prefabricated off-site in segments.  These segments will then be transported to the site by barge and lifted into place for installation.  To ensure navigation safety during the installation of the deck segments, suitable temporary marine traffic management will be implemented.

2.9.5           Construction Methodology for Viaducts

2.9.5.1      Viaducts will be required for the mainline crossing North Lantau Interchange and Tsing Yi Connection, and the associated slip roads.  The viaducts will be primarily constructed by using precast concrete segmental method so as to minimise the on-site casting work.  In other words, the viaduct segments will be manufactured at an off-site casting yard, transported to the construction site and assembled together to complete the whole viaduct structure.  This method promotes the efficiency of the construction activities and need for on-site concrete casting. 

2.9.5.2      Alternatively, when site constraints limit accessibility for delivering precast deck segments, cast-in-situ construction using formwork and falsework would be considered as an alternative option. 

2.9.6           Construction Methodology for Rock Cuttings

2.9.6.1      The rock hills at Lantau Island near Yi Chuen and Tso Wan will be excavated for site formation for the proposed at-grade roads and tunnel portals.  According to the available geological data, the construction of the proposed anchorages at both ends of the main bridge will also require rock excavation.

2.9.6.2      To optimise cost and time efficiency for the Project, it is proposed to adopt open blasting for the large amount of rock cuttings at North Lantau Interchange.  The selected locations for open blasting are primarily in areas with low population density.  To ensure safety and suppress dust generation, additional measures such as blasting screens, blast cages, and blast mats will be implemented.  A well-designed open blasting design will also be utilised to effectively manage and control the effects of flyrock.

2.9.6.3      Conventional rock excavation using mechanical breaking with pre-splitting would still be considered for the construction of anchorage at Tsing Yi due to the smaller volume of land excavation when compared to the North Lantau Interchange.

2.9.6.4      Regarding habitat preservation and waterflow retention, the following measures are envisaged:

·       In order to preserve the headwater of the north-branching tributary in watercourse at North Lantau, it is proposed to replace the intersecting section with a box culvert and relocating the permanent structures to avoid encroachment;

·       Implement temporary stream diversions to maintain waterflow and minimise run-off as well as subsequent impact on watercourses and associated fauna; and

·       Establish work exclusion zones around watercourses and use elevated platforms to minimise impact on banks and stream beds.

2.9.7           Summary of Construction Methodology

2.9.7.1      Possible construction methods which have been investigated for the construction of the Project and the reasons for selection are summarised in Table 2.4.

Table 2.4          Comparison and Summary of Possible Construction Methods for the TYLL

Section

Possible Construction Method

Pros

Cons

Tunnel

Drill-and-blast

(Recommended)

·   Significantly decrease and limit potential environmental impacts, specifically concerning noise, dust, and visual disturbances to areas in close proximity to the portals

·   More effective for rock tunnel excavation than mechanical breaking methods, which significantly reduces the construction period, providing both financial benefits and a faster project commissioning

·   Risk of storage and delivery of explosives to work site.

Tunnel Boring Machine

·   Less labour required for the construction of tunnel.

·   Less suitable for hard ground profiles such a those found in North Lantau.

·   Land required for set of  launching shaft and receiving shaft which would impose significant impact on natural terrain causing consequential ecological impact.

Reclamation

DCM (Recommended primary ground treatment method)

·   Considered as the most robust option with the least shortcomings when compared with other ground treatment schemes given the Project’s needs.

·   Avoid the need for disposal of thick marine deposits.

·   Ineffective in areas with shallow depth of marine deposits.

Fully dredged method (Recommended for areas where DCM is ineffective)

·   For areas with soft marine deposits where DCM is ineffective, it is technically required to dredge the whole layer of marine deposits and replace it with firm materials for controlling the settlement of the reclaimed islands and to ensure stability of the seawall structures

·   Disturbance of seabed may cause generation of suspended solids.

Pile-supported VIPS

Bored pile

(Recommended)

·   The bored piles would be used for supporting the VIPS. It aims to provide the protection to bridge structures.

·   Reduction in vibration and noise generated during the piling process

·   More expensive

Driven pile

·   Less expensive

·   Generation of significant noise and vibration during the piling process.

·   Percussion piling may cause disturbance to the seabed and generate suspended solids.

Main Bridges- foundations

Large diameter bored pile foundations for tower support (Recommended)

·   Accelerate construction

·   Reduce noise and minimising vibrations

·   More expensive

Driven pile

·   Less expensive

·   Generation of significant noise and vibration during the piling process.

·   Percussion piling may cause disturbance to the seabed and generate suspended solids.

·   Driven piles may not have enough capacity for the large loads from the towers

Main Bridges- tower

Jump form or slip form methods for tower construction (Recommended)

·   Considered as the most robust option taking account into the construction time, cost, durability, and maintenance requirements.

·   Less C&D materials / waste generated

·   Require another trade of skilled workers and additional construction equipment.

Timber formwork for tower construction

·   Conventional construction method and require less special skilled labour force and specialists when comparing with other construction methods

·   More C&D materials / waste to be generated

 

Viaducts

Precast concrete segmental method (Recommended)

·   Better control of quality and workmanship for works in fabrication yard.

·   Minimise the need for on-site concrete casting.

·   Use of steel mould as formwork in the fabrication yard can reduce the generation of C&D waste / materials on site.

·   More efficient construction works as the deck segments can be casted concurrently with superstructure works.

·   Require another trade of skilled workers and additional construction equipment for erecting precast segments.

Cast in-situ concrete

·   Conventional construction method and require less special skilled labour force and specialists when comparing with other construction methods

·   Use of timber formwork, thus more C&D waste / materials will be generated.

·   Site conditions in terms of accessibility and weather can be highly critical to the work, requirement of extreme measures in some situations to control all stages in the production process.

·   Substantial falsework required.

·   Longer construction time.

Rock Cuttings

Open blasting (Recommended for Lantau side)

·   Optimise cost and time efficiency for hard rock slopes.

·   Noise only generated at specific times.

·   Risk of storage and delivery of explosives to work site.

Hydraulic excavation (Recommended for Tsing Yi side)

·   Explosives not required, thus reducing risk to the two PHIs at Tsing Yi.

·   Longer periods of continuous noise generation.

·   Longer construction time

 

2.10            Implementation Programme

2.10.1.1   Currently, the project is in the investigation phase, with ongoing progress in developing the alignment scheme, conducting the traffic impact assessment, EIA, gazettal, engineering study and other major statutory procedures.

2.10.1.2   The construction phase of the Project, which involves activities such as tunnelling, reclamation works, road works, viaduct construction and site formation, is tentatively scheduled to begin in 2027 Q1 and complete in 2033 Q2. The project implementation, including construction and operation of the TYLL, will involve land resumption under prevailing mechanism before commencement of construction of the TYLL. The road scheme for the project will be gazetted under Roads (Works, Use and Compensation) Ordinance (Cap. 370) and the construction works will commence only after the road scheme has been authorised and the land resumption under Cap. 370.

2.10.1.3   The sequence of works will be refined during the detailed design and construction stages of the project.  The sequence of works will be carefully planned such that the environmental impacts would be kept to minimum and within acceptable limits. Collaboration with the nearby concurrent projects (e.g. Route 11 and Road P1, etc.) is required to reduce the potential cumulative environmental impacts. The sequence followings are the measures recommended to be taken during construction:

·       Close liaison with the contractors of other concurrent projects in order to avoid overlapping of construction activities and allow sufficient buffer for works at project interface due to potential delays in the programme so that the cumulative effects of environmental impacts could be minimised.

Land Based Works

·       Temporary stream diversion to maintain the downstream water flow, works exclusion zones and elevated platforms will also be implemented before construction works around watercourses where required to minimise the ecological impact. As the impact on amphibians and other aquatic species of conservation interest are mitigated through translocation works (if applicable) after pre-construction survey, the environmental impact has been minimised such that a specific sequence of land-based works is not considered necessary.

 

·       Blast cages or roof-over protective cover would be provided before the commencement of open blasting works to minimise the air and noise impacts of blasting. During the construction of drill and blast tunnels, a blast door will be installed in the tunnel openings to prevent the escape of fugitive dust from blasting before further blasting works within the tunnels. Therefore, the air and noise impacts are minimised for most periods of the tunnel construction through the blast door. With these mitigation measures, the carrying out of the construction of the two tunnels and slip roads concurrently would result in a similar environmental impact and is assumed in conducting the assessment in lieu of a specific construction sequence.

 

Marine Works

·       Silt curtains will be installed before reclamation works to minimise the marine water quality, marine ecology and fisheries impacts of the works.  The worst-case scenario has been considered for the water quality impacts of the reclamation works in Chapter 5 based on a tentative construction sequence in Appendix 5.2.

 

·       The use of VIPS for vessel protection of the deflection pier at North Lantau reduces the time required for the construction works there when compared to using reclamation for vessel protection, requiring only about 10 months to complete the piling works. This further minimises the marine water quality, marine ecology and fisheries impacts of the works.  The sediment release rate for VIPS is minuscule, being less than 1% of the sediment release rate of the reclamation works. Therefore, it is considered that a specific sequence of works for VIPS is not necessary.

 

Table 2.5      Summary of Key Construction Works for the Project

Description

Tentative Construction Programme

Tsing Yi Connection

Q1 2027 to Q2 2031

Suspension bridge over Ma Wan Fairway

Q1 2027 to Q2 2033

Viaduct connecting two cable-supported bridges

Q1 2028 to Q4 2031

Suspension bridge over Kap Shui Mun Fairway

Q1 2027 to Q2 2030

North Lantau Interchange

Q1 2027 to Q2 2031

2.11            Summary of Alternative Mitigation Measures

2.11.1        Overview

2.11.1.1   Due consideration has been given to address the environmental challenges encountered in the design of the Project.  Environmental protection will be prioritised and fulfilled to the greatest extent possible.  Various key actions have been implemented to address these environmental challenges, which will be discussed in the following sections.

2.11.2        Minimisation of extensive retaining structures on existing geotechnical features at Tsing Yi

2.11.2.1   As mentioned in Section 2.7.4, the alignment has been refined by incorporating the above viaduct into Tsing Sha Highway, at same time providing a direct connection from CTT westbound to TYLL westbound. The recommended alignment is adopted to reduce the length of retaining structures by approximately 115m on existing geotechnical features, as well as reduce the numbers of affected existing geotechnical features such as the man-made slope and the extension of retaining wall.  With the omission of the TYRW-TYLL Viaduct connection that required land adjacent to Sai Tso Wan Road, land resumption is greatly reduced and the number of affected nearby ASRs and NSRs is reduced.  By adopting this alignment design, it would also minimise the landscape and visual impacts at the Tsing Yi Connection.

2.11.3        Avoidance of Reclamation at North Lantau Shoreline

2.11.3.1   The alignment selected in the previous feasibility study and presented in the Project Profile has included reclamations in North Lantau, Ma Wan and Tsing Yi. Further to the refinement on the alignment, the extent of the proposed reclamation works is further reviewed to minimise the footprints of the proposed reclaimed areas with due consideration on the engineering, environmental and port operation aspects.

2.11.3.2   To protect the deflection pier at North Lantau, pile-supported VIPS is proposed to be adopted in the area of existing shoreline. The VIPS structure will be supported by bored piles with a superstructure and hanger slab to protect the pier from vessel impact, thus reclamation is no longer required at North Lantau. The short-term nature, around 10 months subject to actual ground conditions of the piling activities is expected to cause minimal disturbance to surrounding marine fish and fisheries-sensitive receivers.

2.11.3.3   The avoidance of reclamation at North Lantau would benefit the preservation of the intertidal zone and ecosystem along the shoreline, including six species of conservation importance at the intertidal zone, a majority being locally very common shorebirds, such as Great Egret, Pacific Reef Heron, White-throated Kingfisher etc. Moreover, the surfaces of supporting structures for the pile-supported VIPS, present new opportunities for the recruitment, settlement and colonisation of marine benthos, thereby enhancing the overall quality of associated marine ecosystems in the vicinity.

2.11.4        Minimisation of Reclamation and Dredging Extents for the Reclamation in Ma Wan and Tsing Yi

2.11.4.1   Marine anchorages in Ma Wan are combined into a single common anchorage.  This approach reduces the material required for anchorage construction and minimises excavation work.  As a result, both the environmental impact of material excavation and disturbances to the marine environment are reduced.  Furthermore, the combination of anchorages can reduce the overall area of Ma Wan reclamation.

2.11.4.2   This reduction of reclamation area has reduced the total amount of dredged sediments, hence reducing the associated water quality impacts during the construction phase.  The extent of channel narrowing at both MWF and KSMF are also reduced, hence reducing the change in hydrodynamic regime under operational phase.

2.11.4.3   In consideration of the different reclamation methods, different reclamation approaches from dredging to non-dredging were investigated.  Dredging activities would churn up sedimentary materials and additional amount of fill materials would be required to fill the dredged trench, inducing larger water quality impacts.  Quantitative water quality modelling is conducted to assess the impacts induced by the dredging works.  The disposal of large amount of sediment generated would also cause significant waste management implications and secondary environmental impacts from the induced marine traffic (e.g.  air quality and marine ecological impacts).  Therefore, it is proposed that non-dredging method using DCM should be applied subject to engineering design. This method does not require additional filling of the dredged trench, which would minimise the filling activities and the associated water quality impacts.  Additionally, the amount of dredged sediment was reduced by approximately 32,840m3 by adopting DCM when comparing with the design scheme under the previous stage. This would minimise the waste management implications (e.g. disposal of dredged materials) and secondary environmental impacts from the marine traffic induced from the disposal of marine sediments. Based on current ground investigation, it is estimated that DCM would be applied to about 50% of the reclamation area subject to actual ground conditions as shown in Figure 6.1 and Figure 6.2.

2.11.4.4   Combined with the adoption of the VIPS, the total reclamation area in the current scheme (about 19.8 hectares) is reduced by about 4.1 hectares (17%) when compared with the original scheme in the Project Profile (about 23.9 hectares).

2.11.5        Minimisation of Slope Cutting

2.11.5.1   The Project alignment connects Route 11, North Lantau Highway, HKIW-NEL Link and then pass through hilly terrains in North Lantau to Tsing Yi. Measures in the alignment design to minimising slope cutting have been considered and adopted to minimising slope cutting, in order to (i) minimise disruption and impacts to the landscape resources and characters, (ii) minimise the number of trees impacted, (iii) minimise potential impacts to the natural habitats and the associated ecology and (iv) minimise the amount of excavation spoil and construction waste generated. Total generated C&D materials including slope cutting has been reduced by 42% comparing with the design scheme under the previous feasibility study stage of the Project. The reduction and recycling measures for C&D materials during the planning and design stages, as well as through layout optimisation and construction methods is to be considered.

2.11.5.2   The Recommended Alignment of Lantau landing point is shifted northwards, thus enabling the slope cutting location of the North Lantau Interchange to shift eastwards towards a lower terrain.  The modification of the alignment also minimises the substantial slope cutting along the northeast face of Fa Peng Teng. These design modifications substantially preserve the natural features of the area, reduce the volume of excavated materials as well as the associated construction dust impacts.

2.11.5.3   At the Tsing Yi Connection, with the omission of the TYRW-TYLL Viaduct, the length of retaining structures on existing geotechnical features (see also Section 2.11.2) is minimised as the need for clearance of land adjacent to Sai Tso Wan Road is no longer required. The anchorage of main bridge at Tsing Yi side has been further reviewed to avoid direct impact to the adjacent Cheung Tsing Highway structure by shift the anchorage westwards, allowing the anchorage sit at the toe of the existing slope.  This refinement not only substantially minimised the constructability difficulty on existing slope and avoid direct impact to the adjacent highway structure but also minimise the landscape and visual impact at Tsing Yi side.

2.11.6        Avoidance of Direct Impact to Ecological Sensitive Area

2.11.6.1   The recommended TYLL alignment and its associated works footprint were thoroughly considered, evaluated and selected from several alternative alignment options proposed in previous stage studies (S.2.7 refers).  This process has resulted in the current alignment option, which aims to avoid potential direct and indirect impacts on recognised sites of conservation importance and other ecologically sensitive areas, such as the Ma Wan Egretry and Night Roost located approximately 1.3 km north of the project boundaries.

2.11.7        Minimisation of Habitat Loss

2.11.7.1   The Recommended Alignment was tailored to minimise encroachment into natural habitats and ecological resources of high ecological importance, resulting in a final optimised layout that would result in no loss of any natural terrestrial habitats in Tsing Yi. However, a small area (approx. 0.005 ha) of the intertidal zone in Ma Wan South will be lost as a result of the proposed works. Due to engineering constraints posed by the site conditions and the inherent requirement to connect TYLL with other planned roads and highways, areas of natural terrestrial habitats in North Lantau, including shrubland / grassland, watercourse and intertidal zone, would be inevitably impacted. 

2.11.7.2   To minimise the extent of habitat loss and its impact on the ecology in this area, the proportion and extent of slope works, and at-grade roads were minimised and strategically positioned along existing developed area.  Some road sections in North Lantau have opted for tunnel or viaduct form to minimise the footprint of at-grade works and to avoid ecological impact, i.e. the viaduct section at Yi Chuen and tunnel connecting HKIW-NEL Link, which avoid impact on concerned watercourse.

2.11.8        Summary

2.11.8.1   Due consideration has been given above to address the environmental challenges encountered in the design of the Project.  Environmental protection will be prioritised and fulfilled to the greatest extent possible.  Various key actions have been implemented to address the environmental challenges and summarised in Table 2.6.


 

Table 2.6         Summary of Alternative Mitigation Measures

Alternative Mitigation Measures

Details

Environmental Benefits

Environmental / Engineering Disbenefits

Reduce and reuse inert C&D Materials

·  Minimise slope works in North Lantau and Tsing Yi to reduce generation of excavated soil and yard waste; and

·  On-site reuse of inert C&D materials like reclamation filling.

·  Reduce total amount of inert C&D materials for disposal; and

·  Minimise transporting of C&D materials to Public Fill Reception Facilities (PFRFs) thus reducing potential air quality and noise impacts arising from the transportation vehicles / vessels.

 

·  NIL

Encourage recycling of yard waste

·  Yard waste is encouraged to be sent to the Yard Waste Recycling Centre in Y-Park for recycling prior to disposal at the designated landfill site.

 

·  Generate new products from yard waste; and

·  Indirectly increasing the lifespan of existing landfill.

·  Yard waste might need to be stored on-site for a period; and

·  Increase in administration cost.

Adopting GPS or equivalent system

·  Tracking and monitoring of all dump trucks to prohibit illegal dumping and landfilling of C&D materials.

 

·  Prohibit illegal dumping.

 

·  NIL

Disposal / treatment methods for marine sediment

·  Adoption of DCM as a primary ground treatment method for reclamation.

·  Avoid the need for disposal of thick marine deposits; and

·  Reduce disposal and transportation of marine sediment.

·  Ineffective in areas with shallow depth of marine deposits;

·  May involve specialised equipment, materials, and expertise, leading to higher upfront costs compared to traditional dredging

Adopt pile-supported VIPS in the area of existing shoreline.

·  Avoidance of reclamation at North Lantau shoreline; and

·  Protect the deflection pier at North Lantau from vessel impact.

·  Reclamation is no longer required at North Lantau, which benefit the preservation of the intertidal zone and ecosystem along the shoreline; and

·  Alleviate the water pollution caused by the construction of reclamation land.

 

·  The VIPS and other pile-supported structures require ongoing maintenance to ensure their structural integrity, especially in a harsh marine environment.

Adoption of Eco-shoreline

·  Incorporation of eco-shoreline design in the future coastal structures such as seawalls on the reclaimed land as well as surfaces and supporting structures on the pile-supported VIPS; and

·  Incorporation of elements that diversify microhabitats and enhance the quality of settlement substrates.

·  Present new opportunities for the recruitment, settlement and colonisation of marine benthos, thereby enhancing the overall quality of associated marine ecosystems in the vicinity;

·  Encourage recruitment and settlement of corals and other benthos; and

·  Provide sheltering habitats for marine wildlife.

·  Increase in construction cost and maintenance cost.

 

2.12            Concurrent Projects

2.12.1.1   Concurrent projects in the vicinity of the Project site are identified.  The status of these concurrent projects is based on the available information obtained during the course of the EIA Study.   It should be noted that the implementation of individual project would be subject to further development and subsequent actions of the respective project proponent.

2.12.1.2   Two proposed projects, namely the Ma Wan South Development (MWSD) and development at Hongkong United Dockyards (HUD), were identified during the course of this EIA study. For MWSD, there is no concrete implementation programme nor approved rezoning proposal / planning application and associated design plan of these projects are available at the time of this EIA study. While rezoning applications are required for these projects, the current planning application for the HUD development (Application No. Y/TY/2) is still being processed under the Town Planning Ordinance at the time of this EIA study. Besides, the rezoning proposal for the MWSD has not commenced. On the above basis, the potential cumulative environmental impacts of these projects would be assessed qualitatively in this EIA study.

2.12.1.3   The project implementation, including construction and operation of the TYLL, will involve land resumption under prevailing mechanism before commencement of construction of the TYLL. The road scheme for the project will be gazetted under Roads (Works, Use and Compensation) Ordinance (Cap. 370) and the construction works will commence only after the road scheme has been authorised and the land resumption under Cap. 370.

2.12.1.4   A list of the tentative concurrent projects identified at the time of this EIA study is summarised in Table 2.7, while locations of these concurrent projects are indicated in Appendix 2.1.

2.12.1.5   Various cumulative impacts for different concurrent projects have been identified and detailed justification on consideration of various cumulative environmental impacts from individual concurrent project has been included in the corresponding technical assessment sections of this EIA report.


 Table 2.7   Summary of Potential Concurrent Projects

Concurrent Project

Description

Tentative Programme

Assessment of Potential Cumulative Environmental Impact

Start

Complete

Reference for Programme

Construction Phase

Operation Phase

Hong Kong Island West – Northeast Lantau Link

(HKIW-NEL Link)

 

The road project comprises land and subsea tunnels, land and marine viaducts, and at-grade roads.

Under Planning [1]

Under Planning [1]

Project Profile of the Concurrent Project [PP-635/2021]

Cumulative impacts were evaluated in this EIA report.

Cumulative impacts were evaluated in this EIA report.

Road P1 (Tai Ho- Sunny Bay Section)

The road project comprises land viaducts and tunnels, reclamation, and at-grade road.

2027

2031

Project Profile of the Concurrent Project [PP-615/2020]

Cumulative impacts were evaluated in this EIA report.

Cumulative impacts were evaluated in this EIA report.

Route 11 (section between Yuen Long and North Lantau)

Highway project connecting Yuen Long and North Lantau. 

2026

2033

EIA Report of the Concurrent Project [AEIAR-255/2023]

Cumulative impacts were evaluated in this EIA report.

Cumulative impacts were evaluated in this EIA report.

Underground quarrying contract at Tsing Yi North

An underground quarry in the form of cavern and access tunnel with ancillary operations 

2027

2028

N/A

 

 

 

 

Cumulative impacts were evaluated qualitatively in this EIA report.

 

Details of the development (including its emission sources) are not available during the preparation of this EIA study.  On this basis, the cumulative impact from the project (if any) would be considered in separate studies of the project by the respective project proponent.

Sunny Bay Development

Establish the reclamation and infrastructure works extent for future land use.

To be confirmed. (Note: As this project is under review, there is no concrete implementation schedule / construction programme.)

 

Cumulative impacts were evaluated qualitatively in this EIA report.

 

No concrete implementation programme nor approved rezoning proposal / planning application is available during the preparation of this EIA study.   On this basis, the cumulative impact from the project (if any) would be considered in separate studies of the project by the respective project proponent.

Private Housing Development in Ma Wan South

Housing development

To be confirmed. (Note: No concrete implementation programme nor approved rezoning proposal / planning application is available during the preparation of this EIA study.)

Cumulative impacts were evaluated qualitatively in this EIA report.

Cumulative impacts were evaluated qualitatively in this EIA report.

Hongkong United Dockyards (HUD) Development

Housing development

To be confirmed. (Note: No concrete implementation programme nor approved rezoning proposal / planning application is available during the preparation of this EIA study.)

Cumulative impacts were evaluated qualitatively in this EIA report.

Cumulative impacts were evaluated qualitatively in this EIA report.

Notes:

[1]           While the pace to take forward the HKIW-NEL Link had slowed down and the commencement of works would be further reviewed; the relevant road networks have been included in this EIA study for the sake of evaluating the cumulative impacts.

 

2.13            Documentation of Public Concerns

2.13.1.1   During the public inspection period of the Project Profile submitted for the Application of EIA Study Brief (No. ESB-359/2023) in June 2023, several public views and concerns on the Project were received.

2.13.1.2   The Project design has taken into consideration the public views and concerns, and mitigation measures have been recommended as appropriate to minimise potential environmental impacts.  The key views / concerns and the corresponding design considerations and follow up actions taken are summarised in Table 2.8.

Table 2.8 Summary of the Major Concerns and the Subsequent Actions Taken in Response

Key Concerns / Issues

Follow Up Actions Taken

Alignment, Footprint, Reclamation and Associated Facilities

Minimise the project footprint, including but not limited to the road corridor and slope works.

·       The Project's at-grade footprint has been minimised by adopting tunnel design for slip roads to avoid at-grade works near Tai Chuen in North Lantau.

 

·       Due considerations have been taken to minimise slope works in North Lantau and Tsing Yi.

Minimise the extent of reclamation while ensuring the incorporation of necessary eco-features.

·       The reclamation area at Ma Wan has been reduced by adopting a shared marine anchorage at Ma Wan.

 

·       No reclamation area at North Lantau is required due to the shifting of the deflection pier inland and adopting VIPS as bridge protection measures. 

 

·       Eco-features would be adopted at the shoreline where possible.

Concurrent Projects and Cumulative Impacts

HUD development and Ma Wan South Development (MWSD) have not been included as sensitive receivers

·    The rezoning application for the HUD development is still on-going and has not been approved, while the rezoning proposal for the MWSD has not yet commenced. There is no solid information on the implementation programme and approved associated design plan available for these projects.

 

·    Hence, these two projects are not considered as planned sensitive receivers.

 

·    Cumulative impacts from these projects have been considered qualitatively in the EIA report.

Air Quality

The project must comply with Air Quality Objectives (AQOs) at sensitive receivers to ensure acceptable air quality levels.

·    The Project will comply with the Air Quality Objectives (AQOs) at all air sensitive receivers within the assessment area.

Cumulative air quality impacts of the western territory (including Yuen Long, Tuen Mun, Tung Chung, Kwai Chung, Tsuen Wan, Centra/Western) shall be assessed.

·    Cumulative air quality impact from concurrent projects has been assessed in accordance with the EIA Study Brief.  The concerned areas mentioned are however outside the 500m assessment area.

The construction vehicles associated with the proposed Project should not be allowed to access to Lantau Island except the delineated works area directly required by the Project.

 

·    During construction, the haul roads should be paved and regularly wetted to suppress the fugitive dust emission.  Vehicles transporting dusty spoil would be properly covered with mechanical covers or tarpaulin sheets to avoid any dust pickup by gust during travel.

·    Construction vehicles will follow designated transportation routing to avoid use of any local roads, and the truck traffic should avoid peak hours, as far as practicable.  Dump trucks are equipped with water-tight container and mechanical cover, which would not cause fugitive dust emission on the open road. With the implementation of these design measures, it is anticipated that no adverse air quality impact would be caused by the transportation of spoils along the routes.

Noise

The noise criteria specified in the Technical Memorandum on Environmental Impact Assessment at sensitive receiver locations shall be complied with.

·    Noise criteria at all noise-sensitive receivers within the assessment area will be fulfilled.

Cumulative noise impacts shall be assessed.

·    Cumulative noise impacts from concurrent projects have been assessed in accordance with the EIA study brief.

Illegal Dumping

Effective measures to control the illegal dumping of Construction and Demolition (C&D) materials shall be applied.

·    All dump trucks should adopt GPS or equivalent system for tracking and monitoring of the travel routings to prohibit illegal dumping and landfilling of C&D materials.

Ecology and Fisheries

The ecological importance of North Lantau should be taken into account.

·    Through careful optimisation of the Project's footprint and adoption of tunnel and viaduct sections, the permanent loss of natural shrubland and grassland and the areas south of North Lantau Highway has been minimised.

·    Minimisation and optimisation of at-grade works, with tunnels and viaducts designed adopted, where feasible, especially at Yi Chuen, to reduce watercourse loss in W2 and W3.

 

·    Headwater preservation in W2 and replacing intersecting section with box culvert to retain waterflow will be implemented to reduce indirect impact on Romer’s Tree Frog.

 

·    Adoption of viaduct sections and adjustment of tunnel portal location at North Lantau to avoid direct encroachment on watercourse W3 that houses Caridina serrata, thereby reducing any potential impacts on this species. 

 

·    The Project has taken measures to avoid any direct impact on fauna species of conservation importance, such as the Romer's Tree Frog.

Impacts on Chinese White Dolphins (CWD), Brothers Marine Park and mariculture zones should be adequately assessed.

·     The project site is not a key habitat of CWD. The ecological impact assessment has covered an area of 500m as well as other areas likely to be impacted by which included Brothers Marine Park (which is located approx. 4km from the project site).

·    Fisheries impact assessment has been conducted according to the requirements of the EIA-SB. Ma Wan FCZ is the only fisheries sensitive receiver in the vicinity of the project which is located about 450m away from the project area. No WQ exceedance expected with deployment of silt curtains.

Landscape and Visual

To adopt adequate landscape and visual mitigation measures.

·     As stated in above, reclamation extent and slope extent are avoided or minimised subject to engineering design.

 

·    Landscape works are proposed at the reclamation area and affected slope features.

 

·    Aesthetical design on main bridges and viaducts to blend in with the surrounding environment.