TABLE OF CONTENTS
7.2 Environmental Legislation, Standards and Criteria
7.4 Description of Environment
7.5 Identification of Potential Land Contamination Concern
7.8 Initial Evaluation of Potential Land Contamination Impact
7.9 Mitigation of Adverse Environmental Impacts
7.10 Evaluation of Residual Impact
7.11 Environmental Monitoring and Audit
List of Tables
Table 7.1 Past and Existing Facilities / Works Areas within the Proposed Clearance Limit and their Potential Land Contamination Issues to the Project
Table 7.2 Past and Existing Off-Site Facilities / Works Areas and their Potential Land Contamination Issues to the Project
Table 7.3 Aerial Photographs Reviewed
Table 7.4 Summary of Relevant Chemical Waste Producer Records
Table 7.5 Summary of Issued Dangerous Goods Licenses within the Project Area Provided by FSD
Table 7.6 Summary of Incidents Provided by FSD
Table 7.7 Summary of Concerned Sites within Proposed Clearance Limit
Table 7.8 Summary of Concerned Off-site Facilities / Works Areas
Table 7.9 Proposed Sampling and Testing Plan
Table 7.10 Preliminary Sampling and Testing Plan
List of Figures
Figure 7.1 Locations of Potentially Contaminated Sites / Concerned Sites
Figure 7.2 Proposed Sampling Locations (Site STW1)
List of Appendices
Appendix 7.1 Initial Site Appraisal (ISA)
· Section 3.1 and 3.2 (Potential Contaminated Land Issues) of Annex 19 “Guidelines for Assessment of Impact on Sites of Cultural Heritage and Other Impacts” of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) (EPD, effective since 30 June 2023)
· Guidance Note for Contaminated Land Assessment and Remediation (Guidance Note) (EPD, April 2023)
The Guidance Note sets out the requirements for proper assessment and management of potentially contaminated sites such as oil installations (e.g. oil depots, petrol filling stations), gas works, power plants, shipyards / boatyards, chemical manufacturing / processing plants, steel mills / metal workshops, car repairing / dismantling workshops and scrap yards. In addition, this Guidance Note provides guidelines on how site assessments should be conducted and analysed and suggests practical remedial measures that can be adopted for the remediation of contaminated sites.
· Practice Guide for Investigation and Remediation of Contaminated Land (Practice Guide) (EPD, April 2023)
The Practice Guide outlines typical investigation methods and remediation strategies for the range of potential contaminants typically encountered in Hong Kong.
· Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (Guidance Manual) (EPD, April 2023)
The Guidance Manual introduces the risk-based approach in land contamination assessment and presents instructions for comparison of soil and groundwater data to the Risk-Based Remediation Goals (RBRGs) for 54 chemicals of concern (COCs) commonly found in Hong Kong. The RBRGs were derived to suit Hong Kong conditions by following the international practice of adopting a risk-based methodology for contaminated land assessment and remediation and were designed to protect the health of people who could potentially be exposed to land impacted by chemicals under four broad post restoration land use categories. The RBRGs also serve as the remediation targets if remediation is necessary.
· Aerial photographs and topographic maps held by the Lands Department (LandsD);
· Hong Kong Geological Survey (HKGS) Map (Series HGM20);
· Available records on dangerous goods (DG), chemical waste producers (CWP), chemical spillage/leakage and incidents within the Project Area from Environmental Protection Department (EPD) and Fire Services Department (FSD); and
· Relevant ground investigation (GI) reports from the Civil Engineering and Development Department (CEDD) Civil Engineering Library.
Table 7.1 Past and Existing Facilities / Works Areas within the Proposed Clearance Limit and their Potential Land Contamination Issues to the Project
|
Site ID1 |
Site Name |
Partially / Fully Encroached to the Proposed Clearance Limit |
Proposed Works under the Project |
Any Potential Issues to the Project? |
|
TYTL 108RP & TYTL 80, West Tsing Yi |
|
|
||
|
HUD1 |
Dockyard (TYTL 108RP) |
Partially encroached |
Facilities within the Proposed Clearance Limit to be demolished; viaduct/bridge erection |
To be reviewed in Table 7.7 |
|
HUD2 |
Sai Tso Wan Concrete Batching Plant (TYTL 108RP) |
Partially encroached (only the existing access road within the Proposed Clearance Limit) |
Provision of access road (main portion of the site (including the concrete batching plant) to be retained) |
To be reviewed in Table 7.7 |
|
HUD4 |
Former Floating Dock (TYTL 80) |
Fully encroached (floating on sea) |
Reclamation works |
No2 |
|
West Tsing Yi / Sai Tso Wan |
|
|
||
|
STW1 |
Public Carpark (STT3878K&T) and Adjacent Vegetated Land |
Partially encroached |
Construction of haul road for road modification/realignment work, site office and site storage area |
To be reviewed in Table 7.7 |
|
STW2 |
Truck Marshalling Area (STT3194K&T) |
Partially encroached |
Construction of Tsing Yi Connection viaduct and possible site office |
To be reviewed in Table 7.7 |
|
WTY1 |
DSD Rock Storage Area (GLA-TKT 1939) |
Fully encroached |
Construction of Tsing Yi Connection viaduct, site office and site storage area |
To be reviewed in Table 7.7 |
|
WTY2 |
Former LandsD Works Area (Formerly as GLA-TKT 1926) |
Fully encroached |
Site storage area |
To be reviewed in Table 7.7 |
|
WTY4 |
Lantau Link Viewing Platform Car Park |
Fully encroached |
Site storage area |
To be reviewed in Table 7.7 |
|
Northeast Lantau |
|
|
||
|
LT1 |
CEDD Slope Works Site |
Partially encroached |
Construction of North Lantau Interchange |
To be reviewed in Table 7.7 |
|
LT2 |
Vacant Land (GLA-TIS 801 & GLA-TIS 854) |
Partially encroached |
Works storage area |
To be reviewed in Table 7.7 |
|
LT3 |
Lantau Toll Plaza Administration Building |
Partially
encroached |
Facilities to be retained; the encroached part of the existing access road will be used for viaduct works in tandem with Route 11 |
To be reviewed in Table 7.7 |
|
LT4 |
Radar Station |
Partially encroached |
To be retained; deep underground tunnelling works only within bedrock (at depth of approximately 110m bgl). No soil excavation and aboveground works. |
No |
Remark:
* Sites shaded grey were further reviewed under the ISA in Appendix 7.1.
1 Refer to Figure 7.1 for site locations and the extents of sites.
2 Potential land contamination issues associated with the former floating dock to the Project is not anticipated as the dock was a marine vessel floating on open water.
Table 7.2 Past and Existing Off-Site Facilities / Works Areas and their Potential Land Contamination Issues to the Project
|
Site ID1 |
Site Name |
Facility within Project Area? |
Distance from Proposed Clearance Limit (m) |
Proposed Works under the Project |
Any Potential Issues to the Project? |
|
TYTL 108RP & TYTL 80, West Tsing Yi |
|
|
|||
|
HUD3 |
Sai Tso Wan 2 Concrete Batching Plant (TYTL 108RP) |
Yes |
10 m |
To be retained |
Site close to the Proposed Clearance Limit. Potential issues to be reviewed in Table 7.8. |
|
West Tsing Yi / Sai Tso Wan |
|
|
|
|
|
|
STW3 |
Shell Tsing Yi Installation (TYTL 108 S.A) |
No |
10 m |
To be retained |
Site close to the Proposed Clearance Limit. Potential issues to be reviewed in Table 7.8. |
|
WTY3 |
MTR – Tsing Yi Ventilation Building |
Yes |
155 m |
To be retained |
No potential issues given the distance from the Proposed Clearance Limit. |
|
TM1 |
Tsing Ma Control Area (TMCA) - Tsing Yi Administration Building |
Yes |
35 m |
To be retained |
No potential issues given the distance from the Proposed Clearance Limit. |
|
TM2 |
TMCA - Workshop |
Yes |
< 1 m |
To be retained |
Site close to the Proposed Clearance Limit. Potential issues to be reviewed in Table 7.8. |
|
TM3 |
TMCA - Tsing Yi Interchange Depot |
Yes |
< 1 m |
To be retained |
Site close to the Proposed Clearance Limit. Potential issues to be reviewed in Table 7.8. |
|
TM4 |
TMCA - Tsing Yi Interchange Electrical Substation |
Yes |
12 m |
To be retained |
No potential issues given the distance from the Proposed Clearance Limit. |
|
Northeast Lantau |
|
|
|
|
|
|
LT5 |
MTRL - East Lantau Traction Substation & East Lantau Tunnel (East) Ventilation Building |
Yes |
3 m |
To be retained |
Site close to the Proposed Clearance Limit. Potential issues to be reviewed in Table 7.8. |
Remark:
* Sites shaded grey were further reviewed under the ISA in Appendix 7.1.
1 Refer to Figure 7.1 for site locations and the extents of sites.
7.5.1 General
7.5.2 Review of Historical Land Uses
Table 7.3 Aerial Photographs Reviewed
|
Year |
Site Description |
|
1963 |
The Project Area is mainly occupied by natural terrain and open water, village houses and agricultural land. |
|
1973 |
Vacant land was observed at Kam Chuk Kok, west Tsing Yi. No other significant land uses changes were observed. |
|
1983 |
Container storage (Sites HUD1, HUD2 and HUD3) and electrical substation (Site HUD1) on newly reclaimed land were observed at Shek Wan, west Tsing Yi. Excavation was observed at Wok Tai Wan, west Tsing Yi. A dockyard on newly reclaimed land was observed south and outside of the Project Area (Site STW3). No other significant land uses changes were observed. |
|
1993 |
Construction works of the existing North Lantau Highway, existing Lantau Link and existing Tsing Ma Bridge were observed at Lantau and Tsing Yi, and on newly reclaimed land at Tai Chuen and Ma Wan. Existing radar station (Site LT4) (to be retained under the Project) was observed at Lantau. New reclamation was observed at Sites HUD1, HUD2 and HUD3. The container storage (Site HUD1 and Site HUD3) and electrical substation (Site HUD1) at Shek Wan were changed to dockyard. Site HUD1 consisted of existing workshops, container storage, existing electrical substation and existing administration building and Site HUD3 consisted of container storage. The container storage at Site HUD2 was changed to open storage. Floating dock (Site HUD4) was observed. Vacant land was observed at Sai Tso Wan (Site STW1). The dockyard at Site STW3 was changed to existing oil installation outside of the Project Area and further reclamation was observed in the western portion of Site STW3. |
|
2003 |
Existing North Lantau Highway, existing Lantau Link and existing Tsing Ma Bridge were observed. Existing Lantau Toll Plaza Administration Building (Site LT3) and toll gate were observed at Tai Tsing Chau, northeast Lantau. Vacant land (Site LT2) and existing MTRL - East Lantau Traction Substation & East Lantau Tunnel (East) Ventilation Building (Site LT5) were observed at Tai Chuen, northeast Lantau. Existing Tai Pai Tsui Pier and vacant land were observed at Ma Wan. Existing North West Tsing Yi Interchange, vacant land (Site WTY1), existing car park (Site WTY2) and existing Lantau Link Viewing Platform Car Park (Site WTY4) were observed at west Tsing Yi. The existing Tsing Ma Control Area (TMCA) facilities (Site TM1, Site TM2, Site TM3 and Site TM4) and existing MTR - Tsing Yi Ventilation Building (Site WTY3) were observed at west Tsing Yi and Wok Tai Wan. The open storage at Site HUD2 was replaced by existing Sai Tso Wan Concrete Batching Plant and existing electrical substation. Car parks were observed at Site STW1 and Site STW2, west Tsing Yi. Vegetated land was observed at Site STW1 adjacent to the car park. Existing Cheung Tsing Highway was observed. |
|
2013 |
Car park at Site STW1 was vacated. The adjacent vegetated land remains unchanged. No other significant land uses changes were observed. |
|
2022 |
Toll gate was no longer observed at Lantau Link / North Lantau Highway. Container storage was replaced by open storage of steel reinforcing bars within the dockyard (Site HUD1). The portion of the dockyard at Site HUD3 was changed to a construction site for the concrete batching plant. A works area was observed at the car park at Wok Tai Wan, west Tsing Yi (Site WTY2). Existing public carpark was observed along the access road at Kam Chuk Kok (Site STW1). No change was observed at the adjacent vegetated land. |
Remarks:
Source of aerial photographs: Survey and Mapping Office, Lands Department
* Site ID of affected facilities / works areas within the Proposed Clearance Limit (refer to Table 7.1) are shown in bold.
** Site ID of concerned off-site facilities / works areas that were reviewed (refer to Table 7.2) are shown in underline.
7.5.3 Site Geology
· The 1:20,000 Hong Kong Geological Survey (HKGS) Map Sheet No.9. (1994);
· The 1:20,000 Hong Kong Geological Survey (HKGS) Map Sheet No.10. (1991);
· The 1:100,000 Hong Kong Geological Survey (HKGS) Map of Hong Kong, Web-based Edition (2006); and
· The Geological Survey Sheet Report No.6, Geology of Tung Chung and Northshore Lantau Island (GEO, 2002)
7.5.4 Information from Government Departments
Environmental Protection Department
Table 7.4 Summary of Relevant Chemical Waste Producer Records
|
CWP ID |
Site ID |
Company Name |
Address |
Status |
Business Nature |
|
TYTL 108RP & TYTL 80, West Tsing Yi |
|||||
|
1 |
HUD1 |
Hongkong United Dockyards Limited |
Sai Tso Wan Road, Tsing Yi, NT |
Valid |
Repairing of ship |
|
2 |
HUD1 |
Van Oord ACZ B.V. |
Hongkong United Dockyards Ltd., Sai Tso Wan Road, Tsing Yi, NT |
Valid |
Dredging industry |
|
3 |
HUD1 |
Gilgen Nabtesco (Hong Kong) Ltd |
Hongkong United Dockyards Ltd., Tsing Yi, NT |
Valid |
Contracting |
|
4 |
HUD1 |
John Logistic Co. Ltd. |
TYTL No. 108, R.P. Hongkong United Dockyards Ltd., Tsing Yi, N.T. |
Valid |
Vehicle maintenance |
|
5 |
HUD1 |
Hollandsche Aanneming Maatschappy B.V. |
HUD Building, Sai Tso Wan Rd, Tsing Yi, KL |
Invalid |
Dredging contractor |
|
6 |
HUD1 |
Wartsila China Limited |
108RP, Sai Tso Wan Road, Tsing Yi Island |
Invalid |
Marine diesel Engine repair |
|
7 |
HUD4 |
Chau Kee Marine Contractors Company Limited |
Floating Dock "Unit" at Anchorage off Premises of Hongkong United Dockyards Ltd. at TYTL 108 RP, Sai Tso Wan Road, Tsing Yi, New Territories |
Valid |
Tanks cleaning, garbage services |
|
8 |
HUD2/HUD3 |
Anderson Concrete Limited |
Tsing Yi Town Lot 108RP (part) |
Valid |
Concrete batching plant |
|
9 |
HUD2/HUD3 |
Anderson Concrete Limited |
Tsing Yi Town Lot 108RP, Tsing Yi, NT |
Valid |
Concrete batching plant |
|
10 |
HUD2/HUD3 |
Gammon Construction Limited |
Concrete Batching Plant at TYTL 108R.P. Terminal, Tsing Yi, NT |
Valid |
Civil engineering & construction |
|
West Tsing Yi |
|||||
|
11 |
TM1/ TM2/ TM3 |
TIML MOM Limited |
Tsing Ma Control Area, North West Tsing Yi Interchange, Tsing Yi, Territories |
Valid |
Road management |
|
12 |
TM1/ TM2/ TM3 |
Wing Hing Construction Company Limited |
Tsing Ma Control Area, North West Tsing Yi Interchange, Tsing Yi |
Valid |
Road management |
|
13 |
TM1/ TM2/ TM3 |
Excellent Dragon Limited |
Tsing Ma Control Area, North West Tsing Yi Interchange, Tsing Yi, N.T. |
Valid |
Road management |
|
14 |
TM1/ TM2/ TM3 |
Wader Engineering International Limited |
Tsing Ma Control Area, North West Tsing Yi Interchange, Tsing Yi, N.T. |
Valid |
Road management |
|
15 |
TM1/ TM2/ TM3 |
Transport Infrastructure Management Limited |
Tsing Ma Control Area, North West Tsing Yi Interchange, Tsing Yi, New Territories |
Invalid |
Road management |
|
16 |
LT3 |
Tsing Ma Management Limited |
Garage at Lantau Admin. Bldg. Lantau, NT |
Invalid |
Road management |
Fire Services Department
Table 7.5 Summary of Issued Dangerous Goods Licenses within the Project Area Provided by FSD
|
No. |
Type of DG |
Quantity |
Location of Storage |
Site ID |
|
1. |
Class 2.1 |
1,200 litres |
TYTL 108RP, Sai Tso Wan Road, Tsing Yi Island |
HUD1 / HUD2 / HUD3 |
|
2. |
Class 2.2 |
4,840 litres |
||
|
3. |
Class 3 |
3,300 litres |
||
|
4. |
Class 3 |
8,600 litres |
||
|
5. |
Class 3 |
13,635 litres |
||
|
6. |
Class 3 |
45,910 litres |
||
|
7. |
Class 3 |
12,500 litres |
North West Tsing Yi Interchange |
TM1 / TM2 / TM3 |
|
8. |
Class 3 |
5,600 litres |
||
|
9. |
Class 3 |
1,500 litres |
||
|
10. |
Class 3 |
1,000 litres |
||
|
11. |
Class 3 |
1,000 litres |
Table 7.6 Summary of Incidents Provided by FSD
|
No. |
Date |
Type of Incident |
Address |
Within the Proposed Clearance Limit? |
Nature of Incident Related to Land Contamination? [1] |
|
1. |
27/1/2021 |
Car accident |
Lamppost FC1605, near North West Tsing Yi Interchange |
No |
N/A |
|
2. |
21/3/2021 |
Vegetation fire |
Tso Wan, House No.7 |
No |
N/A |
|
3. |
21/5/2021 |
Traffic accident |
Lamppost HM007N, near Lantau Link |
Yes |
To be discussed in Section 7.5.4.13 |
|
4. |
24/8/2021 |
No. 2 fire alarm |
Lamppost TY01, near North West Tsing Yi Interchange |
No |
N/A |
|
5. |
13/11/2021 |
Vegetation fire |
Lantau Link, TC bound |
Unknown |
No |
|
6. |
15/11/2021 |
Vegetation fire |
Sai Tso Wan Road |
No |
N/A |
|
7. |
28/11/2021 |
Mountain rescue |
Sam Chuen Hillside UTM Grid Reference JK967731 |
No |
N/A |
|
8. |
6/2/2022 |
Vegetation fire |
Lamppost FA4900, near Tsing Yi Road West |
No |
N/A |
|
9. |
16/2/2022 |
Hoax bomb threat |
Sai Tso Wan Road / Tsing Tim Street |
No |
N/A |
|
10. |
25/2/2022 |
Traffic accident |
Lamppost HM008S, near Lantau Link |
No |
N/A |
|
11. |
15/6/2022 |
Traffic accident |
Roadside outside MTR TYI Ventilation Building, North West Tsing Yi Interchange |
No |
N/A |
|
12. |
21/11/2022 |
Mountain rescue |
Sam Chuen Tsing Chau Tsai Peninsula |
No |
N/A |
|
13. |
19/12/2022 |
No. 2 fire alarm |
16 Sai Tso Wan Road, Nam Wan Tunnel and West Control Building |
No |
N/A |
|
14. |
24/1/2023 |
Traffic accident |
Lamppost HM12, near North West Tsing Yi Interchange |
No |
N/A |
|
15. |
31/1/2023 |
Mountain rescue |
Lamppost VC0431 |
No |
N/A |
|
16. |
17/2/2023 |
No.1 fire alarm |
Tsing Ma Bridge Openground underneath Tsing Yi Tower |
No |
N/A |
|
17. |
19/2/2023 |
Drown |
Nam Wan Pier |
Yes |
No |
|
18. |
7/4/2023 |
No.1 fire alarm |
North West Tsing Yi Interchange, Tsing Yi Administration Building, TYS2/TYS2; 2/F Telecommunication Equipment Room |
No |
N/A |
|
19. |
14/4/2023 |
Traffic accident |
Lamppost TM004N, near North West Tsing Yi Interchange |
No |
N/A |
|
20. |
23/4/2023 |
No. 2 fire alarm |
Lamppost BC1806, near Cheung Tsing Highway |
Yes |
To be discussed in Section 7.5.4.14 |
|
21. |
23/4/2023 |
Traffic accident |
Lamppost TM007S, near Lantau Link, TC Bound, Upper Deck Tsing Ma Bridge |
Yes |
To be discussed in Section 7.5.4.13 |
|
22. |
17/5/2023 |
Vessel injuries |
Tang Lung Chau |
Yes |
No |
|
23. |
18/5/2023 |
Mountain rescue |
Lantau Link |
Unknown |
No |
|
24. |
22/12/2020 |
No. 2 fire alarm (LPG leakage) |
SHELL LPG Plant, Tsing Tim Street |
No |
N/A |
Remarks:
[1]. N/A: Incident records outside the Proposed Clearance Limit.
7.5.5 Site Walkovers
7.5.6 Summary of Site Appraisal
Table 7.7 Summary of Concerned Sites within Proposed Clearance Limit
|
Concerned Site ID |
Site Name1 |
Hotspots |
Site Observation / Current Potentially Contaminating Activities |
Corresponding Photographic Record Reference in Appendix D of Appendix 7.1 |
Past Potential Contaminating Land Use / Activities |
Any Potential Land Contamination Issues? / Potential COCs2 |
Future Land Uses / RBRGs Land Use Scenario |
|
TYTL 108RP & TYTL 80, West Tsing Yi |
|
|
|
|
|||
|
HUD1 |
Dockyard (89,500
m2) |
To be confirmed when site is accessible for site walkover |
The site is located at the eastern end of Tsing Ma Bridge and was inaccessible for site inspection.
Based on peripheral observations, the site was concrete paved. Administration building, crane, open storage of steel reinforcing bars, electrical substation and suspected workshop were observed within the site. Detailed site activities could not be determined.
Based on EPD information, there was no record of spillage /
leakage of chemical wastes or chemicals for the site. However, there were a
total of 4 valid and 2 invalid CWP records within the site, associating with
repairing of ship, dredging industry, contracting, vehicle maintenance and
marine diesel engine repair.
|
Photo Nos. 1058, 1085, 1199, 5712 and 5728 in PR5 |
· Former container storage (1983 – 2013) · Former electrical substation (1983) |
Yes.
Potential COCs are: · Metals · VOCs · SVOCs · PCRs · PCBs (for former & existing substation only) · Free cyanide (for shipyard only) · Dioxins and furans (for shipyard only and if presence of incineration / burning activities) · TBTO (for shipyard only) |
Roads (viaducts) and works area / RBRGs (Lower of Industrial or Public Park) |
|
HUD2 |
Sai Tso
Wan Concrete Batching Plant |
To be confirmed when site is accessible for site walkover |
The site is located at the eastern end of Tsing Ma Bridge and was inaccessible for site inspection.
Based on peripheral observations, the site was concrete paved. Concrete batching facilities and electrical substation were observed 30 m and 10 m outside the Proposed Clearance Limit respectively. The portion of the site encroached into the Proposed Clearance Limit consisted of access road only.
Based on EPD information, there was no record of spillage / leakage of chemical wastes or chemicals for the site. However, there were a total of 3 CWP records potentially within the site, associated with concrete batching plant and civil engineering & construction.
Based on FSD information, there were no incidents involving DG/chemicals within the site. However, there were a total of 6 issued DG licenses within lot TYTL 108RP. As discussed in Section 7.5.4.8, further review will need to be carried out to identify if the DG stores are within the encroached portion of Site HUD2 and Proposed Clearance Limit, and if there will be any potential land contamination issues.
|
Photo No. 5746 in PR5 |
· Former container storage (1983) · Former open storage (1993) |
Yes. Although, the encroached portion of the site consisted of access road only, there could be land contamination issues associated with past operation of container storage, open storage and concrete batching plant. In addition, the potential land contamination issues associated with nearby concrete batching facilities and electrical substation should be reviewed during site walkover at a later stage when the site is accessible.
Potential COCs are: · Metals · VOCs · SVOCs · PCRs · PCBs (for electrical substation only) |
Roads (access road) / RBRGs (Lower of Industrial or Public Park) |
|
West Tsing Yi / Sai Tso Wan |
|
|
|
|
|||
|
STW1 |
Public Carpark (STT3878K&T) and Adjacent Vegetated Land (25,700 m2) (Encroached Area: 9,100 m2) |
Stain (24 m2) |
The site is located in Sai Tso Wan. The carpark was largely unpaved. Private cars, long vehicles, concrete mixer trucks, and oil tanker trucks were observed. No vehicle maintenance activities were observed / reportedly carried out at the site.
Within the encroached portion of the public carpark, general refuse scattering on the ground and a waste truck containing general refuse in the east of the encroached portion of the site were observed. No signs of chemicals / stains / spillage / stressed vegetation were observed in the vicinity of the general refuse and the waste truck. A patch of stain (approx. 24 m2) was observed on unpaved ground adjacent to a petrol oil tanker truck in the northeast of the encroached portion of the site. No other signs of chemical stains / spillage or stressed vegetation were observed within the encroached portion of the site and the immediately surroundings.
In addition to the above, an area parked with diesel tanker trucks was observed in the southeast of the site but was located outside the Proposed Clearance Limit (approx. 80 m from the area of the site encroached to the Proposed Clearance Limit). Multiple diesel tanker trucks were observed, connected with extended hoses to pumps and flow meters. Oil drums were observed behind the diesel tanker trucks. The area was unpaved with oil stains observed. Furthermore, oil stain and stressed vegetation (approx. 25 m2 in total) were observed near the diesel tanker truck parking area but were also located outside the Proposed Clearance Limit (approx. 130 m from the area of the site encroached to the Proposed Clearance Limit).
Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site.
The stain observed within the encroached portion of the public carpark could be due to the adjacent petrol oil tanker truck. There could be land contamination issues associated with the patch of stain. However, given the small size of the stain (approx. 24 m2) and any contamination likely to be shallow, the land contamination is expected to be localised.
For the diesel tanker truck parking area and referring to Section 7.4.1.2, no construction works (including soil excavation) will be carried out in the area under the Project as the area is outside the Proposed Clearance Limit. Furthermore, as the diesel tanker truck parking area, oil stains and stressed vegetation were outside the Proposed Clearance Limit and the extended hoses, pumps and flow meters were all above ground, the diesel tanker truck parking area is not expected to be an off-site source of land contamination to the Project. No potential land contamination issues associated with the diesel tanker truck parking area to the Project are therefore anticipated.
|
Photo Nos. 0847, 0851, 0852, 5620, 7474 (Diesel Tanker Truck Parking Area), 0923, 5650 (Stain), 0910, 0912 (Stain), 0827, 0888, 0901, 0927 (Stressed Vegetation), 0946, 1310 and 5658 in PR7 to PR9 |
N/A |
Yes (for the patch of stain within the encroached portion of the public carpark).
Potential COCs are: · Metals · VOCs · SVOCs · PCRs |
Roads (viaducts) / RBRGs (Lower of Industrial or Public Park) |
|
STW2 |
Truck Marshalling Area (STT3194K&T) (11,400 m2)
|
- |
The site is located in Sai Tso Wan.
Based on observation, the site was paved with concrete in good condition with no signs of chemicals or chemical stains / spillage or stressed vegetation were observed. Parked private cars and concrete mixer truck were observed. No vehicle maintenance / refuelling activities were observed.
Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site.
|
Photo Nos. 1206, 1231, 3665 and 3666 in PR6 |
N/A |
No |
N/A |
|
WTY1 |
DSD Rock Storage Area (GLA-TKT 1939) (48,100 m2) (Encroached Area: 48,000 m2) |
- |
The works area is under Contract No. DC/2020/05 Relocation of Sha Tin Sewage Treatment Works to Caverns – main caverns construction and is located in Wok Tai Wan. The works site is currently operated by DSD, AECOM (consultant) and China State - Alchmex Joint Venture (contractor).
Based on site observations and as reported by the site representative, the works area was unpaved and has used as a storage site for excavated rocks from Sha Tin Cavern. No vehicle / equipment maintenance / refuelling activities are carried out on site. No signs of chemicals or chemical stains / spillage or stressed vegetation were observed.
Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site.
|
Photo Nos. 1141, 1189, 5774, 7567, 7571 in PR3 |
N/A |
No |
N/A |
|
WTY2 |
Former
LandsD Works Area (Formerly as GLA-TKT 1926) |
- |
The site was previously a works area under Contract No. 8/LANDS/21 and was located in Wok Tai Wan. The works area was previously occupied by LandsD, AECOM (consultant) and Fraser Construction Company Limited (contractor) from 2018 to 2022. The works has already completed. As reported by the former site representative, the works area was previously used as storage area for construction materials (soil nail rebars, erosion control mat, wire mesh, planks, steel moulds) only. No vehicle / equipment maintenance / refuelling activities / chemical storages were reportedly carried out on site.
Based on observation, the site was currently vacant. The site was paved with bricks with no signs of chemicals or chemical stains / spillage or stressed vegetation were observed. No vehicle / equipment maintenance / refuelling activities was observed within the site.
Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site.
|
Photo No. 6085 in PR4 |
N/A |
No |
N/A |
|
WTY4 |
Lantau
Link Viewing Platform Car Park |
- |
The car park is located in Wok Tai Wan.
Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site.
|
Photo Nos. 1687 and 6094 in PR4 |
N/A |
No |
N/A |
|
Northeast Lantau |
|
|
|
|
|
|
|
|
LT1 |
CEDD Slope Works Site (13,800 m2) (Encroached Area: 12,500 m2) |
- |
The works site is under Contract No. GE/2020/10 Landslip Prevention and Mitigation Programme, 2017, Package F, Landslip Prevention and Mitigation Works and is located in Slope Features No. 10 NE-A/C 108, 500m east of the Toll Gate of North Lantau Highway. The works site is currently operated by CEDD, AECOM (consultant) and Fraser Construction Company Limited (contractor).
Based on site observations and as reported by the site representative, landslip preventive and mitigation works were carried out within the site. Based on observation, the site is largely unpaved except the works area in the northeast of the site was paved with plywood. No vehicle / equipment maintenance / refuelling activities are carried out on site. No signs of chemicals or chemical stains / spillage or stressed vegetation were observed.
An air compressor was observed with drip tray in good condition in the northeast of the site but was located outside the Proposed Clearance Limit. No signs of stain / spillage / stressed vegetation were observed in the vicinity of the air compressor.
Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site.
|
Photo Nos. 1469, 1478, 1485, 5924 and 5938 in PR1 |
N/A |
No |
N/A |
|
LT2 |
Vacant Land (GLA-TIS 801 & GLA-TIS 854) (20,200 m2) |
- |
The site is located in Tai Chuen and was inaccessible for detailed site walkover. No peripheral inspection was conducted for the site.
Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site.
|
N/A |
N/A |
To be confirmed when site is accessible for site walkover |
Works area / works storage / RBRGs (Industrial) (if applicable) |
|
LT3 |
Lantau Toll Plaza Administration Building (5,900 m2) |
- |
The site is located in Northeast Lantau.
Based on EPD / FSD information, there were no chemical spillage / DG / incident records for the site. There was an invalid CWP record within the site (refer to CWP ID 16 in Table 7.4), associated with the administration building. However, as discussed above, the facilities, including the administration building, will be retained under the Project, and no signs of contamination / contaminating activities were observed within the encroached portion of the site. Based on the above, no potential land contamination issue associated with the site to the Project is anticipated.
|
Photo Nos. 1537 and 1541 in PR2 |
N/A |
No
|
N/A |
Note:
1. Refer to Figure 7.1 for location of the sites.
2. The potential Chemicals of Concerns (COCs) were determined based on Practice Guide. For Site HUD1 and Site HUD2, the potential COCs are subject to change based on findings of further site appraisal when the site is accessible.
VOCs – volatile organic
chemicals; BTEX – benzene, toluene, ethylbenzene and xylenes; MTBE – methyl
tert-butyl ether; SVOCs – semi-volatile organic chemicals;
Polyaromatic hydrocarbons (PAHs) in the RBRGs include, acenaphthene,
acenaphthylene, anthracene, benzo(a)anthracene, benzo(a)pyrene,
benzo(b)fluoranthene, benzo(g,h,i)perylene, benzo(k)fluoranthene, chrysene,
dibenzo(a,h)anthracene, fluoranthene, fluorene, indeno(1,2,3-cd)pyrene,
naphthalene, phenanthrene and pyrene;
PCRs – petroleum carbon ranges; PCBs – polychlorinated biphenyls; and TBTO – tributyltin oxide.
Table 7.8 Summary of Concerned Off-site Facilities / Works Areas
|
Concerned Site ID |
Site Name1 |
Site Observation / Current Potentially Contaminating Activities |
Corresponding Photographic Record Reference in Appendix D of Appendix 7.1 |
Past Potential Contaminating Land Use / Activities |
Potential Off-Site Source of Land Contamination? |
|
TYTL 108RP & TYTL 80, West Tsing Yi |
|||||
|
HUD3 |
Sai Tso Wan 2 Concrete Batching Plant (TYLL 108RP) (13,800 m2) |
The site is located at the eastern end of Tsing Ma Bridge. The site is located within the Project Area but is approximately 10 m from the Proposed Clearance Limit, separated by fences and the existing Sai Tso Wan Road. The site was inaccessible for site inspection.
Based on peripheral observation, the site was largely paved with concrete with good condition. Concrete batching facilities and electricity substation were observed within the site (approx. 23 m and 10 m from the Proposed Clearance Limit respectively). The fences and the portion of Sai Tso Wan Road were in good condition with no signs of chemicals stain / leakage / stressed vegetation observed.
Based on EPD information, there was no record of spillage / leakage of chemical wastes or chemicals for the site. However, there are a total of 3 valid CWP records associated with either Site HUD2 or HUD3.
Based on FSD information, there were no incidents involving DG/chemicals within the site. However, there were a total of 6 issued DG licenses related to either Site HUD1, Site HUD2 or Site HUD3.
|
Photo Nos. 1038 in PR6 and 1014 in PR7 |
· Former container storage (1983)
|
No Given there are physical separation between the site, and no signs of chemicals stain / leakage / stressed vegetation observed on the Sai Tso Wan Road, the site is therefore not considered as an off-site source of land contamination to the Project. |
|
West Tsing Yi / Sai Tso Wan |
|||||
|
STW3 |
Shell Tsing Yi Installation (TYTL 108 S.A) (150,900 m2) |
The site is located in Sai Tso Wan outside the Project Area. The site is located approximately 10 m from the Proposed Clearance Limit (Site STW1), enclosed with concrete fences and separated by Sai Tso Wan Road. The site was inaccessible for the site inspection.
Based on peripheral observation, the site was paved with concrete. Fuel tanks and administration building were observed within the site. The concrete fences and the portion of Sai Tso Wan Road near the oil installations was in good condition with no signs of chemical stains / spillage and stressed vegetation observed. Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site.
|
Photo Nos. 1010, 0812, 0997 in PR10 |
· Former dockyard (1983)
|
No
Given there are physical separations between the site and the Proposed Clearance Limit, and no signs of chemicals stains / spillage and stressed vegetation observed in the portion of Sai Tso Wan Road near the oil installation, the site is not considered as an off-site source of land contamination to the Project. |
|
Tsing Ma Control Area |
|||||
|
TM2 |
TMCA – Workshop (5,600 m2) |
The site is located in Tsing Ma Control Area (TMCA), and mainly comprise of access road, vegetation and 2 suspected workshop structures. The suspected workshop structures are located east of the site away from the Proposed Clearance Limit. Although the boundary of the site is less than 1m from the Proposed Clearance Limit, the closest distance of the workshop structures to the Proposed Clearance Limit is approximately 22 m. The site was inaccessible for site inspection.
Based on peripheral observation, areas of the site closest to the Proposed Clearance Limit were access road, concrete Jersey barriers and vegetation only. These areas separated the Proposed Clearance Limit from the suspected workshop structures and were observed in good condition with no signs of chemicals stain / leakage / stressed vegetation.
Based on EPD information, there was no record of spillage / leakage of chemical wastes or chemicals for the site. However, there were a total 4 valid and 1 invalid CWP records associated with the TMCA facilities.
Based on FSD information, there were no incidents involving DG/chemicals within the site. However, there were a total of 5 issued DG licenses associated with the TMCA facilities.
|
Photo Nos. 1703 and 5972 in PR4 |
N/A |
No
Given there were physical separations between the suspected workshop structures and the Proposed Clearance Limit and the physical separations were observed in good condition with no signs of chemicals stains / spillage and stressed vegetation, the site is not considered as an off-site source of land contamination to the Project |
|
TM3 |
TMCA - Tsing Yi Interchange Depot (7,100 m2) |
The site is located in TCMA within the Project Area and is situated on the top of the rocky slope (refer to Photo 5738 in PR6). The rocky slope itself is within the Proposed Clearance Limit with height of approximately 65 m. Although the boundary of the site is less than 1m from the Proposed Clearance Limit, the nearest proposed works under the Project are expected to be the open road section of TYLL, approximately 23 m from the site. The site was inaccessible for site inspection.
Based on peripheral observation, the site was surrounded by vegetation and the area closest to the Proposed Clearance Limit was vegetation only. The vegetation was observed to be in good condition with no signs of stain / spillage / stressed vegetation.
Based on EPD information, there was no record of spillage / leakage of chemical wastes or chemicals for the site. However, there were a total 4 valid and 1 invalid CWP records associated with the TMCA facilities.
Based on FSD information, there were no incidents involving DG/chemicals within the site. However, there were a total of 5 issued DG licenses associated with the TMCA facilities.
|
Photo Nos. 3090 and 5738 (rocky slope) in PR6 |
N/A |
No
Given the site is situated on the top of the rocky slope, and the area near the Proposed Clearance Limit were rocky slope and vegetation only, the site is not considered as an off-site source of land contamination to the Project. |
|
Northeast Lantau |
|||||
|
LT5 |
MTRL - East Lantau Traction Substation & East Lantau Tunnel (East) Ventilation Building (1,700 m2) |
The site is located within the Project Area, at the base of the rocky slope. The rocky slope itself is within the Proposed Clearance Limit. The site is located approximately 3 m from the Proposed Clearance Limit. The building structures within the site (ventilation building and traction substation) were observed separated from the Proposed Clearance Limit by the access road and fences. The site was inaccessible for site inspection.
Based on the peripheral observation, the site was paved with concrete. The fences and access road were observed in good condition with no signs of chemicals stain / leakage / stressed vegetation. Based on EPD / FSD information, there were no CWP / chemical spillage / DG / incident records for the site. |
Photo Nos.1441 and 1500 in PR1 |
N/A |
No
The site was located at the base of the rocky slope. The physical separation (access road) between the building structures and the Proposed Clearance Limit were observed in good condition with no signs of chemicals stain / leakage / stressed vegetation. The site is therefore not considered as an off-site source of land contamination to the Project. |
Note:
1. Refer to Figure 7.1 for the location of the sites.
· Urban Residential;
· Rural Residential;
· Industrial; and
· Public Park.
Site STW1
Site HUD1 and Site HUD2
Table 7.9 Proposed Sampling and Testing Plan
|
Site ID |
Hotspot(1) |
Sampling Location ID (1) |
Sampling and Testing Rationale |
Grid Size (m2) |
Sampling Method |
Sample Matrix/ Depth (2) |
Parameters to be Tested (3) |
||||
|
VOCs |
SVOCs |
PCRs |
Metals |
||||||||
|
STW1 (25,700 m2) (Encroached area: |
Stain (24 m2) |
STW1-EBH01 to EBH03 |
Sampling to target the hotspot at the stain location (approx. 24 m2). |
4 |
Borehole drilling to 2m below the groundwater table or 6m bgl |
Soil |
(i) 0.5m bgl (ii) 1.5m bgl (iii) 3.0m bgl (iv) at GW level or 6m bgl(4) |
ü |
ü |
ü |
ü |
|
GW |
If present(4) |
ü |
ü |
ü |
Mercury only |
||||||
Notes:
(1) Refer to Figure 7.2 for hotspots and proposed sampling locations.
(2) bgl = below ground level; GW = groundwater
(3) The testing parameters refer to the parameters as shown in Table 2.1 – RBRGs for Soil & Soil Saturation Limit and Table 2.2 – RBRGs for Groundwater and Solubility Limit under VOCs, SVOCs, Metals and PCRs in the Guidance Manual.
Since RBRGs values of benzo(a)anthracene, benzo(a)pyrene, benzo(g,h,i)perylene, benzo(k)fluoranthene, bis-(2-Ethylhexyl)phthalate, dibenzo(a,h)anthracene, indeno(1,2,3-cd)pyrene and phenol were not available for groundwater, the said parameters would not be tested in groundwater samples.
(4) The actual
depth of soil sampling would be subjected to site constraints (e.g.
encountering of boulders or underground concrete structures). The termination
depth of sampling should be at groundwater table or 6m bgl, whichever is
shallower. Groundwater sample would only be collected if encountered.
Table 7.10 Preliminary Sampling and Testing Plan
|
Site ID (1) |
Suspected Potentially Contaminating Land Use (2) |
Approx. Site Area (m2) |
Approx. Site Area within Proposed Clearance Limit (m2) |
Testing Parameters (Potential COCs)(3) |
Recommended Minimum Number of Sampling Locations within the Proposed Clearance Limit (4) |
|
HUD1 |
Dockyard (including electrical substation, open storage of steel reinforcing bars and workshop), former electrical substation and former container storage |
89,500 |
24,000 |
Metals (Full List), VOCs (Full List), SVOCs (Full List), PCRs, PCBs (for substation only), free cyanide (for shipyard only), dioxins and furans (for shipyard only and if presence of incineration / burning activities) and TBTO (for shipyard only) |
32 |
|
HUD2 |
Concrete batching plant, electrical substation, former container storage and former open storage |
15,300 |
960 |
Metals (Full List), VOCs (Full List), SVOCs (Full List), PCRs and PCBs (for electrical substation only) |
6 |
Notes:
(1) Refer to Figure 7.1 for the sites.
(2) Due to limited site access and only peripheral site inspections were carried out, the land use may be subject to change after further site appraisal.
(3) The potential COCs are based on findings of the Practice Guide and will be confirmed after the site is accessible for further site appraisal.
Full list refers to the parameters as shown in Table 2.1 – RBRGs for Soil & Soil Saturation Limit and Table 2.2 – RBRGs for Groundwater and Solubility Limit under metals, Volatile Organic Compounds (VOCs), Semi-Volatile Organic Compounds (SVOCs), and Petroleum Carbon Ranges (PCRs) in the Guidance Manual.
PCBs refer to polychlorinated biphenyls
TBTO refers to tributyltin oxide
(4)
Based
on Table 2.1 of Practice Guide and site area within the Proposed Clearance
Limit. The actual number of sampling locations will be subject to the findings
of the further site appraisal when the site is accessible.
7.9.1 Recommended Further Works
7.9.2 Mitigation Measures for Remediation Works
· Excavation profiles must be properly designed and executed with attention to the relevant requirements for environment, health and safety;
· Excavation shall be carried out during dry season to minimise contaminated run-off from contaminated soils;
· Supply of suitable clean backfill material (or treated soil) after excavation;
· Stockpiling site(s) shall be lined with impermeable sheeting and bunded. Stockpiles shall be fully covered by impermeable sheeting to reduce dust emission. If this is not practicable due to frequent usage, regular watering shall be applied. However, watering shall be avoided on stockpiles of contaminated soil to minimise contaminated run-off;
· Vehicles containing any excavated materials shall be suitably covered to limit potential dust emissions or contaminated wastewater run-off, and truck bodies and tailgates shall be sealed to prevent any discharge during transport or during wet conditions;
· Speed control for the trucks carrying contaminated materials shall be enforced;
· Vehicle wheel and body washing facilities at the sites’ exit points shall be established and used; and
· Pollution control measures for air emissions (e.g. from biopile blower and handling of cement), noise emissions (e.g. from blower or earthmoving equipment), and water discharges (e.g. run-off control from treatment facility) shall be implemented and complied with relevant regulations and guidelines.