|
Highways Department
|
Agreement No. CE 78/2022 (HY)
Tsing Yi – Lantau Link
– Investigation, Design and Construction
Environmental Impact Assessment Report –
Executive Summary
September 2025
|
|
|
|
|
Prepared and Checked by: |
|
15 September 2025 |
|
Lam, Cheung Fai HKIQEP EIA Expert (Membership No. PM0131)
|
||
AECOM ASIA COMPANY LIMITED
Disclaimer:
This report is prepared for Highways Department (HyD) and is given for its sole benefit in relation to and pursuant to Agreement No. CE 78/2022 (HY) Tsing Yi – Lantau Link – Investigation, Design and Construction and may not be disclosed to, quoted to or relied upon by any person other than HyD without our prior written consent. No person (other than HyD) into whose possession a copy of this report comes may rely on this report without our express written consent and HyD may not rely on it for any purpose other than as described above.
TABLE OF CONTENTS
1.2 Purpose of this Executive Summary
2.1 Objective and Scope of Project
2.2 Designated Projects under Environmental Impact Assessment Ordinance
2.4 Consideration of “With” and “Without” Project Scenarios
2.5 Environmental Benefits of the Project
2.6 Design Changes to the Project
2.7 Consideration of Alignment Options
2.8 Construction Methodologies
3. KEY FINDINGS OF THE ENVIRONMENTAL IMPACT ASSESSMENT
3.5 Waste Management Implications
3.7 Terrestrial and Marine Ecological Impact
3.9 Landscape and Visual Impacts
3.10 Cultural Heritage Impact 22
4. Environmental monitoring and audit (EM&A)
5. Summary of ENVIRONMENTAL outcomes
List of Tables
Table 2.1 Schedule 2 Designated Projects in this Project
Table 2.2 Summary of Landing Options
Table 2.3 Summary of Alignment Options for Tsing Yi Connection
Table 2.4 Summary of Alignment Options for Main Bridges cum North Lantau Interchange
Table 2.5 Summary of Alternative Mitigation Measures
Table 2.6 Summary of Possible Construction Methods for the Project
Table 5.1 Summary of Key Environmental Problems Avoided and Sensitive Areas Protected
Table 6.1 Summary of Environmental Impacts
List of Figures
Figure 2.1 General Layout Plan
Figure 2.2 Designated Project Elements
Figure 2.3 Alternative Alignment Options
· Section 2 presents the purpose and nature of the Project, consideration of alternative options and construction methods for the Project;
· Section 3 presents the key findings of the environmental impact assessment;
· Section 4 describes the proposed environmental monitoring and audit programme for the Project; and
· Section 5 presents the conclusions.
(a) construction of the cable-supported bridges crossing the MWF and KSMF (hereinafter referred to as the “Main Bridges”) including:
(i) a dual three-lane 3-span continuous and earth-anchored suspension bridge crossing the MWF between Ma Wan and Tsing Yi with a main span of about 1400 m;
(ii) a dual three-lane earth-anchored single-tower suspension bridge crossing the KSMF between North Lantau and Ma Wan with a main span of about 500 m;
(b) construction of North Lantau Interchange, consisting of slip roads, tunnel and viaducts at North Lantau to connect the cable-supported bridge crossing the KSMF to North Lantau Highway, the proposed Tsing Lung Bridge under Route 11 and the proposed Hong Kong Island West – Northeast Lantau Link (HKIW-NEL Link);
(c) construction of Tsing Yi Connection, consisting of extension of the TYLL mainline from the proposed cable-supported bridge crossing the MWF to connect with the Tsing Sha Highway at the west of Nam Wan Tunnel and provision of slip roads and viaducts to connect with the local roads in Tsing Yi;
(d) construction of viaduct at Ma Wan South to connect the Main Bridges;
(e) modification / realignment of Tsing Sha Highway and Cheung Tsing Highway; and
(f) associated works including civil, marine, drainage, sewerage, road works, traffic aids, street lighting, traffic control and surveillance system (TCSS), toll collection facilities, bridge facilities, fire services works, electrical and mechanical (E&M) works, re-provisioning of facilities affected and utility diversion, environmental mitigation works, landscaping works, site clearance and demolition, earth works, slope works, geotechnical works, natural terrain hazard mitigation works, reclamation works, etc.
Table 2.1 Schedule 2 Designated Projects in this Project
|
Schedule 2 Designated Project (1) |
Designated Project Element under the Project |
|
|
Item A.1 |
A carriageway for motor vehicles that is an expressway, trunk road, primary distributor road or district distributor road. |
TYLL, comprising Main Bridges, North Lantau Interchange and Tsing Yi Connection, is proposed as trunk road. |
|
Item A.8 |
A carriageway bridge for motor vehicles, or a railway bridge, the length between abutments for which is more than 100 m, with bridge piers over the sea supporting the bridge. |
· A 3-span continuous and earth-anchored suspension bridge crossing the MWF between Ma Wan and Tsing Yi with a main span of about 1400 m. · A single-tower suspension bridge crossing KSMF between North Lantau and Ma Wan with a main span of about 500 m. |
|
Item C.1 |
Reclamation works (including associated dredging works) more than 5 ha in size. |
· Tsing Yi Tower Island: approximately 6.0 ha in size. · Ma Wan South Tower Island: approximately 7.9 ha in size. · Ma Wan South Anchorage Island: Approximately 4.7 ha in size. · Kap Shui Mun Tower Island: approximately 1.2 ha in size. · Total reclamation area: 19.8 ha. |
|
Item C.2 |
Reclamation works (including associated dredging works) more than 1 ha in size and a boundary of which is less than 500 m from the nearest boundary of an existing or planned specified area (2) that is wholly or partly situated on or over any foreshore and sea-bed (3). |
· The nearest boundary of Ma Wan Tung Wan Beach is located within 500m from the boundary of reclamation works for the Ma Wan South Anchorage Island. |
|
Item C.12 |
A dredging operation that is less than 500m from the nearest boundary of an existing or planned specified area (2) that is wholly or partly situated on or over any foreshore and sea-bed (3). |
· The nearest boundary of Ma Wan Tung Wan Beach is located within 500m from the dredging operation for the Ma Wan South Anchorage Island. |
Notes:
(1) Refer to the amended Schedule 2, Part I of EIAO (effective since 30 June 2023).
(2) For this Project under Items C.2 and C.12, specified area refers to bathing beach.
(3) Foreshore and sea-bed has the meaning given by section 2 of the Foreshore and Sea-bed (Reclamations) Ordinance (Cap. 127).
Table 2.2 Summary of Landing Options
|
Alignment Option |
Pros |
Cons |
Recommended Option (Y/N) |
|
Recommended Alignment |
· Connection to the Tsing Yi North Coastal Road Cheung Tsing Highway and Tsing Sha Highway. · Adequate separation between TYLL and Tsing Ma Bridge to prevent aerodynamic interference. · Minimised the proportion and extent of slope work, and at-grade roads were minimised and strategically positioned along the existing developed area. · Smaller reclamation extent compared to Alternative Landing Options 1 and 2. |
/ |
Y |
|
Alternative Landing Option 1 |
/ |
· No connection to the Tsing Yi North Coastal Road. · Travelling distance is about 40% longer than the Recommended Alignment · Additional reclamation works and considerable amount of cut slopes and tunnelling works associated with the proposed slip roads in Tsing Yi west would be required · Generate large amount of C&D materials |
N |
|
Alternative Landing Option 2 |
/ |
· Aerodynamic interference of two closely spaced long-span bridges would cause road safety concerns on both Tsing Ma Bridge and TYLL. · Additional reclamation works and realignment of Ma Wan Fairway would be required · Proposed alignment and its associated reclamation would be very close to the existing residential blocks of Ma Wan and Ma Wan Tung Wan beach, resulting in significant visual and environmental impacts. |
N |
|
Alternative Landing Option 3 |
/ |
· Inadequate space and headroom for proposed slip road connection to Cheung Tsing Highway and Tsing Sha Highway due to the presence of several layers of existing viaducts at merging / diverging points. · Proposed alignment is close to the existing oil depot and there might not be adequate space for constructing hazard mitigation measures. |
N |
Table 2.3 Summary of Alignment Options for Tsing Yi Connection
|
Alignment Option |
Pros |
Cons |
Recommended Option (Y/N) |
|
Tsing Yi Option 1 |
· Direct connection to Tsing Yi Road West. |
· Construction of viaduct TYRWV requires land adjacent to Sai Tso Wan Road. · No direct connection between TYLL and Cheung Tsing Tunnel (CTT). · Large temporary working platforms are anticipated for the construction of bored pile wall along existing slopes. · Affect large number of trees (~909 nos. of trees) at existing slope. · Closer to the two existing PHIs (~20m) and air sensitive receivers (ASRs) at Sai Tso Wan. · Large construction area would impose greater environmental implication. |
N |
|
Tsing Yi Option 2 |
· Retaining wall construction would not be required. |
· Construction of TYRWV requires land adjacent to Sai Tso Wan Road. · Appropriate widening of the marginal strips or hard shoulders to satisfy adequate forward visibility distance. · No direct connection between TYLL and CTT. · Affect large number of trees (~909 nos. of trees) at existing slope. · Closer to the two existing PHIs (~10m) and ASRs at Sai Tso Wan. · Large construction area would impose greater environmental implication and generate higher amount of construction waste. |
N |
|
Tsing Yi Option 3 (Recommended) |
· The amount of retaining structures is less than Tsing Yi Option 1 and 2. · The modification of existing road is less than Tsing Yi Option 2 by approximately 4.3km. · Direct connection of TYLL westbound and Cheung Tsing Tunnel westbound. · TYRWV incorporated into Tsing Sha Highway. · Omission of TYRWV leads to smaller construction works area and minimise landscape and visual impacts. · Affect smaller number of trees (~461 nos. of trees) at existing slope. · Further away from the existing PHIs (~60m); relatively fewer air sensitive receivers and no noise sensitive receivers to be affected. · The works area is reduced by 15ha. as compared with Tsing Yi Option 1 and 2 |
· Appropriate widening of the marginal strips or hard shoulders to satisfy adequate forward visibility distance. · Large temporary working platforms are anticipated for the construction of bored pile wall along existing slopes. |
Y |
Table 2.4 Summary of Alignment Options for Main Bridges cum North Lantau Interchange
|
Alignment Option |
Pros |
Cons |
Recommended Option (Y/N) |
|
Main Bridges cum North Lantau Option 1 |
· Full closure to KSMF is not required for cable-stayed bridge construction.
|
· Increased deck width of Lantau side span is required to cater for the merging/diverging length. · Significant increase on site-formation and tunnelling works required on North Lantau Island. · Require reclamation at North Lantau and larger reclamation area in Ma Wan. The total reclamation area is approximately 26.3ha. · Generate large amount of marine sediment. · An approximately 2,420 of trees would be affected. |
N |
|
Main Bridges cum North Lantau Option 2 (Recommended) |
· Curved alignment beginning at Lantau Shore with reduced site formation works. · Reclamation at North Lantau is not required. · The total reclamation area is approximately 19.8ha., which reduced the overall area of reclamation by approximately 6.5 ha as compared with Main Bridges cum North Lantau Option 1. · Minimise slope cutting at North Lantau hence preserve the natural features of the area to minimise ecological impacts and tree felling. · An approximately 1,920 of trees would be affected. |
· One-off short duration of full closure at KSMF is required. |
Y |
Summary of Alternative Mitigation Measures
Table 2.5 Summary of Alternative Mitigation Measures
|
Alternative Mitigation Measures |
Details |
Environmental Benefits |
Environmental / Engineering Disbenefits |
|
Reduce and reuse inert C&D Materials |
· Minimise slope works in North Lantau and Tsing Yi to reduce generation of excavated soil and yard waste; and · On-site reuse of inert C&D materials like reclamation filling. |
· Reduce total amount of inert C&D materials for disposal; and · Minimise transporting of C&D materials to Public Fill Reception Facilities (PFRFs) thus reducing potential air quality and noise impacts arising from the transportation vehicles / vessels. |
· NIL |
|
Encourage recycling of yard waste |
· Yard waste is encouraged to be sent to the Yard Waste Recycling Centre in Y-Park for recycling prior to disposal at the designated landfill site. |
· Generate new products from yard waste; and · Indirectly increasing the lifespan of existing landfill. |
· Yard waste might need to be stored on-site for a period; and · Increase in administration cost. |
|
Adopting GPS or equivalent system |
· Tracking and monitoring of all dump trucks to prohibit illegal dumping and landfilling of C&D materials. |
· Prohibit illegal dumping.
|
· NIL |
|
Disposal / treatment methods for marine sediment |
· Adoption of deep cement mixing (DCM) as a primary ground treatment method for reclamation. |
· Avoid the need for disposal of thick marine deposits; and · Reduce disposal and transportation of marine sediment. |
· Ineffective in areas with shallow depth of marine deposits; and · May involve specialised equipment, materials, and expertise, leading to higher upfront costs compared to traditional dredging. |
|
Adopt pile-supported VIPS in the area of existing shoreline |
· Avoidance of reclamation at North Lantau shoreline; and · Protect the deflection pier at North Lantau from vessel impact. |
· Reclamation is no longer required at North Lantau, which benefit the preservation of the intertidal zone and ecosystem along the shoreline; and · Alleviate the water pollution caused by the construction of reclamation land. |
· The VIPS and other pile-supported structures require ongoing maintenance to ensure their structural integrity, especially in a harsh marine environment. |
|
Adoption of Eco-shoreline |
· Incorporation of eco-shoreline design in the future coastal structures such as seawalls on the reclaimed land as well as surfaces and supporting structures on the pile-supported VIPS; and · Incorporation of elements that diversify microhabitats and enhance the quality of settlement substrates. |
· Present new opportunities for the recruitment, settlement and colonisation of marine benthos, thereby enhancing the overall quality of associated marine ecosystems in the vicinity; · Encourage recruitment and settlement of corals and other benthos; and · Provide sheltering habitats for marine wildlife. |
· Increase in construction cost and maintenance cost. |
Table 2.6 Summary of Possible Construction Methods for the Project
|
Section |
Possible Construction Method |
Selection Reason |
|
Tunnel |
Drill-and-blast |
· Significantly decrease and limit potential environmental impacts, specifically concerning noise, dust, and visual disturbances to areas in close proximity to the portals · More effective for rock tunnel excavation than mechanical breaking methods, which significantly reduces the construction period, providing both financial benefits and faster project commissioning |
|
Reclamation |
DCM (primary ground treatment method) |
· Considered as the most robust option with the least shortcomings when compared with other ground treatment schemes given the Project’s needs · Avoid the need for disposal of thick marine deposits |
|
Fully dredged method (for areas where DCM is ineffective) |
· For areas with soft marine deposits where DCM is ineffective, it is technically required to dredge the whole layer of marine deposits and replace it with firm materials for controlling the settlement of the reclaimed islands and to ensure stability of the seawall structures |
|
|
Pile-supported VIPS |
Bored pile |
· The bored piles would be used for supporting the VIPS. It aims to provide the protection to bridge structures. · Reduction in vibration and noise generation during piling process as compared with other piling methods. |
|
Main Bridges (Foundation) |
Large diameter bored pile foundations for tower support |
· Accelerate construction · Reduce noise and minimising vibrations |
|
Main Bridges (Tower) |
Jump form or slip form methods for tower construction |
· Considered as the most robust option taking account into the construction time, cost, durability, and maintenance requirements · Less C&D materials / waste generated |
|
Viaducts |
Precast concrete segmental method |
· Better control of quality and workmanship for works in fabrication yard · Minimise the need for on-site concrete casting · Use of steel mould as formwork in the fabrication yard can reduce the generation of C&D waste / materials on site · More efficient construction works as the deck segments can be cast concurrently with superstructure works |
|
Rock Cuttings |
Open blasting (Recommended for Lantau side) |
· Optimise cost and time efficiency for hard rock slopes · Noise only generated at specific times |
|
Hydraulic excavation (Recommended for Tsing Yi side |
· Explosives not required, thus reducing risk to the two PHIs at Tsing Yi. |
1. Installation of silt curtain;
2. Dredging for seawall and four main reclamation area simultaneously (Approx. 12 numbers of dredgers);
3. Installation of geotextile, sand blanket and primary silt curtain;
4. Carry out DCM (approx. 50%) for main reclamation area;
5. Backfilling of fully dredged zone;
6. Installation of rockfill; and
7. Reclamation filling to formation level.
· In order to preserve the headwater of the north-branching tributary in watercourse at North Lantau, it is proposed to replace the intersecting section with a box culvert and relocating the permanent structures to avoid encroachment;
· Implement temporary stream diversions to maintain waterflow; and
· Establish work exclusion zones around watercourses and use elevated platforms to minimise impact on banks and stream beds.
· Close liaison with the contractors of other concurrent projects in order to avoid overlapping of construction activities and allow sufficient buffer for works at project interface due to potential delays in the programme so that the cumulative effects of environmental impacts could be minimised.
Land Based Works
· Temporary stream diversion to maintain the downstream water flow, works exclusion zones and elevated platforms will also be implemented before construction works around watercourses where required to minimise the ecological impact. As the impact on amphibians and other aquatic species of conservation interest are mitigated through translocation works (if applicable) after pre-construction survey, the environmental impact has been minimised such that a specific sequence of land-based works is not considered necessary.
· Blast cages or roof-over protective cover would be provided before the commencement of open blasting works to minimise the air and noise impacts of blasting. During the construction of drill and blast tunnels, a blast door will be installed in the tunnel openings to prevent the escape of fugitive dust from blasting before further blasting works within the tunnels. Therefore, the air and noise impacts are minimised for most periods of the tunnel construction through the blast door. With these mitigation measures, the carrying out of the construction of the two tunnels and slip roads concurrently would result in a similar environmental impact and is assumed in conducting the assessment in lieu of a specific construction sequence.
Marine Works
· Silt curtains will be installed before reclamation works to minimise the marine water quality, marine ecology and fisheries impacts of the works. The worst-case scenario has been considered for the water quality impacts of the reclamation works based on a tentative construction sequence.
· The use of VIPS for vessel protection of the deflection pier at North Lantau reduces the time required for the construction works there when compared to using reclamation for vessel protection, requiring only about 10 months to complete the piling works. This further minimises the marine water quality, marine ecology and fisheries impacts of the works. The sediment release rate for VIPS is minuscule, being less than 1% of the sediment release rate of the reclamation works. Therefore, it is considered that a specific sequence of works for VIPS is not necessary.
· Air Quality Impact
· Noise Impact
· Water Quality Impact
· Waste Management Implications
· Land Contamination
· Ecological Impact
· Fisheries Impact
· Landscape and Visual Impact
· Cultural Heritage Impact
· Hazard to Life
Table 5.1 Summary of Key Environmental Problems Avoided and Sensitive Areas Protected
|
Design Approach |
Environmental Problems Avoided and Sensitive Areas Protected |
|
Optimised the alignment
|
· The current alignment avoided direct impact on residential development at Ma Wan and indirect impact on Ma Wan Egrety, as well as direct or indirect impacts on Tung Lung Chau Lighthouse which is a declared monument. |
|
Adoption of environmentally friendly construction methods |
· Adoption of off-site precast structures / modular integrated construction method to minimise the impacts on air quality, noise, water quality and waste during construction. |
|
Minimisation of extensive retaining structures on existing geotechnical features at Tsing Yi |
· The refined alignment design reduced slope works and land resumption at Tsing Yi; · No. of affected air and noise sensitive receivers have been reduced; and · The landscape and visual impacts at the Tsing Yi Connection has been minimised. |
|
Avoidance of Reclamation at North Lantau Shoreline
|
· The avoidance of reclamation at North Lantau would benefit the preservation of the intertidal zone and ecosystem along the shoreline, including six species of conservation importance at the intertidal zone. |
|
Minimisation of reclamation and dredging extents for the reclamation in Ma Wan and Tsing Yi |
· The total amount for dredged sediments has been reduced, hence reducing the associated water quality impacts during construction phase · The extent of channel narrowing at both MWF and KSMF has been reduced, hence reducing the change in hydrodynamic regime under operation phase. · The total reclamation area has been reduced by about 17 %. |
|
Minimisation of slope cutting
|
· Minimised disruption to the landscape resources and characters · Minimised potential impacts to the natural habitats and associated ecology · Minimised the amount excavation spoil and generation of C&D materials. |
|
Avoidance of direct impact to ecological sensitive area |
· The current alignment avoided potential direct and indirect impacts on recognised sites of conservation importance and other ecologically sensitive areas, such as the Ma Wan Egretry and Night Roost located on the Project's northern side |
|
Minimisation of Habitat Loss |
· To minimise the extent of habitat loss and its impact on the ecology in this area, the proportion and extent of slope works and at-grade roads were minimised and strategically positioned along existing developed area. · Some road sections in North Lantau have opted for tunnel or viaduct form to minimise the footprint of at-grade works and to avoid ecological impact, i.e. the viaduct section at Yi Chuen and tunnel connecting HKIW-NEL Link, which avoid impact on concerned watercourse. |
|
Avoidance of illegal dumping
|
· The recommended preventive measures would avoid / minimise the chance of illegal dumping. |
|
Implementation of Environmental Monitoring and Auditing System
|
· Ensure all the recommended measures are properly in place and their effectiveness. |
Table 6.1 Summary of Environmental Impacts
|
Sensitive Receivers / Assessment Points |
Impact Prediction Results (Without Mitigation) |
Key Relevant Standards/Criteria |
Extents of Exceedance (Without Mitigation) |
Impact Avoidance Measures / Mitigation Measures |
Residual Impacts (After Implementation of Mitigation Measures) |
||
|
Air Quality Impact |
|||||||
|
Construction Impact |
|||||||
|
Representative existing residential, commercial developments and government uses within 500m from the boundary of the Project site. |
· Potential air quality impact from the construction works of the Project would mainly be related to construction dust from site formation, site clearance, excavation, reclamation, tunnelling, foundation works, handling and stockpiling of dusty materials, wind erosion of exposed area and operation of barging points, use of on-site mechanical machineries, and gaseous emissions from construction vehicles and construction vessels. · Potential air quality impact would also be expected from operation of a potential temporary concrete batching plant. · Potential odour impact from dredged sediment. · The cumulative air quality impacts from concurrent projects within the 500 m assessment area have been assessed. |
· Annexes 4 and 12 of the EIAO-TM · Air Quality Objectives (AQOs) |
N/A |
Control measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices listed below shall be carried out to further minimise construction air quality impact: · Use of regular watering to reduce dust emissions from blasting, exposed site surfaces and unpaved roads, particularly during dry weather; · Use of frequent watering for particularly dusty construction areas and areas close to ASRs; · Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines; · For the work sites close to the ASRs with a separation distance less than 10 m, provide hoardings of not less than 3.5 m high from ground level along the site boundary; for the other work sites in general, provide hoarding not less than 2.4 m high from ground level along site boundary except for site entrance or exit; · Avoid position of material stockpiling areas, major haul roads and dusty works within the construction site close to concerned ASRs; · Avoid unnecessary exposed earth; · Locate all the dusty activities away from any nearby ASRs as far as practicable; · Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty material storage piles near ASRs; · Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations; · Establish and make use of vehicle wheel and body washing facilities at the exit points of the site; · Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs; · Imposition of speed controls for vehicles on site haul roads; · The Contractor shall observe and comply with Air Pollution Control Ordinance (APCO) and its subsidiary regulation, particularly the Air Pollution Control (Construction Dust) Regulation; · The Contractor shall undertake at all times to prevent air nuisance as a result of the construction activities; · The Contractor shall ensure that there will be adequate water supply / storage for dust suppression; · The Contractor shall devise and arrange methods of working and carrying out the works in such a manner so as to minimise air quality impact on the surrounding environment, and shall provide experienced personnel with suitable training to ensure that these methods are implemented properly; · Before the commencement of any work, the Contractor may be required to submit the methods of working, plant, equipment and air pollution control system to be used on the site for the Project Manager’s inspection and approval · For the tunnelling works by drill-and-blast, in addition to the regular watering at spoiling handling and unpaved / paved haul roads, a blast door should be installed at the opening to avoid the escape of fugitive dust from the blasting. The blast door should remain closed and ventilation with dust filter with dust removal efficiency of at least 80% at exhaust should remain stopped during blasting. Water spaying should be applied to facilitate dust settlement. The areas within 30m from the blasting area should be wetted with water prior to blasting and blasting shall not be carried out when the strong wind signal or tropical cyclone warning signal No. 3 or higher is hoisted; · For open blasting activities, blast cages or roof-over protective cover should be provided, water spray should be provided before blasting and on blasted material prior to transportation, and at the mucking out locations, as well as regular watering at unloading points of spoils. Blasting shall not be carried out when the strong wind signal or tropical cyclone warning signal No. 3 or higher is hoisted; and · Dust control measures will be implemented in the potential CBP as required in A Guidance Note on the Technical, Management and Monitoring Requirements for Specified Process – Cement Works (Concrete Batching Plant) (BPM 3/2 (2025). Control measures to mitigate potential exhaust emission from non-road mobile machineries (NRMMs) during construction phase: · Connect construction plant and equipment to main electricity supply and avoid use of diesel generators and diesel-powered equipment; · Avoid exempted NRMMs as far as practicable; and · Deploy electrified NRMMs as far as practicable Control measures to mitigate potential odour impact: · Tarpaulin covering of dredged materials during transportation and temporary storage, etc. as far as practicable; · Instigation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if any air quality issues arise; · Barges would be equipped with tight fitting seals to ensure dredged materials are well confined; · Loading of dredged materials would be controlled to avoid splashing; and · Any odorous materials shall be transported away from the Project site within 24 hours. Control measures to mitigate potential air quality impact from construction vessels: · Switch off vessel engines during hotelling and utilise land-based electricity as far as practical; · Use fuel that fulfil requirements stated in the Air Pollution Control (Fuel for Vessels) Regulation and Air Pollution Control (Marine Light Diesel) Regulation; · Maintain navigation routes farthest away from ASRs as practicable; · The barging points should be provided with 1) tipping hall enclosed by 3-side screen with top; and 2) water spraying and flexible dust curtains; and · At the detailed design stage, project team should timely apply for the temporary electricity with a target that the necessary cables laying works could be completed before the commencement of the works contract. In addition, timely provision of electricity to construction sites can facilitate the use of Electric Vehicles (EVs) in public works contracts. The project team should specify the use of EV(s) as well as the installation of designated medium-speed charger for each EV as a standard provision at the site accommodation in each public works contract. |
· No adverse residual impacts anticipated. |
||
|
Operation Impact |
|||||||
|
Existing and planned residential, commercial developments and government uses within 500m from the boundary of the Project site. |
Air Quality Impact NO2 · 19th highest 1-hr average conc.: 100 – 124 μg/m3 · 10th highest 24-hr average conc.: 48 – 66 μg/m3 · Annual average conc.: 25 – 38 μg/m3
RSP · 10th highest 24-hr average conc.: 51 – 56 μg/m3 · Annual average: 19 – 22 μg/m3 FSP · 19th highest 24-hr average conc.: 28 – 30 μg/m3 · Annual average: 12 – 14 μg/m3
|
Prevailing AQO NO2 · 1-hr average conc.: 200 µg/m3 (Number of exceedances allowed: 18). · 24-hr average conc.: 120 µg/m3 (Number of exceedances allowed: 9). · Annual average conc.: 40 µg/m3. RSP · 24-hr average conc.: 75 µg/m3 (Number of exceedances allowed: 9). · Annual average conc.: 30 µg/m3. FSP · 24-hr average conc.: 37.5 µg/m3 (Number of exceedances allowed: 18). · Annual average conc.: 15 µg/m3. |
N/A |
· No adverse air quality impact is anticipated during the operational phase of the Project, thus mitigation measure is deemed not necessary. |
· No adverse residual impacts anticipated. |
||
|
Noise Impact |
|||||||
|
Construction Impact |
|||||||
|
Existing, planned and committed NSRs. |
· Adverse air-borne and ground- borne construction noise impacts are not anticipated with proper implementation of good control measures and environmental monitoring and audit. · The Contractor will also be required to prepare a CNMP. |
· Annexes 5 and 13 of the EIAO-TM
|
N/A |
Good control measures are recommended to minimise the construction noise impact as far as practical: · Good site practices to limit noise emissions at source; · Use of QPMEs and quieter construction methods; · Use of temporary noise barriers, movable noise barrier, noise enclosure noise insulating fabric, silencer, etc., to screen noise from construction equipment; · Install acoustic tunnel door or enclosure at tunnel portals for construction activities to be carried out inside tunnel during restricted hours; · Alternative use of plant items within one worksite, wherever practicable; and · Providing sufficient separation distance between NSRs and items of PME. |
· No adverse residual impacts anticipated. |
||
|
Operation Impact (Road Traffic Noise) |
|||||||
|
Existing, planned and committed NSRs within 300m from the Project Boundary |
Existing NSRs · Predicted overall noise levels ranged from 61 – 62 dB(A) under unmitigated scenario. · No noise exceedance is expected for all existing NSRs.
Planned and committed NSRs · No identified committed / planned NSRs with programme during preparing the EIA study so that no planned NSRs in this assessment. |
· Annexes 5 and 13 of the EIAO-TM
|
· N/A |
· Provision of low noise road surfacing on “Project Roads” with design speed of 80 km/hr or above under unmitigated scenario. |
· No adverse residual impacts anticipated. |
||
|
Operation Impact (Fixed Noise) |
|||||||
|
Existing, planned and committed NSRs. |
· No adverse impact arising from the Project is anticipated as no fixed noise sources would be proposed under the Project. |
· EIAO-TM Annex 5 and Annex 13, and IND-TM |
N/A |
N/A |
N/A |
||
|
Water Quality Impact |
|||||||
|
Construction Impact |
|||||||
|
Representative WSRs within 500m from the boundary of the Project site |
The potential sources of water quality impact associated with the construction works include: · Reclamation at different locations between North Lantau and Tsing Yi Island; · Potential dredging when it is unavoidable due to the presence of thin layer and soft marine deposits, or when the soils beneath the marine clay are excessively stiff, making it challenging or impractical to achieve the desired embedment condition using the DCM method; · Construction site run-off; · Wastewater discharges from general construction activities; · Accidental spillage of chemical; and · Sewage effluent produced by on-site workforce. |
· Annexes 6 and 14 of the EIAO-TM · WPCO (Cap. 358) · Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) · Practical Note for Professional Persons (ProPECC) PN 2/24 · Water Supplies Department (WSD) Water Quality Criteria (for flushing water intake) |
· The reclamation filling activities would result in short-duration exceedances observed during the wet season at WM4. |
· Deployment of silt-curtain; · Mitigation measures and good site practices in ProPECC PN 2/24 “Construction Site Drainage; · Practices in ETWB TC (Works) No. 5/2005 “Protection of natural streams / rivers from adverse impacts arising from construction works”; · Waste Disposal Regulation; and · Provision of interim treatment facilities, such as chemical toilets, for construction workforce. |
· No adverse residual impacts anticipated |
||
|
Operation Impact |
|||||||
|
Representative WSRs within 500m from the boundary of the Project site |
Potential water quality impacts associated with the operational phase include: · Change in hydrodynamic regime and local flow pattern in the vicinity of reclamation areas at Tsing Yi, Ma Wan and North Lantau; and · Surface run-off from paved areas of the Project. |
· Annexes 6 and 14 of the EIAO-TM · WPCO (Cap. 358) · TM-DSS · ProPECC PN 1/23 |
N/A |
· Adequate design in silt trap for the new road drainage which take into account the guidelines in ProPECC PN 1/23; and · Best Storm Water Management Practices and Storm Water Pollution Control Plan to reduce non-point source pollution. |
· No adverse residual impacts anticipated |
||
|
Waste Management Implications |
|||||||
|
Construction Impact |
|||||||
|
C&D materials, sediment, chemical wastes, general refuse and floating refuse |
· Around 2,227,500 m3 of Inert C&D materials would be generated during construction phase, while about 1,773,980 m3 would be reused on Site and 453,520 m3 would be deliver to Public Fill Reception Facilities; · Around 139,000 m3 of non-inert C&D materials will be generated; · Expected certain amount (about 140,279 m3 of category L and 56,206 m3 of Category M and H (equal to or not exceeding 10x LCEL)) of excavated / dredged sediment would be generated during reclamation and piling works; · Small quantity of chemical wastes in the order of few hundred litres per month; · Around 369 tonnes of general refuse will be generated from construction works and on-site staff and workers; and · Estimated only around 5m3 of trapped floating refuse per year would be collected from the newly constructed seawall. |
· Annexes 7 and 15 of the EIAO-TM · Waste Disposal Ordinance (Cap. 354) · Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N) · Land (Miscellaneous Provisions) Ordinance (Cap. 28) · Public Health and Municipal Services Ordinance – Public Cleansing and Prevention of Nuisances Regulation (Cap. 132BK) · Dumping at Sea Ordinance (DASO) (Cap.466) · Project Administration Handbook for Civil Engineering Works (PAH) |
N/A |
· Implementation of good site practices, waste reduction measures and proper storage, collection and transportation of waste. |
· No adverse residual impact anticipated |
||
|
Operation Impact |
|||||||
|
N/A |
· Only few hundred litres per month in maximum of chemical waste would be generated during regular maintenance activities; and · Estimated only around 5m3 of trapped floating refuse per year would be collected from the newly constructed seawall. |
· Waste Disposal Ordinance (Cap. 354)
|
N/A |
· Implementation of good site practices, waste reduction measures and proper storage, collection and transportation of waste. |
· No adverse residual impact anticipated |
||
|
Land Contamination |
|||||||
|
Onsite construction workers and future occupants |
· Three potentially contaminated sites have been identified. When site access is available, SI will be carried out to determine the extent of the contamination, if any. |
· Annex 19 of the EIAO-TM · Guidance Note for Contaminated Land Assessment and Remediation (EPD, April 2023) · Practice Guide for Investigation and Remediation of Contaminated Land (EPD, April 2023) · Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (EPD, April 2023) |
N/A |
· Sampling and testing plans had been proposed for the potentially contaminated sites; · Further site appraisal should be carried out within the Proposed Clearance Limit and off-site facilities / works areas at a later stage of the Project in order to confirm / update the land uses / activities and to identify the presence of on-stie and off-site potential contamination sources; · In addition, should there be any expansion of the Proposed Clearance Limit, further site appraisal would also be required to be carried out within the expanded area; · CAP(s), presenting the findings of the further site appraisal, the latest site conditions of the concerned sites, updated sampling strategy and testing protocol, should be submitted to EPD for approval; and · The recommended further assessment and remediation works, including the submission of CAP(s), CAR(s) / (RAP(s) and RR(s) should follow relevant Guidance Manual, Guidance Note and Practice Guide. |
· No residual impact is anticipated |
||
|
Ecological Impact |
|||||||
|
Construction Impact |
|||||||
|
Ecological resources likely to be impacted by the Project |
· Impact of permanent and temporary loss of developed area, plantation, shrubland / grassland, watercourses W1 and intertidal zone is considered low; while that on watercourses W2 and W3, and the sea is considered low to moderate; · Impact of loss, injuries or mortalities of species of conservation importance with high mobility, flight ability and/or with low site fidelity, e.g. avifauna, mammals, butterflies and reptiles is considered low; · Impact of loss, injuries or mortalities of species of conservation importance with lower mobility, or with restricted habitat niche is considered:- - Low to moderate for plants and corals; - Low to moderate for Romer’s Tree Frog; and - Low for amphioxus. · Impact of habitat fragmentation and wildlife movement is considered low to moderate; · Impact of construction disturbance on adjacent habitats, species of conservation importance and associated flora and fauna is considered low; and · Impact of changes in water qualities, hydrodynamic properties and sedimentation hydrology due to run-off, discharge and reclamation on aquatic-associated species is considered: - - Low on watercourses, marine habitats and associated fauna; - Low to moderate on Romer’s Tree Frog and Caridina serrata; and - Low on marine habitats and associated fauna |
· Annex 8 and Annex 16 of EIAO-TM |
N/A |
· Minimising and localising at-grade works to lower quality habitats such as developed area and plantation; · Minimising the extent of loss of more natural habitats such as watercourses and shrubland / grassland by opting for tunnel and viaduct sections; · Minimising the land required for temporary works to the necessary minimum for the proposed works; · Minimising the extent of permanent loss, retaining waterflow of W2 through avoiding works at its upper tributary and constructing box culvert at section coinciding with at-grade road section; · Optimising tunnel length and level to avoid and minimise the extent of loss of W3; · Where no actual construction works are required, vegetation clearance along watercourses should be avoided, adoption of work exclusion zone and elevated temporary works planform atop watercourses should be implemented to avoid and minimise impact on watercourse; · Minimising overall reclamation extent by opting for pile-supported VIPS at North Lantau, the construction for which would be of much smaller scale and extent, and reclamation at Yi Chuen is avoided; · Conduct detailed pre-construction survey to identify individuals of plant, coral and amphibian species of conservation importance to be affected by works; · Carry out in-situ preservation, transplantation / translocation or compensation planting where appropriate to avoid and minimise direct impact on plant, coral and amphibian species of conservation importance; · Leverage enhancement opportunities presented by newly established coastal structures/shorelines to incorporate eco-shoreline features/elements; · Implementation of construction phasing and habitat reinstatement following completion of temporary works to minimise the impact of habitat fragmentation and wildlife movement impediment; · Implementation of precautionary measures and good site practice to minimise construction disturbance on adjacent habitats, species of conservation importance and associated flora and fauna; · Temporary stream diversion to retain waterflow and avoid run-off of construction materials into watercourses in accordance to guidelines specified in ETWB TC(W) No. 5/2005 Protection of Natural Streams/Rivers from Adverse Impacts Arising from Construction Works (ETWB, 2005); · Implementation of water quality specific mitigation measures recommended in the WQIA and best management practices as stipulated in ProPECC PN 2/24 “Construction Site Drainage” and ETWB TC(W) No. 5/2005 “Protection of natural streams/rivers from adverse impacts arising from construction works” to reduce the impact of water quality deterioration due to run-off, discharge and reclamation on waterbodies and aquatic-associated species; and · Deployment of silt curtains during reclamation and other marine works. |
· No significant residual impact from the project is expected with implementation of recommended mitigation measures and adoption of precautionary and enhancement measures |
||
|
Operation Impact |
|||||||
|
Ecological resources likely to be impacted by the Project |
· Low direct impact on habitat loss due to occupation by permanent structures; · Low to moderate impact from injuries or mortalities of wildlife due to roadkill and collision; · Impact of habitat fragmentation and wildlife movement is considered low; · Very low impacts from operation disturbance on adjacent habitats, species of conservation importance and associated flora and fauna; · Very low water quality impact from road run-off on adjacent watercourses and associated aquatic fauna; and · Very low impact from changes in hydrodynamic properties and sedimentation hydrology in nearby waters. |
· Annex 8 and Annex 16 of EIAO-TM |
N/A |
· Incorporation of fencing, u-shaped channels, hedge planting of dense vegetation to prevent access by and guide wildlife away from the at-grade road structures and lead them towards the passageways under the viaduct sections to minimise the likelihood of wildlife injuries and mortalities due to roadkill and collision. |
· No adverse residual impact is anticipated |
||
|
Fisheries |
|||||||
|
Construction Impact |
|||||||
|
Fisheries resources and habitats likely to be impacted by the Project |
· Minor impacts from loss of fishing grounds and habitat due to reclamation and pilling works, and works area for construction; · Insignificant impact from disruption of fish culture activity; · Insignificant impact from deterioration of water quality due to marine works; and · Insignificant impact from underwater sound generated during marine works. |
· Annex 9 and Annex 17 of EIAO-TM |
N/A |
· Follow mitigation measures, good practices and guidelines to minimise water quality impacts. |
· No adverse residual impact is anticipated |
||
|
Operation Impact |
|||||||
|
Fisheries resources and habitats likely to be impacted by the Project |
· Minor impact from loss of fishing grounds and fisheries habitat due to reclamation and piling works; · Insignificant impact from change in hydrodynamics induced by the footprint of the superstructures; and · Insignificant impact from deterioration of water quality due to surface run-off. |
· Annex 9 and Annex 17 of EIAO-TM |
N/A |
· No specific mitigation measure is required. |
N/A |
||
|
Landscape and Visual |
|||||||
|
Construction Impact |
|||||||
|
Existing LRs and LCAs within the assessment area
|
· Key affected LRs: - Negligible - Slight - Moderate · Key affected LCAs: - Negligible - Slight - Moderate
|
· Annexes 10 and 18 of the EIAO-TM · Environmental Impact Ordinance Guidance Note No. 8/2023
|
N/A |
· CM1 - Trees without impact from the proposed works should be retained and any existing trees unavoidably affected by the works should be transplanted as far as possible in accordance with DEVB TC(W) – No. 4/2020; · CM2 - Erection of decorative screen hoarding with advance planting or hoarding compatible with the surrounding setting; · CM3 - Construction facilities and activities on work sites and areas should be carefully managed and controlled, including height and disposition / arrangement, to minimise any potential adverse landscape impacts; and · CM4 - Reinstatement of the temporarily affected landscaped area within assessment area in like-for-like basis would be implemented to restore the existing natural environment as far as possible. |
· Key affected LRs: - Negligible - Slight - Moderate LR1.1, LR1.3, LR1.4, LR1.5, LR2.1 and LR2.3. · Key affected LCAs: - Negligible LCA1.5, LCA2.1 and LCA2.3; - Slight LCA1.3, LCA1.4 and LCA2.4; and - Moderate LCA1.1, LCA1.2 and LCA2.2. |
||
|
Operation Impact |
|||||||
|
Existing LRs and LCAs and Key Public Viewers / VPs within the assessment area
|
· Key affected LRs: - Negligible LR1.7, LR1.8, LR1.9, LR2.4, LR2.5 and LR2.6; - Slight LR1.2, LR1.6, LR2.2 and LR2.7; and - Moderate LR1.1, LR1.3, LR1.4, LR1.5, LR2.1 and LR2.3.
· Key affected LCAs: - Negligible LCA1.5, LCA2.1 and LCA2.3; - Slight LCA1.3, LCA1.4 and LCA2.4; and - Moderate LCA1.1, LCA1.2 and LCA2.2.
· Key affected VPs: - Negligible VP-A2; - Slight VP-B5, VP-A5 and VP-T1; and - Moderate VP-A3, VP-A4, VP-B3, VP-B4 and VP-P1.
|
· Annexes 10 and 18 of the EIAO-TM · Environmental Impact Ordinance Guidance Note No. 8/2023 |
N/A |
· OM1 - Aesthetically pleasing design as regard to the form, material and finishes should be incorporated to bridges, ancillary buildings and other associated engineering facilities so as to blend in the structures with the adjacent landscape and visual context; · OM2 - Buffer screen planting, including shrubs, to provide screening if space is available; · OM3 - As far as practicable, compensatory tree planting requirement of 1:1 in terms of number in accordance with DEVB TC(W) No. 4/2020 for compensation of felled trees subject to the availability of space and agreement made with relevant departmental parties; and · OM4 - Landscape treatments on slope or retaining structure should be adopted in accordance with GEO Publication No. 1/2011 – Technical Guidelines on Landscape Treatment for Slopes, subject to the availability of space and agreement made with relevant departmental parties. |
· Key affected LRs: - Negligible residual impact on Day 1 and in Year 10 of Operation LR1.7, LR1.8, LR1.9, LR2.4, LR2.5 and LR2.6; - Slight residual impact on Day 1 and reduced to Negligible in Year 10 of Operation LR1.2, LR1.6, LR2.2 and LR2.7; and - Moderate residual impact on Day 1 and reduced to Slight in Year 10 of Operation LR1.1, LR1.3, LR1.4, LR1.5, LR2.1 and LR2.3. · Key affected LCAs - Negligible residual impact on Day 1 and in Year 10 of Operation LCA1.5, LCA2.1 and LCA2.3; - Slight residual impact on Day 1 and reduced to Negligible in Year 10 of Operation LCA1.3, LCA1.4 and LCA2.4; and - Moderate residual impact on Day 1 and reduced to Slight in Year 10 of Operation LCA1.1, LCA1.2, and LCA2.2. · Key affected VPs: - Negligible residual impact on Day 1 and in Year 10 of Operation VP-A2, VP-A5, VP-T1; and - Slight residual impact on Day 1 and in Year 10 of Operation VP-A3, VP-A4, VP-B3, VP-B4 and VP-B5; and - Moderate residual impact on Day 1 and in Year 10 of Operation VP-P1 |
||
|
Impact on Cultural Heritage |
|||||||
|
Construction Impact |
|||||||
|
Terrestrial archaeology |
· No site of archaeological interest or area with archaeological potential is encroached by the works areas; and · No terrestrial archaeological impact is anticipated.
|
· Antiquities and Monuments Ordinance (Cap.53); · EIAO (Cap.499) and EIAO-TM Annexes 10 and 19. |
N/A |
· No impact on archaeology is anticipated; and · As a precautionary measure and pursuant to the Antiquities and Monuments Ordinance (Cap. 53), the project proponent and his contractor(s) are required to inform AMO immediately when antiquities or supposed antiquities are discovered in the course of works, so that appropriate mitigation measures, if needed, can be timely formulated and implemented in agreement with and to the satisfaction of AMO. |
· No adverse residual impact anticipated |
||
|
Built heritage |
· No direct or indirect impact is anticipated on the built heritage identified. |
· Antiquities and Monuments Ordinance (Cap.53); · Environmental Impact Assessment Ordinance (EIAO) (Cap.499) and EIAO-TM Annexes 10 and 19. |
N/A |
· N/A |
· N/A |
||
|
Marine archaeology |
· Diver survey was conducted to establish the archaeological potential of 11 side scan sonar contacts and 22 magnetic contacts located within 100m from potential area of dredging and determine whether further mitigation or action is required. No impact on marine archaeology is anticipated. |
· Guidelines for MAI. |
N/A |
· No impact on marine archaeology is anticipate; and · As a precautionary measure and pursuant to the Antiquities and Monuments Ordinance (Cap. 53), the project proponent and his contractor(s) are required to inform AMO immediately when antiquities or supposed antiquities are discovered in the course of works, so that appropriate mitigation measures, if needed, can be timely formulated and implemented in agreement with and to the satisfaction of AMO. |
· No adverse residual impact anticipated. |
||
|
Operation Impact |
|||||||
|
Terrestrial archaeology, built heritage and marine archaeology |
· No impact would be anticipated during the operational phase. |
· Antiquities and Monuments Ordinance (Cap. 53); · EIAO including EIAO-TM; and · Guidelines for MAI. |
N/A |
· No mitigation measure would be required. |
· No adverse residual impact anticipated |
||
|
Hazard to Life |
|||||||
|
Existing, committed and planned population in the vicinity of the PHIs (i.e. Chevron Terminal and Shell Tsing Yi Installations (STYI)), on-site transport and use of explosives of the Project |
Chevron Terminal and STYI · For both PHIs, the off-site individual risk level of 1×10-5 per year does not encroach to nearby land population and the societal risk falls into the “ALARP” region. On-site Transport / Use of Explosives · Both individual risk and societal risk comply with the criteria outlined in Annex 4 of the EIAO-TM.
|
· Annex 4 of the EIAO-TM |
N/A |
Chevron Terminal and STYI · No adverse impact is anticipated. Nonetheless, implementation of good safety practices during construction phase are recommended. These include: - Establishment of emergency response / evacuation plans; - Safety / emergency response training and drills for all personnel; - Maintain the number of construction workers on-site to a minimum; - Shielding provision such as mesh fencing to be installed along the slip road between the proposed works areas and the terminal; and - Risk assessment should be undertaken and method statement with lifting plan should be formulated by the Contractor prior commencement of lifting works.
On-site Transport/ Use of Explosives · No adverse impact is anticipated. Nevertheless, the following recommendations should be implemented: For the on-site transport of explosives: - Emergency plan should be developed to address uncontrolled fire during transport. Case of fire near an explosive carrying vehicle in jammed traffic should be included in the plan. Activation of fuel and battery isolation switches on vehicle when fire breaks out should also be included in the emergency plan to reduce likelihood of prolonged fire leading to explosion; - Working guideline should be developed to define procedure for explosives transport during adverse weather such as thunderstorm; - Detonators should be transported separately from other Class 1 explosives. Separation of vehicles should also be maintained through the trip; - Develop procedure to ensure the availability of parking space on site for the explosives carrying vehicle. Delivery should not be commenced if parking space on site is not secured; - Hot work should be suspended during passage of the diesel vehicle truck and bulk emulsion truck in the tunnels; - Speed limit for the diesel vehicle truck and bulk emulsion truck in the tunnels should be imposed. The truck may be escorted while underground to ensure route is clear from hazards and obstructions; - Fire screen should be used between cabin and the load on the vehicle; - Lining should be provided within the transportation box on the vehicle; - Ensure packaging of detonators remains intact until handed over at blasting site; - Ensure that cartridged emulsion packages are not damaged before every trip; and - Use experienced driver with good safety record. For the safe use of explosives: - Blast Charge Weight should be within Maximum Instantaneous Charge (MIC) as specified for the given blast face; - Temporary mitigation measures such as blast doors or heavy duty blast curtains should be installed at the portals at suitable locations underground to prevent flyrock and control the air overpressure; - Secure refuge areas to workers within the construction sites should be identified for their temporary shelter during blasting; - A Chief Shotfirer and a Blasting Engineer shall be employed in addition to the normal blasting personnel to ensure that the works are safe and coordinated between blasting areas; - Shotfirer to be provided with a lightning detector, and appropriate control measures should be in place; - A boulder survey should be undertaken based on the likely Peak Particle Velocity (PPV) values that would result from the blasting process. Those boulders subject to the vibration higher than the allowable limit should be strengthened, removed, or constructed with boulder fence, prior to the commencement of blasting; - Establishment of no-blast zones for areas of high sensitivity/risk; - The surface blasting benches will be covered with blasting cages, blast mats and blasting screens to limit flyrock potential; - All hiking paths/ footpaths located within the 200m assessment area will be temporarily closed during blasting/ explosives delivery from the barging point to the blasting sites; - Drill bits larger than 64mm should not be brought to the sites to avoid drilling a larger blasthole by accident; and - The Contractor will place warning signs at the concerned area (i.e. Yi Chuen) to let the residents know the blasting schedule at the surface blasting site S01 so that they have to be evacuated or stay indoor away from windows. Before the commencement of blasting, the contractor will also strike a gong to alert the residents and notify the residents in person to ensure all potentially affected personnel are fully aware of the surface blasting. |
· No adverse residual impact anticipated |
||