10.1. Summary of Environmental Outcomes
10.1.1. This section summarises the overall environmental outcomes due to construction and operation of the proposed WHS Crematorium in accordance with Section 3.6 of the Environmental Impact Assessment (EIA) Study Brief No.: ESB-362/2023. As stated in Section 1 and Section 2, environmental considerations have been the key considerations throughout the development of the Project. Alternative options for designs and construction methodologies have been duly considered. Besides, all the options considered have ensured that environmental impacts could be avoided or minimised where practicable and mitigated by implementation of suitable mitigation measures to fulfil all the statutory requirements. The technical assessments conducted (Section 3 to Section 7) have demonstrated that the requirements in the EIA Study Brief (ESB-362/2023) and Technical Memorandum of the Environmental Impact Assessment Ordinance (EIAO-TM) have been met.
10.1.2. This EIA report predicted that, with the implementation of the recommended mitigation measures, construction and operation of the proposed WHS Crematorium would be environmentally acceptable with no adverse residual impacts on the population and environmentally sensitive resources. Table 10.1 summarises the key environmental outcomes arising from the EIA study. The summary of environmental impacts and the summary of key assessment assumptions, limitation of assessment methodologies etc. are presented in Table 10.2 and Table 10.3, respectively.
Table 10.1 Summary of Key Environmental Outcomes
|
Issue |
Environmental
Outcome |
|
Population and
Environmentally Sensitive Areas Protected |
-
Population and
environmental sensitive areas in the vicinity of the Project site have been
protected through the avoidance and/or minimisation of environmental impacts
from the construction and operation of the Project. -
Duly selected to
locate away from the densely urbanised areas. It is situated within the
existing WHS Cemetery, with the nearest residential noise
sensitive receiver (i.e. the village houses in Nam Wa
Po) about 370m away from the Project
Boundary,
outside the 300m noise impact assessment area. -
Population
protected from air quality impacts include air sensitive receivers within
500m from the Project Boundary including approximately 80 residential
dwellings at Nam Wa Po, Blossom Villa and approximately 20 residential dwellings at Wo Hop Shek Village. -
Based on
cumulative air quality impacts of the proposed crematorium, vehicular
emissions and existing WHS crematorium, no exceedance of the Air Quality
Objectives
(AQO) pollutants and other relevant
pollutants are predicted and no adverse operation
phase impacts are expected to occur. As
such, the total affected population has been minimised as much as
practicable. -
The proposed use
is compatible with the surrounding cemetery landscape. In addition, the
Project is situated within the bottom of a trough area where the natural
terrain could provide shielding and the visual impact would be minimised. -
Slope works have to be carried out at the eastern corner of the
Project Boundary for slope safety reason which the slope works would encroach
onto the Water Gathering Ground (WGG). With the recommended mitigation
measures implemented properly, no adverse environmental impact is anticipated
on the WGG. -
No recognized
sites of conservation importance are identified within the 500m Assessment
Area. Lam Tsuen Country Park and the
Ecologically Important Stream at Kau Lung Hang are the closest recognized
sites of conservation importance, with the former located at more than 1.4 km
to the southwest of the Project Boundary and the latter flowing through the
lowland area at Nam Wa Po outside the Assessment Area. |
|
Environmentally Friendly Options
Considered and Incorporated in the Preferred Option |
-
The Project is
located within a trough area. The surrounding slopes partially screens the building
structure of the proposed crematorium including the chimneys from the
sensitive uses and hence minimise its visual impact. -
Minimise the
extent of slope cutting and site formation works and
generate less amount of inert and non-inert C&D materials. -
Less fugitive
dust generated during construction works. -
There are
existing access roads leading to the Project site where construction of new roads
are not required and hence less associated
environmental pollutions. |
|
Environmental Designs
Recommended |
-
Locate the cremator
room on 1/F and service halls scattered around to make use of site topology
and avoid extensive excavation work would generate less amount of inert and
non-inert C&D materials, and hence substantially reduce the amount of
deep excavation. -
Optimise heights
of chimneys at a level similar to the ridge to be
better screened by natural terrain. -
Choose nine
standard 170kg cremators and one large 250kg cremator over all ten large
cremators to balance the need to handle heavier bodies while promote energy
efficiency and reduce air pollutant emission. -
Choose Towngas
as the fuel for the cremators to emit negligible SO2 and less CO2
and CO and to avoid construction of underground fuel tanks. |
|
Key Environmental Problems
Avoided |
-
Avoid locating
the Project near sensitive receivers. The air and noise sensitive receivers
are about 370m from the Project Boundary. -
Avoid direct
impact on landscape with distinctive character/resources and would not induce
pronounced visual change from key public viewing points or on existing
visually sensitive areas and major visual resources enjoyed by the public
being affected. -
Avoid direct
loss of habitats of higher ecological value, such as perennial natural water
courses and mixed woodland of moderate ecological value. |
|
Compensation Areas Included |
-
Terrestrial and
aquatic habitat are mainly of low ecological value. Hence, compensation is
considered not necessary. |
|
Environmental Benefits of
Environmental Protection Measures Recommended |
-
The recommended
environmental protection and mitigation measures for the Project are
summarised in Appendix 9.1 of this EIA Report. The measures focus on minimizing air
quality, noise, water quality, waste and ecological impacts during design,
construction, and operation phases. -
For air quality,
the measures propose to use appropriate pollution control systems, maintain specific
temperatures during cremation, use Towngas as fuel for cremation for reduced
emissions, and treat flue gas generated from joss paper burning. These
measures ensure the air quality of the proposed WHS Crematorium is acceptable
during construction and operation phases. -
Noise control
measures involve using quieter construction methods, movable noise barriers,
noise enclosures, and implementation of good site practices to limit noise
emissions at source. These measures aim to minimize noise pollution, thereby
reducing disturbance to NSRs in the area.
-
Water quality mitigation
measures include controlling site runoff, connecting to new and existing public
sewers for treatment at existing sewage treatment works(STW),
and handling sewage effluent from the workforce, etc. These measures aim to ensure
compliance with relevant environmental protection standards and regulations,
minimize potential impact to the identified WSRs, thereby protecting water
quality and aquatic ecosystems. -
Design of site
drainage and disposal of various site effluents generated during operation of
the WHS Crematorium facilities should follow the relevant guidelines and
practices as given ProPECC PN 1/23. -
Sewage to be
generated by working staff and the public during the operation phase will be
diverted to a new public sewer connected to the existing sewers at Kiu Tau
Road and Ming Yin Road, which will eventually be conveyed to the Shek Wu Hui
Sewage Treatment Works. -
Surface runoff
generated during the operation of the Project will be discharged to the
nearby existing government drainage system, which could cope with a design
return period of 1 in 50 years. Peripheral drain will be provided to collect
all surface runoff across the site. -
Waste management
measures involve exploring alternatives to reduce, reuse and recycle waste
generated during the construction and operation of the proposed WHS
Crematorium and implementing good site practices such as obtaining necessary
permits, preparing waste management plans, employing licensed waste
collectors, adopting trip ticket systems, staff training, separating and
recycling waste, and maintaining proper records. The measures aim to reduce
the amount of waste generated and ensure proper disposal of waste, thereby reducing
landfill usage, conserving resources, and minimizing pollution. -
Ecological
mitigation measures include avoidance of direct loss of floral/ faunal
species of conservation importance, avoidance/ minimization of the potential
indirect disturbance to natural watercourses and associated wildlife, and
minimization measures for potential light glare and sky glow. Furthermore, good site practices from an
ecological perspective have also been recommended to avoid and minimize the
potential disturbance to the wildlife and habitat nearby. The benefits of
these measures include but are not limited to preserving biodiversity,
maintaining ecosystem health, and protecting species of conservation
importance. |
Table 10.2 Summary of Environmental Impacts
|
Sensitive Receiver/ Assessment Point |
Impact Prediction Result (without Mitigation) |
Key Relevant Standard/ Criterion |
Extent of Exceedance (without Mitigation) |
Impact Avoidance Measure/ Mitigation Measure |
Residual Impact (after Implementation of Mitigation Measure) |
|
Air Quality Impact |
|
|
|
|
|
|
Construction Phase |
|
|
|
|
|
|
ASRs
located within 500m from the Project Boundary include the following: § Cheung
Kee Stoneworks § Kin Fuk
Stone Factory § Village
house no. 168 at Nam Wa Po § Village house no. 50A at
Nam Wa Po § Temporary structures |
§ Limited dust
impact § No
exceedances of other relevant criteria are anticipated |
§ Annexes 4
and 12 of the EIAO-TM § Hong Kong
AQO § APCO Cap.
311 |
§ N/A |
§ Implementation
of dust control measures stipulated in Air Pollution Control (Construction
Dust) Regulation § Implementation
of controls stipulated in the Air Pollution Control (Fuel Restriction)
Regulations § Adhere to
the guidelines recommended in DEVB’s TC No. 1/2015 Emissions Control of NRMM
in Capital Works Contracts of Public Works and the Air Pollution Control (Non-road Mobile Machinery (NRMM)) (Emission) Regulation § Adhere to the
guidelines recommended in DEVB’s TC No. 13/2020 Timely Application of
Temporary Electricity and Water Supply for Public Works Contract and Wider
Use of Electric Vehicles in Public Works Contracts § Adhere to the
guidelines recommended in EPD’s Recommended Pollution Control Clauses for
Construction Contracts |
§ No residual
impact is anticipated |
|
Operation Phase |
|
|
|
|
|
|
ASRs located
within 500m from the Project Boundary include the following: § Cheung
Kee Stoneworks § Kin Fuk
Stone Factory § Village
house no. 168 at Nam Wa Po § Village house no. 50A at
Nam Wa Po § Temporary structures |
§ No
exceedances of AQO at the ASRs would be caused by the Project |
§ Annexes 4
and 12 of the EIAO-TM § Hong Kong
AQO § APCO Cap.
311 § OEHHA Acute
Reference Exposure Level § OEHHA
Chronic Reference Exposure Level § WHO Air
Quality Guidelines for Europe § OEHHA
Cancer Potency Information § USEPA
Reference Concentration for Inhalation Exposure § Ammonia
Fact Sheet, AERISA |
§ N/A |
§ Design,
operation, and maintenance of cremators shall adhere to the guidelines
stipulated in BPM 12/2 (2020) § Design,
operation, and maintenance of joss paper burners shall follow Guidelines on
Air Pollution Control for Joss Paper Burning at Chinese Temples, Crematoria
and Similar Place |
§ No residual
impact is anticipated |
|
Noise Impact |
|
|
|
|
|
|
Construction Phase |
|
|
|
|
|
|
§ No noise
sensitive receiver (NSR) is identified in the 300m assessment area § Nearest village
houses in Nam Wa Po which are located outside the assessment
area |
§ Construction
noise impact due to the Project would be minimal |
§ Annexes 5
and 13 of the EIAO-TM § Leq (30mins)
75 dB(A) at 1m from the external façade of domestic dwellings |
§ N/A |
§ Standard
noise control measures such as adoption of quieter construction method, use
of QPME, use of movable noise barriers and noise enclosure to screen noise
from PMEs § Implementation
of good site practices to limit noise emissions at source would be
implemented through standard contract document clauses, which include the
“Recommended Pollution Control Clauses for Construction Contracts”, to ensure
the construction noise impact would be minimised during the construction
phase |
§ No residual
impact is anticipated |
|
Operation
Phase |
|
|
|
|
|
|
§ No noise
sensitive receiver (NSR) is identified in the 300m assessment area § Nearest
village houses in Nam Wa Po which are located
outside the assessment area |
§ Fixed plant
noise - No exceedances of fixed plant noise criteria § Road
traffic noise - The small percentage increase (less than 6.9%) in flows on
the Kiu Tau Road and Ming Yin Road during both normal day and festive day,
would not be expected to significantly increase the noise levels (i.e. less
than 1.0dB(A)) at surrounding sensitive receivers |
§ Annexes 5
and 13 of the EIAO-TM § IND-TM
under NCO § 5 dB(A)
below the appropriate ANL shown in Table 3 of the IND-TM, or the prevailing
background noise levels (whichever is lower) § Annexes 5
and 13 of the EIAO-TM |
§ N/A |
§ M&E
equipment of the Project will meet the maximum permissible SWL (i.e., 108
dB(A) and 100 dB(A) during daytime/evening (0700-2300 hrs) and nighttime (2300-0700
hrs) respectively) to ensure compliance with statutory requirements and
guidelines at NSR. § No mitigation
measure is required. |
§ No residual
impact is anticipated |
|
Water Quality Impact |
|
|
|
|
|
|
Construction Phase |
|
|
|
|
|
|
WSRs within 500m assessment area include the
following: § A very
small portion of Water Gathering Ground § Sand trap
with retained water within Project Boundary § Watercourse
within Project Boundary § Watercourses to the north of the Project Boundary § Watercourses to the east and south of the Project
Boundary |
§
General construction works for the
Project would be land-based only. §
Potential water pollution arising
from: -
General construction works; -
Sewage from workforce; -
Accidental spillage of chemicals. |
§ Annexes 6
and 14 of the EIAO-TM § Water
Pollution Control Ordinance (Cap. 358) § TM-DSS § HKPSG Ch 9 § ProPECC PN
2/23 § “Conditions
of Working within Water Gathering Ground” by WSD § Code of
Practice on the Packaging Labelling and Storage of Chemical Wastes, and Waste
Disposal (Chemical Waste) (General) Regulation (Cap 354C) |
§ N/A |
§ Mitigation
measures and good site practices in ProPECC PN 2/23 Construction Site
Drainage § Measures in
WSD’s Conditions of Working within Water Gathering Ground § Discharge
of effluent should comply with the standards as stipulated in the TM-DSS § Sufficient
portable toilets shall be provided and maintained by licensed contractor who
shall be responsible for proper sewage collection and disposal § Notices at
conspicuous locations to remind the construction team not to discharge any
sewage or wastewater into the surrounding environment during the construction
phase § Mitigation measures to reduce the
potential water quality impact due to accidental spillage of chemicals |
§ No residual
impact anticipated |
|
Operation
Phase |
|
|
|
|
|
|
WSR within 500m assessment area include the
following: § A very
small portion of Water Gathering Ground § Sand trap
with retained water within Project Boundary § Watercourse
within Project Boundary § Watercourses to the north of the Project Boundary § Watercourses to the east and south of the Project
Boundary |
§ Potential
water pollution arising from: - Wastewater
generated by the operation of the crematorium facilities - Sewage from
visitors and staff - Surface
runoff generated from the proposed WHS Crematorium site |
§ Annexes 6
and 14 of the EIAO-TM §
Water Pollution Control Ordinance (Cap. 358) § TM-DSS § HKPSG Ch 9. §
ProPECC PN 1/23 |
§ N/A |
§ Guidelines
in ProPECC PN 1/23 Drainage Plans subject to Comment by the EPD § Surface
runoff will be discharged to the nearby existing government drainage system.
Peripheral drain will be provided to collect all surface run § Sewage to
be generated by visitors and staff will be diverted to new public sewer
connected to the existing sewers in the vicinity § Wastewater
generated by the operation of the crematorium facilities (i.e. joss paper
burner) should comply with WPCO and will be discharged to the manhole
provided by the Project and conveyed to the sewage treatment works for
further treatment |
§ No residual
impact anticipated |
|
Waste Management Implication |
|
|
|
|
|
|
Construction Phase |
|
|
|
|
|
|
§ The waste
transportation routes and the waste disposal sites /
facilities assessed. |
§ 254,410,000
kg of inert C&D materials and 7,950 m3 of non-inert
C&D materials would be generated during the construction phase § 19,340,000kg
of inert materials would be re-used on site while the remaining 235,070,000
kg would be transported to PFRF for the reuse in other projects § 150 m3
of non-inert C&D materials would be re-used before disposed to landfill
while 7,800 m3 would be disposed of at designated landfill § Less than
50L of chemical waste will be generated per month § 200 kg per
day of general refuse would be generated from the on-site workers |
§ EIAO-TM
Annexes 7 and 15 § Waste
Disposal Ordinance (Cap. 354) § Waste
Disposal (Chemical Waste) (General) Regulation (Cap. 354C) § Waste
Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N) § Public
Health and Municipal Service Ordinance (Cap. 132BK) – Public Cleansing and
Prevention of Nuisance Regulation § Land
(Miscellaneous Provisions) Ordinance (Cap. 28) § Development
Bureau Technical Circular (Works) (TC(W)) No. 6/2010 Trip ticket System for
Disposal of Construction & Demolition Materials § Code of
Practice on the Packaging Labelling and Storage of Chemical Wastes and Waste
Disposal (Chemical Waste) (General) Regulation (Cap 354C) |
§ N/A |
§ Follow
waste management hierarchy principles of waste avoidance, minimization,
recycling/reuse, treatment and disposal § Implementation
of good site practices and waste reduction measures § Implement
trip-ticket system for surplus C&D materials disposal § Explore
alternatives to eliminate the use of chemicals, reduce the generation
quantities or to select a chemical type of less impact on environment, health
and safety during planning stage § Collect
chemical waste by licensed chemical waste collectors for proper disposal at
licensed chemical treatment facilities § General
refuse is collected by waste collector to minimize odour, pest and litter
impacts § Three-color
recycling bins should be provided for recycling of recyclable waste and
collected by waste collector § A
trip-ticket system will be implemented for surplus C&D materials disposal
in accordance with ETWB TC(W) No.31/2004 and the Construction Waste Disposal
Charging Scheme. The surplus inert C&D materials should be delivered to a
public fill reception facility. Copies or counterfoils of trip tickets will
be kept for record purpose § Transportation
of construction waste will be monitored by means of dump trucks equipped with
real-time tracking and monitoring devices |
§ No residual
impact is anticipated |
|
Operation
Phase |
|
|
|
|
|
|
§ N/A |
§ 149.6 kg
bone ash and 122.4 kg non-combustible residues are generated daily by the
cremators § 30 kg/day
fly ash would be generated from the APC equipment § A small
amount of chemical waste in the form of cleaning fluids, solvents,
lubrication oil and fuel would be generated during regular plant maintenance
and servicing of transformer, switch room, hydraulic lifts, etc. § Small
amount of general refuse would be generated by visitors and staffs |
§ EIAO-TM
Annexes 7 and 15 § Waste
Disposal Ordinance (Cap. 354) § Code of
Practice on the Packaging Labelling and Storage of Chemical Wastes and Waste
Disposal (Chemical Waste) (General) Regulation (Cap 354C) § Waste
Disposal (Chemical Waste) (General) Regulation and the Land (Miscellaneous
Provision) Ordinance (Cap. 28) |
§ N/A |
§ Implementation
of good site practices and waste reduction measures § Properly
collect and handle bottom ash to avoid dust emissions § Optimize
the effectiveness of combustion during cremation process § Chemical
waste should be collected by drum-type containers and removed by licensed
chemical waste contractor § Plant /
equipment maintenance schedules should be planned in order
to minimize the generation of chemical waste § Solid
and liquid chemical wastes that cannot be recycled should be
disposed of at an appropriate facility. Copies/ counterfoils from collection
receipts issued by the licensed chemical waste collector shall be kept for a
record purpose |
§ No residual
impact is anticipated |
|
Ecological Impact |
|
|
|
|
|
|
Construction Phase |
|
|
|
|
|
|
§ Ecological
sensitive receivers include habitats, flora and fauna species within 500m
Assessment Area § Survey
transects and sampling points presented in Figure 7.1 |
Potential ecological impacts with the predicted
impact significance of Low to Moderate or above, in the absence of mitigation
measures, include: § Direct loss
of terrestrial species of conservation importance § Direct loss
of aquatic/ wetland species of conservation importance § Glare and
sky glow § Artificial
lighting § Change of
water quality Construction site runoff |
§ Annex 8 and
Annex 16 of the EIAO-TM |
§ N/A |
§ Avoidance
of direct loss of floral/ faunal species of conservation importance, and
translocation and transplantation measures before site clearance if necessary § Avoidance/
minimization of potential indirect disturbance to natural watercourses and
associated wildlife § Minimization
of potential light glare and sky glow § Good site
practices from an ecological perspective to avoid and minimize the potential
disturbance to the wildlife and habitats nearby |
§ No residual
impact |
|
Operation Phase |
|
|
|
|
|
|
§ Ecological
sensitive receivers include habitats, flora and fauna species within 500m
Assessment Area § Survey
transects and sampling points presented in Figure 7.1 |
Potential ecological impacts with the predicted
impact significance of Low to Moderate or above, in the absence of mitigation
measures, include: § Deterioration
in quality of terrestrial habitats and disturbance to Wildlife due to light
glare and sky glow § Deterioration
in quality of aquatic habitats and potential disturbance to wildlife resulted
from change of water quality |
Annex
8 and Annex 16 of the EIAO-TM |
N/A |
§ Discharge
surface runoff to the nearby government drainage system § Provide
peripheral drains to collect surface runoff § Minimisation
of the amount of artificial lighting, esp. upward-facing lighting to avoid
impacts on nearby woodland habitats |
No residual impact |
Table 10.3 Key Assessment Assumptions and Limitation of Assessment Methodologies
|
Assessment Methodology |
Key Assessment Assumption |
Limitation of Assessment Methodologies/ Assumptions |
Prior Agreement with Authority |
Proposed Alternative Assessment Tools/
Assumptions |
|
Air Quality Impact |
|
|
|
|
|
Construction Phase |
|
|
|
|
|
§ Annexes 4
and 12 of the EIAO-TM § EIA Study
Brief (ESB-362/2023) |
§ N/A |
§ N/A |
§ N/A |
§ N/A |
|
Operation Phase |
|
|
|
|
|
§ Annexes 4
and 12 of the EIAO-TM § EIA Study
Brief (ESB-362/2023) § Guidelines
on Assessing the 'TOTAL' Air Quality Impacts § Guidelines
on Choice of Models and Model Parameters § Guidelines
on the Estimation of 10-minute Average SO2 Concentration for Air
Quality Assessment in Hong Kong § Technical
Notes on Air Quality Modelling |
§ Receptors
on other FEHD premises in the 500m assessment area are considered as on-site
population and have been excluded from the assessment. § Joss paper
burners of the Project and existing WHS crematorium will have insignificant
impact to air quality as their design, operation and maintenance adheres to
the guidelines stipulated in Guidelines on Air Pollution Control for
Joss Paper Burning at Chinese Temples, Crematoria and Similar Place. As such,
emissions from joss paper burners have not been modelled. § AERMOD was utilized for the modelling of
all emissions in cumulative assessment. § PATH
background concentration at year 2030 was adopted. § In the
emergency operation scenario, only the Project will operate for 24-hours
continuously whereas the existing WHS crematorium will still operate under
the normal hours of 08:30 to 23:00. § Only the
short-term air quality impact (e.g. hourly and daily average values) has been
assessed for the emergency operation scenario. Based on past
experience at other crematoriums, the circumstances leading to
emergency operation are rare and therefore will have minimal impact to long
term pollutant concentrations (e.g. annual average values). § Emissions
of the proposed WHS Crematorium follows the requirements stipulated in BPM
12/2 (2020). |
§ The
feasibility of adopting lower emission limits for the cremators would be
explored at a later stage of the Project when more design details are
available (e.g. during application for an SP licence). |
§ Target
emission levels for the cremators |
§ N/A |
|
Noise Impact |
|
|
|
|
|
Construction
Phase |
|
|
|
|
|
§ Annexes 5
and 13 of the EIAO-TM § EIA Study
Brief (ESB-362/2023) § GW-TM under
NCO |
§ Assumptions
made in the assessment are based on the latest design which may be subject to
detailed design. |
§ The
programme and plant inventory for proposed construction works adopted in the
assessment might vary in future. |
§ Assessment
methodology |
§ N/A |
|
Operation Phase |
|
|
|
|
|
§ Annexes 5
and 13 of the EIAO-TM § EIA Study Brief
(ESB-362/2023) § IND-TM
under NCO |
§ Assumptions
made in the assessment are based on the latest design which may be subject to
detailed design. |
§ The noise
performance of the proposed fixed plants would be reviewed during detailed
design stage with due regard to the characteristics of tonality,
impulsiveness and intermittency. If the noise exhibits characteristics of
tonality, intermittency or impulsiveness during the detailed design or the
commissioning of the plant, the SWL should be reduced in accordance with the
recommendation given in Section 3.3 of IND-TM to ensure noise compliance at
the NSRs. § As the
maximum allowable SWLs are adopted, which the SWL of each equipment may be
lower in actual case, overestimation is considered. |
§ Assessment methodology |
§ N/A |
|
Water Quality Impact |
|
|
|
|
|
§ Annexes 6
and 14 of the EIAO-TM § EIA Study
Brief (ESB-362/2023) |
§ Types and
quantities of waste water to be generated from the
Project are based on the Project design, engineering assessments, and
construction details available at the time of this EIA Study. |
§ N/A |
§ N/A |
§ N/A |
|
Waste Management Implication |
|
|
|
|
|
§ Annexes 7
and 15 of the EIAO-TM § EIA Study
Brief (ESB-362/2023) |
§ The amount and
types of wastes to be generated were estimated based on best available information,
relevant studies or engineering judgement. |
§ N/A |
§ N/A |
§ N/A |
|
Ecological Impact |
|
|
|
|
|
§
EIA Study Brief (ESB-362/2023) §
Annex 8 and Annex 16 of the EIAO-TM §
EIAO Guidance Notes No. 6/2010, No. 7/2023 and No. 10/2023 |
§
N/A |
§
The evaluation and assessment of ecological impact were
undertaken based on the results of literature review and ecological field
survey. |
§
N/A |
§
N/A |
10.2.1. This EIA Study has examined the possible environmental impacts stemming from both the construction and operation phases, in accordance with the Study Brief (ESB-362/2023) and the EIAO-TM. Based on the assessments carried out, the Project is expected to meet the relevant environmental standards with the implementation of the recommended mitigation measures during both the construction and operation phases.