TABLE OF CONTENTS

6     Waste Management ImplicationS.. 6-1

6.1      Introduction. 6-1

6.2      Environmental Legislation, Standards and Criteria. 6-1

6.3      Assessment Methodology. 6-4

6.4      Identification of Waste Management Implications. 6-5

6.5      Prediction and Evaluation of Waste Implications. 6-5

6.6      Mitigation of Adverse Environmental Impacts. 6-20

6.7      Evaluation of Residual Impacts. 6-28

6.8      Environmental Monitoring and Audit Requirements. 6-29

6.9      Conclusion. 6-29

 

List of Tables

Table 6.1         Other Relevant Documents and Information

Table 6.2         Tentative Programme for Management of C&D Materials

Table 6.3         Estimated Quantities of C&D Materials during Major Construction Activities

Table 6.4         Summary of Chemical Screening Results

Table 6.5         Estimated Quantities of Sediment under each Disposal Option

Table 6.6         Summary of General Refuse during Construction Phase

Table 6.7         Tentative Transportation Routings for Waste Disposal during Construction Phase

Table 6.8         Summary of Estimated Amount of Waste to be Generated and Handled during Construction Phase

Table 6.9         Tentative Transportation Routings for Waste Disposal during Operational Phase

Table 6.10       Summary of Estimated Amount of Waste to be Generated and Handled during Operational Phase

 

List of Figures

Figure 6.1        Proposed and As-built Sediment Sampling Locations (Sheet 1 of 2)

Figure 6.2        Proposed and As-built Sediment Sampling Locations (Sheet 2 of 2)

Figure 6.3        Potential Hot Spots for Floating Refuse Accumulation


List of Appendices

Appendix 6.1         Sediment Sampling and Testing Plan (SSTP) (Marine Section)

Appendix 6.2         Summary of Chemical Screening Results and Disposal Options

Appendix 6.3         Laboratory Analytical Report (Chemical Screening)

Appendix 6.4         Extract of Geotechnical Fieldwork and Laboratory Test Report under the Feasibility Review Study

Appendix 6.5         Summary of Laboratory Testing Results from Feasibility Review Study and the Determined Sediment Category / Disposal Option

Appendix 6.6         Details of Sediment Quantity Estimation

 


6                          Waste Management ImplicationS

6.1                    Introduction

6.1.1.1           This section identifies the types of wastes that are likely to be generated during the construction and operation of the Project and evaluates the potential environmental impacts that may result from the handling, transport and disposal of these wastes.

6.1.1.2           Mitigation measures and good site practices regarding waste handling, storage, collection and disposal have been recommended with reference to the criteria and guidelines as stated in the requirements given in Clause 3.4.7 and Appendix E of the EIA Study Brief (ESB-359/2023), as well as Annexes 7 and 15 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) and relevant waste legislation and guidelines.

6.2                    Environmental Legislation, Standards and Criteria

6.2.1               General

6.2.1.1           The criteria and guidelines for assessing waste management implications are outlined in Annexes 7 and 15 of the EIAO-TM, respectively.

6.2.1.2           The following legislation and guidelines also cover the handling, treatment and disposal of wastes in the Hong Kong Special Administrative Region (HKSAR):

l  Waste Disposal Ordinance (Cap. 354) and subsidiary regulations;

l  Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C);

l  Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N);

l  Land (Miscellaneous Provisions) Ordinance (Cap. 28);

l  Public Health and Municipal Services Ordinance (Cap. 132) – Public Cleansing and Prevention of Nuisances Regulation (Cap. 132 BK);

l  Dumping at Sea Ordinance (Cap. 466);

l  Paragraph 4.2.1 of Chapter 4 of the Project Administration Handbook for Civil Engineering Works (PAH) - Management of Dredged/Excavated Sediment; and

l  Works Bureau Technical Circular (WBTC) No. 12/2000 Fill Management

 

Waste Disposal Ordinance (Cap. 354)

6.2.1.3           The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes.  Construction waste is defined under Cap. 354N of the WDO as any substance, matter or thing that is generated and abandoned from construction works regardless of whether or not it has been processed or stockpiled before being abandoned, excluding sludge, screenings or any matter removed or generated from desludging, desilting or dredging works.  Under WDO, waste can be disposed of only at designated waste disposal facilities licensed by the Environmental Protection Department (EPD).

Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C)

6.2.1.4           Issued under the WDO, the Waste Disposal (Chemical Waste) (General) Regulation controls the possession, storage, collection, transport and disposal of chemical wastes.  EPD has also issued three guidelines (updated in 2022) detailing how the Contractor should comply with the regulations on chemical wastes, namely A Guide to the Chemical Waste Control Scheme, A Guide to the Registration of Chemical Waste Producers and Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N)

6.2.1.5           Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material.  Construction waste delivered to a sorting facility for disposal must contain more than 50% by weight of inert material, and construction waste delivered to a Public Fill Reception Facility (PFRF) for disposal must consist entirely of inert material.

Land (Miscellaneous Provisions) Ordinance (Cap. 28)

6.2.1.6           The inert portion of Construction and Demolition (C&D) materials (including rocks, soil, broken concrete, building debris etc.) may be taken to Public Fill Reception Facilities (PFRFs) operated by the Civil Engineering and Development Department (CEDD).  The Land (Miscellaneous Provisions) Ordinance requires that individuals or companies who deliver public fill to the PFRFs are required to obtain Dumping Licences.  The licences are issued by CEDD under delegated authority from the Director of Lands.

6.2.1.7           Individual licences and windscreen stickers are issued for each vehicle involved.  Under the licence conditions, public fill reception facilities will only accept soil, sand, rubble, brick, tile, rock, boulder, concrete, asphalt, masonry or used bentonite.  In addition, in accordance with paragraph 12 of the Development Bureau Technical Circular (Works) (DEVB TC(W)) No.6/2010, Public Fill Committee (PFC) will advise on the acceptance criteria.  The material will, however, be free from marine mud, household refuse, plastic, metal, industrial and chemical wastes, animal and vegetable matter and any other materials considered unsuitable by the PFRF supervisor.

Public Health and Municipal Services Ordinance – Public Cleansing and Prevention of Nuisances Regulation (Cap. 132BK)

6.2.1.8           The Public Cleansing and Prevention of Nuisances Regulation provides control on illegal dumping of wastes on unauthorised / unlicensed sites.  The illegal dumping of wastes can lead to a fine and/or imprisonment.

Dumping at Sea Ordinance (Cap. 466)

6.2.1.9           This Ordinance came into operation in April 1995 and empowers the Director of Environmental Protection (DEP) to control the disposal and dumping of substances and articles at sea for the protection of the marine environment.  Under the Ordinance, a dumping permit from the DEP is required for the disposal of regulated substances within and outside the waters of Hong Kong.  The permit contains terms and conditions which include the following specifications, but not limited to:

l  Type and quantity of substances permitted to be dumped;

l  Location of the disposal grounds;

l  Requirement of equipment for monitoring the disposal operations; and

l  Environmental monitoring requirements.

Paragraph 4.2.1 of Chapter 4 of the Project Administration Handbook for Civil Engineering Works (PAH) - Management of Dredged/Excavated Sediment

6.2.1.10        The paragraph 4.2.1 of Chapter 4 of the PAH is subsumed from Environment, Transport and Works Bureau Technical Circular (Works) (ETWB TC(W)) No. 34/2002 – Management of Dredged/Excavated Sediment.

6.2.1.11        Paragraph 4.2.1 of Chapter 4 of the PAH sets out the procedure for seeking approval to and the management framework for marine disposal of dredged / excavated sediment.  It outlines the requirements to be followed in assessing and classifying the sediment and explains the marine disposal arrangement for the classified material.  Based on paragraph 4.2.1 and Appendix 4.30 of the PAH, there are three types of disposal options for dredged/excavated sediments. 

l  Type 1 – Open Sea Disposal;

l  Type 2 – Confined Marine Disposal; and

l  Type 3 – Special Treatment/Disposal. 

 

6.2.1.12        For Type 3 disposal, the Project Proponent shall be responsible for identifying and agreeing with the DEP the most appropriate treatment and/or disposal arrangement.

Works Bureau Technical Circular (WBTC) No. 12/2000 - Fill Management

6.2.1.13        WBTC No. 12/2000 explains how fill resources, C&D material, and dredged / excavated sediment disposal are managed.

6.2.2               Other Relevant Environmental Guidelines

6.2.2.1           Other relevant circulars / guidelines are applicable to waste management practices for the Project are tabulated in Table 6.1.

Table 6.1      Other Relevant Documents and Information

Bureau / Development

Documents / Guidelines / Technical Circulars

Development Bureau

·       WBTC No. 2/93 - Public Dumps

·       WBTC No. 2/93B - Public Filling Facilities

·       WBTC No. 12/2000 - Fill Management

·       WBTC No. 16/96 - Wet Soil in Public Dumps

·       WBTC Nos. 4/98 and 4/98A - Use of Public Fill in Reclamation and Earth Filling Projects

·       WBTC No. 19/2001 - Metallic Site Hoardings and Signboards

·       WBTC No. 12/2002 - Specifications Facilitating the Use of Recycled Aggregates

·       ETWB TC(W) No. 19/2005 - Environmental Management on Construction Sites

·       Development Bureau Technical Circular (Works) (DEVB TC(W)) No. 06/2010 - Trip Ticket System for Disposal of Construction and Demolition Materials

·       DEVB TC(W) No. 08/2010 - Enhanced Specification for Site Cleanliness and Tidiness

·       DEVB TC(W) No. 09/2011 - Enhanced Control Measures for Management of Public Fill

CEDD

·       Section 4.1.3 of Chapter 4 of the PAH for Civil Engineering Works, Management of Construction/Demolition Materials including Rock

EPD

·       A Guide to the Chemical Waste Control Scheme

·       A Guide to the Registration of Chemical Waste Producers

·       Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes

 

6.3                    Assessment Methodology

6.3.1.1           The assessment of waste management impacts arising from the construction and operational activities of the Project has been undertaken in accordance with the EIA Study Brief and criteria given in Annexes 7 and 15 of the EIAO-TM, including the following tasks:

l  Identification of the construction and operation activities of the Project which could give rise to waste;

l  Estimation of types and quantities of waste generated;

l  Examination of opportunities for waste reduction and re-use (both on-site and off-site) and the required disposal options for each type of waste; and

l  Evaluation of potential impacts caused by improper handling, collection, transportation and re-use / disposal of wastes with respect to potential hazards, air and odour emissions, noise, wastewater discharges and public transport.

6.3.1.2           Prior to considering the disposal options for various types of waste, opportunities for reducing waste generation, on-site or off-site reuse and recycling have been evaluated.  Measures which can be taken in the planning and design phases (e.g. by modifying the design approach), and in the construction phases for maximising waste reduction have been separately considered.  Practices to promote segregation of waste materials are additionally considered for advancing the waste management efficiency.

6.3.1.3           After considering all the opportunities for reducing waste generation and maximising reuse, the types and quantities of the waste required to be disposed of have been estimated and the disposal options for each type of waste have been described.  The disposal method recommended for each type of waste has taken into account the results of the assessment.  The impacts caused by handling (including stockpiling, labelling, packaging and storage), collection, transportation and reuse / disposal of waste have been addressed and appropriate mitigation measures have been proposed.

6.4                    Identification of Waste Management Implications

6.4.1               Construction Phase

6.4.1.1           Potential waste mainly generated from the construction works of the Project.  The construction activities to be carried out for the Project mainly include site clearance, slope works, demolition / removal of existing facilities, excavation, piling works, tunnelling (e.g. drill-and-blast), road works and pavement, dredging of sediments, etc.  The types of waste associated with these construction activities include:

l  C&D materials;

l  Sediments;

l  Chemical waste;

l  General refuse; and

l  Floating refuse.

 

6.4.2               Operational Phase

6.4.2.1           Minor chemical waste during maintenance activities, and floating refuse at artificial seawall are expected to be generated during the operation of the Project.  Since no administration building would be constructed under the Project, no general refuse would be generated during operation phase.

6.5                    Prediction and Evaluation of Waste Implications

6.5.1               Construction Phase

Construction and demolition (C&D) materials

6.5.1.1           C&D materials would be generated from construction works of the Project mainly from site clearance, excavation / foundation works, piling works, demolition of existing structures, earthworks and slope works, tunnelling and construction works.  The C&D materials would comprise both inert C&D materials (e.g. soil, rock and concrete, etc.) and non-inert C&D materials (e.g. vegetation, timber, paper, etc.).  The non-inert C&D materials would be reused and recycled before disposal to landfill.  Yard waste would be sent to the Yard Waste Recycling Centre in Y-Park for recycling prior to disposal at the designated landfill site.  Given that a certain amount of yard waste is anticipated arising from the construction activities of the Project, it should be required to be handled in accordance with the principles of reduce, reuse, and recycle (3Rs).  The following guidelines have to be taken into account when handling yard waste:

l  Relevant guidelines posted by EPD through EPD’s website (https://www.epd.gov.hk/epd/english/environmentinhk/waste/manage_facility/ypark.html) and Y Park’s website (https://www.ypark.hk/zh-hant/)

l  "Guidelines on Yard Waste Reduction and Treatment" issued by Development Bureau

l  "Development Bureau Technical Circular (Works) No. 4/2020 Tree Preservation"

6.5.1.2           During general layout design, devising construction method described in Section 2 and planning of construction programme, considerations have been given to minimise the generation of inert C&D materials and maximise the use of generated inert C&D materials for other construction works.

6.5.1.3           Based on the current latest design information, it was estimated that the total quantity of C&D materials generated would be approximately 2,366,500 m3 (2,227,500 m3 of inert materials and 139,000 m3 of non-inert materials) which will be generated during construction phase of the Project.  The major construction activities that generate C&D materials would be carried out from Year 2027 to Year 2029.  It should be noted that these quantities are initial estimates only and would need to be further reviewed and updated as the design progresses. Table 6.2 below shows the tentative programme for disposal of C&D materials and import fill required.

Table 6.2       Tentative Programme for Management of C&D Materials

Period

Estimated Quantities (m3) [1][2]

Disposal of Non-inert C&D Materials, m3

Inert C&D Materials, m3

Total Generated Inert C&D Materials

On-site reuse

 Delivered to PFRF

Import

Soft Public Fill

Rock Public Fill

Soft Public Fill

Rock Public Fill

2027

116,600 *

1,126,094

1,126,094

-

-

120,626

80,418

2028

22,400

799,059

647,886

30,235

120,939

308,506

205,670

2029 [3]

-

302,347

-

60,469 *

241,877 *

-

-

2030 to 2033 [3] [4]

-

-

-

-

-

-

-

Sub-Total

139,000

2,227,500

1,773,980

90,704

362,816

429,132

286,088

Total

139,000

2,227,500

1,773,980

453,520

715,220

Note:

[1]       The bulk factor 1.4 has been applied.

[2]          Figures in Table 6.2 may not sum exactly to totals due to rounding.

[3]          Estimated only small amount of non-inert C&D materials would be generated during 2029 to 2033 subject to actual site conditions.

[4]          No major construction works would generate inert C&D materials starting from Year 2030 and most of the inert C&D materials would be re-use and recycled subject to actual site conditions.

*        The peak periods for non-inert C&D materials and inert C&D materials sent off-site.

6.5.1.4           The inert C&D materials should be reused on-site, subject to the review at detailed design stage, before delivered to PFRF (such as Tuen Mun Area 38 Fill Bank, subject to the designation from the PFC) for beneficial use in other projects with potential fill demand. Referring to Table 6.2, the estimated amount of inert C&D materials generated during the construction phase would be around 2,227,500 m3, of which around 453,520 m3 is expected to deliver to PFRF and around 1,773,980 m3 is expected to be reused on-site as backfill material. As estimated, the generated inert C&D materials would not be sufficient for reclamation works until 2028. Therefore, importing of inert C&D materials from public fill is required. After completion of reclamation works, all generated inert C&D materials would be delivered to PFRF in 2029 according to Table 6.2.

6.5.1.5           For non-inert C&D materials, they are mainly generated from the site clearance and removal of vegetation prior to the site formation works, upon exhaustion of reuse / recycle effort, they would be disposed of at landfill. As shown in Table 6.2, the amount of non-inert materials generated during the construction phase is expected to be around 139,000 m3.  It is the Contractor’s responsibility to separate the inert and non-inert C&D materials on-site.  A stockpiling area should be assigned to facilitate the sorting of inert and non-inert C&D materials and store the inert C&D materials for subsequent backfilling.  Limited spatial area is available within the site boundary and subject to actual on-site conditions, land required for stockpile area would be minimised.

6.5.1.6           A summary of the estimated quantities of C&D materials generated from the site clearance, excavation / foundation works, tunnelling, slope works and other  construction activities together with the estimated volumes of C&D material to be disposed of at the public filling area designated by CEDD and at landfill during construction phase are presented in Table 6.3.

Table 6.3       Estimated Quantities of C&D Materials during Major Construction Activities

Handling of C&D Material

Estimated Amount of C&D Materials to be Generated (m3)

(with Bulk Volume) [1]

Total C&D Materials (m3)

 [1]

Inert C&D Materials

Non-inert C&D Materials

Reuse on-site

1,773,980

-

1,773,980

Deliver to PFRFs / Reuse in other Concurrent Projects

453,520

 

-

453,520

 

Disposal at Landfills

-

139,000

139,000

Total C&D Materials

2,227,500

139,000

2,366,500

Note: 

[1]       The bulk factor 1.4 has been applied.

 

6.5.1.7           A Construction and Demolition Material Management Plan (C&DMMP) would be prepared in accordance with Section 4.1.3 of the PAH and submitted to PFC for approval.  With the implementation of proper management for C&D materials and good site practices, no unacceptable environmental impacts (including potential hazard, air and odour emissions, noise, wastewater discharges and ecology) and public transport impact caused by handling, collection, transportation and reuse / disposal of C&D materials arising from the Project would be anticipated.

Sediment

6.5.1.8           Sediment would be generated mainly from reclamation works as well as piling and excavation works for construction of towers and anchorages after reclamation at/near Tsing Yi, Ma Wan and Kap Shui Mun.  Based on the latest construction methods as detailed in Section 2, both dredged and non-dredged methods would be adopted for the reclamation works. The evaluation of the minimisation of dredging extent can be referenced in S2.9.3 and S2.11.4.

Review of Existing Sediment Quality Data

6.5.1.9           EPD conducts routine monitoring of the marine sediment quality across the territory of Hong Kong waters.  The nearest EPD’s sediment monitoring station is Tsing Yi South (WS1) located within the Western Buffer Water Control Zone.  The latest available sediment quality data (from 2019 to 2023) are summarised in the Annual Marine Water Quality Report 2023 published by EPD. 

6.5.1.10        Based on the EPD’s annual report, except for copper and zinc, all the levels of metals, organic-PAHs and non-organic PAHs were not exceeding the LCEL. For copper, the highest level measured (78 mg/kg) was above the corresponding LCEL but not exceeding the UCEL. For zinc, the highest level measured (300 mg/kg) was above the corresponding UCEL but not exceeding 10 times the LCEL.

Sediment Sampling and Testing Plan (SSTP)

6.5.1.11        In order to characterise the proposed excavated/dredged sediment for marine disposal option and pursuant to Clause 3 in Appendix E of the EIA Study Brief, a Sediment Sampling and Testing Plan (SSTP) (Marine Section) was prepared with reference to Paragraph 4.2.1 of Chapter 4 of the PAH and was agreed by EPD on 26 March 2024.  The SSTP details the ranges of parameters to be analysed; the number, type and methods of sampling; sample preservation; chemical and biological laboratory test methods to be used.  The agreed SSTP is enclosed in Appendix 6.1.  It should be noted that the SSTP and the related sediment sampling and testing would only serve the purpose for fulfilling the EIA Study of the Project.  To fulfil the requirements under the Dumping at Sea Ordinance (DASO), separate SSTP and additional ground investigation (GI) works may need to be carried out at a later stage of the Project.

6.5.1.12        As proposed in the agreed SSTP under the EIA Study, a volume-based approach with reference to Appendix 4.21 of the PAH was adopted to determine the number of sampling locations.  Based on the adopted sampling arrangement, a total of 39 marine-based sampling locations were proposed within the possible reclamation areas and tentative excavation/dredging extent for sediment sampling and testing (i.e. Tier II chemical and Tier III biological screenings) under the PAH. The proposed sampling locations, sampling grids, possible reclamation areas, tentative excavation / dredging extent are shown in Figure 5.1.1 and 5.1.2 in Appendix 6.1.

Sediment Sampling and Testing Works

6.5.1.13        Ground Investigation (GI) works was conducted between February and March 2024 and in April 2025 according to the agreed SSTP.  The sampling works were conducted by Fugro Geotechnical Services Limited.  The laboratory testing was carried out by Fugro Technical Services Limited, an HOKLAS accredited laboratory.

6.5.1.14        The sediment sampling locations were conducted taken into consideration the site constraints (e.g. restricted access due to shallow water depth and opposition of private owner of nearby land lots).  Apart from VC-32, all as-built sampling locations were still within the corresponding sampling grid and are shown in Figure 6.1 and Figure 6.2.

6.5.1.15        The sediment sampling was carried out by means of grab sampling at the seabed level and the vibrocoring method for the vertical sediment profiles below.  Undisturbed samples using vibrocore were collected from seabed surface, 0.9 m down, 1.9 m down, 2.9 m down and thereafter every 3 m down to the proposed termination depth.  The sediment sampling was terminated at least 1 m below the base of sediment layer, subject to site condition.

6.5.1.16        As biological screening is not required (refer to Section 6.5.1.23 below), no reference grab sediment sample was collected from EPD’s routine sediment monitoring station PS6 at Port Shelter (850234E, 820057N).

6.5.1.17        Of the proposed sampling locations near Ma Wan, no sediment excavation / dredging works are expected within the sampling grid of VC-25 (refer to Figure 6.1).  As such, VC-25 would not be assessed under this assessment.  For sampling locations VC-06, VC-09 and VC-11, due to proximity to the shore and shallow water depth, access of sampling vessels to the areas were not possible. Therefore, no sampling works were carried out for VC-06, VC-09 and VC-11 (refer to Figure 6.1).

6.5.1.18        Of the 11 sampling locations near Tsing Yi, sampling works at 7 sampling locations (i.e. VC-32 to VC-35, VC-37, VC-38 and VC-58) were opposed by the private owner of nearby land lots due to the possible adverse impact to its operations. Thus, no sampling works for the 7 sampling locations were possible. For VC-32, a sampling attempt was carried out approximately 20 m west of the proposed sampling grid but no sediment was encountered.  For the remaining 4 sampling locations (viz. VC-36, VC-55, VC-56 and VC-57), as requested by the private owner of nearby land lots to minimise impact to its operations, the sampling locations (viz. VC-36, VC-55A, VC-56A/VC-56B (for VC-56) and VC-57A) were relocated but were still well within the corresponding sampling grids. Two sampling attempts were made for VC-56 (i.e. VC-56A/VC-56B) but no sediments were encountered.  The proposed and as-built sampling locations near Tsing Yi are shown in Figure 6.2.

6.5.1.19        Based on the above, sampling was conducted at 30 marine-based sampling locations (24 near Ma Wan and 6 near Tsing Yi (including 2 sampling attempts for VC-56 (VC-56A/VC-56B) and a sampling attempt for VC-32 (approximately 20 m west of the proposed sampling grid). Nine (9) of the 30 sampling locations (viz. VC-12, VC-23, VC-32 (approximately 20 m west of the proposed sampling grid), VC-45, VC-49, VC-52, VC-55A, VC-56A and VC-56B; refer to Figure 6.1 and Figure 6.2) did not encounter sediment and as such, no sediment samples were collected and tested from these locations.  

6.5.1.20        Following the above, 59 sediment samples were collected from the remaining 21 sampling locations for laboratory testing. The relevant sampling locations are listed below.

 

·        VC-05

·        VC-13

·        VC-16

·        VC-17

·        VC-18

·        VC-24

·        VC-26

·        VC-27

·        VC-28

·        VC-29

·        VC-30

·        VC-31

·        VC-36

·        VC-46

·        VC-47

·        VC-48

·        VC-50

·        VC-51

·        VC-53

·        VC-54

·        VC-57A

 

 

6.5.1.21        The collected sediment samples were tested for chemical screening with parameters as stated in paragraph 4.2.1 of Chapter 4 of the PAH.  The chemical screening results are summarised in Table 6.4 with details provided in Appendix 6.2.  Laboratory analytical reports for chemical screening are provided in Appendix 6.3.

6.5.1.22        Based on the chemical screening results, Category M sediment was found in 4 samples at sampling locations VC-46 and VC-57A, with silver, zinc, copper and/or mercury levels above the corresponding LCEL but not exceeding the UCEL. The remaining samples were identified as Category L sediment. 


 

Table 6.4       Summary of Chemical Screening Results

Sediment Category

No. of Samples

Percentage

Category L (equal to or not exceeding LCEL)

55

93.2%

Category M (above LCEL but equal to or not exceeding UCEL)

4

6.8%

Category H (above UCEL but equal to or not exceeding 10x LCEL)

0

0%

Category H (above 10x LCEL)

0

0%

Total:

59

100%

 

6.5.1.23        Based on the chemical screening results and according to paragraph 4.2.1 of Chapter 4 of the PAH, no biological screening is required.

Sediment Disposal Options and Quantities

6.5.1.24        Based on the screening results and the above findings, the disposal options for each of the sediment samples were determined in accordance with paragraph 4.2.1 of Chapter 4 of the PAH.  The sediment quantities to be generated under each disposal option were then estimated with consideration of (i) the reclamation works as well as piling and excavation works for construction of towers and anchorages after reclamation at/near Tsing Yi, Ma Wan and Kap Shui Mun, (ii) the depths and thicknesses of the underlying sediment based on the sediment sampling works and (iii) the determined disposal options of the sediment samples as based on the chemical screening results.

6.5.1.25        As discussed in Section 6.5.1.17, no samples were able to be collected from the sampling grids of VC-06, VC-09 and VC-11 near Ma Wan.  In order to categorise the possible sediment within the sampling grids of VC-06 and VC-09, the results from adjacent VC-05 and VC-16 (both as Category L / Type 1 – Open Sea Disposal) were adopted for the respective sampling grids.  For VC-11, as no sediment was encountered in its nearest sampling location (VC-45), it is assumed that no sediment is present within the grid of VC-11.

6.5.1.26        Referring to Section 6.5.1.18, due to opposition of private owner of nearby land lots, no sampling works were carried out for 7 sampling locations near Tsing Yi (i.e. VC-32 to VC-35, VC-37, VC-38 and VC-58). For VC-32, as no sediment was encountered in the sampling attempt approximately 20 m west of the proposed sampling grid, it is assumed that no sediment is present within the grid of VC-32.

6.5.1.27        For the remaining 6 sampling locations near Tsing Yi (i.e. VC-33 to VC-35, VC-37, VC-38 and VC-58), references were made to the findings of the Geotechnical Fieldwork and Laboratory Test Report prepared under the Feasibility Review Study (Contract No. HY/2021/22 Tsing Yi – Lantau Link – Ground Investigation).  Extract of the report is shown in Appendix 6.4.  Based on the report, environmental GI works were conducted in 2022 and a total of 10 vibrocore sediment samples were collected at 2 sampling locations (VC01 and VC02) as shown in Figure 6.2.  According to the laboratory test reports and with reference to the sediment quality criteria in Appendix 4.28 of PAH, all the collected sediment samples were classified as Category L / Type 1 – Open Sea Disposal.  The laboratory testing results from the Feasibility Review Study and the determined category / disposal option are summarised in Appendix 6.5.

6.5.1.28        Based on the testing results from this EIA study (i.e. from VC-36 and VC-57A) and the above Feasibility Review Study, only Category L / Type 1 – Open Sea Disposal and Category M / Type 2 - Confined Marine Disposal sediments were identified near Tsing Yi.  Nevertheless, considering the past and present land uses in the area (e.g. former floating dock, dockyard and concrete batching plant), it is assumed that all sediment within the 6 inaccessible sampling grids (i.e. VC-33 to VC-35, VC-37, VC-38 and VC-58) are contaminated Category H / Type 2 – Confined Marine Disposal sediment as a conservative approach.

6.5.1.29        In addition, as discussed in Section 6.5.1.19, as no sediment was encountered at VC-12, VC-23, VC-45, VC-49, VC-52, VC-55A, VC-56A and VC-56B, it is assumed that no sediment would be excavated/dredged within the respective sampling grids.

6.5.1.30        According to the tentative construction programme, sediment due to reclamation works would be generated in Q2 of 2027 to Q1 of 2028.  Based on current estimation, the quantities for each disposal type are presented in Table 6.5. Detailed calculations of excavated / dredged sediment quantities and assumptions are presented in Appendix 6.6.  To minimise sediment disposal, it is proposed to on-site reuse the Category L sediment generated (e.g. as backfilling materials), subject to site condition and engineering design.  Beneficial reuse would be considered during the detailed design and construction stages before the disposal of excavated / dredged sediment.

Table 6.5       Estimated Quantities of Sediment under each Disposal Option

Disposal Option

Corresponding Category

Estimated In-situ Quantity [1] [2] (m3)

Type 1 – Open Sea Disposal

Category L Sediment

140,279

Type 2 – Confined Marine Disposal at disposal site(s) allocated by Marine Fill Committee (MFC)

Category M Sediment

8,986

Category H Sediment (equal to or not exceeding 10x LCEL)

47,220

Total

196,485

Notes:

[1]     The quantities shown in the table are estimates based on the finalized sediment excavated / dredging extent for the reclamation works and bridge towers and anchorages construction.  To minimise sediment disposal, it is proposed to on-site reuse the Category L sediment generated (e.g. as backfilling materials), subject to site condition and engineer design. Beneficial reuse would be considered during the detailed design and construction stages before the disposal of excavated / dredged sediment.

[2]     The estimated quantities included marine deposit and excluded other materials such as fill and alluvium.

 

6.5.1.31        Surplus sediment that are not reused within the reclamation area would be disposed of at the designated marine disposal areas according to paragraph 4.2.1 of Chapter 4 of the PAH.  The disposal options for the excavated / dredged sediment should follow the procedures in paragraph 4.2.1 of the PAH.  The transportation routing and frequency for marine disposal to designated disposal outlets shall be agreed with EPD / HyD during the construction phase prior to marine disposal.  The recommended mitigation measures for marine disposal are discussed in Section 6.6. No adverse waste management implications and environmental impacts (including potential hazard, air and odour emissions, noise, wastewater discharge and ecology) are anticipated if the recommended mitigation measures are implemented.

Chemical Waste

6.5.1.32        The maintenance and servicing of construction plant, equipment and vehicles involve the use of a variety of chemicals and generate chemical wastes.  The possible chemical waste that would be generated during the course of construction works includes:

l  Oil and grease associated with plant maintenance;

l  Spent hydraulic fluid from plant machinery;

l  Scrap batteries from vehicle maintenance; and

l  Used paint, cleaners, solvents used in maintaining mechanical equipment.

6.5.1.33        It is difficult to quantify the amount of chemical waste that would arise from the construction activities as it would be highly dependent on the Contractor’s on-site maintenance activities and the quantity of plant and equipment utilised.  It is anticipated that the quantity of chemical waste, such as lubrication oil and solvent produced from plant maintenance, would be small (in the order of few hundred litres per month).  The amount of chemical waste to be generated would be quantified in the Waste Management Plan (WMP) to be prepared by the Contractor.  The disposal of chemical waste by licensed collector is expected to require maximum 1 trip per day for transporting the chemical waste.  With the implementation of measures recommended in Section 6.6, no adverse environmental impacts and public transport impact associated with handling, collection, transportation, and disposal of chemical waste is expected.

6.5.1.34        Materials classified as chemical waste shall require special handling and storage arrangements by the Contractor.  All chemical waste shall be collected by a licensed collector and be disposed of at a licensed chemical waste treatment and disposal facility such as Chemical Waste Treatment Centre (CWTC) at Tsing Yi via the tentative transportation routing as presented in Table 6.7.  Unused chemical or those with remaining functional capacity would be reused and recycled on-site or by licensed companies.  Mitigation and control requirements for chemical wastes are detailed in Section 6.6.  Provided that the handling, storage and disposal of chemical wastes are in accordance with these requirements and that stipulated in the Waste Disposal (Chemical Waste) (General) Regulations and the Code of Practice on Packaging, Labelling and Storage of Chemical Wastes published by EPD, adverse environmental impacts (including potential hazard, air and odour emissions, noise, wastewater discharge and ecology) and public transport impact would be negligible.

General Refuse

6.5.1.35        General refuse comprises general site wastes, such as packaging and container waste from materials and equipment used on the site, and refuse generated by workforce during the construction phase of the Project.  Improper collection and removal of general refuse would give rise to hygiene problems and adverse environmental impacts, e.g. odour impacts, and contamination of the nearby marine waters if being blown away by wind, flushed or leached into the sea.

6.5.1.36        The number of workforces to be employed for the Project is not available at this stage, but it is anticipated that the maximum number of construction workers to be working on-site at any one time to be about 260.  Based on a generation rate of 0.65 kg per worker per day, the daily arising of general refuse during the construction period would be about 169 kg/day.  The estimated amount of general refuse generated during construction phase is summarised in  Table 6.6.

 Table 6.6    Summary of General Refuse during Construction Phase

Phasing

Period

Approximate no. of workforce

Daily waste generation

(kg/day) [1]

Duration

(Month)

Approximate total amount generated

(tonnes) [2]

Site formation/ Earthworks

Q1/2027 – Q4/2028

260

169

24

105.5

Construction Works

Q4/2028 – Q4/2033

260

169

60

263.6

Notes:

[1]     Adopt generation rate of 0.65 kg/person /day

[2]     Assume 26 working days per month

 

6.5.1.37        The general refuse will be collected on-site on a daily basis, separately from C&D materials by an appropriate waste collector to be employed by the Contractor.  The general refuse would be disposed of at strategic landfill, e.g. West New Territories (WENT) Landfill.  Prior to disposal off-site, such refuse will be temporarily put in suitably covered storage areas / bins where they will have to be regularly cleaned and maintained to avoid attracting vermin and pests.  With proper on-site handling and storage as well as regular disposal of the waste, no unacceptable environmental impact (including potential hazard, air and odour emissions, noise and wastewater discharges) or public transport impact would be anticipated.  Recommendations of mitigation measures for managing general refuse are presented in Section 6.6.1.24.

Floating Refuse

6.5.1.38        Floating refuse tends to accumulate near the coastline as shoreline refuse as they will be drifted by wind and tide, especially in summer months following heavy rains and typhoons.  Floating refuse may be accumulated in the newly constructed seawall during the construction phase.  Referring to the approved Tung Chung New Town Extension EIA Report (EIAO Register No.: AEIAR-196/2016), it was estimated that approximately 11.5 m3 of floating refuse would be collected from its 3.4 km long newly constructed artificial seawall.  Considering the total length of artificial seawall of this Project is approximately 1.48 km long, it is estimated that approximately 5 m3 of floating refuse will be collected from the newly constructed seawall during each year of construction. 

6.5.1.39        Floating refuse (i.e., food scraps, plastics, waste paper and empty containers, etc.) may also be generated by the construction workforce unintentionally while working along the coastline.  Proper waste management and training to workers, such as avoiding placing waste collection bins close to the sea and ensuring construction materials are well covered to prevent occurrence of wind-blown light materials should be considered.  Additionally, accidental losses of construction materials and wastes when transporting to and from the designated sites might occur.  Nevertheless, the amount of floating refuse generated from the Project under these events is expected to be limited.

6.5.1.40        During the construction phase, the Contractor will be responsible for the collection of any refuse within the works area.  Figure 6.3 shows the potential hot spots of floating refuse accumulation. In case floating refuse is identified, the right boat and tools to be used for cleanup depend on the floating refuse, as well as the locations. The floating refuse shall be removed, stored and disposed of together with the general refuse for disposal as detailed in Section 6.5.1.37, after separating the recyclables for recycling.  With implementation of proper refuse collection practice and the mitigation measures as detailed in Section 6.6, no adverse environmental impact (including potential hazard, air and odour emissions, noise, wastewater discharge and ecology) with regard to floating refuse would be anticipated during construction phase, or after completion of the Project.

Transportation Arrangement for Waste Disposal during Construction Phase

6.5.1.41        Stockpiling areas and barging point facilities would be set up at both Tsing Yi and North Lantau to handle waste generated during construction phase. The C&D materials will be reused or recycled on-site, and any surplus would be timely transported out of construction works area to barging points for further handling.   Subject to actual on-site condition, details will be reviewed in design stage. The locations of stockpiling areas and barging points are shown in Figure 6.3.

6.5.1.42        For transportation routing and frequency of trucks / vessels for waste disposal, the Contractor will be requested to use the suitable route to transport waste generated from the Project to the dedicated treatment facilities/disposal sites for disposal. The transportation routings may change subject to the actual road / marine traffic conditions.  Nevertheless, with the implementation of appropriate mitigation measures (e.g. using water-tight containers and covered trucks), no adverse environmental impacts are expected due to the transportation of waste. The tentative transportation route is summarised in Table 6.7

Table 6.7      Tentative Transportation Routings for Waste Disposal during Construction Phase

Treatment Facility / Disposal Site / Transfer Point

Type of Waste

Tentative Transporting Routing

Maximum Frequency of Trip for the Identified Waste Types

[2] [3] [4] [5]

Barging Points

(as a transfer point of marine route)

Inert C&D Materials, Non-inert C&D Materials, General Refuse and Floating Refuse

From Tsing Yi Area

Land Route

Via Tsing Sha Highway to Tsing Yi barging point

 

Inert C&D Materials

Land Route:

149 trips / day

 

Non-inert C&D Materials, General Refuse and Floating Refuse

Land Route:

58 trips / day

From Lantau Area

Land Route

Via Lantau Link to Lantau barging point

PFRFs (such as Tuen Mun Area 38 Fill Bank) and reuse in concurrent projects

Inert C&D Materials

From Tsing Yi Barging Point

Marine Route:

-        Via Ma Wan Fairway to Ha Pang Fairway to Castle Peak Fairway to Tuen Mun Area 38 Fill Bank

 

-        Via Ma Wan Fairway to other concurrent projects

Inert C&D Materials

Marine Route:

1 trip / day

 

From Lantau Barging Point

Marine Route:

-        Via Kap Shui Mun Fairway to Ha Pang Fairway to Castle Peak Fairway to Tuen Mun Area 38 Fill Bank

 

-        Via Kap Shui Mun Fairway to other concurrent projects

From Tsing Yi Area

Land Route:

-        Via Lantau Link, North Lantau Highway, Tuen Mun-Chek Lap Kok Link and Lung Mun Road to Tuen Mun Area 38 Fill Bank

 

-        Via Lantau Link to other concurrent projects

Inert C&D Materials

Land Route:

149 trips / day

 

From Lantau Area

Land Route:

-        Via North Lantau Highway, Tuen Mun-Chek Lap Kok Link and Lung Mun Road to Tuen Mun Area 38 Fill Bank

 

-        Via North Lantau Highway to other concurrent projects

WENT Landfill

Non-inert C&D Materials, General Refuse and Floating Refuse

From Tsing Yi Barging Point

Marine Route

Via Ma Wan Fairway to Ha Pang Fairway to Castle Peak Fairway to Urmston Road Fairway to WENT Landfill

Non-inert C&D Materials and General Refuse

Floating Refuse

 

Marine Route:

1 trip / day

 

Land Route:

58 trips / day

 

 

From Lantau Barging Point

Marine Route

Via Kap Shui Mun Fairway to Ha Pang Fairway to Castle Peak Fairway to Urmston Road Fairway to WENT Landfill

From Tsing Yi Area

Land Route:

Via Lantau Link, North Lantau Highway, Tuen Mun-Chek Lap Kok Link, Lung Mun Road, Lung Kwu Tan and Nim Wan Road to WENT Landfill

From Lantau Area

Land Route:

Via North Lantau Highway, Tuen Mun-Chek Lap Kok Link, Lung Mun Road, Lung Kwu Tan and Nim Wan Road to WENT Landfill

Type 1 - Open Sea Disposal at marine disposal site(s) allocated by MFC (Typically South Cheung Chau and East of Ninepin) [1]

Category L Sediment [6]

From Reclamation Sites

Marine Route:

-        Via Ma Wan Fairway/Kap Shui Mun Fairway, Western Fairway, West Lamma Fairway and South Shek Kwu Chau Fairway (for South Cheung Chau);

 

-        Via Ma Wan Fairway/Kap Shui Mun Fairway, Western Fairway, East Lamma Channel, south of Hong Kong Island and Tathong Channel (for East of Ninepin)

Category L Sediment

Marine Route:

1 trip / day   

Type 2 - Confined Marine Disposal at marine disposal site(s) allocated by MFC
(Typically East Sha Chau) [1]

Category M Sediment and Category H Sediment (equal to or not exceeding 10x LCEL) [6]

From Reclamation Sites

Marine Route:

-        Via Ma Wan Fairway/Kap Shui Mun Fairway, Ha Pang Fairway and Castle Peak Fairway (for East Sha Chau)

 

Category M Sediment and Category H Sediment (equal to or not exceeding 10x LCEL)

Marine Route:

1 trip/ day

 

CWTC

Chemical Waste

Tsing Yi Section

Land Route:

-        Via Tsing Sha Highway and Tsing Yi Road to CWTC

Chemical Waste

Land Route:

1 trip / day

 

Lantau Section

Land Route:

-        Via Lantau Link, Tsing Sha Highway and Tsing Yi Road to CWTC

Note:

[1]       For marine-based sediment, as stated in Section 6.5.1.30, to minimise sediment disposal, it is proposed to on-site reuse the Category L sediment generated (e.g. as backfilling materials), subject to site condition and engineer design. Beneficial reuse would be considered during the detailed design and construction stages before the disposal of excavated / dredged sediment.

[2]       Frequency of truck trip is based on assumed capacity of 6.5 m3 per truck with bulk factor of 1.4 and 26 days per month. The bulk factor 1.4 has been applied.

[3]       Frequency of barge trips are based on assumed capacity of 2,000 m3 per barge with bulk factor of 1.4 and 26 days per month. 

[4]       The assumption of the bulk density of Municipal Solid Waste (MSW) is 311.73kg/m3.

[5]       The peak of inert C&D materials is peak at 2029 and non-inert C&D materials is peak at 2027.

[6]       As stated in Section 6.5.1.30, according to the tentative construction programme, sediment due to reclamation works would be only generated in Q2 of 2027 to Q1 of 2028(12 months).

 

Summary of Waste to be Generated and Handled during Construction Phase

6.5.1.43        The summary of the various waste types identified above during construction phase of the Project with their proposed handling method / disposal outlets as discussed in above sections is summarised in Table 6.8 below.

6.5.1.44        In addition, trip ticket system would be implemented with reference to DEVB TC(W) No. 6/2010 Trip Ticket System for Disposal of Construction & Demolition Materials, to monitor disposal of waste and to control fly-tipping at PFRFs or landfills.  Additionally, all dump trucks and vessels should be equipped with Global Positioning System (GPS) or equivalent system for real time tracking and monitoring of their travel routings and parking locations to prohibit illegal dumping and landfilling of C&D materials or marine sediments.  A recording system for the amount of waste generated, recycled and disposed (including disposal sites) as well as travel routings and parking locations should be proposed.

 

Table 6.8      Summary of Estimated Amount of Waste to be Generated and Handled during Construction Phase

Type of Waste

Source

Total Quantity (with Bulk Volume)

Proposed Handling Method / Disposal Outlets

Generated

On-site reused / recycled

Off-site reused / recycled

Disposed

Inert C&D Materials

Materials generated from site clearance, excavation/ foundation works, piling works, demolition of existing structures, earthworks and slope works, tunnelling and construction works

 

2,227,500 m3

1,773,980m3

 

453,520 m3

 

-

·  Reuse within the site / deliver to PFRFs (such as Tuen Mun Area 38 Fill Bank), subject to allocation of PFC.

 

·  Reuse in other concurrent projects.

Non-inert C&D Materials

139,000 m3

-

 

-

139,000 m3

 

·  Reuse or recycling before disposal at WENT Landfill.

Sediment

Dredging works for reclamation, piling, excavation works for the construction of towers and anchorages after reclamation  

140,279 m3 (Category L)

140,279 m3

 

-

-

·  Category L sediment generated would be reused on-site (e.g. as backfilling materials), subject to site condition and engineering design.

 

·  Surplus Category L sediment, if any, will be disposed of at designated marine disposal site.  Final disposal site (typically South Cheung Chau / East of Ninepin) shall be determined by MFC; and disposal arrangement on a need basis.

 

56,206m3 (Category M and Category H (equal to or not exceeding 10x LCEL))

-

 

-

56,206 m3

(Category M and Category H (equal to or not exceeding 10x LCEL))

 

·  Final disposal site (typically East Sha Chau) shall be determined by MFC; and disposal arrangement on a need basis.

 

Chemical Waste

Oil and grease associated with plant maintenance;

Spent hydraulic fluid from plant machinery;

Scrap batteries from vehicle maintenance; and

Used paint, cleaners, solvents used in maintaining mechanical equipment

 

Few hundred liters per month

-

 

-

 

Few hundred liters per month

·  Store in compatible containers in designated area on site.

·  To be collected and/or recycled by a licensed collector.

·  Recycled by licensed facility and/or disposal of at the CWTC.

 

General Refuse

Refuse generated from construction workforce

 

369 tonnes

-

-

369 tonnes

·  Provide on-site collection points together with recycling bins.

·  To be collected by an appropriate waste collector to be employed by the Contractor.

·  Reuse or recycle before disposal of at WENT Landfill.

Floating Refuse

Floating refuse trapped within the Project area 

 

5 m3 / year

-

-

5 m3 / year

·  If collected by Contractor of this Project within works area, it will be disposed of together with general refuse before disposal of at WENT Landfill after separating recyclables.

Notes:

[1]   Frequency of truck trip is based on assumed capacity of 6.5 m3 per truck with bulk factor of 1.4 and 26 days per month.  The duration of the major excavation and construction is expected to be 54 months in total based on tentative construction programme.

[2]   Frequency of barge trip is based on assumed capacity of 2,000 m3 per barge with bulk factor of 1.4 and 26 days per month.  The duration of the major excavation and construction is expected to be 54 months in total based on tentative construction programme.


6.5.2               Operational Phase

Chemical Waste

6.5.2.1           Chemical wastes such as used paints, lubricants and used batteries may be generated during maintenance activities.  This waste may pose environmental, health and safety hazards.  Measures as stipulated in the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes would be strictly followed for the handling and disposal of chemical waste. 

6.5.2.2           Should any chemical waste be generated during operational phase, the operator should register with EPD as a chemical waste producer.  The chemical waste would be readily accepted for disposal of at the CWTC at Tsing Yi or other licensed facilities for final treatment and disposal by licensed chemical waste collectors. 

6.5.2.3           Since the estimated quantities of chemical waste generated from the operational phase would be only few hundred litres per month in maximum for general maintenance activities, no adverse environmental impact is anticipated with proper storage, handling and disposal of this waste.

Floating Refuse

6.5.2.4           As mentioned in Section 6.5.1.38, it is anticipated that approximately 5 m3 of floating refuse would be collected during operational phase of this Project every year.  Floating refuse will be collected by regular operation of Marine Department (MD)’s appointed contractorWith the proper seawall design and implementation of management control practices, no adverse environmental impact associated with floating refuse is anticipated.

6.5.2.5           Floating refuse trapped within the Project area during operational phase will be collected by MD’s appointed contractor and disposed to landfill correspondingly.  The collection frequency is suggested to be at least monthly interval in accordance with MD’s agreement.  In case there are any recyclable components in the floating refuse collected, they should be separated from the collected floating refuse.  The contractor shall conduct on-site sorting of the recyclable component and be responsible to arrange respective recycling companies to collect these components.

6.6                    Mitigation of Adverse Environmental Impacts

6.6.1               Construction Phase

Waste Management Hierarchy

6.6.1.1           The waste management hierarchy has been applied in the assessment and development of mitigation measures for waste which aims at evaluating the desirability of waste management methods include the followings in descending preference:

l  Avoidance and reduction of waste generation;

l  Reuse of materials;

l  Recovery and recycling of residual materials; and

l  Treatment and disposal according to relevant laws, guidelines and good practices.

6.6.1.2           Good site practices and waste reduction measures to achieve avoidance and minimisation of waste generation in the hierarchy are recommended in the following sections.  Environmental Management Plan (EMP) and trip ticket system are recommended for monitoring management of waste.

6.6.1.3           Besides, the Contractor is encouraged to deliver waste materials to EcoPark and Y·PARK for reuse and recycling. Referring to latest information in EcoPark’s website, at least 9 tenants, including waste metals, waste wood, waste electrical and electronic equipment (WEEE), waste plastics, waste batteries, construction and demolition waste, waste glass, waste rubber tyres and wastepaper, are engaging in recycling business. In general, Y·PARK mainly receives 6m long or below tree trunks and its attached tree branches, twigs and leaves.  The Contractor can consider transferring yard waste generated during slope works and tunnel works at North Lantau to Y·PARK for reuse or recycle after proper treatment.  Specifically, in order to minimise the generation of yard waste, the Project Proponent shall:

l  Avoid unnecessary removal or excessive pruning of trees. Preserve trees in their original locations and implement tree transplanting when on-site preservation is not feasible;

l  Segregate various types of yard waste and shred wood to facilitate reuse and recycling;

l  Reuse yard waste on-site for a variety of purposes (e.g., decomposition and composting, recreational and decorative uses, and mulching in planting areas, etc.); and

l  Identify recycling options (e.g. delivery to Y-park) for yard waste that cannot be directly reused on-site.

6.6.1.4           Where yard waste generation is unavoidable, sorting of yard waste for recycling and reuse on-site should always be the priority. Yard waste shall be separated from C&D material to facilitate recycling, such as delivery them to Y-park so as to minimise the quantity of waste to be disposed at landfill site. The Contractor should be responsible for cutting and shredding the yard waste in order to meet the collection requirement of the recycling outlet for processing. Disposal of yard waste directly at landfills should only be regarded as the last resort, when no alternatives are available.

Good Site Practices

6.6.1.5           It is anticipated that adverse waste management implications would not arise in the construction site, provided that good site practices are strictly followed.  Recommendations for good site practices during the construction phase include:

l   Nomination of approved personnel, such as a site manager, to be responsible for implementation of good site practices, arrangements for waste collection and effective disposal to appropriate facilities;

l   Training of site personnel in site cleanliness, concepts of waste reduction, reuse and recycling, proper waste management and chemical waste handling procedures;

l   Provision of sufficient waste reception / disposal points of a suitable vermin-proof design that minimises windblown litter;

l   Arrangement of regular collection of waste for transporting off-site and final disposal;

l   Adoption of appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers;

l   Provision of regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors;

l   Adoption of a recording system for the amount of wastes generated, recycled and disposed (including the disposal sites); and

l   Preparation of WMP, as a part of the EMP in accordance with ETWB TC(W) No. 19/2005 - Environmental Management on Construction Sites for submission to the Project Manager for approval. 

6.6.1.6           In order to monitor the delivery of C&D materials to the designated PFRF and landfill; and to avoid illegal dumping and control fly-tipping, a trip ticket system should be included.  One may make reference to DEVB TC(W) No. 6/2010 for details.  A recording system for the amount of waste generated, recycled and disposed, including the disposal sites, should also be set up.  Warning signs should be put up to remind the designated disposal sites.  CCTV should also be installed at the vehicular entrance and exit of the site as additional measures to prevent illegal dumping / fly-tipping.  When delivering inert C&D materials to a PFRF for beneficial reuse, the material shall only consist of soil, rock, concrete, brick, cement plaster / mortar, inert building debris, aggregates and asphalt, and be free from marine mud, household refuse, plastic, metals, industrial and chemical waste, animal and vegetable matter, and other material considered to be unsuitable by the Filling Supervisor.  GPS or equivalent systems should also be equipped at all dump trucks and vessels for real-time tracking and monitoring of transportation of inert C&D materials to designated locations as one of the practicable means of avoiding illegal dumpling and landfilling.

Waste Reduction Measures

6.6.1.7           Good management and control of construction site activities / processes can minimise the generation of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices.  Recommendations to achieve waste reduction are discussed as follow:

l   Segregate and store different types of construction related waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;

l   Provide separate labelled bins to segregate recyclable waste such as aluminium cans from other general refuse generated by the work force, and to encourage collection by individual collectors;

l   Recycle any unused chemicals or those with remaining functional capacity;

l   Maximise the use of reusable steel formwork to reduce the amount of C&D materials;

l   Wood, steel and other metals shall be separated for re-use and / or recycling prior to disposal of non-inert C&D materials to minimise the quantity of waste to be disposed of to landfill;

l   Adopt proper storage and site practices to minimise the potential for damage to, or contamination of construction materials;

l   Plan the delivery and stock of construction materials carefully to minimise the amount of surplus waste generated;

l   Adopt pre-cast construction method instead of cast-in-situ method for construction of concrete structures; and

l   Minimise over-ordering and wastage through careful planning during procurement of construction materials.

6.6.1.8           In addition to the above good site practices and waste reduction measures, specific mitigation measures are recommended below for the identified waste so as to minimise environmental impacts during handling, transportation and disposal of these wastes.

Storage, Collection and Transportation of Waste

6.6.1.9           Storage of materials on-site may induce adverse environmental impacts if not properly managed.  The following recommendations should be implemented to minimise the impacts:

l   Waste, such as soil, should be handled and stored well to ensure secure containment, thus minimising the potential of pollution;

l   Storage areas should be maintained and cleaned routinely;

l   Stockpiling area should be provided with covers and water spraying system to prevent materials from wind-blown or being washed away; and

l   Different locations should be designated to stockpile each material type to enhance reuse.

6.6.1.10        Waste collectors should be employed for the collection and transportation of waste generated. For chemical waste, licensed waste collector for its transportation and disposal should be employed in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.  The following recommendations should be implemented to minimise the impacts:

l   Remove waste in a timely manner;

l   Employ trucks with cover or enclosed containers for waste transportation;

l   Obtain relevant waste disposal permits from the appropriate authorities;

l   Dispose waste at licensed waste disposal facilities; and

l   Maintain records of quantities of waste generated, recycled and disposed.

Construction and Demolition Material

6.6.1.11        Subject to site situation, the generated C&D materials should be sorted on-site into inert C&D materials and non-inert C&D materials.  To minimise the impact resulting from collection and transportation of C&D materials, non-inert C&D materials, such as wood, plastic, steel and other metals should be reused or recycled and, as a last resort, disposed to landfill.  Inert C&D materials should be recycled and reused.  With reference to Table 6.8, inert C&D materials are expected to be delivered to Tuen Mun Area 38 Fill Bank.  Within the stockpiling areas, the following measures should be taken to control potential environmental impacts or nuisance:

l   Proper handling and storage of waste by means of covers and/or water spraying system to minimise the potential environmental impact and to prevent materials from wind-blown or being washed away;

l   Covering materials during heavy rainfall;

l   Locating stockpiles suitably so as to minimise potential visual impacts;

l   Displaying warning signs at the designated disposal sites.  CCTV should be installed at the vehicular entrance and exit of the site as additional measures to prevent fly-tipping; 

l   Adopting GPS or equivalent system for tracking and monitoring of all dump trucks for the Project to record their travel routings and parking locations to prohibit illegal dumping and landfilling of C&D materials; and

l   Minimising land intake of stockpile areas, subject to site condition.

Sediment

6.6.1.12        The sediment should be excavated/dredged, handled, transported and disposed of in a manner that would minimise adverse environmental impacts.  To minimise sediment disposal, it is proposed to on-site reuse the Category L sediment generated (e.g. as backfilling materials) subject to site condition and engineering design.  Beneficial reuse would be considered during the detailed design and construction stages before the disposal of excavated/dredged sediment.

6.6.1.13        Requirements of the Air Pollution Control (Construction Dust) Regulation, where relevant, shall be adhered to during excavation/dredging, transportation and disposal of the sediment.

6.6.1.14        For off-site disposal, the basic requirements and procedures specified under paragraph 4.2.1 of Chapter 4 of the PAH shall be followed.  MFC of CEDD is managing the disposal facilities in Hong Kong for the excavated/dredged sediment, while EPD is the authority of issuing marine dumping permit under the DASO.

6.6.1.15        For the purpose of site allocation and application of marine dumping permit and if considered necessary by EPD (Marine Dumping Control Section / Territorial Control Office), separate SSTP (including the possible additional sampling works within the sampling grids of VC-06, VC-09, VC-11, VC-32 to VC-35, VC-37, VC-38 and VC-58) shall be submitted to EPD for agreement under DASO.  Additional GI works, based on the SSTP, shall then be carried out in order to confirm the disposal arrangements of the excavated/dredged sediment.  Sediment Quality Report(s) (SQR), reporting the chemical and biological screening results and the estimated quantities of sediment under different disposal options, shall then be submitted to EPD for agreement under DASO.

6.6.1.16        To ensure disposal space is allocated for the Project, the Project Proponent should be responsible for obtaining agreement from MFC on the rationale for sediment excavation/dredging and the allocation of the disposal site.  The contractor(s), on the other hand, should be responsible for the application of the marine dumping permit under DASO from EPD for the sediment disposal.

6.6.1.17        The excavated/dredged sediments are expected to be loaded onto the barge at barging points under this Project and transported to the designated disposal sites allocated by MFC. The excavated/dredged sediment would be disposed of according to its determined disposal options and paragraph 4.2.1 of Chapter 4 of the PAH.

6.6.1.18        Stockpiling of contaminated sediments should be avoided.  If temporary stockpiling of contaminated sediments is necessary, the excavated / dredged sediment should be covered by tarpaulin and the area should be placed within earth bunds or sandbags to prevent leachate from entering the ground, nearby drains and surrounding water bodies.  The stockpiles should be completely paved or covered by linings in order to avoid contamination to underlying soil or groundwater.  Separate and clearly defined areas should be provided for stockpiling of contaminated and uncontaminated materials.  Leachate, if any, should be collected and discharged according to the Water Pollution Control Ordinance.

6.6.1.19        In order to minimise the potential odour / dust emissions during excavation / dredging and transportation of the sediment, the excavated / dredged sediments shall be wetted during excavation / dredging / material handling and shall be properly covered when placed on trucks or barges.  Loading of the excavated / dredged sediment to the barge shall be controlled to avoid splashing and overflowing of the sediment slurry to the surrounding water.

6.6.1.20        The barge transporting the sediments to the designated disposal sites shall be equipped with tight fitting seals to prevent leakage and shall not be filled to a level that would cause overflow of materials or laden water during loading or transportation.  In addition, monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation.  To avoid illegal dumping, all dumping vessels have to be approved in a marine dumping permit issued under the DASO.  Each of the vessels has to be installed with an automatic recording equipment, namely the Front End Mobile Unit (FEMU), which is a key component of the Real Time Tracking & Monitoring of Vessel (RTTMV) System of EPD.  The FEMU transmits self-monitoring data direct from the barge at sea to the Control Centre at EPD through General Packet Radio Service (GPRS) mobile communication network.  The transportation route avoiding the ecological sensitive areas should be proposed when applying the dumping permit.

6.6.1.21        Referring to Section 6.5.1.18, due to the opposition of private owner of nearby land lots, no sampling works were carried out for 7 sampling locations near Tsing Yi (i.e. VC-32 to VC-35, VC-37, VC-38 and VC-58). According to Section 6.6.1.15, additional sampling works will be carried out for the 7 sampling locations under DASO. In case Type 3 – Special Treatment / Disposal sediment were identified in the additional sampling works, the Project Proponent shall be responsible for identifying and agreeing with the DEP the most appropriate treatment and/or disposal arrangement for the Type 3 sediment as required in the PAH. A possible disposal arrangement for Type 3 sediment is by geosynthetic containment. A geosynthetic containment method is a method whereby the sediments are sealed in geosynthetic containers and, at the disposal site, the containers would be dropped into the designated contaminated mud pit where they would be covered by further mud disposal and later by the mud pit capping, thereby meeting the requirements for fully confined mud disposal. Similar disposal methods have been used for projects in Europe, the USA and Japan and the issues of fill retention by the geosynthetic fabrics, possible rupture of the containers and sediment loss due to impact of the container on the seabed have been addressed[1].

6.6.1.22        Moreover, the geosynthetic containment method was proposed for Type 3 sediment disposal in a number of EIA studies in Hong Kong, including Central Kowloon Route (EIAO Register No.: AEIAR-171/2013), Tseung Kwan O – Lam Tin Tunnel and Associated Works (EIAO Register No.: AEIAR-173/2013), Shatin to Central Link – Hung Hom to Admiralty Section (EIAO Register No.: AEIAR-166/2012) and Protection Works at Causeway Bay Typhoon Shelter (EIAO Register No.: AEIAR-159/2011), Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link (EIAO Register No.: AEIAR-143/2009) and Wan Chai Development Phase II and Central-Wan Chai Bypass (WDII) (EIAO Register No.: AEIAR-125/2008). Under WDII, field trials had been undertaken to demonstrate the feasibility on the use of the geosynthetic containment. A report on the field trials concluded that disposal by sealing the sediments in geosynthetic containers and dropping these containers into the contaminated mud pits at East Sha Chau has been shown to be a successful and viable disposal method.  The use of a geosynthetic container system for special disposal was considered to be an effective system with negligible loss of contaminants to the marine environment during disposal.

Chemical Waste

6.6.1.23        For those processes which will generate chemical waste, alternatives could be found to eliminate/minimise the use of chemicals, to reduce the generation quantities or to select a chemical type of less impact on environment, health and safety.  If chemical waste is produced at the construction site, the Contractor would be required to register with the EPD as a Chemical Waste Producer and must follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.  Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately.  Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosives, flammable, oxidising, irritant, toxic, harmful, corrosive, etc.  The Contractor shall employ a licensed collector to transport and dispose of the chemical wastes at a licensed chemical waste treatment and disposal facility such as CWTC at Tsing Yi in accordance with the Waste Disposal (Chemical Waste) (General) Regulation. 

General Refuse

6.6.1.24        General refuse should be stored in enclosed bins or compaction units separate from C&D materials and chemical wastes.  A reputable waste collector should be employed by the Contractor to remove general refuse from the site, on a daily basis to minimise odour, pest and litter impacts. An enclosed and covered area is preferred to reduce the occurrence of wind-blown light materials.

6.6.1.25        The collected general refuse will be disposed of at designated landfill.  Clearly labelled recycling bins should be provided on site in order to encourage segregation and recycling of aluminium cans, plastic wastes, and wastepaper in order to reduce general refuse production. 

6.6.1.26        The contractor should carry out an education programme for workers in avoiding, reducing, reusing and recycling of materials generation.  Posters and leaflets advising the use of the bins should also be provided on site as reminders.  The recyclable waste materials should then be collected by reliable waste recycling agents on a regular basis.

Floating Refuse

6.6.1.27        To minimise the chance of trapping / accumulating floating refuse within the Project area, the artificial seawall has been designed with a circular shape and sloping edges which can help redirect wave energy and avoid sharp edges where water can become stagnant, thus reducing debris collection. The use of a variable profile (e.g. combining vertical and sloped sections) would enhance hydrodynamics and minimise flat areas that trap debris.  Besides, the design has reduced relatively sharp turns and smoothen / carved out the sharp corners of the proposed seawalls. With proper seawall design and implementation of management control practices, no adverse impact arising from floating refuse is anticipated.

6.6.1.28        Apart from collecting and storing waste with good waste management practice on-site to avoid having waste transported to sea under extreme weather conditions, the Contractor for marine works should be responsible for the collection of refuse, if any, within the works area.  The Contractor shall collect and remove floating refuse at regular intervals on a daily basis to keep water bodies within the site boundary and the neighbouring water bodies free from rubbish during the construction phase.  In case floating refuse is identified, a waste collection vessel is needed to remove the floating materials and eventually store and dispose of together with the general refuse, after separating the recyclables for recycling.

6.6.2               Operational Phase

Chemical Waste

6.6.2.1           Generation of chemical waste should be reduced. For those processes which generated chemical waste, alternatives could be found to eliminate the use of chemicals, to reduce the generation quantities or to select a chemical type of less impact on environment, health and safety.  Same as construction phase, chemical waste generated during maintenance works in operational phase should be stored in appropriate containers and collected by a licensed chemical waste collector. Chemical wastes such as spent lubricant oil should be recycled at an appropriate facility.  For those that cannot be recycled, it should be disposed of at either the CWTC, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

Floating Refuse

6.6.2.2           Same as the existing practice, floating refuse scavenging and collection service will also be provided by the Contractor of MD.  Floating refuse trapped within the Project area during operational phase will be collected and disposed to landfill correspondingly.  The collection frequency is suggested to be at least monthly interval in accordance with MD’s agreement.  In case there are any recyclable components in the floating refuse collected, the MD’s contractor is suggested to conduct on-site sorting of the recyclable component and be responsible to arrange respective recycling companies to collect these components.

6.6.2.3           Table 6.9 summarised the tentative transportation routing for waste disposal during operational phase, while Table 6.10 summarised the estimated amount of waste to be generated and handled during operational phase.


 

Table 6.9      Tentative Transportation Routings for Waste Disposal during Operational Phase

Treatment Facility / Disposal Site

Type of Waste

Tentative Transporting Routing

Maximum Frequency of Trip for the Identified Waste Types [1]

CWTC

Chemical Waste

From Tsing Yi Area

Land Route

Via Tsing Sha Highway to the CWTC

 

1 trip per day

From Lantau Area

Land Route

Via Lantau Link to Tsing Sha Highway to the CWTC

 

Subject to MD’s contractor existing practice

Floating Refuse

Operational phase will be collected by MD’s appointed contractor and disposed to landfill correspondingly.  The transport route and collection frequency are suggested to be at least monthly interval in accordance with MD’s agreement.

 

Note:

[1]       The truck capacity of chemical waste is 6.5 m3 per truck

 

Table 6.10    Summary of Estimated Amount of Waste to be Generated and Handled during Operational Phase

Type of Waste

Generated from

Materials to be Generated

Total Amount to be Generated

Handing Procedures

Handling / Disposal Routes

Chemical Waste

Maintenance and service activities, e.g. E&M plant and equipment

Scrap batteries, spent hydraulic fluid, waste fuel,

lubrication oil, used plant, cleaning fluids and solvent

 

Few hundred liters per month

·   Stored in compatible containers in designated area on-site

 

·   Collected by licensed collectors

Recycled by licensed facility or disposal of at the CWTC

Floating Refuse

Accumulation along seawall

Litter and debris

Around 5 m3 / year

·   Existing regular operation of MD’s contractor to collect floating refuse in the vicinity

Same as the existing practice, collected by appointed contractor of MD

 

6.7                    Evaluation of Residual Impacts

6.7.1.1           With the implementation of the recommended mitigation measures for the handling, transportation and disposal of the identified waste arising, residual impacts would not be expected during the construction and operation of the proposed Project.

6.8                    Environmental Monitoring and Audit Requirements

6.8.1               Construction Phase

6.8.1.1           It is the Contractor’s responsibility to ensure that all wastes produced during the construction of the Project are handled, stored and disposed of in accordance with good waste management practices and EPD’s regulations and requirements.  The recommended mitigation measures should form the basis of the site WMP to be developed by the Contractors as part of the EMP in accordance with ETWB TC(W) No. 19/2005 Environmental Management on Construction Sites and submitted to the Project Manager for approval at the construction stage.  The monitoring and auditing requirements stated in ETWB TC(W) No.19/2005 should be followed with regard to the management of C&D materials. 

6.8.1.2           Monthly site audit should be conducted by the Environmental Team (ET) during construction phase to check if wastes are being managed in accordance with approved procedures.  The audits should cover site inspection on all aspects of on-site waste management practices including waste generation, storage, recycling, transport and disposal.  Apart from site inspections, waste management related documents including licences, permits, disposal and recycling records should be reviewed and audited for compliance with the legislation of the recommended good site practice and other waste management mitigation measures under the site audit.

6.8.1.3           Besides, auditing on the implementation of the trip ticket system in accordance with DEVB TC(W) No. 6/2010 and incorporate the requirements as appropriate should also be required.

6.8.2               Operational Phase

6.8.2.1           Adverse environmental impacts would not be anticipated with the implementation of good waste management practices following the existing practices of regular maintenance works.  Environmental audit programme on waste management for the operational phase of the Project would not be required.

6.9                    Conclusion

6.9.1.1           During construction phase, waste generated from the Project include C&D materials from construction activities, chemical wastes from maintenance and servicing of construction plants and vehicles, general refuse from workforce, floating refuse and sediments.  It is recommended that the inert C&D materials be reused on-site to minimise the amount of inert C&D materials delivered off-site to PFRF.   In particular, subject to site condition, the inert C&D materials generated would be reused for reclamation.  Improper handling, collection, transportation and re-use / disposal of the wastes will result in hygiene problems and adverse environmental impacts, e.g. odour nuisance, and pollution of nearby water bodies.  It is recommended that these wastes be handled, transported and disposed of according to the recommended good site practices and measures.  With the implementation of these measures, no adverse environmental impacts (including potential hazard, air and odour emissions, noise and wastewater discharges) would be anticipated during the construction phase.

6.9.1.2           The main types of waste generated from the operation of the Project are floating refuse and chemical waste.  In accordance with existing practices, floating refuse will be collected and disposed to landfill by regular operation of MD’s contractor.  With the implementation of management control practices, no adverse environmental impact would be anticipated.



[1] MTR Corporation Limited (2011). Consultancy Agreement No. NEX/2213 Environmental Impact Assessment (EIA) Study for Shatin to Central Link – Hung Hom to Admiralty Section (EIAO Register No.: AEIAR-166/2012).